Professional Documents
Culture Documents
Abstract: Detailed schedules are essential in the development of project baselines; they are needed for tracking and progress reporting,
as well as for the administration of construction disputes. Thus, it is necessary to ensure the fitness for purpose of these schedules. Presented
Downloaded from ascelibrary.org by UNIVERSITY OF PITTSBURGH on 01/20/15. Copyright ASCE. For personal use only; all rights reserved.
in this paper is a structured method to assist owners or their agents in reviewing and evaluating detailed schedules submitted by contractors.
The method is developed making use of related knowledge extracted from the literature and augmented by expert opinions gathered from
an online questionnaire survey and structured interviews. A composite index is introduced to evaluate the overall level of schedules’ fitness
for purpose, taking into account the level of importance of each evaluation criterion. The method was implemented in a software applica-
tion to facilitate its use. Schedules of three actual and one hypothetical projects are analyzed to demonstrate the essential features of the
developed method and to highlight its capabilities. In addition, an empirical method is developed to review job logic, making use of in-depth
analysis of the data collected from the schedules of three building construction projects. DOI: 10.1061/(ASCE)LA.1943-4170.0000142.
© 2014 American Society of Civil Engineers.
Author keywords: Schedule audit; Schedule evaluation; Schedule review and assessment; Schedule development checklist.
articles and conference proceedings, and (3) recommended prac- activities, negative float).
tices and guides developed by professional organizations and The defined criteria were grouped into two major categories:
government agencies. The criteria presented here are not intended (1) obligatory and (2) complementary. Each schedule must sat-
to be exhaustive; rather, the intention was to avoid trivial criteria isfy the obligatory criteria of contractual compliance, acceptable
and incorporate frequently disregarded criteria in terms of clarity job logic (respecting the sequence of construction tasks), and
and practicality. Following a careful examination and review of reasonable activity duration (accounting for scope of work and pro-
the literature, an initial draft of 67 provisions was prepared with ductivity of crews involved). A schedule that does not satisfy any of
the aim of refining and clustering them in the next step (Moosavi these criteria is considered failed or unacceptable. The complemen-
2012). To ensure that the defined criteria are to the point, practical, tary category encompasses recommended criteria for consideration
and clear to construction professionals, 20 sessions of structured while reviewing schedules. Thus, if a schedule is able to satisfy the
interviews were conducted (Moosavi 2012). The results led to obligatory criteria, the evaluation process continues, using the com-
the use of 48 schedule assessment criteria, clustered as shown plementary criteria, to examine to what degree it satisfies its fitness
in Fig. 1. The defined criteria assess schedules from different for purpose. A detailed description of the criteria and its construc-
perspectives including: tion can be found in Moosavi (2012).
Obligatory Criteria
to elicit his feedback on the developed method and the defined rules and the HVAC trade was started when framing was 55% complete.
through a structured interview (Moosavi 2012). The interview The expert stated that the successor trades could start sooner
revealed general agreement between the expert’s assessments and (i.e., using larger overlaps) and that typically when foundation is
those generated by the developed methods; except for the over- 30% complete framing can start. He also added that the HVAC
laps between foundation and framing trade, between framing and trade could start when framing was 30% complete and the curtain
curtain wall trade, and, finally, between framing and HVAC trade. wall trade could start when the framing of three floors was done.
Analysis of the three cases showed that the framing trade was The final result was a set of rules for the assessment of the job logic
started when the foundation was 70% complete. Also, the curtain of schedules developed for educational building construction
wall trade was started when framing of five floors was completed, (Table 3). Application of these rules helps users to quickly gain an
(VB) and performs three tiers of schedule assessment: (1) assess- with MSP 2007. Thus, if a schedule is developed using other sched-
ment of schedules against industry benchmarks, (2) job logic as- uling software, it should first be converted to MSP format.
sessment of selected construction trades, and (3) assessment of In its first tier of assessment, SAE automatically calculates 14
productivity and crew size considered for a number of commonly quantitative schedule assessment metrics and compares the results
used trades in building construction. SAE consists of three main to industry benchmarks (Moosavi 2012). These include the total
modules: a user interface, coded using VB, to facilitate data entry; number of activities, total number of critical activities, criticality
an assessment engine to evaluate schedules, which was coded rate (number of critical activities divided by total number of activ-
using VB application (VBA) for Microsoft Project (MSP); and a ities), near criticality rate (number of near critical activities divided
with critical activities divided by total project cost), project effort activities to those stored in the developed database. If SAE finds
ratio [critical path effort (number of labors) divided by total project any disagreement of more than 30%, the ID and name of related
effort], number of activities with out-of-range duration, number of activities will be listed in the generated assessment report and high-
critical activities with out-of-range duration, number of activities lighted directly on the schedule under review. It should be noted
with out-of-range total float, activities with negative total float, that the default value of 30% used here can be revised.
open-ended activities (activities with no predecessor or successor),
total number of constraints, total number of relationships, and re-
lationships per activity. It is noteworthy to indicate that while the Case Examples
user can modify the float value that renders activities near critical, it
was set at 10 days (O’Brien and Plotnick 2010) as a default value. To demonstrate the use of the developed method and its com-
After conducting this level of assessment, SAE reports the cal- puter application, schedules of four case examples, including three
culated metrics and lists the activities with out-of-range attributes actual projects (Projects A, B, and C) and one hypothetical project
in the assessment report and highlights these activities directly on (Project D), were analyzed. The three case examples were also
the schedule being evaluated. The software also presents a set of assessed by the DCMA 14-Point method and the results compared.
recommendations for corrective action based on the analysis per- The three actual projects are three institutional buildings con-
formed. A typical report for the first tier of assessment is presented structed for Concordia University in Montreal, Canada. These proj-
in Fig. 5. ects are buildings located in the two campuses of the University in
The next level of assessment focuses on the job logic of Montreal. The hypothetical schedule is a built-in template provided
schedules. For this purpose, a set of typical activities associated by MSP 2007. This schedule was merely used to test the second
with reinforced concrete framing of building construction was and third tiers of schedule assessment, evaluating job logic and the
incorporated into the developed software application, including rationale behind productivities and crew sizes. The characteristics
typical relationships among them. These relationships are devel- of these projects are summarized in Table 4.
oped based on the sequence of work for a set of common activities The schedules of the three real projects were assessed based on
in building construction. At this level of assessment, the assessment the developed method of schedule assessment and its software ap-
engine reads activity names and recognizes the defined keywords plication, which is mainly concerned with quantitative evaluation
(e.g., rebar, which represents a rebar installation activity). After- criteria. These schedules were reviewed to determine the assess-
wards, actual relationships for recognized activities would be com- ment provisions that they satisfy. At the end of the assessment pro-
pared by the necessary predecessors and successors (e.g., rebar cess, the SDI (the total sum of weights of the satisfied provisions)
A received a SDI of 562 (out of 1,000), while Schedules B and C high total float, and (4) the schedules were not loaded with resour-
received 441 and 327, respectively (Moosavi 2012). There was a set ces. In addition, Schedule C had several activities with leads in their
of common deficiencies among the three cases. As a result, the relationships and a multitude of open-ended activities (Moosavi
schedules were unable to satisfy the criteria pertinent to Resource 2012). The results of assessments are summarized in Table 5.
Loading, Responsibility Assignment, Trade’s Peak Resource Load- To test the second and third tiers of assessment, the hypothetical
ing, Peak to Average Labor Ratio, Duration of Critical Activities, schedule was used since the actual projects were not developed
Project Cost Ratio, Project Effort Ratio, Lag Duration, Open-Ended at the required level of detail. Thirty schedule activities regarding
Activities, Activities Float, and others (Moosavi 2012). Thus, these concrete framing were subject to job logic assessment. To test the
schedules lost approximately 400 points. In addition, Schedules B developed software application, the dependencies among 10 activ-
and C were unable to satisfy Critical Path, Constraints, Permits and ities (out of 30 activities) were deliberately revised by deleting
Environmental Remediation, Relationship Ratio, and Submittals the necessary predecessors and successors (Moosavi 2012). For
Review criteria (Moosavi 2012). This is because those schedules instance, the necessary relationships between form work activities
were found to have excessive application of constraints, no inclu- and pour concrete activities were deleted. Then the automated job
sion of obtaining permits and review of submittals activities, and an logic assessment was performed. The software was able to high-
abnormally high activity relationships ratio. Fig. 6 shows a snap- light the 10 activities with faulty job logic. The activities associated
shot depicting the analyzed critical path for Project C. The differ- with the framing trade for the first and third floors were randomly
ence between the SDI of Projects B and C originated from four selected to perform the third tier of assessment, which performs
57 Pour 2nd floor slab 4 days Jul. 3, 2007 Jul. 6, 2007 Pour 2nd floor slab
58 Cure 2nd floor slab 7 days Jul. 9, 2007 Jul. 17, 2007 Cure 2nd floor slab
59 Strip forms from 2nd floor slab 2 days Jul. 18, 2007 Jul. 19, 2007 Strip forms from 2nd floor slab
60 Form 3rd floor including all floor openings 5 days Jul. 18, 2007 Jul. 24, 2007 Form 3rd floor including all floor openings
61 Install rebar and in-floor utilities (including mechanical, 5 days Jul. 18, 2007 Jul. 24, 2007 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
electrical, plumbing)
62 Pour 3rd floor slab 4 days Jul. 25, 2007Jul. 30, 2007 Pour 3rd floor slab
63 Cure 3rd floor slab 7 days Jul. 31, 2007 Aug. 8, 2007 Cure 3rd floor slab
64 Strip forms from 3rd floor slab 2 days Aug. 9, 2007 Aug. 10, 2007 Strip forms from 3rd floor slab
65 Form roof slab including all floor openings 5 days Aug. 9, 2007 Aug. 15, 2007 Form roof slab including all floor openings
66 Install rebar and in-floor utilities (including mechanical, 5 days Aug. 9, 2007 Aug. 15, 2007 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
electrical, plumbing)
67 Pour roof slab 4 days Aug. 16, 2007 Aug. 21, 2007 Pour roof slab
68 Cure roof slab 7 days Aug. 22, 2007 Aug. 30, 2007 Cure roof slab
69 Strip forms from roof slab 2 days Aug. 31, 2007 Sep. 3, 2007 Strip forms from roof slab
70 Form 1st floor 4 days Jul. 20, 2007 Jul. 25, 2007 Form 1st floor
71 Install electrical underground 1 wk Jul. 20, 2007 Jul. 26, 2007 Install electrical underground
72 Install plumbing underground 1 wk Jul. 20, 2007 Jul. 26, 2007 Install plumbing underground
73 Install rebar and in-floor utilities 4 days Jul. 20, 2007 Jul. 25, 2007 Install rebar and in-floor utilities
74 Pour 1st floor slab 4 days Jul. 27, 2007 Aug. 1, 2007 Pour 1st floor slab
75 Cure 1st floor slab 7 days Aug. 2, 2007 Aug. 10, 2007 Cure 1st floor slab
76 Strip forms from 1st floor slab 2 days Aug. 13, 2007 Aug. 14, 2007 Strip forms from 1st floor slab
Fig. 7. Schedule D after third tier of assessment (activities with faulty attributes highlighted)
Conclusion
13(5), 665–678.
The authors would like to thank Mr. Peter Bolla, Associate Government Accountability Office (GAO). (2009). “GAO cost estimating
Vice President and Director of Concordia University’s Facilities and assessment guide, best practices for developing and managing
Management Department, for providing the schedules used in capital program costs.” GAO-09-3SP, GAO, Washington, DC.
the case study, as well as all the professionals who kindly donated Moosavi, S. F. (2012). “Assessment and evaluation of detailed schedule in
their time and participated in the questionnaire survey. building construction.” Master’s thesis, Concordia Univ., Montreal.
Moosavi, S. F., and Moselhi, O. (2012). “Schedule assessment and evalu-
ation.” Proc., 2012 Construction Research Congress, ASCE, Reston,
References VA, 535–544.
National Defense Industrial Association (NDIA) Industrial Committee
Berg, E., Cervantes, R., Johnson, K., Marks, C., and Yoo, A. (2009). “IMP/ for Program Management (ICPM). (2011). Planning and scheduling
IMS training: Integrated master plan/integrated master schedule basic excellence guide (PASEG).” Working draft v1.1b—Public release,
analysis.” Schedule analysis, Revision 21NOV09, U.S. Dept. of NDIA, Arlington, VA.
Defense, Defense Contract Management Agency, Washington, DC. O’Brien, J., and Plotnick, F. (2010). CPM in construction management,
Bingham, E. (2010). “Development of the project definition rating index 7th Ed., McGraw Hill, New York.
(PDRI) for infrastructure projects.” Master thesis, Arizona State Univ., Project Management Institute (PMI). (2007). Practice standard for
Tempe, AZ. scheduling, 1st Ed., Newtown Square, PA.
Cho, C. (2000). “Development of project definition rating index (PDRI) for RSMeans. (2009). RSMeans building construction cost data, Kingston,
building projects.” Ph.D. thesis, Univ. of Texas, Austin, TX. MA.