FIJI
CYCLONES
1|Page
A. Summary
A. SUMMARY 2
B. PREFACE 5
C. POPULATIONS 13
D. LOGISTICS COORDINATION GROUP (LCG) AND SUB-GROUPS – TERMS OF REFERENCE & STANDARD
OPERATIONS PROCEDURES 17
A. LOGISTICS COORDINATION 17
B. THE LOGISTICS COORDINATION GROUP (LCG) 17
C. LOGISTICS COORDINATION GROUP (LCG) – TERMS OF REFERENCE & STANDARD OPERATIONS PROCEDURES 19
TERMS OF REFERENCE 19
STANDARD OPERATING PROCEDURES 21
CUSTOMS CLEARANCE FACILITATION CELL (CCFC) – TERMS OF REFERENCE 24
INTRODUCTION: 24
RESPONSIBILITIES: 24
DISPATCHING AND CARGO TRACKING CELL (DCTC) – TERMS OF REFERENCE 25
INTRODUCTION: 25
REPORTING LINE: 25
RESPONSIBILITIES: 25
2|Page
TRANSPORT CELL (TC) – TERMS OF REFERENCE 26
REPORTING LINE: 26
RESPONSIBILITIES: 26
INFORMATION MANAGEMENT CELL (IMC) – TERMS OF REFERENCE 27
INTRODUCTION: 27
REPORTING LINE: 27
RESPONSIBILITIES: 27
1. BACKGROUND INFORMATION 28
2. CYCLONE EMERGENCY PROCEDURES AND RESPONSE ARRANGEMENTS 31
3. SCENARIO DETAILS: 39
4. OPERATIONAL SUMMARY 42
5. CONCEPT OF OPERATIONS 44
6. LOGISTICS RESPONSE WORK PLAN 49
7. PREPAREDNESS (MINIMUM PREPAREDNESS MEASURES) 53
3|Page
4|Page
B. PREFACE
This document is a living document. It is envisaged that this plan will be continuously developed and revised to become as
effective as practical. Divisional and District Level Plans will be formulated to complement this plan.
This Plan is produced under the authority of the Natural Disaster Management Act 1998 and the National Disaster
Management Plan 1995.
Further this Plan is in line with the proposed changes as prescribed under the DRAFT Fiji National Disaster Risk
Management Arrangements 2006.
1. PURPOSE
The purpose of this Emergency Logistics Response Plan for Cyclones is to provide a tool for logistics preparedness and
response arrangements for cyclones in Fiji. It includes operational procedures and guidelines to ensure an adapted
response to the effects of cyclones in the different areas potentially concerned.
2. OBJECTIVES
To define responsibilities and tasks of the emergency response services concerned by Emergency Logistics
Operations
To enhance the Response capacity of the concerned Agencies to anticipate and respond to cyclonic hazards
To improve coordination of response agencies and authorities regarding emergency logistics operations
To avoid duplication in logistics tasks carried out by the different agencies and organizations
To prepare and organize the logistics resources needed to respond to a cyclonic threat.
3. LIMITATIONS
This Plan should be read in conjunction with the Natural Disaster Management Act (1998), the National Disaster
Management Plan (1995) and the DRAFT National Disaster Risk Management Arrangements (2006).
This plan should also be read in conjunction with the Standard Operating Procedures for Cyclones detailed in the Country
Information Package and other Divisional / Provincial / District / City Response Plans
5|Page
5. WARNING
The Nadi Tropical Cyclone Warning Centre (TCWC) will issue special weather bulletins from the initial alert to threat.
Furthermore, the release of Alert or Warning messages should be accompanied with simple verbal/text explanation for
people to understand the terminology and can easily interpret the meaning
WARNINGS
Issued every three hours
Issued when there is an imminent threat of a tropical cyclone
6|Page
The relevant warning information is to be disseminated widely by the concerned agencies. Dissemination of alerts and
warnings will be issued to a group of key agencies and the general public.
The following organizations and institutions have been identified as key agencies for the flood warning arrangements:
NDMO
Divisional Commissioners
Provincial Administrators
District Officers
Police
National Fire Authority
SDMO –Health Centers
Fiji Red Cross Society
LAWRM
Media Outlets
Vodafone
Fiji Military Forces
Ministry of Agriculture
Ministry of Education
District Advisory Council
Rural Local Authorities
Fiji Electricity Authority
Telecom Fiji Ltd
Schools Management
Community Service Organizations
FMS will follow up the Initial Alert with a phone call to the contact persons as listed on the Contact List for the agencies
below:
NDMO
Concerned Divisional Commissioners
Concerned Provincial Administrators
Concerned District Officers
Concerned Police Station
7|Page
Background Info
Fiji’s location in the South Pacific Ocean between 15-22° South and 175-178° West, exposes the country to tropical
cyclones, which are the most frequent hazard process to occur in Fiji and result in the most damage (Campbell, 1984;
Fairbairn, 1997).
On average, Fiji experiences 10 to 15 tropical cyclones per decade, of which 2 to 4 result in severe damage (Fiji
Meteorological Office, undated).
The cost of tropical cyclones and associated rainfall, flooding, storm surges, salt spray and high winds in Fiji is often high.
- Tropical cyclones in Fiji affect an average of 28,837 people per event (CRED/EM-DAT, 2004).
- The most expensive event in recent years was Tropical Cyclone Kina (1993) with total damage estimated at US$100
million (equivalent to 7% of Fiji’s GDP) (Fairbairn, 1997). Following Kina, Tropical Cyclone Ami (2003) resulted in
damages of US$30 million and Tropical Cyclone Gavin (1998) caused US$15 million worth of damage (OCHA, 2003).
- Cyclone Oscar (1983) affected 200,000 people, over a quarter of Fiji’s population.
Because it is a relatively compact archipelago it is possible for most major Fiji islands to be affected at the same time by a
large catastrophe, causing devastating damages equal to a substantial fraction of the country’s GDP.
Figure below shows the path of the eye, or center, of major tropical cyclones having affected Fiji since 1945. These storms
can be very wide, with damaging winds and rain extending throughout Fiji. The color of the path reflects the intensity of the
storm, as measured using the Saffir- Simpson tropical cyclone scale shown in the first table. A more intense storm such as a
category 4 or 5 has more damaging winds, higher precipitation rates and storm surge levels.
8|Page
Saffir-Simpson Tropical Cyclone Intensity Scale
The second table shows the Mean Return Period of tropical cyclone of different categories passing within 100km of Suva.
For example a tropical cyclone of Saffir-Simpson intensity 3 or higher is expected to pass within 100km from Suva once
every 12 years, on average.
2. Exposure
The exposure includes residential, commercial, industrial, and public assets. Figure 3 illustrates the exposure distribution
around Fiji color coded by concentration of replacement value.
9|Page
The population, the number of residential units as well as the housing characteristics were derived from the 2007 Fiji
Islands Bureau of Statistics.
The table below summarizes population and building stock or “exposure” as well as key economic values for Fiji.
10 | P a g e
11 | P a g e
12 | P a g e
C. Populations
General
Viti Levu has the largest land area of 10, 388 square kilometers comprising 57 percent of the land area.
The 2007 census report estimated Fiji's population at 905,949. There is a high degree of variability in the distribution of
Fiji's population among the provinces. Viti Levu contains 76 percent of Fiji's population, while Vanua Levu is home to
another 18 percent. The remaining 6 percent is distributed roughly among the 95 small islands.
The populations in the Central and Eastern divisions were estimated to be at 342,530 and 39,074 respectively (2007
census). The following table shows the population of the various provinces in the Central and Eastern Divisions.
Tailevu 55 887
Bau 26 866
Nakelo 9 430
Sawakasa 6 010
Verata 9 824
Wainibuka 3 757
Naitasiri 160 112
Lomaivuna 4 754
Matailobau 3 960
Waimaro 3 766
Wainimala 3 717
Rewa 101 210
Beqa 1 200
Noco 3 106
Rewa 7 016
Suva 89 888
Namosi 6 901
Namosi 892
Veivatuloa 3 630
Wainikoroiluva 2 379
Serua 18 420
Nuku 3 679
Serua 14 741
13 | P a g e
Eastern Division Statistics
Lau 10 516
Cicia 1 045
Kabara 885
Lakeba 1 692
Lomaloma 956
Matuku 669
Moala 1 319
Moce 477
Mualevu 933
Nayau 338
Oneata 157
Ono 738
Totoya 714
Vulaga 396
Other islands 297
Lomaiviti 16 415
Batiki 256
Gau 2 602
Koro 3 545
Nairai 602
Ovalau 9 092
Other islands 318
Kadavu 9 535
Nabukelevu 2 502
Naceva 1 709
Nakasaleka 1 930
Tavuki 3 907
Rotuma 2 095
Itumuta 187
Itutia 737
Juju 263
Malhaha 251
Noatau 277
Oinafa 224
Pejpei 156
14 | P a g e
INFORMATION ON THE NORTHERN DIVISION
General
Vanua Levu has a land area of 5, 532 square kilometres and is the second largest island, comprising 30 percent of the land
area.
The 2007 census report estimated Fiji's population at 905,949. There is a high degree of variability in the distribution of
Fiji's population among the provinces. Viti Levu contains 76 percent of Fiji's population, while Vanua Levu is home to
another 18 percent. The remaining 6 percent is distributed roughly the ninety-five small islands.
The population in the Northern division was estimated to be at 139, 516( 2007 census). From this estimation, there are
about 109, 465 living in the rural areas and 30 051 living in the urban areas. The population of Labasa was estimated to be
at 54, 070 and Savusavu was estimated to be at 11, 842.
The following table shows the population of the three provinces in Vanua Levu.
Bua 13 779
Bua 4 521
Vuya 4 521
Wainunu 3 723
Cakaudrove 49 678
Cakaudrove 13 222
Nasavusavu 11 842
Rabi 2 721
Saqani 2 585
Tunuloa 3 396
Vaturova 4 569
Wailevu 6 303
Wainikeli 5 049
Macuata 71 106
Cikobia 103
Dogotuki 2 079
Labasa 54 070
Macuata 9 313
Sasa 5 541
15 | P a g e
INFORMATION ON THE WESTERN DIVISION
General
Viti Levu has the largest land area of 10, 388 square kilometers comprising 57 percent of the land area.
The 2007 census report estimated Fiji's population at 905,949. There is a high degree of variability in the distribution of
Fiji's population among the provinces. Viti Levu contains 76 percent of Fiji's population, while Vanua Levu is home to
another 18 percent. The remaining 6 percent is distributed roughly the ninety-five small islands.
The population in the Western division were estimated to be at 319 054 ( 2007 census). The following table shows the
population of the various provinces in the Division.
Ba 212 197
Ba 41 062
Magodro 5 183
Nadi 52 768
Naviti 2 735
Nawaka 12 105
Tavua 23 464
Vuda 90 941
Yasawa 2 608
Nadroga/ 57 972
Navosa Baravi 8 515
Cuvu 7 303
Malolo 2 722
Malomalo 15 836
Nasigatoka 12 907
Navosa 5 121
Ruwailevu 4 645
Vatulele 4 923
Ra 30 216
Nakorotubu 4 234
Nalawa 4 158
Rakiraki 14 787
Saivou 7 037
16 | P a g e
D. Logistics Coordination Group (LCG) and Sub-groups – Terms of
Reference & Standard Operations Procedures
a. Logistics Coordination
Nevertheless, up until now, none of those logistics actors were involved in any preparedness activities.
As this was considered as one of the major weaknesses in Fiji’s DM framework, a permanent Logistics Coordination Group
has been established in 2012.
1
The LCG is a newly established coordination working group, in charge of the coordination and supervision of logistics
activities linked to Emergency Preparedness and Disaster Management in Fiji.
This LCG is chaired by the Permanent Secretary of Provincial Development Ministry, who is also the National Disaster
Controller during Emergency Operations.
1
Inception in April 2012
17 | P a g e
o FCOSS
o Adra
o The Rotary
o Etc.
- The Red Cross Movement
- United Nations Agencies
o UNOCHA
o UNICEF
o WHO
o UNFPA
o Etc
- Private sector companies
o DHL
o FMF
o Transport Companies
o Freight Forwarders
In order to maintain the efficiency of the coordination and of the preparedness activities, an Executive Cell was appointed
to manage and coordinate the activities of the LCG. Members of this Executive Cell are:
- One representative from the NDMO – The head of the Planning and Emergency Operations Unit
- One representative from the NGOs - the coordinator of PCIDRR, emergency specialist in Fiji
- One representative from the Red Cross – the Logistics Coordinator of FRCS
- One representative from the Private Sector – the DG of DHL
- One representative from the military – The head of the Logistics Cell in the RFMF
- One representative from the UN – from OCHA
Database outlining locations in which NGOs, Red Cross and other International partners have pre-
positioned relief supplies.
Implement any other logistics and emergency preparedness activity identified by the LCG participants,
approved and included in the work plan.
18 | P a g e
c. Logistics Coordination Group (LCG) – Terms of Reference &
Standard Operations Procedures
Terms of Reference
Objectives:
To ensure that logistical responses to disaster events are coordinated in a timely and effective manner and to
facilitate the movement of relief commodities during emergencies.
To address logistics gaps, bottlenecks and duplication in logistics operations and ensures that they are
appropriately addressed
Responsible to:
The Logistics Coordination Group is responsible to the National Disaster Controller. As an operational component of the
response it sits alongside the NEOC.
Scope:
The Logistics Coordination Group is operational in nature. It involves both preparedness for and response to disaster
events through the engagement of humanitarian organizations, governmental agencies and other stakeholders to address
logistics needs and identify and address logistical bottlenecks.
Members:
Chair
Permanent Secretary for the Divisional Development and National Disaster Management Ministry
LCG Coordination
An Executive Cell is established to coordinate the activities / responsibilities of the LCG.
The members of the Executive Cell are:
Joji Satakala - representative from the NDMO – head of the Planning and Emergency Operations Unit
Anthony Blake - representative from the NGOs - Coordinator of PCI-DRR
Keith Andrews - representative from the Red Cross – Logistics Coordinator for FRCS
Nick Taylor - representative from the Private Sector – DG of DHL
Major Loanakadavu - representative from the RFMF – head of the Logistics Cell in the RFMF
Peter Muller - representative from the UN – Head of OCHA office in Suva
LCG Members
19 | P a g e
Representatives from governmental agencies (including the Government owned commercial companies, such as
2
AFL, FPCL, etc.), involved in Logistics operations
Representatives from UN agencies, National Red Cross Society and NGOs
Representatives from donors and regional coordination agencies
Representatives from private companies involved in related Logistics chain Operations, food production /
distribution, telecommunications ...
Notes
Membership criteria: LCG is open to all organisations with capacity to implement / support logistics operations to
respond to humanitarian emergencies in Fiji. The main criterion is operational relevance.
In addition to their own organization, members may represent one or more organisations that are not members of
the LCG at their request.
When appropriate, other institutions and agencies may be invited to participate in LCG meetings.
Principles:
The Logistics Coordination Group is based upon the principles of partnerships, preparedness, accountability and leadership.
Information Management
Provide a platform to (i) exchange information, (ii) to be better able to make decisions to improve coordination
and (iii) identify and clear logistical bottlenecks.
Collect, analyze and disseminate logistics information within its members, and across the wider humanitarian
community.
Capacity Building
Gather and share logistics capacity building information amongst the humanitarian community.
2
It is required that each governmental agency involved in Logistics related Operations during emergency phases, appoint one of its
representative – at decision-making level – to be the focal person for the LCG. This person should also be the one deployed in the NEOC
during Emergency Operations phases
20 | P a g e
Promote / support training to strengthen the operational capacities of its members and other identified agencies
at national / divisional / district levels.
Provide operational advice, best practices and troubleshooting assistance to NEOC Participants
Means
Endeavour that necessary means are made available for preparedness and emergency response activities.
Preparedness
Lead the identification/assessment and prioritization of key logistics bottlenecks and gaps impeding delivery of
essential assistance
Ensure adequate logistics preparedness through an Inter-Agency contingency planning process
Operations
Design Concept of Operation (CONOPS) and Standard Operating Procedures (SOPs)
Recommend to partners standard operation procedures, alternative logistics solutions and a cost/benefit analysis
for each solution
Liaise with operating organisations to avoid congestion on logistics infrastructure and assets (supplying corridors,
transport, local suppliers, etc) and to ensure proper coordination of the aid flow
Where necessary, identify and mobilize resources (i.e. financial, HR, assets) to be provided under the coordination
of Logistics Coordination Group participating organizations)
Information Management
Compile and disseminate logistics information
Activation:
The LCG is active during both “normal times” and “emergency phases”.
During the “normal times”, the LCG implement preparedness and capacity building activities.
During “emergency phases”, the LCG switches to an operational body, coordinating emergency logistics operations
as defined in the Logistics Contingency plans and related SOPs.
o The activation of the emergency phase is decided by the National Disaster Controller.
o On a daily basis, members of the Executive Cell manage / coordinate the Emergency Logistics Operations
and are seconded to the NEOC / DivEOC operations.
21 | P a g e
Operations:
Meeting Place: NDMO Office
Support – provides and receives support from the NEOC. Support can also be requested from the humanitarian community
to assist in the running of the Logistics Coordination Group.
Ad-hoc cells: During emergencies, and upon identified needs, the LCG may establish technical cells, aiming at managing
specific components of the Logistics operations. Those cells are:
- Customs Clearance Facilitation Cell (CCFC)
- Dispatching and Cargo Tracking Cell (DCTC)
- Transport Cell (TC)
- Information Management Cell (IMC)
The ToRs of those cells are detailed here under.
Stand Down:
Declared: During meeting of LCG
Non-declared: On advice of National Disaster Controller.
Upon specific request, support may continue through the recovery phase of a disaster.
Essential Equipment:
HF / VHF radios
Vehicles
Mobile phones
Sat Phones
Information Access/Management
Required:
Maps of all of the Fiji Islands including current logistical infrastructure.
Templates for information management- situation reports, minutes of meetings, etc.
Templates and systems for cargo tracking
Current contact details of all LCG members
Responsible to produce:
Sitreps for logistical information
Meeting minutes
Other relevant information for dissemination to humanitarian community.
NDMO
Provide staff to support LCG operations, responsible for the overall running of the operational response -
Provide a location for LCG meetings
22 | P a g e
Information management
Telecommunications
Provide up to date frequencies for radios.
Provide communication assets such as phones and radios
Provide technical support
Assist with training
Fiji Airports –
Facilitate the receipt and dispatch of relief goods through the airport
Fiji Ports –
Establish standby agreements for use in emergencies,
Provide an inventory of operational marine vessels in the Fiji Islands that could be used to transport assessment
teams and relief items,
Provide staff to assist in the running of logistics hubs and warehouses and facilitate the receipt and dispatch of
relief goods through the ports.
Land department –
Provide maps with current infrastructure information
Provide staff to staff the NEOC mapping desk
Police –
Provide assets for assessment and delivery of relief items
Private Sector -
Provide a link between the commercial sector and the LCG
Help facilitate the procurement of relief items, transport assets and other items needed for the relief effort in an
affordable and efficient manner.
Donors –
Ensure systems are in place for emergency operations to access funds in a timely manner
Be available to assist in filling logistics gaps through the provision of funds or coordination mechanisms.
UN –
To provide assistance, if requested by the National Disaster Controller.
23 | P a g e
Customs Clearance Facilitation Cell (CCFC) – Terms of Reference
Introduction:
During emergencies, if the size of the events requires international assistance, a Customs Clearance coordination
cell, composed by representative from Fiji Procurement Office and FIRCA, may be set up.
In addition, a volunteer support from one of the major Freight Forwarding / Shipping / CC brokers companies
should be a significant added value.
Responsibilities:
Assessment
Assess all entry points
Meet with the Central Customs authorities to review existing customs regulations
-
Information Management
Ensure INGOs and UN agencies’ good understanding of local Customs policies and their application.
Document the “application of customs procedures”.
Keep the humanitarian agencies informed on standard customs procedures
Operations
If required, negotiate facilitation measures with national and local authorities, including registration process for
NGOs / International agencies.
Advise the LCG on main customs issues affecting operations.
Facilitate / support / ensure Customs Clearance procedures for registered humanitarian agencies
Maintain a paper trail for future reference
24 | P a g e
Dispatching and Cargo Tracking Cell (DCTC) – Terms of Reference
Introduction:
During Emergency Response operations, Fiji authorities will set up dispatching centers; all the commodities
transiting through the dispatching center before being sent to distribution areas.
During emergencies, the dispatching centers should be operated by / with the support of private companies
bringing their professional experience for dispatching operations and commodities tracking. This recommendation
will require that prior stand-by agreement – even basic – is signed between NDMO and the pre-identified private
companies.
As all operations in remote locations / outer islands will require repackaging and transshipment operations, this
need to be considered when designing the initial Concept of Operations (an additional hangar, linked to the
dispatching centre, need to be specifically designated to this purpose).
During emergencies, the Customs Clearance coordination cell, composed by representatives from FIRCA, Fiji
Procurement Office and CC companies should be operating from the dispatching center
Reporting line:
The Dispatching & Cargo Tracking Cell reports to the Logistics Coordination Group
Responsibilities:
25 | P a g e
Transport Cell (TC) – Terms of Reference
Reporting line:
The Transport Cell reports to the Logistics Coordination Group & the NEOC
Responsibilities:
The Transport & Shipping Cell is responsible for the following duties:
Land Transport
Define specific transport strategy and procedures and ensure effective integration of transport in Logistics
operations.
Advise on transport management structures and staffing to ensure that they are adequate to meet the
requirements of the logistics strategy.
Organise, lead and participate in transport committees meetings, including at divisional and district levels.
Manage transport operations including all transport assets in order to ensure timely and cost-effective delivery of
cargoes.
Identify, mobilise resources, implement and report on special transport operations.
Ensure that accurate and complete accounting, reporting and internal control systems are functioning and that all
relevant records are maintained.
Ensure effective commodity management and quality control.
Coordinate transport operations with the Dispatching and Cargo Tracking Cell.
Supervise staff as required.
26 | P a g e
Information Management Cell (IMC) – Terms of Reference
Introduction:
During Emergencies, Information Management is of the upmost importance for Emergency Logistics Operations.
Information Management will need to provide updated information about Logistics Operations to the National
Disaster Controller and to the NEOC on a daily basis.
Reporting line:
The Information Management Cell reports to the Logistics Coordination Group, the National Disaster Controller
and to the NEOC
Responsibilities:
The IMC will act as the focal point for collecting, analyzing and disseminating logistics information.
The IMC will work closely with the Logistics Coordination Group (LCG).
Gather information on the overall logistics situation, including comprehensive data on logistics procedures and
bottlenecks from the various LCG participants and national authorities.
Produce LCG reports in specific formats as required within the operations. Key products include: Sitreps,
snapshots, flash news, briefings, road matrix, and area overview.
Liaise with LCG participants, and national counterparts to gather information for the production of daily Sitreps
and weekly bulletins, ensuring that challenges and concerns relating to the logistics operations are represented.
Consolidate and share key logistics information and procedures, such as Concept of Operations and Standard
Operating Procedures (SOPs) ensuring they are regularly revised/updated if required.
Inform relevant stakeholders on commodity tracking reporting procedures.
Prepare talking points and agenda for LCG meetings, compile minutes / action points and ensure timely sharing of
meetings minutes with all participants.
Prepare operational overview, briefings and snapshots on the logistics operation for donors, UN Country Team,
Office of the Humanitarian Coordinator and other stakeholders as requested.
Attend relevant meetings; represent the LCG when requested.
Establish, moderate and maintain LCG mailing list.
Standardize and execute quality control of logistics assessments and activity reports.
Distribute reporting formats as required, and compile logistics plans/forecasts of other organisations.
Establish and maintain internal information sharing mechanisms, documentation formats, assessment formats,
central file store, according to GLCSC guidelines and standardization.
Recognize and assess the sensitivity of information obtained; Respect the confidential nature of sources of
information where relevant.
27 | P a g e
E. Scenarios Details & Logistics Contingency Plan - Cyclones
1. Background information
The climate is tropical with a typical weather pattern of a wet season and a dry season. Fiji is subject to cyclones which is
seasonal between November and April.
During the rainy season, flooding and landslides can occur, especially as a consequence of cyclonic or low pressure events.
Tropical cyclones, with the accompanying strong winds, flood and storm surge, are the most frequent hazards to threaten
Fiji and also have the most damaging impact on our country. Fiji is situated south of the equator and lies in one of the
tropical cyclone-prone areas of the South Pacific. Five to six severe cyclones would usually affect the country in a decade.
Heavy torrential rain that will occur a few days before the onslaught of the wind can cause widespread flooding.
Fiji has been affected by major tropical cyclones in the past, with recent most severe ones being Cyclone Kina in 1993 and
Tropical Cyclone Ami at the beginning of 2003.
Several scenarios could be developed describing the extent of casualties and damage to properties, following a major
cyclone in Fiji. These would differ as well, depending on the magnitude of the cyclone.
Listed below are indications of some of the effects which could be expected:
There would be many casualties from secondary disaster like floods and landslides. The number would depend on
the time of day, and the location of the landslide and flooding as most development is happening in landslide and
flooding prone areas.
Services (power, water, and telecommunications) would be severely disrupted.
Roads, air and sea transport would be severely damaged and disrupted.
Community infrastructure would be severely damaged, disrupting the normal industrial, commercial, government
and service industries. The return to normal community activity would be a long and difficult process.
The country’s financial system could become subject to extreme pressure
The sugar cane and tourist industry would suffer
Emotional stress would be long lasting and widely spread throughout the community.
Planning must be continuously exercised to minimize the effects on the population, and to assist a quick recovery from
such an event.
History:
Storm 17-Jan-1985 28
Storm 10-Mar-1997 25
Storm 2-Jan-1993 21
Storm 14-Jan-2003 17
Storm 8-Apr-2004 16
Storm 19-Jan-1999 12
Storm 1-Mar-1983 9
28 | P a g e
Disaster Date Total Affected
Present Overview:
SOPs, radio frequencies and contact list of the Nadi Tropical Cyclone Warning Centre (Nadi TCWC) are given in Annex 1
“2011/2012 TROPICAL CYCLONE SEASON - SUMMARY OF ALERTS AND WARNINGS PROCEDURES FOR FIJI”
The Nadi TCWC is operated within the Weather Forecasting Division of the Fiji Meteorological Service (FMS) and can be
accessed 24 hours a day as follows:
Telephone: 6724888 (Switchboard) or
6736005, 6736006, 6736007 (Direct)
(Calls must be kept short).
Facsimile: 6720190 / 6720636 / 6720645
Weather Fax: 6721227 (Polling fax)
FMS Web Site: .met.gov.fj or
.met.gov.fj/fijimet/slowlinks (for those with slow internet access)
29 | P a g e
stronger winds within 24 hours over the areas so warned. Apart from average wind speeds, expected winds in momentary
gusts will also be given.
Forecast:
Cyclones season usually runs from November to April (even if some cyclones have been referenced in
May).
Annual forecasts for cyclones are provided, prior to the Cyclone season, by the RSMC Nadi – TCC.
2011 – 2012 Forecasts are provided in Annex 2 “2011/12 Tropical Cyclone Season Outlook in the
Regional Specialised Meteorological Centre Nadi – Tropical Cyclone Centre (RSMC Nadi – TCC) Area of
Responsibility (AOR)”
Impact:
Non-Medical
o Destruction of:
Houses and shelter
Property and livestock
Water sanitation facilities
Infrastructures, communication
o Lack of access to:
Portable safe water
Food
Shelter
o Destroyed or overwhelmed health facilities.
Medical
o Injuries and deaths
o Displacement, overcrowded living conditions and insufficient water sanitation facilities lead to
outbreak of communicable diseases.
o Other health conditions depending on the scenario:
Mental health trauma
Injuries
Humanitarian
o Displacement
30 | P a g e
2. CYCLONE EMERGENCY PROCEDURES AND RESPONSE ARRANGEMENTS
AUTHORITY
This plan is produced under the authority of the National Disaster Management Council and the National Disaster
Management Office.
DECLARATION OF AN EMERGENCY
A state of emergency can only be declared by a council of ministers which should include, the Minister for Regional
Development in his capacity as the Chairman of the NDMC, the Minister for Finance, Minister for Home Affairs. This
decision will be facilitated and made after a rapid initial damage assessment mechanism is completed.
CYCLONE WARNINGS
The Nadi Tropical Cyclone Warning Centre (TCWC) will issue special weather bulletins from the initial alert to threat.
Furthermore, the release of Alert or Warning messages should be accompanied with simple verbal/text explanation for
people to understand the terminology and can easily interpret the meaning
WARNINGS
Issued every three hours
Issued when there is an imminent threat of a tropical cyclone
CYCLONE ALERT
To be issued every six hours, therefore it will be important that the clocks at all the concerning agencies like the Nadi
Tropical Cyclone Warning Center, Radio Stations and DivEOCs are synchronized, particularly when issuing the warnings to
the public.
STAGE THREE – ACTION – RED (Linked Cyclone Warning - Hurricane Force Winds)
Stage 3 will be activated when a natural disaster has occurred in Fiji or parts of Fiji. It will normally become operational
when the immediate danger has passed.
Highest state of readiness
Cyclone impact with risk of destructive wind is imminent
RESPONSE MEASURES
STAGE ONE (WHITE) - READINESS
When Stage ONE (WHITE) is activated, the following actions will be taken
Office hours may be extended at the discretion of the Controller.
Place whole of Fiji on Divisional emergency status, if warranted, and instruct the Div Controller to
activate the national disaster plan upon consultation with the National.
Monitor all activities and be consulted on all matters relating to policy.
Assume responsibility for the activation of the Disaster Plan.
DIVISIONAL LEVEL
DIVISIONAL COMMISSIONER
Notify:
PS-Regional Development
NDMO
Divisional Disaster Management Committee
District Officer
Div Heads Min. of Communications and Works
Div Head Telecom, Fiji
Div Head Fiji Electricity Authority
Divisional Medical Officer
Divisional Education Officer
Hospital Superintended
Divisional Police Commander
Nadi/ Nausori/ Labasa Airport Manager
Branch President, Fiji Red Cross Society
Divisional Planning Officer
Assemble the DivDC at the DivEOC and convene to review preparedness arrangements and
prepare for coordinated response.
Notify District Officer and advise to convene District Disaster Management Council to review
preparedness arrangements and prepare for coordinated response.
DISTRICT LEVEL
32 | P a g e
Notify District Officer and advise to convene District Disaster Management Council to review
preparedness arrangements and prepare for coordinated response. (refer to District SOP - Cyclone
and District Disaster Plan)
MEDIA BROADCAST
Population at risk will continue to be informed of the threat through the relevant channels, Fiji
Broadcasting Commission and FM 96
DivDMC MEMBERS
Report to the DivEOC
Meet and formulate a plan for dealing with the cyclone
DISTRICT COMMITTEES
Activate District EOCs and cyclone response plans
33 | P a g e
DISTRICT LEVEL
Will be operational on a 24 hour basis to coordinate information and provide operational support.
(refer to District SOP - Cyclone and District Disaster Plan)
AGENCIES
All agencies will inform their staff, put people on standby and take necessary precautions in line with
their disaster plan.
SPECIAL NOTE
Cyclones are unpredictable in nature, and therefore it is very easy to be caught out of speed of
movement increases in track alters without warning. Be prepared to initiate action during one stage
which may be listed under another.
Be guided by local weather conditions - they may differ from official or current weather messages.
Information broadcasts are conducted by the NDC, and are designed to provide the community with
more detailed information that may be contained in weather warnings. They are used to walk the
community through the preparedness stage, and are useful in reducing overreaction and rumor
(coconut wireless).
34 | P a g e
AGENCIES - GOVERNMENT DEPARTMENTS AND NGOs
Implement action in accordance with stage three response and preparedness plans.
Standby to respond in accordance with the directions from the Controller and DivEOC
PUBLIC WORKS
Provide transport and machineries to clear roadblocks and for ground reconnaissance intelligence to
the DivEOC
DIVISIONAL ENGINEER
Brief the Divisional Controller on the condition of Evacuation buildings and recommend a suitable
alternate building from which to evacuate affected population.
AIRPORT MANAGER
Provide Clear Runway for emergency landing.
MARINE DEPARTMENT
Provide boats for marine reconnaissance
DEPARTMENTAL HEADS
Activate all Departmental cyclone plans
DIVISIONAL CONTROLLER
Be consulted on all matters relating to the activation of any or all evacuation systems developed for
Divisional and Districts by the DivEOC.
Establish contact with overseas donor representatives.
Locate and brief all operations staff.
Implement Departmental plans.
Inform respective agencies of the current situation.
Locate all heads of divisions.
Install communications and emergency power supplies.
Contact DivEOC director and provide updates.
Assess needs.
Brief department personnel on the situation
35 | P a g e
Implement deployment plan of services and supplies through the use of a priority checklist.
DISTRICT COMMITTEES
Activate and prepare emergency shelters as required and advise the DivEOC
Ensure that all emergency shelters are opened, staffed and equipped with supplies
AIRPORT MANAGER
Brief airlines authorities on the situation at the airports
WATER AUTHORITY
Activate cyclone water supply plans
Fill water trucks
Fuel all vehicles
POLICE
Initiate evacuation procedures through the DivEOC
Deploy security personnel to stricken and evacuated areas and homes of key response personnel as
requested through the DivEOC
Provide ground reconnaissance intelligence to the DivEOC
Assign personnel to:
Protect property
Prevent vandalism
Control traffic
Maintain security at:
Hospitals
Shelters
Air and seaports
Relevant Government offices
Homes of relief workers
36 | P a g e
Issue precautionary hints together with packaged information of the activities of responding agencies
and disseminate situation reports locally through the DivEOC
Advise public of safety of key Government officials through the DivEOC
Advise public to listen to all reports through the DivEOC
Issue precautionary hints together with packaged information of the activities of responding agencies
and disseminate situation reports locally and overseas through the DivEOC
Issue updates and public information via news releases
AS SOON AS POSSIBLE
DIVISIONAL DISASTER CONTROLLER
Establish contact with National Controller for onward transmission to International agencies
regarding the responsibility for the coordination of supplies to the Division
Coordinate the relocation of Government offices to temporary pre-determined alternate sites
through the NEOC if need arises or DivEOC damaged
Maintain communications within and outside the affected Division and with other assisting
organisations through the DivEOC
Make available all relevant information on the disaster to NEOC and Districts through the DivEOC
Coordinate evacuations from stricken or threatened areas to emergency shelters through the DivEOC
PS - MINISTRY OF FINANCE
Activate emergency finance procedures
Assess local relief supplies
Establish lines of credit with merchants enabling easy access to relief supplies during the disaster
DIVISIONAL CUSTOMS
Facilitate speedy customs, immigration and health clearance for international assistance and
resources arriving in the Country through the NEOC for DivEOC.
DISTRICT COMMITTEES
Coordinate the establishment, staffing and management of emergency shelters for the general
population
37 | P a g e
PUBLIC WORKS DEPARTMENT
Provide transportation for relief supplies and personnel
Provide temporary or permanent accommodation required by relief workers
Coordinate transportation and supply through the DivEOC
RED CROSS
Channel International medical assistance through the DivEOC
Assist the DivEOC in coordinating relief assistance and supplies
Assist with food and water distribution and with relief activities
Provide relief supplies to shelter victims
Assist with needs assessment
Assist with the tracing of missing persons.
DISTRICT CHAIRMAN
Coordinate the reception and care of evacuees sent into the district
Provide information to the DivEOC on damage and needs
DivDMC
Deactivate the Agency operation and return to normal operations at own departments.
DISTRICT OFFICER
Convene Executive Council for emergency sessions as necessary.
Appoint a recovery coordinator.
Stand down the response phase.
Deactivate the DivEOC and return to normal operations.
INFORMATION OFFICER
Continue to build and maintain a picture of the cyclone, its effects and recovery measures being
undertaken .
DISTRICT OFFICE
Ensure establishment of central storage area at air and sea ports to receive supplies
GOVERNMENT SUPPLIES
Distribute supplies to district distribution storage
TELECOM FIJI
Restore telecommunications
PWD
Restore roads, bridges and buildings
WATER AUTHORITY
Restore water supplies
HEALTH DEPARTMENT
Certify food and water supplies
Distribute and deploy medical supplies and personnel as required
Ensure Public Health is maintained
3. Scenario details:
Summary
Casualties: Due to an efficient Early Warning system and Evacuation procedures in place, fatalities
and injuries are usually very low, < 30 deaths; injured people <1,000
Infrastructure Damage Buildings destroyed, large debris
Affected/Displaced Persons: < 200.000 people - < 40.000 HH; thousands of homes seriously damaged; tens of
thousands in Evacuation Centers
Economic Impact Up to 10% of Fiji’s GDP
Potential for Multiple Events Yes, seasonal
39 | P a g e
Recovery Timeline Months / Years
Scenario Overview:
General Description –
Cyclones are intense tropical weather systems consisting of dangerous winds and torrential rains. Cyclones often spawn
tornadoes and can produce a storm surge of ocean water that can be up to 24 feet at its peak and 50 to 100 miles wide.
The most destructive companion of Cyclones is the storm surge.
A typical Cyclone is 400 miles in diameter and has an average forward speed of 15 miles per hour (mph) in a range of 0 to
60 mph. The average life span of a Cyclone is 9 days in a range of less than 1 day to more than 12 days. Cyclones’ highest
wind speeds are 20 to 30 miles from the center. Cyclone force winds cover almost 100 miles, and gale-force winds of 40
mph or more may cover 400 miles in diameter. A fully developed Cyclone may tower 10 miles into the atmosphere.
A Cyclone is categorized by its sustained wind intensity on a Saffir-Simpson Cyclone Scale that is used to estimate the
potential for property damage and flooding. “Major” Cyclones are placed in Categories 3, 4, or 5 with sustained wind
intensities between 111 mph to greater than 155 mph. The most dangerous potential storm would be a slow-moving
category 5 Cyclone, making landfall in a highly populated area, and during high tide.
In Fiji, Category 5 Cyclones are rare but not impossible, while category 4 cyclones have been experienced in the past. For
detailed information, refer to chapter 2 – Background information.
Sustained winds at 125 mph with a storm surge greater than 20 feet above normal can be expected. As the storm moves
closer to land, massive evacuations are required. Certain low-lying escape routes are inundated by water anywhere from 5
hours before the eye of the Cyclone reaches land.
Timelines/Event Dynamics –
A tropical storm that develops in the Southern Pacific can easily be upgraded to a Cyclone after 4 or 5 days in the open
waters.
After 4 days, the Cyclone could steady at dangerous Category level on the Saffir-Simpson Cyclone Scale. Models indicate
that the most dangerous cyclones follow a track that goes in the direction of Australia. Nevertheless, destructive cyclones
hit Fiji every 3 to 4 years (see Chapter 2)
The rain associated with the storm can cause rivers to overflow their banks, and several rivers systems may be experiencing
record flood levels.
Key Implications:
The Cyclones could result in more than 30 fatalities (if the evacuations processes are fully implemented) and 1,000 people
with sustained injuries requiring professional treatment. Residents in low-lying areas may be ordered to evacuate 24 hours
prior to projected landfall to inland areas.
Major portions of the concerned areas may become flooded several hours before the landfall or arrival to the closest
proximity of lands. Structures in the low-lying areas may be inundated when storm surges reach their peak. Many older
facilities could suffer structural collapse due to the swift influx of water and degradation of the supporting structural base.
40 | P a g e
Newer facilities and structures may survive the influx of water, but sustain heavy damage to contents on the lower levels. It
is known that several touristic infrastructures are located in dangerous areas that may suffer significant damages /
destructions during severe cyclonic events.
Trees within the storm’s path are damaged or destroyed, generating massive amounts of debris and blocking accesses.
Debris is also generated from structures destroyed or damaged by the Cyclones. Many structures will need to be
demolished.
Service disruptions could be numerous. Shelters throughout the region will be filled to capacity.
Thousands of trapped people may require search and rescue. Until debris is cleared, rescue operations will be difficult
because much of the area may only be reachable by helicopters and small boats.
Wind and downed trees may damage nearly all of the electric lines. Most communications and water distribution systems
within the impacted area will not function due to damages and lack of power.
Thousands will be homeless, and all areas will be in serious need of drinking water. Food will be in short supply.
Military facilities may be damaged, and assistance needed to reconstitute the facilities.
The storm surge may breach and overtop dams and cyclone protection works.
All transportation routes will be damaged to some degree and port facilities will also be adversely affected. Many hospitals
will have severe damage and those that are open may be overwhelmed. Schools that are not severely damaged will be used
as shelters for the disaster victims.
41 | P a g e
4. Operational Summary
Description
Vulnerable
areas /
periodicity
Destruction of:
Houses and shelters
Property and livestock
Water & sanitation facilities
Infrastructures, communication infrastructures, transportation means
Preparedness
Coordination Coordination meetings with NDMO, OCHA, MoH, Divisional Health Authorities, Divisional
EOC, other stakeholders/ actors.
Report on situation, plans, monitoring and surveillance.
43 | P a g e
5. Concept of Operations
The initial Concept of Operations is designed for a first response plan up to 3 months.
The Concept of Operations detailed here under is managed by the Logistics Coordination Group (LCG) in place in Fiji.
The objectives and activities of the Logistics Coordination Group in Fiji are the following:
The foremost objective of the LCG in Fiji is to support the NEOC and DivEOCs in coordinating and operating logistics efforts,
and by association the delivery of various humanitarian assistance programmes.
Based on the request of the National Controller, the LCG will take part to the NEOC and DivEOCs; and mobilize various
logistics assets, including air and sea transportation capacities, power and communication equipment, which will be made
available to both government and humanitarian organizations through the LCG.
Considering the number of affected population in this scenario, during the first 3 months the
humanitarian emergency response will require importing a significant quantity of relief items from abroad.
Gaps in storage capacities are obvious at all entry points and will require the set up of MSUs in pre-
identified areas.
Concretely, air transport for the very initial stage to reach the cut off areas, surface transport and
storage capacity will pose the main challenges to the Government and humanitarian organisations.
Humanitarian organisations will require guidance and support with importation and customs
clearance for the relief items, majority of which will have to be sourced from outside Fiji. Similarly, logistics
coordination and information management will play a key role in ensuring efficiency and effectiveness of the
overall humanitarian response.
Activities
Regarding the response to a major cyclone, Logistics coordination objectives will be met through the execution of the
following activities:
a. Coordination: During the first days, daily meetings will be conducted (at national and divisional levels)
to offer a forum for information sharing and decision-making related to logistics operations. Periodicity will then be
reviewed based on the situation.
b. Customs Clearance facilitation: As import of relief items is needed, for the initial phase of the
operation, the LCG establish a Customs Clearance Facilitation Cell (CCFC), composed by one representative from Fiji
Procurement Office + one from FIRCA. In addition, a volunteer support from one of the major Freight Forwarding /
Shipping / CC brokers companies should be a significant added value. This Cell should provide a link between
organizations importing relief items into Fiji and the governmental authorities for customs clearance.
During emergencies, the Customs Clearance coordination cell should be operating from the main entry point (Nadi
Airport?) and liaise with the Logistics Coordinator.
c. Dispatching and Cargo Tracking Cell (DCTC): During Emergency Response operations, Fiji authorities
will set up dispatching centers, most probably at all entry points and at identified intermediate locations, depending
on the areas affected by the cyclone; all the commodities transiting through the dispatching centers before being
sent to distribution areas.
44 | P a g e
a. During emergencies, the dispatching centers should be operated by the LCG with the support of private
companies bringing their professional experience for dispatching operations and commodities tracking.
b. As all operations in remote locations / outer islands will require repackaging and transshipment
operations, this need to be considered when designing the initial Concept of Operations (an additional
hangar, linked to the dispatching centre, need to be specifically designated to this purpose).
d. Transport Cell (TC): As, during Emergency Response operations, Fiji authorities will set up dispatching
centers; it is recommended that the LCG set up transport cells in NEOC and DivEOC to coordinate / manage transport
operations from the dispatching centers to the distribution areas.
a. The Transport & Shipping Cell is responsible for the following duties:
Land Transport
Manage transport operations including all transport assets – pre-identified by
governmental mapping - in order to ensure timely and cost-effective delivery of
cargoes.
Identify, mobilize resources, implement and report on special transport operations.
Coordinate transport operations with the Dispatching and Cargo Tracking Cell.
Shipping & Air transport
Manage the operational aspects of all chartered vessels carrying organisation
commodities, including loading and discharging operations and the contracting of
stevedoring services.
Appoint, instruct and supervise a network of Freight Forwarding Agents and provide
advice to the appointed agents as required.
Liaise closely with agents and suppliers to ensure that cargo readiness matches vessels
arrival.
e. Access to Ad-Hoc storage services: There are clear storage / commodities management issues at all
main entry points (Suva port, Nadi airport, Lautoka port and Nausori airport).
a. As emergency operations are likely to happen during the wet seasons, open storage is not an option
b. As relief operations to a major cyclone will be of a large scale, direct routing of commodities to the final
delivery points is not an option either.
c. As dispatching centers will operate from all the main entry points / logistics hubs around the operations
areas, it is recommended setting up temporary MSUs close to the dispatching centers.
d. For larger scale scenarios, among the options to consider:
Fiji government / RFMF to procure MSUs that can be set up quickly everywhere in the country.
Sites should be pre-identified for this purpose
Humanitarian community, through the PHT, to get the funding for the procurement of “Logistics
Kits for entry points”. Those kits include a MSU, one prefab for office, power generation and
lightning equipment. This option should get the prior approval of UN HoO.
Stand-by agreements with private transport companies, for the temporary use of part of their
storage capacities during emergency operations. This option being only for a very short time,
before finding a longer term solution.
! Repackaging and transshipment need to be considered when designing the storage /
dispatching center.
e. Storage and dispatching at intermediate hubs (for large scale scenario) / final destination points (outer
islands entry points) are also an issue.
Among options to consider:
Each district to identify temporary storage facilities (governmental buildings, private
companies …) or to select – floods safe - areas for the setting up of tents.
RFMF/other governmental agencies to provide smaller tents for temporary storage
For large scale scenarios on outer islands, MSUs will probably be the only option. UN
agencies / donors to assess this option.
The LCG coordinates the process to request logistics support regarding storage.
f. Information Management: During emergencies, The LCG organizes logistics coordination meetings,
acting as an interlocutor between participating organizations and the NDMO to monitor and resolve gaps in the
45 | P a g e
delivery of assistance. It also provides cargo tracking based on CMRs received and executed, on demand GIS-
Mapping and regular information products such as situation reports and bulletins.
Suggested SOPs
Activation:
The LCG is active during both “normal times” and “emergency phases”.
During the “normal times”, the LCG implement preparedness and capacity building activities.
During “emergency phases”, the LCG switches to an operational body, coordinating emergency logistics operations
as an active component of the NEOC and, upon identified need, of the concerned DivEOCs.
o The activation of the emergency phase is decided by the National Disaster Controller.
o On a daily basis, members of the LCG manage / coordinate the Emergency Logistics Operations and are
seconded to the NEOC / DivEOC operations.
o Upon identified needs, the LCG may decide to setup specific sub-groups for (i) customs procedures, (ii)
dispatching and cargo tracking, (iii) transport and shipping; and (iv) information management.
Operations:
Meeting Place: NDMO Office / NEOC and Divisional Offices / DivEOCs
Support – provides and receives support to / from the NEOC / DivEOCs. Support can also be requested from the
humanitarian community to assist in the running of the Logistics Coordination Group.
Activities:
Liaison
- Participate actively in both the National and Divisional EOCs
- Participate as coordination body to the head of clusters meetings organized by OCHA
- Develop and maintain relevant contacts/networks in the humanitarian, private and governmental structures;
- Intervene, as necessary and as required, on behalf of the humanitarian community to expedite processes and
resolve problems with the Government and among the humanitarian actors;
Information Management
46 | P a g e
- Consolidated IM products - including maps - will be disseminated on a regular basis to ensure that all involved
organisations have access and knowledge of the wider situation affecting the logistics, to aid planning and
decision-making in their respective organisations and clusters.
- During emergencies, the LCG organizes logistics coordination meetings, acting as an interlocutor between
participating organizations and the NDMO to monitor and resolve gaps in the delivery of assistance. It also
provides cargo tracking support based on CMRs received and executed, on demand GIS-Mapping and regular
information products such as situation reports and bulletins.
Transport
- It is recommended that the LCG set up transport cells in NEOC and DivEOC to coordinate / manage transport
operations from the dispatching centers to the distribution areas.
Stand Down:
Declared: During meeting of LCG
Non-declared: On advice of National Disaster Controller.
Upon specific request, support may continue through the recovery phase of a disaster.
Essential Equipment:
HF / VHF radios
Vehicles
Mobile phones
Sat Phones
Information Access/Management
Required:
Responsible to produce:
NDMO
Provide staff to support LCG operations, responsible for the overall running of the operational response -
Provide a location for LCG meetings
Information management
Telecommunications
Provide up to date frequencies for radios.
Provide communication assets such as phones and radios
Provide technical support
Fiji Airports –
Facilitate the receipt and dispatch of relief goods through the airport
Fiji Ports –
Establish standby agreements for use in emergencies,
Provide an inventory of operational marine vessels in the Fiji Islands that could be used to transport assessment
teams and relief items,
Provide staff to assist in the running of operations and facilitate the receipt and dispatch of relief goods through
the ports.
Land department –
Provide maps with current infrastructure information
Provide staff to staff the NEOC mapping desk
RFMF - Police –
Provide assets and manpower for assessment and delivery of relief items
48 | P a g e
Feed logistical information to the LCG for dissemination to other clusters or agencies
Identify bottlenecks in the logistics operations and ensure this information is shared with the LCG for
dissemination.
where possible make transport assets available for use by all relief providers
Private Sector -
Provide operational support to dispatching and cargo tracking activities
Provide a link between the commercial sector and the LCG
Help facilitate the procurement of relief items, transport assets and other items needed for the relief effort in an
affordable and efficient manner.
Donors –
Ensure systems are in place for emergency operations to access funds in a timely manner
Be available to assist in filling logistics gaps through the provision of funds or coordination mechanisms.
UN agencies –
To provide assistance, if requested by the National Disaster Controller.
Logistics Questions to be considered by the Logistics Coordination Group to set up the Emergency Response:
Will there be a need for the deployment of emergency kits and other emergency logistics support equipment, such
as mobile storage units?
Will the disaster response require import operations?
How will the disaster impact on local partners, contractors and suppliers?
What are the local storage locations and their capacities? Are they located in a secure area protected from the
effects of the anticipated disaster (e.g. floods)?
What are the delivery routes from entry points to the affected areas and how easily accessible are they?
Is there enough in-country transport capacity to serve primary, secondary and tertiary needs? If not, how could it
be increased?
What could be the alternative transport modes to reach the affected populations? What would be the schedule
for opening new routes? What actions would be required from the government, UN and others?
How much food items and NFIs are currently available in stocks? How much emergency relief items are en route
and how long will it take to arrive?
49 | P a g e
Logistics Response Work Plan
LOGISTICS WORK PLAN
Status
Due date/ Resources
Lead Comments
To be done
No. Response activities Timeframe needed
Deadline
Done
set
First 24 hours
Inform the Logistics Coordination Group members of the
1
activation of NEOC / DivEOCs
Determine type and quantity of assets available in the affected
2
area and around (for assessment purposes) and share
Collect and centralize information from the field and from
3 partners: accesses, damages to infrastructures, field activities &
capacities, availability of transport assets and storage facilities
If needed, deploy a logistics assessment team to the affected
4
area together with Programme
Call for a logistics coordination meeting to:
Review the logistics requirements
Assess the need for LCG to extend logistics support
5 services to partner agencies
Ensure that logistics efforts are coordinated
50 | P a g e
First 72 hours
As soon as possible, design and share a Logistics Concept of
8 Operations, including services available (entry points, logistics
hubs, dispatching, storage, transport) and how to access them
Receive plans from other clusters and from Divisional authorities
9
(procurement, distributions)
Establish the Customs Clearance Facilitation Cell (CCFC)
Discuss government plans for Customs Clearance process. If
10
needed, provide facilitation to Logistics Coordination members
and to other clusters
Set up the Dispatching and Cargo Tracking Cell (DCTC)
Organize a main logistics hub (dispatching center) near the main
entry points and linked to the DivEOC – reception of relief items,
11
dispatching, transport to intermediate hubs or to districts for
distribution
Organize / ensure the setting up of a cargo tracking system
Identify / secure temporary storage location in intermediate
12
hubs. If needed bring & setup Mobile Storage Units
Set up transport cells in NEOC and DivEOC to coordinate / manage
transport operations from the dispatching centers to the distribution
areas
13 Discuss government plans for transport operations and
procedures to access these services. If needed, provide
facilitation to Logistics Coordination members and to other
clusters for separate operations
If needed, discuss government plans for transport operations to
outer islands.
If needed, include air and sea inter-islands transport operations
14
in the ToRs of the Transport Cell.
If needed, provide facilitation to Logistics Coordination members
and to other clusters for separate operations
All along Emergency Operations
15 Provide regular Sitreps to Logistics Coordination members and to
51 | P a g e
other clusters
Update and share logistics operational reports: pipeline, storage,
16
transport …
Ensure that clearance, storage, dispatching and transport
17 services are accessible to all partners. If needed, coordinate
allocation of ad-hoc transport assets for specific needs
Ensure that operations at the main ports of entry are running
18
smoothly and that no congestion is faced or planned
Ensure that temporary storage operations at the main ports of
19 entry are running smoothly and that no delays are faced or
planned
Provide liaison between agencies: governmental, UN, NGOs,
20
private companies, to ensure a coordinated logistics response
21 Ensure logistical support to other clusters, if needed
22 Attend other clusters meetings (at least the operational ones)
Identify / anticipate gaps and bottlenecks in logistics operations
23
and provide alternative solutions to address them
52 | P a g e
7. Preparedness (Minimum Preparedness Measures)
The emergency logistics preparedness measures are detailed separately (Cf. “Emergency Logistics Preparedness Plan”.
Nevertheless, as cyclones are recurrent in Fiji, a Logistics preparedness meeting should be held at National and Divisional
levels, each year, and prior to the wet/cyclones season.
As cyclones hazards concern the whole country, it is recommended to compile, for all Fijian Districts, provinces, and divisions,
all the necessary logistics related information: infrastructures (roads and bridges data, ports, …), services( transport capacities
available locally, heavy equipment, communications equipment, …), etc.
53 | P a g e