You are on page 1of 19

# Epic Requirement

1
Story Task

Working on lowes login to Backoffice


module issue
Daily Status - Date(07-02-2022
Task Details

Faceing below exception while trying to login to Back office in


lowes environemnt . In SQLException Block
ExceptionReportDAO load java.sql.SQLException: [FMWGEN]
[SQLServer JDBC Driver]The operation was cancelled at the
user's request.
- In SQLException Block ExceptionReportDAO load
___weblogic.jdbc.sqlserverbase.ddco.a(Unknown
Daily Status - Date(07-02-2022)
subtask
Estimate (in
Priority JIRA# Status Start Date End Date
hours)

P2 NA 6 In Progress 7/2/2022 7/2/2022


Today's Effort  (in hrs) Total Actual Effort (in hrs)

6 6
Comments

Weblogic JTA Timeout happening when loading documents for audit. Shared
my analysis to Mounika, as requested to help on the Stored proc
ne_listExpenseReportLine
Daily Status - Date(20-01-2022)
# Epic Requirement

Jasper Server Pro Need be to Integrated to


1 Upgrading Jasper From 1.6.X to 7.5.1
Expense Application

2
Story Task

As admin ,I should be able to Manage reports Implementing Search By and pagination


assignment for users functionality on UserJasperReports page

Story#2, Story#3 first level CodeReview


with ajay
Task Details

when admin is on userJasperReports page admin should be


able to search user by usernumber, username and data should
be dispplayed in paginatoin
subtask

Analyze ExpenseTypeFilter , document page handler, ExpeseTypeManager classes used in Expensetype page
Implement Filter, page handler, Manager classes for userJReprotsmapping page
Do necessary changes in ManageJasperReportsMappingAction wrt Implemented filter, pagehandler and manager
classess
Do change for mappingjasper\list.jsp for search bar and pagination implementation
Deployment and checking and corrections
Estimate (in
Priority JIRA# Status Start Date End Date
hours)
P2 NA 8 Completed 17/1/2022 17/1/2022
P2 NA 24 Completed 18/1/2022 20/1/2022
P2 NA
16 In Progress 21/1/2022 24/1/2022
P2 NA 8 In Progress 25/1/2022 25/1/2022
P2 NA 16 In Progress 27/1/2022 28/1/2022
P1 NA 2 In Progress 20/1/2022 19/1/2022
Today's Effort  (in hrs) Total Actual Effort (in hrs)
NA 9
17

2 2
Comments
need to revist the DB Script used for this. Will start implementation
for jasper requirement today
next page logic is failing . Working on that
Will Integrate other change and will take up for testing

total 19 sources are there , revisited each source line by line. And
shared package to ajay
Meetings
S.No Details Organized
1 Meeting with Mounika Sreehari
Time Spent
30 mins
# Course Link Self Learning Item Self Learning Sub Item

JSX, Props, State, UseState, one


1 React Refreshment
way flow of data
Self Learning
Estimate (in Effort Total Effort on
Status Start Date End Date
hours) (21.12.2021) the course

1 hr Completed 7/2/2022 7/2/2022 1 hr 1


Comments

You might also like