Professional Documents
Culture Documents
Abstract: Performance measurement is a helpful tool for taking corrective actions and controlling a project as far as this enables accurate
Downloaded from ascelibrary.org by National Cheng Kung University on 08/26/14. Copyright ASCE. For personal use only; all rights reserved.
time and cost forecasts during the first stages of the construction effort when the management team still has opportunities to make
adjustments. This paper overcomes the dilemma of practicability and predictability of traditional estimates at completion based on early
progress measurement by presenting the empirical results from the construction project of an industrial facility. The case may be a
reference practice for assessing time and cost performance measurement of any building, whose layout can be reasonably partitioned into
repeatable portions. In such circumstances, an effectively-managed traditional earned value method and appropriate metrics for computing
performance provide project managers with accurate forecasts as useful tools for successful project management and control.
DOI: 10.1061/共ASCE兲CO.1943-7862.0000055
CE Database subject headings: Construction management; Information systems; Monitoring; Costs; Industrial plants; Italy;
Scheduling; Case reports.
the task’s detailed one. The problem accrues in a separate design 共TEAC兲 can be calculated by extrapolating the actual perfor-
and build delivery system as far as the cost breakdown derived mance to the end of the project 共Project Management Institute
from the engineer’s estimates that are traditionally prepared dur- 2005兲. The following formulae indicate that estimates to comple-
ing the detailed design phase. In such a situation the contract tion are consistent with the original budget at completion 共BAC兲
estimates do not align with the work breakdown designed by the and planned duration 共D兲, adjusted by the corresponding perfor-
contractor or the agency project manager to implement and man- mance factor
age the physical construction improvement.
EAC = ACWP + 共BAC − BCWP兲/CPI = BAC/CPI 共1兲
Progress Measurement
TEAC = 共BAC/SPI兲/共BAC/D兲 = D/SPI 共2兲
To produce a reliable evaluation of the actual status of the project,
an effective impartial construction surveying as well as a rigorous The following formula 共Henderson 2005兲 is closely equivalent to
system for timely collection and reporting of information are nec- Eq. 共2兲
essary to provide both the owner and the contractor with accurate
and objective assessment of performance. The objectivity of 共BAC − BCWP兲
TEAC = T + 共D − T兲 ⫻
progress estimation is a crucial issue to consider in the task of 共BAC − BCWS兲SPI
monitoring the project status. Several are the metrics to evaluate where T = time now 共3兲
the physical progress of individual activities 共U.S. Department of
Energy 1980; Fleming 1991兲 depending on the type of task. Problems may arise from the index-based formulae above with
In the case of tasks that involve production of easily measured regard to the accuracy of estimating both cost and time.
deliverables, the “discrete effort” or “units completed” are prac- Some corrections in Eq. 共1兲 may help in better predicting the
ticable and viable metrics for assessing the actual situation. The cost at completion. Christensen 共1999兲, with reference to U.S.
“on/off” technique is a useful approach when accounts cannot be defense contracts, remarks that a different performance factor in
physically measured; progress of an item is 100% complete when Eq. 共1兲 may be used to account for the integrated influence of the
the job is formally accepted as finished. Since the progress record SV to the cost performance; a bad SPI may be an indicator of
of underway tasks is zero, the method may not result in an un- future cost overruns. Thus, the performance index for estimating
derestimation of performance only if measurement is carried out the cost at completion may be either CPI, SPI, or a combination
at the very detailed level of elementary tasks. To overcome the of both indices 共e.g.: CPI⫻ SPI; 0.8 CPI+ 0.2 SPI兲. The diverse
problem, different conventional metrics may be established as a adjustments lead to a range of EACs, where the CPI factor cal-
set of “incremental milestones,” such as the ones required to pre- culation is a reasonable floor to the final cost, and the one ob-
pare, submit, and approve a drawing. In this case, conventional tained by using the product of CPI and SPI is a sufficiently large
percentages are associated to each step of the process based on indication of the maximum final cost 共Christensen 1996兲.
the number of work hours or other quantities, estimated to be Also, during the very first stages of a project the CPI fluctuates
required to that point in relation to the total 共e.g.: 60% at first so that it is not to be considered as a reliable source of future
issue of drawing, 70% returned with comments, 80% other issues, indication, while it has been researched 共Lipke 2005兲 that CPI
95% approved, and 100% ready for construction兲. The incremen- tends to stabilize by the time the project is 20% complete. Fur-
tal milestone approach well applies to longer activities and to the thermore, CPI is likely to worsen from that point in time as the
measurement of WBS items at a higher level than the detailed project progresses. This is mainly due to delay, rescheduling,
task one. and rework, which increases as more activities unfold 共U.S.
Progress of indirect cost may be assessed in terms of appor- Department of Energy 1980; Oberlender 1993兲. Accordingly,
Lipke 共2005兲 has experimentally determined that in engineering
tioned effort in relation to the progress of activities they are
projects a correction factor to the CPI allows for calculating the
linked to. Of course, it is possible to use other methods to mea-
EAC upper bound. The maximum correction factor equals 0.1 and
sure actual progress of individual work packages and tasks. In any
Eq. 共1兲 may be rewritten as
case, a flexible use of all methods permits that each item is re-
corded in the more suitable way. Once the advancement of indi-
BAC/CPI ⬍ EAC ⬍ BAC/共CPI − 0.1兲 共4兲
vidual tasks has been assessed, the aggregated progress at any
level of the WBS up to the project level is calculated as a With sensible variation, select index-based formulas allow, in any
weighted summation of individual lower level progress percent- case, an accurate evaluation of EAC and alternative nonlinear
ages, where weights are calculated based on the original project regression-based models are not as practicable compared to the
budget. little additional precision they provide 共Christensen et al. 1995兲.
CATEGORIES
Downloaded from ascelibrary.org by National Cheng Kung University on 08/26/14. Copyright ASCE. For personal use only; all rights reserved.
WORK
PACKAGES
ACTIVITIES
communication, the agency project schedule is based on the work Work items are specifically defined with regard to the nature
package level of the WBS. The project team has the primary and scope of each work package and assigned a percentage
objective of delivering usable portions of the project as soon as weight of the work package’s original budget. Also, a common
they are finished to assure prompt occupancy and industrial op- work item, defined as “Z-Finishes,” is used for all work package
erations. The WBS proves to be effective for considering different breakdowns to refer to the many, and usually neglected, minor
layout areas as separate schedule milestones. activities required for substantial final completion of any work
Below is the baseline S-curve of the BCWS out of original package. The Z work item was agreed between the construction
cost budgeting and time scheduling. The schedule is based on manager and the contractor to be worth 5% of the work package’s
work package sequencing and estimated durations, and it takes budget.
into account all constraints and milestones agreed upon the con-
For example, the work package code 002.001.001 “Demoli-
tract 共Fig. 3兲.
tions” includes 21 activities just for the first floor of Building
No. 2. Demolition tasks are grouped into four work items,
Field Progress Measurement namely: 共a兲 demolitions in general; 共b兲 doors demolition; 共c兲 win-
The main problem that a project control system faces is the great dows demolitions; and 共d兲 finishing, which in this occurrence is
amount of details and the choice of the proper WBS level for the job to be performed for disposal of demolished materials and
measuring the job progress 共Riggs 2004兲. Due to both the imprac- meticulous cleaning. Below is another example of work item defi-
ticability of monitoring the number of individual elementary tasks nition for monitoring the replacement of the existing asbestos
based on actual quantity surveying and the hardness in assessing cement rooftop 共Fig. 4兲. Table 2 also shows the calculation of the
a reliable progress measurement of the WP based on work pack- relative budget weights of work items that are assumed to be
ages, an intermediate grouping of activities is introduced as a totally worth 95%, since the remaining 5% is assumed to be re-
control element, similarly to a work item level. leased at completion.
0%
JUN
AUG
JUL
OCT
NOV
JAN
SEP
DEC
Fig. 3. S-curve of the project BCWS
The decomposition of a work package into measurable items, host five office “lofts” numbered from 1 to 5. Also the main Plant
which are different from the price items agreed upon the contract, No. 83 is suitable for being split into a number of similar square
may not be a simple task and may result in disputes over under- units of space 共Fig. 1兲.
estimation or overestimation of monthly job progress, which in For each one of the 36 project work packages, a spreadsheet
turn affects payments. For example, it is opportune that the ac- displays the physical layout decomposed into subareas. Individual
tivities involving supply of materials are separately considered as modular units of space contain a cell list of items, whose work
completed, as far as the material is shipped to the site and ac- progress has to be measured 共Fig. 5兲.
cepted by the owner before installation. As far as a work item in a single subarea is quality-checked as
It is worth remarking that the work item breakdown is not completed by a field superintendent, a one mark is recorded on
applied to some work packages that count a few construction the report sheet and this becomes an input to the weighted sum
tasks. In such situations, the work package is the progress control calculation of the total percent progress of the work package. In
element. Whatever the control element, the on/off technique is fact, the percent completion of a single subarea is the weighted
chosen for measuring the job done. The progress of an individual total of percent progress of each work item, while the work pack-
control element is 100% complete only at the point in time it is age progress is obtained by dividing the summation of all space
substantially completed. unit percent progresses by the total number of subareas 关Eq. 共6兲兴
To this end, it is required that the facility areas are decom-
posed in small homogeneous units of space. The task is easily
Work package percent completion
done, thanks to the orthogonal and repetitive structural frame
of the industrial plant layout. For instance, Building No. 2 is a
180 m 共197 yd兲 long and 16 m 共17.5 yd兲 large open plan, which
= 兺 共unit % progress兲/unit count 共6兲
is partitioned into five similar main modules delimited by arrows A cell coloring function of the spreadsheet supports a visual
of columns and four staircases; these subareas are designated to understanding of the construction workflow and better communi-
002.001.003 Roofing
002.001.003.001 Steel plates …
ITEM DESCRIPTION
002.001.003.002 Decontamination …
a Asbestos plating
002.001.003.003 Transportation of asbestos … b Removal
002.001.003.004 Removal of suspensions … 46 c Disposal
tasks d Cladding
002.001.003.005 Steel structure …
e Drain piping
.... ....... ..... ..... ..... ........ ......... ........ ..............
002.001.001.046 Piping grilles … z Finishing
Fig. 4. Progress measurement elements grouping the roofing construction detailed activities
(56)
a 33 1 a 33 1 a 33 1 a 34 1 a 34 1
b 35 1 b 35 1 b 35 1 b 35 b 34
c 37 1 c 36 1 c 36 1 c 37 c 37
z z z z z
(58)
Downloaded from ascelibrary.org by National Cheng Kung University on 08/26/14. Copyright ASCE. For personal use only; all rights reserved.
Budget € 67.947,87
WI w WI % WI % WI % WI % WI %
a 61% a 100% a 100% a 100% a 100% a 100%
b 17% b 100% b 100% b 100% b 0% b 0%
c 17% c 100% c 100% c 100% c 0% c 0%
z 5% z 0% z 0% z 0% z 0% z 0%
% progress (loft) 95% 95% 95% 61% 61%
% progress (work package) 81%
cation of the weekly status reporting. Larger spreadsheets are the electrical and fluid systems job with triple shifts, while
used for the total Plant No. 83 facility area, similarly to Fig. 5. the owner accepts shorter procedures for material acceptance
As a summary, the monitoring process of a modular facility and process quality check. These decisions were taken based
requires the following steps: first, the layout must be decomposed on the information provided by the project control system and
into small uniform units of space areas with reference to the struc- reporting.
tural frame; second, the activities required for one or more sub- Table 3 is the EV monthly reporting summary with perfor-
areas have to be grouped into on/off measurable elements, either mance indices, calculated according to previous definitions. As
under the form of work packages or, in case, as work items; stated above 共Lipke 2005兲, the report and related Fig. 7 show
finally, the total progress of the project is calculated as the the typical cost and time performance behavior, where the cost
weighted summation of individual bottom elements up to the top performance tends to stabilize when the construction project is
level of the WBS. 20% complete and to worsen as far as the project progresses from
This WBS approach and the connection of the progress that point in time. Adjustments are typically undertaken for im-
spreadsheets to the project control software enable handy prepa- proving the cost performance late at the end of the construction
ration of various summary reports. In particular, on a monthly effort. The report also demonstrates that the SPI is not a steady
basis, by executing a specific command implemented on the and reliable indicator from the point in time the project is 20%
project software, the percent progress of a work package calcu- complete.
lated on the spreadsheet file is used to update the percent com- The job progress report at the first level of the WBS 共area
plete attribute of the corresponding work package in the WBS. As codes兲 is also a useful tool for making adjustments to the se-
a result, the contractor is paid the lump-sum price multiplied by quencing of construction operations basically aimed at meeting
the monthly top-level project aggregated percent progress. This contract milestones. The chart below 共Fig. 6兲 helps detect where
amount of money can be also reported by WBS level 共e.g., by job the delay is more important and in which area of the facility the
categories or areas兲 as the summation of each work element bud- job is ahead of time.
get multiplied by the associated percent progress.
Cost and Time Estimates at Completion
EV and Performance Reporting
Based on progress statusing and EV reporting, cost and time es-
Even though the site opens in June, the effective construction timates at completion are calculated at each monthly review step
date is July 1st. During the first months, different conditions of using linear Eqs. 共1兲 and 共3兲. The results are displayed in Table 3.
the rooftop than specified and the need of using helicopters for For example, in September, when the WP progress is far 20.76%
removing the existing roof slabs in specific nighttime slots re- and the ACWP is worth 21.32% of the original budget, it is esti-
quire to make a change order that affects both cost and duration. mated a 2.02% cost overrun to project completion. In fact
Also, other minor design additions are ordered and executed
with no extra time and cost, as a compensation of works that are EAC 共as a fraction of original budget兲
taken out of the original scope. After the September 30th pro-
ject status assessment, the agency project team, the contractor, = BAC/CPI = 100%/0.974 . . . = 102.76% of BAC
and the owner made a major project review for understanding
the causes of delay and taking corrective actions to face the esti- With Eq. 共4兲, the resulting EAC raises to 113.6% of the original
mated time overrun at completion. As a result, since the project budget. These values are considered as the lower and upper bound
targets are negotiated to be not revised, the contractor expedites cost estimates.
Similarly, at the end of September, since the planned project in Eq. 共5兲, where K, C, and h are parameters researched as to fit
duration is 189 days, linear Eq. 共3兲 allows for calculating a 38-day the historical curve of the WP, as cumulated so far. Table 4 pro-
estimated time overrun to completion. Since the CPI tends to vides the logistic-based estimated work progress resulting from
stabilize when the project is 20% complete 共Fig. 7兲, EAC are setting the logistic curve parameters that better interpolates the
reliable only after that point in time. past series of WP data with regard to the project development up
Likewise, TEAC are consistent if calculated when the pro- to September 30th, namely, K = 1.05; C = worth 100; and h = 1.06.
ject is between 20 and 70% complete, to avoid any wrong usage In a general logistic equation, the parameter K is defined as
of the SPI. In fact, the analysis of the SPI trend along the pro- “carrying capacity” because it is the upper limit of the variable
ject development as reported in Fig. 7, demonstrates that index- growth, and this usually equals to 1, referred to as 100%. As far
based calculations that are produced late into the project may as the progress variable is concerned in Eq. 共5兲, project managers
result in an underestimation of the expected project duration be- would expect that K = 1 because 100% is the total work to be done
cause the BCWP tends to equal the BCWS as the project activi- for finishing the project, unless variations are made to the size
ties unfold. of the original total scope of work. In reality, it is necessary that
With the purpose of ameliorating the duration EAC, the K ⬎ 1 for not having a mathematical upper limit, which does not
project controller makes also logistic-curve-based calculations as simulate a point in time when the project can be finished. With
AREA 001 002 003 004 005 006 007 008 009 010 011 012 013 014 015 016 017 018 019
Work scheduled 20% 36% 36% 36% 37% 36% 20% 20% 60% 59% 36% 36% 36% 43% 20% 20% 20% 20% 20%
Work performed 57% 10% 27% 3% 3% 24% 1% 49% 57% 78% 16% 18% 4% 6% 2% 2% 0% 0% 14%
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
001 002 003 004 005 006 007 008 009 010 011 012 013 014 015 016 017 018 019
WS WP
Fig. 6. Job progress reporting with comparison of WP versus WS by main areas of the facility layout
0,9
0,8
0,7
0,6
0,5
Downloaded from ascelibrary.org by National Cheng Kung University on 08/26/14. Copyright ASCE. For personal use only; all rights reserved.
0,4
0,3
0,2
jun jul aug sept oct nov dec jan
CPI SPI
this value, the modeler would rather simulate a so-called 90% completion, but it may be awkward for the cost. In fact, one
completion syndrome 共Sterman 1992兲. Here, K = 1.05 to return the should use Eq. 共5兲 for simulating the ACWP variable behavior,
“5% Finishes 共Work Item Z兲” assumption. In a construction rather than the WP, and should establish the value of K as the
project, a residual of 5% of scope is typically delivered at sub- maximum limit of actual cost at completion, which is the same
stantial completion. unknown variable the modeler wishes to estimate.
With regard to the other parameters of the equation, C is the
total percent original scope to be performed 共100兲, and h is then
determined by imposing WP percent progress values to fit the Findings and Results
logistic equation. The curve-fitting parameter is obtained by reit-
eration as to minimize the summation of square differences be- Table 5 compares index-based and logistic-curve cost and time
tween the logistic-based estimate and the actual percent EAC with the final actual cost and duration of the project that is
progresses: ⌬2, where ⌬ equals the logistic-based estimate percent recorded on the completion date January 28, 2008. The estimates
progress minus the actual percent progress 共see Appendix兲. The are the ones calculated at the September 2007 project review,
curve is then qualitatively validated by comparison to actual when the progress is approximately 21% and the project is two
progress S-curves of past similar projects. The resulting curve is a and a half months into the construction period and four months
good approximation of the past WP line that can be used to esti- before actual completion. This example proves that estimates are
mate the work progress trend to completion and the related reliably predicted at the point in time the project actual progress is
project actual completion 共Fig. 8兲. 20% complete. The report also shows that nonlinear time esti-
With the logistic equation, time overrun is calculated within 29 mates gives a better indication of the total duration of the project
days, less than the one determined using index-based linear esti- at completion because the logistic-equation allows for overcom-
mates. The logistic method is suitable for estimating time at ing the SPI bias.
Table 4. Project Actual Completion Estimated with Alternative Index-Based and Logistic-Based Method
100,00%
80,00%
WS
logistic-based work progress estimate
60,00% WP
index-based work progress estimate
Downloaded from ascelibrary.org by National Cheng Kung University on 08/26/14. Copyright ASCE. For personal use only; all rights reserved.
40,00%
20,00%
0,00%
jun jul aug sept oct nov dec jan feb
More important is the practical implication and the usefulness sufficient time buffer was included into the original schedule to
of performance assessment and estimates to the project team for meet the original deadline.
undertaking control actions. The recovery from cost overruns in As a result, a survey carried out to assess feedback on the
the last months of construction 共see the CPI oscillation in Fig. 7兲 project monitoring method indicated a good level of satisfaction
was directed because of the predictions in the previous months, by the owner with specific regard to timeliness and reliability of
and this involved both scope and quality changes, such as cutting data. Moreover, the contractor showed even larger satisfaction on
corners of some components of electrical equipment, and level of the usefulness and fairness of the method: the contractor defi-
finishes in some service spaces of the facility. nitely benefitted from a system that was originally designed for
controlling the project from the owner’s perspective.
Lessons Learned
Conclusions
The case method used for tracking and estimating the project cost
and time at completion was successful with regard to several With reference to the case of an industrial building project, this
aspects. First, the measurement of the scope progress as com- paper proposes a method for effective monitoring of progress as a
pleted work items for modular units of space enabled standard- process of milestone assessment of layout portions of work com-
ized site inspection and ongoing quality assurance of the WP, for pleted. Based on progress recording, it is demonstrated that linear
a short and prompt final acceptance of the project. Also, the estimates at completion are a reliable source of information for
granularity of the work item proved to give sufficient information project cost control from the point in time the project is 20%
while avoiding an expensive progress measurement task of con- complete and that time at completion is better estimated with the
struction detailed activities. usage of a logistic model.
Second, despite 2.40% of final cost overrun and approximately The proposed method is a way of overcoming the traditional
11% of time overrun, the owner was still satisfied with the project assessment of project linear performance. The linear approach is a
outcomes because of the reliability of the monitoring metrics and useful simplification of the behavior of organizational systems;
process in predicting and communicating any possible deviations this does not take into account the combined action of the several
from the contract targets far ahead of the contract deadline. Fi- actors of a complex project, the rework and feedback that typi-
nally, the reliability of the performance monitoring and forecast- cally delay the project development 共Sterman 1992兲. The S-curve
ing system was an important factor for the project team to force is a better representation of such delayed effects affecting produc-
expediting construction, regardless of the contractor’s belief that a tivity and work rate late into the project. Also, the method is a
Table 5. Comparison between Estimates and Final Actual Cost and Duration
Index-based estimates Logistic estimates Actual completion
Cost 共as % of budget兲 from 102.76 to 113% — 102.40%
Duration 共planned 189 days兲 227 days 219 days 212 days
Time overrun 38 days 29 days 22 days
Completion date 共planned January 5th兲 February 12th February 3rd January 28th
handy compromise between forecast reliability and data availabil- Construction Industry Institute 共CII兲. 共2004兲. Project control for construc-
ity and management. Further research is in the field of regression- tion, CII, Austin, Tex.
based calculation of the logistics equation and in analyzing Eldin, N. N. 共1989兲. “Measurement of work progress: Quantitative tech-
additional feedbacks that typically affect cost and time overruns. nique.” J. Constr. Eng. Manage., 115共3兲, 462–474.
Fleming, Q. W. 共1991兲. “Earned schedule in action.” Cost/schedule
control systems criteria: The management guide to C/SCSC, K.
Acknowledgments Henderson, ed., Probus, Chicago.
Henderson, K. 共2005兲. “Earned schedule in action.” 具http://sydney.
pmichapters-australia.org.au/programs/customer/v_filedown.asp?P
This study is part of a review of construction best practices in ⫽31&FID⫽789354132&ERF⫽n&典 共June 24, 2008兲.
Italy by the Engineering Systems Research Group of Politecnico Hendrickson, C. 共1998兲. “9. Construction planning.” 具http://pmbook.ce.
di Torino. For this case, the writers acknowledge the owner, Fiat cmu.edu/09_Construction_Planning.html典 共Aug. 29, 2008兲.
Partecipazioni S.p.A., for permission of publication and the con- Jung, Y., and Woo, S. 共2004兲. “Flexible work breakdown structure for
struction manager IdEst S.r.l. for support. integrated cost and schedule control.” J. Constr. Eng. Manage.,
130共5兲, 616–625.
Lipke, W. 共2005兲. “Connecting earned value to the schedule.” Crosstalk:
Appendix J. Defense Software Engineering, November 2006, 26–30.
Nepal, M. P., Park, M., and Son, B. 共2006兲. “Effects of schedule pressure
on construction performance.” J. Constr. Eng. Manage., 132共2兲, 182–
Table 6 shows the logistic curve-fitting determination of the
188.
h parameter. The bottom line is a monotone curve with a sole
Oberlender, G. D. 共1993兲. Project management for engineering and con-
minimum point corresponding to the appropriate value of the
struction, McGraw-Hill, New York.
parameter. Project Management Institute. 共2005兲. Practice standard for earned value
management, McGraw-Hill, Newtown Square, Pa.
Riggs, L. S. 共2004兲. “Cost and schedule control in industrial construc-
Notation tion.” CII, Austin, Tex.
Ritz, G. J. 共1994兲. Total construction project management, McGraw-Hill,
The following symbols are used in this paper: New York.
D ⫽ planned duration; and Sterman, J. D. 共1992兲. “System dynamic modeling for project manage-
T ⫽ time, referred to as the date of actual measurement. ment.” 具http://web.mit.edu/jsterman/www/SDG/project.html典 共Mar.
10, 2008兲.
U.S. Dept. of Energy 共DoE兲. 共1980兲. “Cost and schedule control systems
criteria for contract performance measurement. Implementation
References guide.” DoE, MA-0087, May.
Weisstein, E. W. 共1999兲. “Logistic equation.” 具http://mathworld.wolfram.
Christensen, D. S. 共1996兲. “Project advocacy and the estimate at comple- com/LogisticEquation.html典 共Sept. 1, 2008兲.
tion problem.” J. Cost Analysis Management, Spring, 61–72. Winch, G. M. 共2002兲. Managing construction projects, Blackwell, Ox-
Christensen, D. S. 共1999兲. “Using the earned value cost management ford, U.K.
report to evaluate the contractor’s estimate at completion.” Acquisi- Woodward, J. F. 共1997兲. Construction project management getting it right
tion Rev. J., Acquisition University DAU Publications, 283–295. first time, Thomas Telford, London.
Christensen, D. S., Antolini, R. C., and McKinney, J. W. 共1995兲. “A Yang, Y. C., Park, C. J., Kim, J. H., and Kim, J. J. 共2007兲. “Management
review of estimate at completion research.” J. Cost Analysis Manage- of daily progress in a construction project of multiple apartment build-
ment, Spring, 41–62. ings.” J. Constr. Eng. Manage., 133共3兲, 242–253.