MANAJEMEN PROYEK
Firmanto Hadi
Oktaviani Turbaningsih
Project Schedule
Calculate productivity
Calculate work each activities and
Scheduling in project management is the listing of activities, deliverables,
volume or activities estimate duration for
and milestones within a project. A schedule also usually includes a each activities
planned start and finish date, duration, and resources assigned to each
activity. Effective project scheduling is a critical component of successful
time management.
PROJECT YES
SCHEDULE
C.6 Pemasangan
B.1.2.3 Pengurugan B.1.3.3 Armor B.2.4 Pengecoran B.3.4 Pengecoran ship loader
tahap 2 Layer 1 join beam trestle join beam jetty
B.2.6 B.3.5
B.1.3.5 Filter Layer
2 Pemasangan lantai Pemasangan lantai
trestle jetty
5m m
12. 12
6m
= (120x12)/(3x1.2)
= 400 unit
6m 6m
20 cm
120 cm
Information required
1 A1. Direksi keet 7 hari
Activities Duration
✓ Group of work/activities
✓ Duration for each 2 A2. Pengukuran 15 hari
activities 3 A3. Mobilisasi 15 hari
✓ Interdependencies for
each activities 4 B11. Pembuatan Kaisson 50 hari
Project