# Epic Requirement

Jasper Server Pro Need be to Integrated to


1 Upgrading Jasper From 1.6.X to 7.5.1
Expense Application

Understanding Jasper Server Pro 7.5.1 WFM


3 upgrading Jasper server pro from 1.6.X to Build Deployment and configuration for
7.5.1
Expense
Story Task

Implemeting TestConnection Button


functionality in jasper.jspf file
As an admin , I should be able to assign and
unassigne jasper reports to users

Implementation of Discard Message Pop


for Configure JasperServer
Prepare excel sheet for tracking what the
pending task from expense application
end and jasper server end to complete
100% of project

Decide on Org Folder Structure


Daily Status - Date(10-01-2022)
Task Details

when jasper server details are configure admin should have a


ficility to check whether the jasper server is able to login

When Modified any field under configure jasper server tab


and clicked on close button on corporate settings page, we
should get discard message

list out all the pending task for the application completion

Check whether is possible to maintain the maintain the old


jasper orgnization structure in new Jasper pro also so that we
can avoid drill down URL changes in jrxml
Daily Status - Date(10-01-2022)
Estimate (in
subtask Priority JIRA#
hours)
Analyze WFM Code and check how they implemented
this task P1 NA 3
Check the possibilities to implement the same in P2 NA 10
expense application
Check Why configure Jasper Tab is not being checked in P3 NA
CorporateSetting page for draft message 1.5
Do required changes in body.jsp page related to P3 NA
JasperSection page 1

Create Folder Datatypes in Jasper pro server under


orgaganization and create datatypes from old jasper P1 NA 1
server in new jasper server
Create InputControls from old jasper server in new P1 NA 1
jasper server
Export DataTypes and InputControls and try to modify P1 NA 0.5
the js-pro-Sqlserver zip xml files
Status Start Date End Date Today's Effort  (in hrs)
In Progress 10/1/2022 10/1/2022 1.5
In Progress 11/1/2022 12/1/2022 0.5

Completed 10/1/2022 10/1/2022


1
Completed 10/1/2022 10/1/2022
0.5

Completed 10/1/2022 10/1/2022 1.5

Completed 10/1/2022 10/1/2022 1

Completed 10/1/2022 10/1/2022 1

Completed 10/1/2022 10/1/2022 0.5


Total Actual Effort (in hrs) Comments

3.5

1.5

Manual able to create those Datatypes

2.5
Meetings
1 Daily Meeting Ajoy
2 Meeting With Mounika Sreehari
2 hr
30 min
# Course Link Self Learning Item Self Learning Sub Item

056 Introducion
057 MIddleware
058 Creating Custom Middleware
059 Built-In Middleware
060 Third-party Middleware
061 Environments
1 https://codewithmosh.com/p/the- 05 Express- Advance062 Configuration
complete-node-js-course
063 Debugging
064 Templating Engines
065 Database Integration
066 Authentication
067 Structuring Express Applications
068 Project- Restructure the App
Self Learning
Estimate (in Effort Total Effort on
Status Start Date End Date
hours) (21.12.2021) the course

1 hr Completed 22/12/2021 23/12/2021 1 hr 7 hrs


Comments

Need to practice for some days