Professional Documents
Culture Documents
Mechanical Materials
Electrical Materials
Civil Materials
Handl/equip/cons
Summary Ove
Travel Expenses
MACHINERY
Rental Equipments
Site Facilities
Operation Cost
Safety Equipment
Health Expenses
GOSI
Others
Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16
3,200.00 10,700.00 88,537.00 38,760.00 157,673.50 0.00
55,567.00 68,471.00
26,798.00
800.00 19,070.00
11,756.00 9,848.00
3,554.00 1,089.00 13,174.00 6,548.00 3,679.00
100.00 791.91 252.65 1,237.70
10,000.00
5,100.00 2,550.00 2,550.00
791,646.32 791,646.32
200,986.80 200,986.80
249,666.33 249,666.33
66,850.00 66,850.00
126,140.86 126,140.86
29,430.00 29,430.00
88,073.68 88,073.68
180,808.11 180,808.11
15,015.00 15,015.00
2,382.26 2,382.26
13,442.00 13,442.00
1,267,815.55 1,267,815.55
122,747.30 122,747.30
3,155,004.21 3,155,004.21
Total Submitted Invoice ( SR ) -
Balance Amount ( SR ) 291,390,000.00
Project Status
Sep'16 Oct'16 Nov'16 Dec'16 2016 total
0.00 0.00 0.00 0.00 313,970.50
124,038.00
26,798.00
19,870.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
14,169.50
15,015.00
0.00
0.00
60,650.00
430.00
40,000.00
13,000.00
0.00 0.00 0.00 0.00 1,275,456.31
524,748.72
266,897.60
0.00
0.00
0.00
23,843.30
10,558.56
3,790.77
56,850.00
0.00
25,347.00
30,104.00
2,382.26
0.00
10,000.00
10,200.00
0.00
124,700.00
71,452.80
4,834.00
109,747.30
0.00 0.00 0.00 0.00 66,264.00
12,717.00
24,392.00
14,923.00
14,232.00
0.00 0.00 0.00 0.00 136,668.11
34,220.50
1,500.00
49,390.00
26,088.00
0.00
7,260.06
13,442.00
0.00
4,767.55
0.00 0.00 0.00 0.00 210,407.20
210,407.20
0.00
0.00
0.00 0.00 0.00 0.00 1,053,617.58
320,975.22
732,642.36
0.00
0.00 0.00 0.00 0.00 277,166.33
248,166.33
27,950.00
1,050.00
0.00 0.00 0.00 0.00 38,683.68
38,683.68
0.00 0.00 0.00 0.00 68,296.00
0.00
0.00
68,296.00
0.00 0.00 0.00 0.00 3,440,529.71
0.00
0.00 0.00 0.00 0.00 (3,440,529.71)
C1 For columns of Fluid Cooler Plant (Upto bottom level of beams 38.00 level) 420 m3 HAND & CONSTRUCTION 420
FEM-WJ-C2-016
D Concrete, fc'= 40Mpa FEM-WJ-C2-016
For columns of Fluid Cooler Plant 400 m3 HAND & CONSTRUCTION 400 FEM-WJ-C2-016
For beams of Fluid Cooler Plant 1,050 m3 HAND & CONSTRUCTION 1,050 FEM-WJ-C2-016
SECTION 5.00 - MISCELLANEOUS METAL WORK
A. Structural steel walkways for the fluid coolers 300 m HAND & CONSTRUCTION 300
B. External Ladder for for fluid coolers, reaching the walkways at 9.5m 4 No. HAND & CONSTRUCTION 4
C. Ladder 2.5m high for reaching walkway at 12.0m from 9.5m. 4 No. HAND & CONSTRUCTION 4
SECTION 7.00 - VAPOUR RETARDER
Vapour retarder under plain concrete (300 MIC, polyethylene) as per the
A 8 m2 HAND & CONSTRUCTION 8
specifications.
SECTION 7.01 - WATERPROOFING MEMBRANE
Waterproofing system comprising of two layers of reinforced bituminous
A 5,600 m2 HAND & CONSTRUCTION 8,000 127,200.00
waterproofing membrane 4.0 mm thick FEM-WJ-C2-032 (Delivered)
SECTION 7.02 -EXPANSION JOINT
Expansion joint at fluid coolers, complete including backing rod, filler,
A. HAND & CONSTRUCTION
sealant, aluminium covers all as per the specifications and drawings.
A1 For columns. 180 m2 HAND & CONSTRUCTION 180
A2 For beams. 180 m2 HAND & CONSTRUCTION 180
F.6 50 mm2 Bare Copper Wire (BCW) in 20 mm dia. PVC pipe for equipment 3,607.36
gounding including connections to existing equipment PEV bus bar. 200 m 200
G Concrete encased power duct bank
G.1 Duct bank 15-way, 160 mm, UPVC. 100 m 48,006.13 100
62,936.00 FEM-WJ-C2-009 (Delivery of Upvc Pipes)
G.2 Ditto but 8-ways. 20 m 5,120.65 20
H Reinforced concrete power manholes
H.1 Dimension 3 x 3 x 2.5 m. 1 no. 22,226.87 1
H.2 Dimension 3 x 3 x 2.5 m. 4 no. 88,907.49 4
I Furnishing and installation of 2 X 4 inches dia. uPVC pipe
I.1 uPVC pipe including excavation, backfilling, jointing and connection to
2,764.83
handholes 80 no. 80
A.2 Wiring and conduiting of all new additonal sensors, signals and controls to
BMS for the new mechanical equipment to new or existing DDC; verify with 1 lot 137,208.59
mechanical.
A.3 Wiring and conduiting of all new additonal sensors, signals and controls to
BMS for the new electrical equipment to new or existing DDC; Switchgears, 1 lot 205,030.67
transformers, MCCs, etc...
A.4 Programming of BMS System for the new additional sensors, signals,
1 lot HAND & CONSTRUCTION
controls and DDCs.
B. Electomagnetic flowmeters 450 mm for condenser lines including wiring,
conduiting, supports, accessories and terminations to controllers. 12 no. 533,889.57
SUBTOTAL 182,884,231.53
SUBTOTAL 25,459,618.47
SUBTOTAL -
TOTAL 208,343,850.00
SUBTOTAL 111,595,513.19
SUBTOTAL 1,586,056.17
SUBTOTAL 426,325.00
Consumable Materials Purely Matl's.(SAR)
SUBTOTAL 449,472.50
TOTAL 114,057,366.86
SUBTOTAL 3,300,196.39
SUBTOTAL 35,249,339.72
SUBTOTAL -
SUBTOTAL -
TOTAL 38,549,536.11
182,884,231.53
- 182,884,231.53
25,459,618.47
- 25,459,618.47
- -
- 208,343,850.00
on P.O's)
P.O's PRICE
111,595,513.19
- 111,595,513.19
1,586,056.17
- 1,586,056.17
426,325.00
- 426,325.00
449,472.50
449,472.50
- 114,057,366.86
114,895,709.58
36,835,395.89
426,325.00
449,472.50
152,606,902.97
Note: 1.) Profit & Risk Factor 18.5% to (BAC) Budget not included.
2.) Still have an expected cost raise up for Consumable Materials.
SUMMARY
0.00