1. Earned value management (EVM) directly links the three primary project success metrics of cost, schedule, and performance by considering their joint impact on project status.
2. EVM establishes project baselines by defining the work breakdown structure and time-phased project budget.
3. EVM offers top management an excellent view of a firm's ability to efficiently run projects through portfolio tracking and control using earned value.
1. Earned value management (EVM) directly links the three primary project success metrics of cost, schedule, and performance by considering their joint impact on project status.
2. EVM establishes project baselines by defining the work breakdown structure and time-phased project budget.
3. EVM offers top management an excellent view of a firm's ability to efficiently run projects through portfolio tracking and control using earned value.
1. Earned value management (EVM) directly links the three primary project success metrics of cost, schedule, and performance by considering their joint impact on project status.
2. EVM establishes project baselines by defining the work breakdown structure and time-phased project budget.
3. EVM offers top management an excellent view of a firm's ability to efficiently run projects through portfolio tracking and control using earned value.
CHAPTER 13- PROJECT EVALUATION AND CONTROL o The S-curve also provides real-time tracking information Milestone in one
formation Milestone in one form or another, are probably the
in that budget expenditures can be constantly updated simplest and most widely used pf all project control Elements of Control Cycles and the new values plotted on the graph devices 1. Setting a goal The problem with them is that, like S-curves, they are S-Curve Drawbacks - Project goal setting goes beyond overall scope reactive control system development to include setting the project baseline 1. S-curve can identify positive or negative variance The problem is compounded plan (budget expenditure above or below projections) but 2. Measuring Progress Tracking Gantt Chart they do not allow us to make reasonable interpretation as - Effective control systems require accurate project to the cause of variance Is useful for evaluating project performance at specific measurement mechanisms 2. They are providing “reactive” data; that is we plot the point in time 3. Comparing Actual with Planned Performance result of expenditures after the money has already been The tracking Gantt chart allows the project team to - Comparing actual with planned performance. When spent constantly update the project’s status by linking task we have some sense of the original baseline (plan) completion to the schedule baseline and a method for accurately measuring progress, the Milestone Analysis It is also possible to measure both positive and negative next step is to compare the two pieces of information - A milestone is an event or stage of the project that deviations from the schedule base line with the tracking 4. Taking Action represents a significant accomplishment on the read Gantt chart - One we detect significant deviations from the project to the project’s completion plan, it become necessary to engage in some form of Benefits & Drawbacks of Tracking Gantt Charts corrective action minimize or remove the deviation Several Benefits to using milestone as form of Project Control: A key benefit of tracking Gantt chart is that they are Monitoring Project Performance quite easy to understand 1. Milestone signal the completion of important project This type of control chart can be updated very quickly, steps providing a sense of real-time project control 2. Milestone can motivate the project team It is difficult to accurately estimate the time to 3. Milestone offer points at which to reevaluate client needs completion for project, particularly in the case of and any potential change request significant positive or negative variation from the 4. Milestone help coordinate schedule with vendors and baseline suppliers 5. Milestone identify key project review gates Earned Value Management 6. Milestones tell other team members when their An increasingly popular method used in project participation is expected to begin monitoring and control consists of a mechanism The Project S-Curve: A basic tool 7. Milestone can delineate the various deliverables developed in the work Breakdown Structure thereby EVM has been practiced in multiple settings by agencies o To determine project performance and status, a enable the project team to develop a better overall view from governments as diverse as Australia, Canada, and straightforward time/cost analysis is often our first of the project Sweden, as well as by a host of project-based firms in choice numerous industries o Monitoring the status of a project using S-curve become Problems with Milestone EVM recognizes that it is necessary to jointly consider a simple tracking problem the impact of time, cost, and project performance on any o Simplicity is the key benefit of S-curve analysis analysis of current project status. We can illustrate the advance in the project control 3. The use of earned value management for portfolio process that Earned Value Management represents by tracking and control offers top management an excellent comparing it to the other project tracking mechanisms. window in the firm’s ability to efficiently run projects Earned value (EV), on the other hand, directly links all Creating Project Baselines Flow of Earned Value System three primary project success metrics (cost, schedule, and performance). Baseline information is critical regardless of the control - Earned value begins early at North Grumman process we employ, but baselines are elemental when project. In fact, there is a “flow” to the EVM system performing EVM. o Proposal Stage – the specifics of the The actual steps in establishing the project baseline are program are determined at this stage fairly straightforward and require two pieces of data: o Contract award – when North Grumman is o Work Breakdown Structure – identified the selected as the successful contractor, all individual work packages and tasks necessary to critical elements and requirements of the accomplish the project project are defined o Time-Phased Project Budget – takes the WBS o Baseline stage – once the preliminary scope one step further: It allows us to identify the and deliverables have been agreed to correct sequencing of tasks, but more between the contractor and the client, the importantly it enables the project team to detailed planning, project schedule, and determine the points in the project when budget formal work authorization is developed money is likely to be spent in pursuit of those o Maintenance phase – once the project Terminologies for Earned Value tasks. baseline is established and formally signed Steps in Earned Value Management off by key parties, the project passes top\ the monitoring and control stage, where the key 1. Clearly define each activity or task that will be advantage of EVM are clearly realized performed on the project, including its resource needs as well as detailed budget Issues in the Effective use of EVM 2. Create the activity and resource usage schedules 0/100 – the simplest and perhaps least effective method 3. Develop a ‘time-phase” budget that shows expenditures requires that a project activity be assigned a value of across the project’s life zero until the point activity is finished, at which time 4. Total the actual costs of doing each task to arrive at the value switches to 100% actual cost of work performed 50/50 rule – under this decision rule, an activity that has 5. Calculate both a project’s budget variance and schedule been started automatically receives a valuation of 50% variance while it is still in process completed Using Earned Value to Manage a Portfolio of Projects Percentage complete rule – the project manager and team members mutually agree on a set of completion 1. Earned value management can work at the portfolio level milestones, whether they are based on quarters, thirds, or as well as with individual projects some other values 2. Portfolio earned value management table includes the total positive variances for both budget and schedule Human Factors in Project Evaluation & Control Another recurring problem with establishing accurate or The 10 critical success factors represent an important, meaningful EVM results has to do with the need to supplemental source of information on the project’ s recognize the human factor in all project activity status. completion projections. Critical Success Factor Definitions The common feature of control approaches is their reliance on measurable data based on project outcomes; 1. Project mission – relates to the underlying purpose for A key component of any process evaluation of project the project performance must include an assessment of its people, 2. Top management support – has ling been considered of their technical skills, management, teamwork, great importance in distinguishing between ultimate communication processes, motivation, leadership, and so success and failure forth. 3. Project plans and schedules – refers to the importance of Past research examining the impact of human factors on developing a detailed plan of the required stages of the project success bears out the importance of considering implementation process the wider management challenge inherent in managing 4. Client consultation – the “client” is anyone who projects. Included in their list were issues such as: ultimately will be using the product of the project, either o Project coordination and relations among as a customer outside the company or as a department stakeholders within the organization o Adequacy of project structure and control 5. Personnel – includes recruitment, selection, and training o Project uniqueness, importance, and public of project team members exposure 6. Technical task – refers to the necessity of having not o Success criteria salience and consensus only required numbers of personnel for the o Lack of budgetary pressure implementation team but also ensuring that they passes o Avoidance of initial overoptimism and the technical skills and the technology and technical support needed to perform their task conceptual difficulties 7. Client acceptance – refers to the final stage in the project Their findings bear out the importance of having a clear development process, at which time the overall efficacy knowledge of the managerial challenges involved when of the project is to be determined implementing projects 8. Monitoring & feedback – refers to the project control The findings of such research are intriguing because of process by which key personnel receive feedback at each the importance they place on the managerial and human stage of the project implementation on how the project is behavioral aspects of project management for project progressing compared to initial projections success. 9. Communication – is not only essential within the One of the key recurring problems, however, with projects team itself, but also vital between the team and making wider use of nontechnical information as a the rest of the organization as well as with clients method for controlling projects and assessing their 10. Troubleshooting – problem areas exist in almost every ongoing status lies in the question of measurement project development. The measure of a successful The work of Pinto and Slevin13 addresses the project is not the avoidance of problems, but taking the shortcomings with behavioral assessments of project correct steps once problems develop management processes.