You are on page 1of 2

research update: masonry façades

Masonry façade retention


Deborah Lazarus, Associate Director, Arup Research
and Development and member of the Institution’s
Research Panel, outlines a new guide from CIRIA
which will become the industry standard

T
he results of a CIRIA research mended that there must be ‘ownership’ of
project entitled Masonry façade the scheme at all stages from inception to
retention: best practice guidance are completion of the whole of the works.
due to be published soon. The research An outline solution and method state-
has been carried out by Arup, part-funded ment should be provided, generally by the
by the Health and Safety Executive permanent works designer, although it is
(HSE), and has been guided by a steering recognised that often this will be devel-
group of experts drawn from parties oped, and in some cases revised substan-
involved in, or with an interest in, façade tially, by the contractor’s temporary works
retention. The original commission was designers.
for a good practice guide: the change Where the façade retention is carried
made during the course of the research is out as an advance works contract, proce-
a reflection of the breadth of consultation dures should be put in place to ensure
and input to the guide from a number of that responsibility for the temporary
parties. works is clearly maintained and identified
At present within the United Kingdom at all stages. A particular case is where
there is no established guidance or code of there is an unplanned delay to the imple-
practice for the design of façade retention mentation of the permanent works, some-
structures. The lack of such guidance was times by a number of years.
noted as a concern during the course of
consultations. Health and safety issues
Publication of the output of the Façade retention incorporates a number
research project in late 2002, together of activities which may themselves indi- Above: A dramatic example: retention of second and third
with the companion site guide, will vidually present significant hazards. floors of 5, Duke Street, Marks & Spencer, Grafton Street,
provide the industry standard which it is Again, specific recommendations are Dublin
hoped will then be referenced as authori- made, including:
tative guidance by all relevant parties. In • risk assessments should be carried out Below: a rare collapse of a heritage façade in Sydney,
addition to covering the technical, contrac- to determine the inspection regime; Australia in 1990. There were, fortunately, few injuries and
tual and organisational aspects of the • inspections should be carried out and no fatalities
subject, the guide also includes a broad recorded by a competent individual in
selection of case studies and a full set of accordance with a site-specific sched-
design calculations for the retention struc- ule;
ture in one of the projects reported. • residual hazards should be identified as
The involvement of the HSE, both in far as foreseeable in the health and
terms of funding and through the chair- safety plan.
manship and membership of the steering
group, is a reflection of the concern over The responsibilities of the different
the specific health and safety issues asso- parties under the CDM Regulations are
ciated with façade retention. This is seen discussed. Of particular significance is the
in the context of major concern more obligation of the client to provide relevant
generally on such issues within the information about the site and ‘not to
construction industry. The guide covers leave it to contractors to discover hazards’.
this topic in some depth. This is a powerful argument for an early
Within Arup, this project is seen as an and thorough investigation of the existing
important aspect of ongoing work on construction to be carried out. Too often
existing buildings, now being spearheaded this is not given the requisite importance
through an internal network which brings due to concerns over cost and time,
together all aspects of such work on a leading to subsequent delay and difficulty
cross-discipline, inter-office basis. once the main works commence.

Responsibilities Design for wind


A number of important issues regarding The guide recommends that wind loads
the responsibilities of the different parties for the design of the façade retention
are identified. structure should be calculated using BS
One of the key recommendations is for 6399: Part 2 – although it comments that
the appointment of an appropriately qual- that the current edition of BS 5975 still
ified and experienced Temporary Works uses CP 3 Chapter V.
Coordinator for all façade retention Guidance is given on the application of
schemes. Identifying also that the design this code to the design of a temporary
may pass between different parties as the façade retention structure. It is noted that
project progresses, it is further recom- wind forces may be calculated using

19 November 2002 – The Structural Engineer|17


research update: masonry façades

be provided in preference to designing to tion structures. In the temporary case it is


resist its effects, although design loads are more common to clamp the two structures
proposed for cases where this cannot be together using existing openings as far as
done. possible in order to avoid damage to what
is often historic fabric.
Monitoring Given that the vast majority of retained
Information is given on methods of moni- façades are of masonry construction – the
toring and the importance of establishing specific focus of the guide – the general
either the standard or the directional Above: a suitable regime at an early stage. recommendation for the permanent
method. The former is usually applicable A newly Interpretation of the data is discussed, in connections is to use bonded anchors, with
on sites of essentially rectangular plan completed façade particular the need to consider carefully an injection system employed in the most
form, while the latter may offer significant adjoining the both the underlying causes of recorded common use of resin anchors. Both the
economies for larger buildings of less Wigmore Hall in movements, and to look at trends. system and the method of application are
regular plan form. London Illustrations are provided of graphical most suitable for use in old masonry,
Detailed consideration was given to the records of movements, together with which tends to be inherently variable and
appropriate value of Sp to be used for the Top right: interpretation. While design parameters may incorporate inter alia unbonded
design of the retention structure, looking Protecting a for the retention structure are generally skins, an irregular rubble core and voided
at it as a temporary structure and there- conserved façade associated with movement due to wind, units.
fore considering the possibility of using a during building the measured movements are most often Concerns over the use of resin have
value of less than 1.0. However, the a consequence of thermal effects, which been expressed in relation to both
working group preparing the wind may vary quite significantly on a daily performance in fire and long-term creep of
loading guidance for BS 5973 and BS basis, and also ground movement. the material. These are reviewed and
5975 has recommended that temporary reassurance given in both cases.
structures should have a reliability equiv- Fixings Fixings for retained façades more
alent to that of permanent structures, and The guide contains some discussion on generally, and the long-term creep
that the probability factor should not be the connections between the façade and performance of resins were both
reduced unless there were no risks to the both the permanent and temporary reten- presented in more detail by Arup at the
public or workers on the site. This view is 10th Hilti Fastening Academy held in
endorsed by the Building Research London at Imperial College on 21 August
Establishment and the recommendation 2002. More information on the event can
has been adopted within the guide. be found on the website:
(www.hilti.co.uk/editorial).
Other design parameters for the
temporary façade retention system Industry consensus
The different loads that may act upon a Throughout the research period and the
retention structure are described. Façade production of the final publications there
offsets and out-of-plumb generate lateral has been widespread support and cooper-
loading effects have to be considered in ation for the project, and acknowledge-
combination with wind and other loads. ment of the need for it, from both the
These may be significant. steering group and other parties who
Recommendations are given for minimum were consulted.
values, together with the principal lateral Information has been made readily
load combinations to be considered. Right: available; an industry workshop held
It is recommended that the design of The installation of prior to the issue of the second draft
the typical temporary façade retention acoustic bearings received great support and provided valu-
structure should limit its lateral deflec- in the connections able input on specific topics. It is firmly
tion to height/750 under load. The differ- between the believed that the guide has benefited
ent effects that may contribute to actual façades and the greatly from this cooperative approach
deflections on site are discussed. new structure at and can be justifiably represented as
It is also recommended that protection Oxford Circus, containing a consensus view from the
against impact, wherever possible, should Manchester industry. se

18|The Structural Engineer – 19 November 2002

You might also like