You are on page 1of 29

1. ARTHUR F.

ALLEN,  vs. THE PROVINCE OF TAYABAS, G.R. No. L-12283, Appellant's assignments of error relate to the findings of fact and two main issues
July 25, 1918 of law. We pass the facts for the moment, and two main issues of law. We pass the
facts for the moment, to discuss the legal questions.
FACTS:
The first contention of appellant is that the Province of Tayabas is not obligated to
 pay the contractor anything because the contract was not approved by the
Governor-General. This position is absolutely untenable. The law in force when the
contract entered into and when the action was tried, section 2, Act No. 83, as
On April 18, 1914, the Province of Tayabas, represented by the Director of Public
amended by Act No. 1600, made the approval of the Governor-General a
Works, and Arthur F, Allen, contractor, entered into a contract whereby the
prerequisite only to the purchase and conveyance of real estate by a province. The
contractor agreed to construct five reenforced concrete bridges for P39,200. This
grammatical construction of the English text, which is controlling, makes this
contract was in the usual form. One provision was that the bridges were to be
perfectly clear. Moreover, the law now in force (Administrative Code of 1917,
constructed "in accordance with the said advertisements, instructions to bidders,
section 2068) has removed any possibility of doubt and has at the same time
general conditions, plans, specifications, proposal, and this agreement." Other
revealed legislative intention, by placing the requirement for the Governor-
paragraphs of the contract concerned the method and rate of payment for extras.
General's approval of transfers of real estate by provinces in a section separate
and distinct from the section of the Code giving the corporate powers of provinces.
Four of the bridges were accepted by the Government and paid for. The dispute
between the parties arose as to the fifth bridge, No. 53.3 and as to certain extras.
The remaining legal issue merits more extended consideration. Appellant's
As to this bridge, the Province of Tayabas paid to the contractor P4,360 on
contention is that the certificate by the district engineer and the Director of Public
account of the contract price thereof, but refused to pay the balance of P2,840
Works must be obtained before suit can be brought on a contract; that the findings
because plaintiff had deviated from the specifications and because the work was
of these officials are conclusive; and that the complaint must contain an averment
defective. The province further refused to pay for certain extras. To recover the
to this effect. Appellee's reply must contain an averment to this effect. Appellee's
balance upon the contract was the purpose of the contractor in bringing action for
reply is that neither the law nor the contract requires the submission to arbitration
P9,685 (amended complaint), alleged to be due him by the Province of Tayabas.
of disputes between the Government and the contractor, and that a mere
The common averments of the six causes of action were: (1) Residence; (2) the
administrative procedure incident to payment has been established.
contract; (3) the faithful compliance "with all the terms and conditions of the said
contract" on the part of the contractor, and completion and delivery of the bridges
in question; (4) refusal of defendant to pay plaintiff the balance due for bridge No. Act No. 1401, as amended by Act No. 1752, was in force when this action was
53.3 for certain extras, and as damages, although frequently requested to do so. instituted. The same provisions are now found in slightly altered phraseology in
Defendant demurred to the complaint on the ground that it did not state facts section 1917-1923 of the Administrative Code of 1917. The law gives a district
sufficient to constitute a cause of action, because: (a) The approval of the engineer supervision over all contacts connected with public works, which exceed
Governor-General to the contract had not been given as contemplated by section 2 the estimated cost of P500. Section 6 of Act No. 1401, as amended by section 3 of
of the Provincial Government Act (No. 83) and (b) the certificate for payment had Act No. 1752, reads:
not been accomplished by the Director of Public Works or the district engineer as
provided by section 6, of Act No. 1401, as amended. The demurrer was overruled. No payments, partial or final, shall be made on any public works without a
Thereupon defendant answered, renewing as a special defense the grounds of the certificate on the vouchers therefor to the effect that the work for which
demurrer, alleging defective work on the part of the plaintiff, and admitting a total of payment is contemplated has been accomplished, inspected, and
P2,454.78, the amount certified by the Director of Public Works and the district accepted. Such certificate for work under the supervision of the district
engineer, as due the plaintiff. The trial court gave judgment for the plaintiff- engineer shall be signed by him or his duly authorized representative. For
contractor for P4,905, with legal interest from July 14, 1914, and costs. Defendant work not under his supervision such certificate shall be signed by the
moved for a new trial, which was denied, duly excepted and perfected a bill of provincial treasurer.
exceptions to this court.
Section 1922 of the Administrative Code of 1917, reads:
No payment, partial or final, shall be made on any public work of Both the law and the contract provide in mandatory language for a certificate of
construction or repair without a certificate on the voucher therefor to the acceptance by the Director of Public Works or his representative before any
effect that the work for which payment is contemplated has been payment shall be made on any public work for the Government.
accomplished in accordance with the terms of the contract and has been
duly inspected and accepted. Such certificate shall be signed by a duly Contracts of this character, giving into the hands of a third person or of the
authorized representative of the Director of Public Works having full purchaser the power of acceptance or non-acceptance, are not unusual. Courts
knowledge of the facts in the case. have frequently upheld them. The law regards the parties as competent to contract
in this manner. Municipal and provincial contracts, being on the same footing as
Contractors are of course bound to take notice of the provisions of the law relating those of natural persons, may not be breached with impunity. That mutuality exists
to contracts. Statutory requirements cannot be departed from for the in undoubted. The party who deliberately enters into such an agreement, whether
accommodation of either party to a contract. As a matter of acts, in the present wisely or unwisely, must abide by it. The public corporation, in the absence of a
instance, this obligation is intensified in so far as the contractor is concerned for showing of fraud or concealment, is estopped by the approval of its officer who is
the instructions to bidders contains this clause: "The contractor shall comply with authorized to accept the work, from contesting the contractor's right to the contract
all existing or future laws, the municipal or provincial building ordinances and price. (City of Omaha vs. Hammond [1876], 94 U.S., 98; City Street Improvement
regulations in so far as the same are binding upon or affect the parties hereto, the Co. vs. City of Marysville, [1909], 155 cal., 419.) Likewise, the contractor must not
work, or those engaged thereon." (No. 23). only deliver a product with which the party of the second party ought to be
satisfied, but with which he must be satisfied, or he is not bound to accept it. The
The instructions to bidders, a part of the contract, under the heading of rule is well-settled that in the absence of fraud or of such gross mistake as would
"Payments," also contains the following: necessarily imply bad faith, contractors with public corporations are concluded by
the decisions of engineers or like officers where the contract contains such a
stipulation. The public corporation can rely on the provision in a contract that
51. Payments will be made monthly, based upon the estimates of work
performance by the other party shall be approved by or satisfactory to it, or a
satisfactorily completed and accepted by the Director during the preceding
particular officer, board or committee. (Second Nat. Bank vs. Pan-American Bridge
month. Upon such estimates the Province of Tayabas, P.I. shall pay to the
Co. [1910], 183 Fed., 391, reviewing Federal decisions; Silsby Manuf'g
contractor a sum equal to ninety (90) per cent thereof up to and until such
Co. vs. Town of Chico [1885], 24 Fed., 893; 23 L.R.A. [1910], 322, Notes.)
time as the total work shall have been completed or the contract canceled,
as herein provided.
A leading example is the case of Sweeney vs. United States ([1883], 109 U.S.,
618), in which a contractor sought to recover from the United States the price of
52. The acceptance of the work from time to time for the purpose of
wall built by him around the National Cemetery. The contract provided that the wall
making partial payments, shall not be considered as a final acceptance of
shall be received and become the property of the United States after the officer or
the work in question.
civil engineer, to be designated by the Government to inspect the work, should
certify that it was in all respects such as the contractor agreed to construct. The
53. Whenever the contract, in the opinion of the Director, shall be officer designated for that purpose refused to so certify on the ground that neither
completely performed on the part of the contractor, the Director shall the material nor the workmanship was such as the contract required. As the officer
proceed promptly to measure the work and shall make out and certify the exercised an honest judgment in making his inspection and as there was on his
final estimates and acceptance for the same. The province shall then, part neither fraud nor such grave mistake as implied bad faith, it was adjudged that
excepting for cause herein specified, pay to the contractor promptly after the contractor had no cause of action on the contract against the United States.
the execution of said certificate the remainder which shall be found due,
excepting therefrom such sum or sums as may be lawfully retained under
The old common law rule required a strict or literal performance of contracts. The
any of the provisions of this contract; Provided, That nothing herein
modern rule sanctions a substantial performance of contractual relations. The law
contained shall be construed to waive the right of the Director, hereby
now looks to the spirit of the contract and not to its letter. Even though a plaintiff is
reserved, to reject the whole or any portion of the aforesaid work should
not entirely free from fault or omission, the courts will not turn him away if he has in
the same be found to have been constructed in violation of any of the
good faith mad substantial performance. Of course the terms of the contract may
conditions or covenant of this contract.
be such that the contract has agreed that the another shall have the absolute and
unreviewable right to reject the article or work if not satisfied with it; in such case Phil., 399), is a valid one in law, and unless it be first complied with, no action can
the contractor shall abide by his word. But when the terms, or the nature of the be brought.
contract, or the circumstances are such as to make it doubtful, whether the
contractor has made any such unwise agreement, the courts will ordinarily What then are the remedies of the contractor? In the first place he has his
construe the contract as an "agreement to do the thing in such way as reasonably administrative remedy, which is to complete the work substantially according to the
ought to satisfy the defendant." (Parlin & Orendorff Co. vs. City of Greenville contract and ask for the approval of the proper official. If such officer refuse or
[1904], 127 Fed., 55; Swain vs. Seamens [1870], 9 Wall., 254.) Thus, it has been culpably neglect to perform a ministerial duty, such as making out the warrant, it is
held that the provision of a contract to perform work for the city requiring the possible that mandamus will lie to coerce the officer. A stipulation requiring the
contractor to obtain the certificate of the city engineer that the work has been done approval of some one as a condition to a recovery by the contractor would not bar
in accordance with the contract and the approval of such work by certain boards or the party of his remedies by action at law. The right to redress in the courts where
committees, before he is entitled to payment therefor, does not deprive him of the substantial compliance with the terms of a contract are set forth, and where the
right to recover for the work, if it has been done in substantial conformity to the proof discloses the withholding of the certificate by an officer for insufficient
contract, because the city's officers arbitrarily or unreasonably refuse the certificate reasons, should not be taken away by inference or anything short of a district
and approval called for. (City of Elizabeth vs. Fitzgerald [1902], 200 U.S., 611.) agreement to waive it. (Aetna Indemnity Co. vs. Waters [1909], 110 Md., 673.) As
a condition precedent to action by the courts, fraud or bad faith on the part of the
Substantial performance and the unfounded refusal of the certificate of approval responsible Government official, or arbitrary or unreasonable refusal of the
can be proved in various ways. Thus, acceptance and occupancy of the building certificate or approval must be alleged and proved.
by the owner amounts to an acknowledgment that the work has been performed
substantially as required by the contract. (Campbell and Go-Tauco vs. Behn, To concentrate our facts and legal principles — we find the contractor supported
Meyer & co. [1904], 3 Phil., 590 affirmed on appeal to the United States Supreme by one expert insisting that the work and the materials actually conform to the
Court [1905], 200 U.S., 611.) Other circumstances, as partial payment, also show specifications; and we have this as resolutely denied by competent Government
acquiescence on the part of purchaser. engineers. We find substantial performance of the contract not proved to the
satisfaction of the Government's technical adviser, but proved to the satisfaction of
Appellee speaks of the provisions of the law and the portions of the contract in the trial court. Ordinarily, we would not review the facts unless the findings of the
questions as possibly constituting an arbitration agreement. We deem these trial court are plainly and manifestly contrary to the proof. But here it was
provisions to be more correctly labeled a condition precedent to the contractor's incumbent on the trial court to take about the same view of the findings of the
right to obtain payment; the condition is for the satisfaction of the Government. Government's engineers as the appellate court would take of the findings of the
Nevertheless, considered as species of abitration, it was a convenient and proper trial court, or that any court would take of the findings of customs boards,
method, duly agreed upon between the parties, to determine questions that would assessors, and the like. In order to set aside the action of the Director of Public
necessarily arise in the performance of the contract, about which men might Works or his authorized representative, fraud or bad faith on the part of these
honestly differ. It would be highly improper, for courts out of untoward jealousy of engineers must be established. Has this been proved? The judge in the course of
their jurisdiction. The New York theory of refusal to uphold such agreements, his decision incidentally remarked: "It may as well be said here that there appears
because of the opinion that they violate the spirit of the laws creating the courts, is to have been a great deal of ill-feeling between plaintiff and the engineer in charge
hardly agreed to by more progressive jurisdictions. (See U.S. Asphalt Refining of this construction." Is this observation in connection with the testimony of the
Co. vs. Trinidad Lake Petroleum Co. [1915], 222 Fed., 1006.) Unless the plaintiff and of one engineer sufficient to demonstrate fraud or bad faith? We think
agreement is such as absolutely to close the doors of the courts against the not. In other words we believe that the contractor cannot maintain an action for the
parties, which agreement would be void (Wahl and Wahl vs. Donaldson, Sims & stipulated price when the engineer has in good faith, in pursuance of the contract,
Co. [1903], 2 Phil., 301), courts will look with favor upon such amicable withheld his certificate. The decision of the responsible engineer cannot be
arrrangements and will only with great reluctance interfere to anticipate or nullify subjected to the revisory power of the courts without doing violence to the terms of
the action of the arbitrator. For instance, a policy of fire insurance, contained a the contract and the law.
clause providing that in the event of a loss under the policy, unless the company
shall deny all liability, as a condition precedent to the bringing of any suit by the The Province of Tayabas, having accepted bridge No. 53.2, should of course pay
insured upon the policy, the latter should first submit the question of liability and the balance due, or P2,840. It should not be permitted to deduct the cost of the test
indemnity to arbitration. Such a condition, the Supreme Court of the Philippines of the bridge, P900.12, for this is a legal question for resolution by the courts, and
held in Chang vs. Royal Exchange Assurance Corporation of London ([1907], 8
the contract contains no such stipulation. (See Ripley vs. U.S. [1912], 223 U.S.,
695.) But the findings of the Government engineers on all the other points covered
by causes of action 2, 3, 4, 5 and 6 are deemed to be conclusive, fraud or bad faith
not having been proved. Thus, we have P2,840, plus P269.10, plus P214.80, plus
P6, plus P25, or P3,354.90 due plaintiff.

One point made by appellant is that the demurrer to the complaint was improperly
overruled. An elementary principle of pleading heretofore approved by this court in
Government of Philippine Islands vs. Inchausti & Co. ([1913], 24 Phil., 315) is
brought to our notice, namely: "If the plaintiff's right of action depends upon a
condition precedent he must allege and prove the fulfillment of the condition or a
legal excuse for its non-fulfillment. And if he omits such allegation, his declaration,
complaint, or petition, will be bad on demurrer." Undoubtedly, the complaint should
have alleged either the performance of the condition precedent, approval by the
Director of Public Works or the District Engineer, or a good and sufficient excuse
for not obtaining it. It is possible that if sitting in first instance, we would so hold
with defendant, but on appeal such a backward sweep would avail nothing but
delay. Moreover, the complaint contains the general averment that the plaintiff fully
and faithfully complied with all the terms and conditions of the said contract, while
some months subsequent to the filing of the complaint but previous to the trial, the
defendant accepted the bridge. A failure to allege a condition precedent or a legal
reason for dispensing with it may be cured by the issues tendered by the answer
and the proof. (Donegan vs. Houston [1907], 5 Cal. App., 626.)

To summarize, we are of opinion and so hold that the law makes the approval of
the Governor-General a prerequisite only to the purchase or conveyance of real
property by a province; that the provisions of the law and the form of the contract,
usually followed in this jurisdiction, providing for the certificate of approval by the
Director of Public Works or his representative, are in the nature of a condition
precedent, which must be alleged and proved, and that this certificate is conclusive
in the absence of a showing of fraud or bad faith.

Judgment shall be modified so that the plaintiff shall recover from the defendant
P3,354.90 with legal interest thereon from July 14, 1914, until paid, without special
finding as to costs in either instance. So ordered.

Torres, Johnson and Fisher, JJ., concur.


Carson and Street, JJ., concur in the result.
2. G.R. No. 121171 December 29, 1998 The Philippine Government undertook to support the financing of MMIC by
purchase of MMIC debenture bonds and extension of guarantees. Further, the
ASSET PRIVATIZATION TRUST, petitioner, Philippine Government obtained a firm commitment form the DBP and/or other
vs. government financing institutions to subscribe in MMIC and issue guarantee/s for
COURT OF APPEALS, JESUS S. CABARRUS, SR., JESUS S. CABARRUS, JR., foreign loans or deferred payment arrangements secured from the US Eximbank,
JAIME T. CABARRUS, JOSE MIGUEL CABARRUS, ALEJANDRO S. PASTOR, Asian Development Bank, Kobe Steel, of amount not exceeding US$100 Million.2
JR., ANTONIO U. MIRANDA, and MIGUEL M. ANTONIO, as Minority Stock-
Holders of Marinduque Mining and Industrial Corporation, respondents. DBP approved guarantees in favor of MMIC and subsequent requests for
guarantees were based on the unutilized portion of the Government commitment.
Thereafter, the Government extended accommodations to MMIC in various
amounts.
KAPUNAN, J.:
On July 13, 1981, MMIC, PNB and DBP executed a Mortgage Trust
Agreement3 whereby MMIC, as mortgagor, agreed to constitute a mortgage in
The petition for review on  certiorari before us seeks to reverse and set aside the
favor or PNB and DBP as mortgagees, over all MMIC's assets; subject of real
decision of the Court of Appeals which denied due course to the petition
estate and chattel mortgage executed by the mortgagor, and additional assets
for certiorari  filed by the Asset Privatization Trust (APT) assailing the order of the
described and identified, including assets of whatever kind, nature or description,
Regional Trial Court (RTC) Branch 62, Makati City. The Makati RTC's order upheld
which the mortgagor may acquire whether in substitution of, in replenishment, or in
and confirmed the award made by the Arbitration Committee in favor of
addition thereto.
Marinduque Mining and Industrial Corporation (MMIC) and against the
Government, represented by herein petitioner APT for damages in the amount of
P2.5 BILLION (or approximately P4.5 BILLION, including interest). Article IV of the Mortgage Trust Agreement provides for Events of Default, which
expressly includes the event that the MORTGAGOR shall fail to pay any amount
secured by this Mortgage Trust Agreement when due. 4
Ironically, the staggering amount of damages was imposed on the Government for
exercising its legitimate right of foreclosure as creditor against the debtor MMIC as
a consequence of the latter's failure to pay its overdue and unpaid obligation of Article V of the Mortgage Trust Agreement prescribes in detail, and in addition to
P22 billion to the Philippine National Bank (PNB) and the Development Bank of the the enumerated events of defaults, circumstances by which the mortgagor may be
Philippines (DBP). declared in default, the procedure therefor, waiver of period to foreclose, authority
of Trustee before, during and after foreclosure, including taking possession of the
mortgaged properties.5
The antecedent facts
of the case.
In various requests for advances/remittances of loans if huge amounts, Deeds of
Undertaking, Promissory Notes, Loan Documents, Deeds of Real Estate
The development, exploration and utilization of the mineral deposits in the Surigao
Mortgages, MMIC invariably committed to pay either on demand or under certain
Mineral Reservation have been authorized by Republic Act No. 1528, as amended
terms the loans and accommodations secured from or guaranteed by both DBP
by Republic Acts Nos. 2077 and 4167, by virtue of which laws, a Memorandum of
and PNB.
Agreement was drawn on July 3, 1968, whereby the Republic of the Philippines
thru the Surigao Mineral Reservation Board, granted MMIC the exclusive right to
explore, develop and exploit nickel, cobalt and other minerals in the Surigao By 1984, DBP and PNB's financial both in loans and in equity in MMIC had
mineral reservation.1 MMIC is a domestic corporation engaged in mining with reached tremendous proportions, and MMIC was having a difficult time meeting its
respondent Jesus S. Cabarrus, Sr. as President and among its original financial obligations. MMIC had an outstanding loan with DBP in the amount of
stockholders. P13,792,607,565.92 as of August 31, 1984 and with PNB in the amount of
P8,789,028,249.38 as July 15, 1984 or a total Government expose of Twenty Two
Billion Six Hundred Sixty-Eight Million Five Hundred Thirty-Seven Hundred
Seventy and 05/100 (P22, 668,537,770.05), Philippine Currency. 6 Thus, a In withdrawing their dispute from the court and in choosing to
financial restructuring plan (FRP) designed to reduce MMIC's interest expense resolve it through arbitration, the parties have agreed that:
through debt conversion to equity was drafted by the Sycip Gorres Velayo
accounting firm. 7 On April 30, 1984, the FRP was approved by the Board of (a) their respective money claims shall be reduced to purely
Directors of the MMIC.8 However, the proposed FRP had never been formally money claims; and
adopted, approved or ratified by either PNB or DBP.9
(b) as successor and assignee of the PNB and DBP interests in
In August and September 1984, as the various loans and advances made by DBP MMIC and the MMIC accounts, APT shall likewise succeed to the
and PNB to MMIC had become overdue and since any restructuring program rights and obligations of PNB and DBP in respect of the
relative to the loans was no longer feasible, and in compliance with the directive of controversy subject of Civil Case No. 9900 to be transferred to
Presidential Decree No. 385, DBP and PNB as mortgagees of MMIC assets, arbitration and any arbitral award/order against either PNB and/or
decided to exercise their right to extrajudicially foreclose the mortgages in DBP shall be the responsibility be discharged by and be
accordance with the Mortgage Trust Agreement. 10 enforceable against APT, the parties having agreed to drop PNB
and DBP from the arbitration.
The foreclosed assets were sold to PNB as the lone bidder and were assigned to
three newly formed corporations, namely, Nonoc Mining Corporation, Maricalum 2. Submission. The parties hereby agree that (a) the controversy
Mining and Industrial Corporation, and Island Cement Corporation. In 1986, these in Civil Case No. 9900 shall be submitted instead to arbitration
assets were transferred to the Asset Privatization Trust (APT). 11 under RA 876 and (b) the reliefs prayed for in Civil Case No. 9900
shall, with the approval of the Trial Court of this Compromise and
On February 28, 1985, Jesus S. Cabarrus, Sr., together with the other Arbitration Agreement, be transferred and reduced to pure
stockholders of MMIC, filed a derivative suit against DBP and PNB before the RTC pecuniary/money claims with the parties waiving and foregoing all
of Makati, Branch 62, for Annulment of Foreclosures, Specific Performance and other forms of reliefs which they prayed for or should have prayed
Damages. 12 The suit, docketed as Civil Case No. 9900, prayed that the court: (1) for in Civil Case No. 9900. 13
annul the foreclosures, restore the foreclosed assets to MMIC, and require the
banks to account for their use and operation in the interim; (2) direct the banks to The Compromise and Arbitration Agreement limited the issues to the following:
honor and perform their commitments under the alleged FRP; and (3) pay moral
and exemplary damages, attorney's fees, litigation expenses and costs. 5. Issues The issues to be submitted for the Committee's
resolution shall be (a) Whether PLAINTIFFS have the capacity or
In the course of the trial, private respondents and petitioner APT, as successor of the personality to institute this derivative suit in behalf of the MMIC
the DBP and the PNB's interest in MMIC, mutually agreed to submit the case to or its directors, (b) Whether or not the actions leading to, and
arbitration by entering into a "Compromise and Arbitration Agreement," including,. the PNB-DBP foreclosure of the MMIC assets were
stipulating,  inter alia: proper, valid and in good
faith. 14
NOW THEREFORE, for and in consideration of the foregoing
premises and the mutual covenants contained herein the parties This agreement was presented for approval to the trial court. On October 14, 1992,
agree as follows: the Makati RTC, Branch 61, issued an order, to wit:

1. Withdrawal and Compromise. The parties have agreed to WHEREFORE, this Court orders:
withdraw their respective claims from the Trial Court and to
resolve their dispute through arbitration by praying to the Trial 1. Substituting PNB and DBP with the Asset
Court to issue a Compromise Judgment based on this Privatization Trust as party defendant.
Compromise and Arbitration Agreement.
2. Approving the Compromise and Arbitration in the obligations of, MMIC in proportion to its 87% equity in tile
Agreement dated October 6, 1997, attached as total capital stock of MMIC.
Annex "C" of the Omnibus Motion.
x x x           x x x          x x x
3. Approving the Transformation of the reliefs
prayed for [by] the plaintiffs in this case into pure As this Committee holds that the FRP is valid, DBP's equity in
money claims; and MMIC is raised to 87%. So pursuant to the above provision of the
Compromise and Arbitration Agreement, the 87% equity of DBP is
4. The Complaint is hereby DISMISSED. 15 hereby deducted from the actual damages of P19,486,118,654.00
resulting in the net actual damages of P2,531,635,425.02 plus
The Arbitration Committee was composed of retired Supreme Court Justice interest.
Abraham Sarmiento as Chairman, Atty. Jose C. Sison and former Court of Appeals
Justice Magdangal Elma as Members. On November 24, 1993, after conducting DISPOSITION
several hearings, the Arbitration Committee rendered a majority decision in favor
of MMIC, the pertinent portions of which read as follows: WHEREFORE, premises considered, judgment is hereby
rendered:
Since, as this Committee finds, there is no foreclosure at all as it
was not legally and validly done, the Committee holds and so 1. Ordering the defendant to pay to the Marinduque Mining and
declares that the loans of PNB and DBP to MMIC. for the payment Industrial Corporation, except the DBP, the sum of
and recovery of which the void foreclosure sales were undertaken, P2,531,635,425.02 with interest thereon at the legal rate of six per
continue to remain outstanding and unpaid. Defendant APT as the cent (6%) per annum  reckoned from August 3, 9, and 24,
successor-in-interest of PNB and DBP to the said loans is 1984, pari passu, as and for actual damages. Payment of these
therefore entitled and retains the right, to collect the same from actual damages shall be offset by APT from the outstanding and
MMIC pursuant to, and based on the loan documents signed by unpaid loans of MMIC with DBP and PNB, which have not been
MMIC, subject to the legal and valid defenses that the latter may converted into equity. Should there be any balance due to MMIC
duly and seasonably interpose. Such loans shall, however, be after the offsetting, the same shall be satisfied from the funds
reduced by the amount which APT may have realized from the representing the purchase price of the sale of the shares of Island
sale of the seized assets of MMIC which by agreement should no Cement Corporation in the amount of P503,000,000.00 held under
longer be returned even if the foreclosures were found to be null escrow pursuant to the Escrow Agreement dated April 22, 1988 or
and void. to such subsequent escrow agreement that would supercede [sic]
it pursuant to paragraph (9) of the Compromise and Arbitration
The documentary evidence submitted and adopted by the parties Agreement;
(Exhibits "3", "3-B"; Exhibit "100"; and also Exhibit "ZZZ") as their
exhibits would show that the total outstanding obligation due to 2. Ordering the defendant to pay to the Marinduque Mining and
DBP and PNB as of the date of foreclosure is Industrial Corporation, except the DBP, the sum of
P22,668,537,770.05, more or less. P13,000.000.00, as and for moral and exemplary damages.
Payment of these moral and exemplary damages shall be offset
Therefore defendant APT can, and is still entitled to, collect the by APT from the outstanding and unpaid loans of MMIC with DBP
outstanding obligations of MMIC to PNB and DBP amounting to and PNB, which have not been converted into equity. Should there
P22,668,537,770.05, more or less, with interest thereon as be any balance due to MMIC after the offsetting, the same shall be
stipulated in the loan documents from the date of foreclosure up to satisfied from the funds representing the purchase price of the
the time they are fully paid less the proportionate liability of DBP sale of the shares of Island Cement Corporation in the amount of
as owner of 87% of the total capitalization of MMIC under the P503,000,000.00 held under escrow pursuant to the Escrow
FRP. Simply put, DBP shall share in the award of damages to, and Agreement dated April 22, 1988 or to such subsequent escrow
agreement that would supercede [sic] it pursuant to paragraph (9) 4. Under Section 24 of Rep. Act 876, the Court must make an
of the Compromise and Arbitration Agreement; order vacating the award where the arbitrators exceeded their
powers, or so imperfectly executed them, that a mutual, final and
3. Ordering the defendant to pay to the plaintiff, Jesus S. definite award upon the subject matter submitted to them was not
Cabarrus, Sr., the sum of P10,000,000.00, to be satisfied likewise made. 17
from the funds held under escrow pursuant to the Escrow
Agreement dated April 22, 1988 or to such subsequent escrow Private respondents filed a "REPLY AND OPPOSITION" dated November 10,
agreement that would supersede it, pursuant to paragraph (9) of 1984, arguing that a dismissal of Civil Case No. 9900 was merely a "qualified
the Compromise and Arbitration Agreement, as and for moral dismissal" to pave the way for the submission of the controversy to arbitration and
damages; and operated simply as "a mere suspension of the proceedings" They denied that the
Arbitration Committee had exceeded its powers.
4. Ordering the defendant to pay arbitration costs.
In an Order dated November 28, 1993, the trial court confirmed the award of the
This Decision is FINAL and EXECUTORY. Arbitration Committee. The dispositive portion of said order reads:

IT IS SO ORDERED. 16 WHEREFORE, premises considered, and in the light of the parties


[sic] Compromise and Arbitration Agreement dated October 6,
1992, the Decision of the Arbitration Committee promulgated on
Motions for reconsideration were filed by both parties, but the same were denied.
November 24, 1993, as affirmed in a Resolution dated July 26,
1994, and finally settled and clarified in the Separate Opinion
On October 17, 1993, private respondents filed in the same Civil Case No. 9900 dated September 2, 1994 of Committee Member Elma, and the
an "Application/Motion for Confirmation of Arbitration Award." Petitioner countered pertinent provisions of RA 876, also known as the Arbitration Law,
with an "Opposition and Motion to Vacate Judgment" raising the following grounds. this Court GRANTS PLAINTIFFS' APPLICATION AND THUS
CONFIRMS THE ARBITRATION AWARD, AND JUDGMENT IS
1. The plaintiffs Application/Motion is improperly filed with this HEREBY RENDERED:
branch of the Court, considering that the said motion is neither a
part nor the continuation of the proceedings in Civil Case No. 9900 (a) Ordering the defendant APT to the Marinduque Mining and
which was dismissed upon motion of the parties. In fact, the Industrial Corporation (MMIC), except the DBP, the sum of
defendants in the said Civil Case No. 9900 were the Development P3,811,757,425.00, as and for actual damages, which shall be
Bank of the Philippines and the Philippine National Bank (PNB); partially satisfied from the funds held under escrow in the amount
of P503,000,000.00 pursuant to the Escrow Agreement dated April
2. Under Section 71 of Rep. Act 876, an arbitration under a 22, 1988. The balance of the award, after the escrow funds are
contract or submission shall be deemed a special proceedings and fully applied, shall be executed against the APT;
a party to the controversy which was arbitrated may apply to the
court having jurisdiction, (not necessarily with this Honorable (b) Ordering the defendant to pay to the MMIC, except the DBP,
Court) for an order confirming the award; the sum of P13,000,000.00 as and for moral and exemplary
damages;
3. The issues submitted for arbitration have been limited to two:
(1) propriety of the plaintiffs filing the derivative suit and (2) the (c) Ordering the defendant to pay to Jesus S. Cabarrus, Sr., the
regularity of the foreclosure proceedings. The arbitration award sum of P10,000,000.00 as and for moral damages; and
sought to be confirmed herein, far exceeded the issues submitted
and even granted moral damages to one of the herein plaintiffs;
(d) Ordering the defendant to pay the herein THE ORIGINAL CASE, CIVIL CASE NO. 9900, HAD
plaintiffs/applicants/movants the sum of P1,705,410.23 as PREVIOUSLY BEEN DISMISSED.
arbitration costs.
II
In reiteration of the mandates of Stipulation No. 10 and Stipulation
No. 8 paragraph 2 of the Compromise and Arbitration Agreement, THE RESPONDENT JUDGE COMMITTED GRAVE ABUSE OF
and the final edict of the Arbitration Committee's decision, and with DISCRETION AND ACTED WITHOUT OR IN EXCESS OF
this Court's Confirmation, the issuance of the Arbitration JURISDICTION, IN ISSUING THE QUESTIONED ORDERS
Committee's Award shall henceforth be final and executory. CONFIRMING THE ARBITRAL AWARD AND DENYING THE
MOTION FOR RECONSIDERATION OF ORDER OF AWARD.
SO ORDERED. 18
III
On December 27, 1994, petitioner filed its motion for reconsideration of the Order
dated November 28, 1994. Private respondents, in turn, submitted their reply and THE RESPONDENT JUDGE GROSSLY ABUSED HIS
opposition thereto. DISCRETION AND ACTED WITHOUT OR IN EXCESS OF AND
WITHOUT JURISDICTION IN RECKONING THE COUNTING OF
On January 18, 1995, the trial court handed down its order denying APT's motion THE PERIOD TO FILE MOTION FOR RECONSIDERATION, NOT
for reconsideration for lack of merit and for having been filed out of time. The trial FROM THE DATE OF SERVICE OF THE COURT'S COPY
court declared that "considering that the defendant APT, through counsel, officially CONFIRMING THE AWARD, BUT FROM RECEIPT OF A XEROX
and actually received a copy of the Order of this Court dated November 28, 1994 COPY OF WHAT PRESUMABLY IS THE OPPOSING
on December 6, 1994, the Motion for Reconsideration thereof filed by the COUNSEL'S COPY THEREOF. 20
defendant APT on December 27, 1994, or after the lapse of 21 days, was clearly
filed beyond the 15-day reglementary period prescribed or provided for by law for On July 12, 1995, he Court of Appeals, through its Fifth-Division, denied due
the filing of an appeal from final orders, resolutions, awards, judgments or course and dismissed the petition for certiorari.
decisions of any court in all cases, and by necessary implication for the filing of a
motion for reconsideration thereof." Hence, the instant petition for review on  certiorari imputing to the Court of Appeals
the following errors:
On February 7, 1995, petitioner received private respondents' Motion for Execution
and Appointment of Custodian of Proceeds of Execution dated February 6, 1995. ASSIGNMENT OF ERRORS

Petitioner thereafter filed with the Court of Appeals a special civil action I
for certiorari  with temporary restraining order and/or preliminary injunction dated
February 13, 1996 to annul and declare as void the Orders of the RTC-Makati
dated November 28, 1994 and January 18, 1995 for having been issued without or THE COURT OF APPEALS ERRED IN NOT HOLDING THAT
in excess of jurisdiction and/or with grave abuse of discretion. 19 As ground THE MAKATI REGIONAL TRIAL COURT, BRANCH 62 WHICH
therefor, petitioner alleged that: HAS PREVIOUSLY DISMISSED CIVIL CASE NO. 9900 HAD
LOST JURISDICTION TO CONFIRM THE ARBITRAL AWARD
UNDER THE SAME CIVIL CASE AND NOT RULING THAT THE
I APPLICATION FOR CONFIRMATION SHOULD HAVE BEEN
FILED AS A NEW CASE TO BE RAFFLED OFF AMONG THE
THE RESPONDENT JUDGE HAS NOT VALIDLY ACQUIRED DIFFERENT BRANCHES OF THE RTC.
JURISDICTION MUCH LESS, HAS THE COURT AUTHORITY,
TO CONFIRM THE ARBITRAL AWARD CONSIDERING THAT II
THE COURT OF APPEALS LIKEWISE ERRED IN HOLDING 4. The Complaint is hereby DISMISSED. 22
THAT PETITIONER WAS ESTOPPED FROM QUESTIONING
THE ARBITRATION AWARD, WHEN PETITIONER The term "dismiss" has a precise definition in law. "To dispose of an
QUESTIONED THE JURISDICTION OF THE RTC-MAKATI, action, suit, or motion without trial on the issues involved. Conclude,
BRANCH 62 AND AT THE SAME TIME MOVED TO VACATE discontinue, terminate, quash." 23
THE ARBITRAL AWARD.
Admittedly, the correct procedure was for the parties to go back to the court where
III the case was pending to have the award confirmed by said court. However,
Branch 62 made the  fatal mistake of issuing a final order dismissing the case.
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT While Branch 62 should have merely suspended the case and not dismissed
THE RESPONDENT TRIAL COURT SHOULD HAVE EITHER it,24 neither of the parties questioned said dismissal. Thus, both parties as well as
DISMISSED/DENIED PRIVATE RESPONDENTS' said court are bound by such error.
MOTION/PETITION FOR CONFIRMATION OF ARBITRATION
AWARD AND/OR SHOULD HAVE CONSIDERED THE MERITS It is erroneous then to argue, as private respondents do, that petitioner APT was
OF THE MOTION TO VACATE ARBITRAL AWARD. charged with the knowledge that the "case was merely stayed until arbitration
finished," as again, the order of Branch 62 in very clear terms stated that the
IV "complaint was dismissed." By its own action, Branch 62 had lost jurisdiction over
the case. It could not have validly reacquired jurisdiction over the said case on
THE COURT OF APPEALS ERRED IN NOT TREATING mere motion of one of the parties. The Rules of Court is specific on how a new
PETITIONER APT'S PETITION FOR  CERTIORARI  AS AN case may be initiated and such is not done by mere motion in a particular branch
APPEAL TAKEN FROM THE ORDER CONFIRMING THE of the RTC. Consequently, as there was no "pending action" to speak of, the
AWARD. petition to confirm the arbitral award should have been filed as a new case and
raffled accordingly to one of the branches of the Regional Trial Court.
V
II
THE COURT OF APPEALS ERRED IN NOT RULING ON THE
LEGAL ISSUE OF WHEN TO RECKON THE COUNTING OF Petitioner was not estopped from
THE PERIOD TO FILE A MOTION FOR RECONSIDERATION. 21
questioning the jurisdiction of
The petition is impressed with merit.
Branch 62 of the RTC of Makati.
I
The Court of Appeals ruled that APT was already estopped to question the
The RTC of Makati, Branch 62, jurisdiction of the RTC to confirm the arbitral award because it sought affirmative
relief in said court by asking that the arbitral award be vacated.
did not have jurisdiction to confirm
The rule is that "Where the court itself clearly has no jurisdiction over the subject
matter or the nature of the action, the invocation of this defense may be done at
the arbitral award.
any time. It is neither for the courts nor for the parties to violate or disregard that
rule, let alone to confer that jurisdiction this matter being legislative in
The use of the term "dismissed" is not "a mere semantic imperfection". The character." 25 As a rule then, neither waiver nor estoppel shall apply to confer
dispositive portion of the Order of the trial court dated October 14, 1992 stated in jurisdiction upon a court barring highly meritorious and exceptional
no uncertain terms: circumstances. 26 One such exception was enunciated in  Tijam vs.
Sibonghanoy, 27 where it was held that "after voluntarily submitting a cause and Sec 1. Petition for Certiorari: — When any tribunal, board or officer
encountering an adverse decision on the merits, it is too late for the loser to exercising judicial functions, has acted without or in excess of its
question the jurisdiction or power of the court." or his jurisdiction, or with grave abuse of discretion and there is no
appeal, nor any plain, speed, and adequate remedy in the ordinary
Petitioner's situation is different because from the outset, it has consistently held course of law, a person aggrieved thereby may file a verified
the position that the RTC, Branch 62 had no jurisdiction to confirm the arbitral petition in the proper court alleging the facts with certainty and
award; consequently, it cannot be said that it was estopped from questioning the praying that judgment be rendered annulling or modifying the
RTC's jurisdiction. Petitioner's prayer for the setting aside of the arbitral award was proceedings, as the law requires, of such tribunal, board or officer.
not inconsistent with its disavowal of the court's jurisdiction.
In the instant case, the respondent court erred in dismissing the special civil action
III for  certiorari, it being clear from the pleadings and the evidence that the trial court
lacked jurisdiction and/or committed grave abuse of discretion in taking cognizance
of private respondents' motion to confirm the arbitral award and, worse, in
Appeal of petitioner to the
confirming said award which is grossly and patently not in accord with the
arbitration agreement, as will be hereinafter demonstrated.
Court of Appeals thru certiorari
IV
under Rule 65 was proper.
The nature and limits of the
The Court of Appeals in dismissing APT's petition for certiorari  upheld the trial
court's denial of APT's motion for reconsideration of the trial court's order
Arbitrators' power.
confirming the arbitral award, on the ground that said motion was filed beyond the
15-day reglementary period; consequently, the petition for certiorari could not be
resorted to as substitute to the lost right of appeal. As a rule, the award of an arbitrator cannot be set aside for mere errors of
judgment either as to the law or as to the facts. 29 Courts are without power to
amend or overrule merely because of disagreement with matters of law or facts
We do not agree.
determined by the arbitrators. 30 They will not review the findings of law and fact
contained in an award, and will not undertake to substitute their judgment for that
Section 99 of Republic Act No. 876, 28 provides that: of the arbitrators, since any other rule would make an award the commencement,
not the end, of litigation. 31 Errors of law and fact, or an erroneous decision of
. . . An appeal may be taken from an order made in a proceeding matters submitted to the judgment of the arbitrators, are insufficient to invalidate an
under this Act, or from a judgment entered upon an award award fairly and honestly made. 32 Judicial review of an arbitration is thus, more
through  certiorari proceedings, but such appeals shall be limited limited than judicial review of a trial. 33
to questions of law. . . ..
Nonetheless, the arbitrators' award is not absolute and without exceptions. The
The aforequoted provision, however, does not preclude a party aggrieved by the arbitrators cannot resolve issues beyond the scope of the submission
arbitral award from resorting to the extraordinary remedy of certiorari  under Rule agreement. 34 The parties to such an agreement are bound by the arbitrators'
65 of the Rules of Court where, as in this case, the Regional Trial Court to which award only to the extent and in the manner prescribed by the contract and only if
the award was submitted for confirmation has acted without jurisdiction or with the award is rendered in conformity thereto. 35 Thus, Sections 24 and 25 of the
grave abuse of discretion and there is no appeal, nor any plain, speedy remedy in Arbitration Law provide grounds for vacating, rescinding or modifying an arbitration
the course of law. award. Where the conditions described in Articles 2038, 36
2039,   and 1040   of the Civil Code applicable to compromises and arbitration
37 38

Thus, Section 1 of Rule 65 provides: are attendant, the arbitration award may also be annulled.
In Chung Fu Industries (Phils.) vs. Court of Appeals, 39 we held: (b) That there was evident partiality or corruption in the arbitrators
or any of them; or
. . . . It is stated explicitly under Art. 2044 of the Civil Code that the
finality of the arbitrators' award is not absolute and without (c) That the arbitrators were guilty of misconduct in refusing to
exceptions. Where the conditions described in Articles 2038, 2039 postpone the hearing upon sufficient cause shown, or in refusing
and 2040 applicable to both compromises and arbitrations are to hear evidence pertinent and material to the controversy; that
obtaining, the arbitrator's award may be annulled or rescended. one or more of the arbitrators was disqualified to act as such
Additionally, under Sections 24 and 25 of the Arbitration Law, under section nine hereof, and willfully refrained from disclosing
there are grounds for vacating, modifying or rescinding an such disqualifications or any other misbehavior by which the rights
arbitrator's award. Thus, if and when the factual circumstances of any party have been materially prejudiced; or
referred to the above-cited provisions are present, judicial review
of the award is properly warranted. (d) That the arbitrators exceeded their powers, or so imperfectly
executed them, that a mutual, final and definite award upon the
According, Section 20 of R.A. 876 provides: subject matter submitted to them was not made. (Emphasis ours)

Sec. 20. Form and contents of award. — The award must be xxx xxx xxx.
made in writing and signed and acknowledge by a majority of the
arbitrators, if more than one; and by the sole arbitrator, if there is Section 25 which enumerates the grounds for modifying the award provides:
only only. Each party shall be furnished with a copy of the award.
The arbitrators in their award may grant any remedy or relief which Sec. 25. Grounds for modifying or correcting award — In anyone
they deem just and equitable and within the scope of the of the following cases, the court must make an order modifying or
agreement of the parties, which shall include, but not be limited to, correcting the award, upon the application of any party to the
the specific performance of a contract. controversy which was arbitrated:

x x x           x x x          x x x (a) Where there was an evident miscalculation of figures, or an


evident mistake in the description of any person, thing or property
The arbitrators shall have the power to decide only those matters referred to in the award; or
which have been submitted to them. The terms of the award shall
be confined to such disputes. (Emphasis ours). (b) Where the arbitrators have awarded upon a matter not
submitted to them, not affecting the merits of the decision upon the
x x x           x x x          x x x matter submitted; or

Sec. 24 of the same law enumerating the grounds for vacating an award states: (c) Where the award is imperfect in a matter of form not affecting
the merits of the controversy, and if it had been a commissioner's
Sec. 24. Grounds for vacating award. — In any one of the report, the defect could have been amended or disregarded by the
following cases, the court must make an order vacating the award court.
upon the petition of any party to the controversy when such party
proves affirmatively that in the arbitration proceeding: x x x           x x x          x x x

(a) The award was procured by corruption, fraud, or other undue Finally, it should be stressed that while a court is precluded from overturning an
means; or award for errors in the determination of factual issues, nevertheless, if an
examination of the record reveals no support whatever for the arbitrators
determinations, their award must be vacated. 40 in the same manner, an award 4. So when PNB-DBP proceeded with the foreclosure, it was done
must be vacated if it was made in "manifest disregard of the law." 41 without bad faith but with the honest and sincere belief that
foreclosure was the only alternative; a decision further explained
Against the backdrop of the foregoing provisions and principles, we find that the by Dr. Placido Mapa who testified that foreclosure was, in the
arbitrators came out with an award in excess of their powers and palpably devoid judgment of PNB, the best move to save MMIC itself.
of factual and legal basis.
Q : Now in this portion of Exh. "L" which was marked as Exh. "L-
V 1", and we adopted as Exh. 37-A for the respondent, may I know
from you, Dr. Mapa what you meant by "that the decision to
foreclose was neither precipitate nor arbitrary"?
There was no financial

A : Well, it is not a whimsical decision but rather decision arrived at


structuring program:
after weighty consideration of the information that we have
received, and listening to the prospects which reported to us that
foreclosure of mortgage what we had assumed would be the premises of the financial
rehabilitation plan was not materialized nor expected to
was fully justified. materialize.

The point need not be belabored that PNB and DBP had the legitimate right to Q : And this statement that "it was premised upon the known fact"
foreclose of the mortgages of MMIC whose obligations were past due. The that means, it was referring to the decision to foreclose, was
foreclosure was not a wrongful act of the banks and, therefore, could not be the premised upon the known fact that the rehabilitation plan earlier
basis of any award of damages. There was no financial restructuring agreement to approved by the stockholders was no longer feasible, just what is
speak of that could have constituted an impediment to the exercise of the banks' meant "by no longer feasible"?
right to foreclose.
A : Because the revenue that they were counting on to make the
As correctly stated by Mr. Jose C. Sison, a member of the Arbitration Committee rehabilitation plan possible, was not anymore expected to be
who wrote a separate opinion: forthcoming because it will result in a short fall compared to the
prices that were actually taking place in the market.
1. The various loans and advances made by DBP and PNB to
MMIC have become overdue and remain unpaid. The fact that a Q : And I suppose that was what you were referring to when you
FRP was drawn up is enough to establish that MMIC has not been stated that the production targets and assumed prices of MMIC's
complying with the terms of the loan agreement. Restructuring products, among other projections, used in the financial
simply connotes that the obligations are past due that is why it is reorganization program that will make it viable were not met nor
"restructurable"; expected to be met?

2. When MMIC thru its board and the stockholders agreed and A : Yes.
adopted the FRP, it only means that MMIC had been informed or
notified that its obligations were past due and that foreclosure is x x x           x x x          x x x
forthcoming;
Which brings me to my last point in this separate opinion. Was
3. At that stage, MMIC also knew that PNB-DBP had the option of PNB and DBP absolutely unjustified in foreclosing the mortgages?
either approving the FRP or proceeding with the foreclosure.
Cabarrus, who filed this case supposedly in behalf of MMIC should
have insisted on the FRP. Yet Cabarrus himself opposed the FRP;
In this connection, it can readily be seen and it cannot quite be Sec. 2. No restraining order temporary or permanent injunction
denied that MMIC accounts in PNB-DBP were past due. The shall be issued by the court against any government financial
drawing up of the FRP is the best proof of this. When MMIC institution in any action taken by such institution in compliance with
adopted a restructuring program for its loan, it only meant that the mandatory foreclosure provided in Section 1 hereof, whether
these loans were already due and unpaid. If these loans were such restraining order, temporary or permanent injunction is
restructurable because they were already due and unpaid, they sought by the borrower(s) or any third party or parties, except after
are likewise "forecloseable". The option is with the PNB-DBP on due hearing in which it is established by the borrower and
what steps to take. admitted by the government financial institution concerned that
twenty percent (20%) of the outstanding arrearages has been paid
The mere fact that MMIC adopted the FRP does not mean that after the filing of foreclosure proceedings. (Emphasis supplied.)
DBP-PNB lost the option to foreclose. Neither does it mean that
the FRP is legally binding and implementable. It must be pointed Private respondents' thesis that the foreclosure proceedings were null and void
that said FRP will, in effect, supersede the existing and past due because of lack of publication in the newspaper is nothing more than a mere
loans of MMIC with PNB-DBP. It will become the new loan unsubstantiated aliegation not borne out by the evidence. In any case, a disputable
agreement between the lenders and the borrowers. As in all other presumption exists in favor of petitioner that official duty has been regularly
contracts, there must therefore be a meeting of minds of the performed and ordinary course of business has been followed. 43
parties; the PNB and DBP must have to validly adopt and ratify
such FRP before they can be bound by it; before it can be VI
implemented. In this case, not an iota of proof has been presented
by the PLAINTIFFS showing that PNB and DBP ratified and Not only was the foreclosure rightfully exercised by the PNB and DBP, but also,
adopted the FRP. PLAINTIFFS simply relied on a legal doctrine of from the facts of the case, the arbitrators in making the award went beyond the
promissory estoppel to support its allegations in this regard. 42 arbitration agreement.

Moreover, PNB and DBP had to initiate foreclosure proceedings as mandated by In their complaint filed before the trial court, private respondent Cabarrus, et al.
P.D. No. 385, which took effect on January 31, 1974. The decree requires prayed for judgment in their favor:
government financial institutions to foreclose collaterals for loans where the
arrearages amount to 20% of the total outstanding obligations. The pertinent
provisions of said decree read as follow: 1. Declaring the foreclosures effected by the defendants DBP and
PNB on the assets of MMIC null and void and directing said
defendants to restore the foreclosed assets to the possession of
Sec. 1. It shall be mandatory for government financial institutions, MMIC, to render an accounting of their use and/or operation of
after the lapse of sixty (60) days from the issuance of this Decree, said assets and to indemnify MMIC for the loss occasioned by its
to foreclose the collaterals and/or securities for any loan, credit, dispossession or the deterioration thereof;
accommodation, and/or guarantees granted by them whenever the
arrearages on such account, including accrued interest and other
charges, amount to at least twenty percent (20%) of the total 2. Directing the defendants DBP and PNB to honor and perform
outstanding obligations, including interest and other charges, as their commitments under the financial reorganization plan which
appearing in the books of account and/or related records of the was approved at the annual stockholders' meeting of MMIC on 30
financial institutions concerned. This shall be without prejudice to April 1984;
the exercise by the government financial institutions of such rights
and/or remedies available to them under their respective contracts 3. Condemning the defendants DBP and PNB, jointly and
with their debtors, including the right to foreclosure on loans, severally to pay the plaintiffs actual damages consisting of the
credits, accommodations and/or guarantees on which the loss of value of their investments amounting to not less than
arrearages are less than twenty percent (20%). P80,000,000, the damnum emergens and lucrum cessans in such
amount as may be established during the trial, moral damages in
such amount as this Honorable Court may deem just and of APT based on the counterclaims of DBP and PNB in an amount
equitable in the premises, exemplary damages in such amount as as may be established or warranted by the evidence. This decision
this Honorable Court may consider appropriate for the purpose of of the arbitration committee in favor of APT shall likewise finally
setting an example for the public good, attorney's fees and settle all issues regarding the foreclosure of the MMIC assets so
litigation expenses in such amounts as may be proven during the that the funds held in escrow mentioned in par. 9 hereunder will
trial, and the costs legally taxable in this litigation. thus be released in full in favor of
APT. 46
Further, plaintiffs pray for such other reliefs as may be just and
equitable in the premises. 44 The clear and explicit terms of the submission notwithstanding, the Arbitration
Committee clearly exceeded its powers or so imperfectly executed them: (a) in
Upon submission for arbitration, the Compromise and Arbitration Agreement of the ruling on and declaring valid the FRP; (b) in awarding damages to MMIC which
parties clearly and explicitly defined and limited the issues to the following: was not a party to the derivative suit; and (c) in awarding moral damages to Jesus
S. Cabarrus, Sr.
(a) whether PLAINTIFFS have the capacity or the personality to
institute this derivative suit in behalf of the MMIC or its directors; The arbiters overstepped

(b) whether or not the actions leading to, and including, the PNB- their powers by declaring as
DBP foreclosure of the MMIC assets were proper, valid and in
good faith. 45 valid the proposed Financial

Item No. 8 of the Agreement provides for the period by which the Committee was Restructuring Program.
to render its decision, as well as the nature thereof:
The Arbitration Committee went beyond its mandate and thus acted in excess of
8. Decision. The committee shall issue a decision on the its powers when it ruled on the validity of, and gave effect to, the proposed FRP.
controversy not later than six (6) months from the date of its
constitution. In submitting the case to arbitration, the parties had mutually agreed to limit the
issue to the "validity of the foreclosure" and to transform the relief prayed for
In the event the committee finds that PLAINTIFFS have the therein into pure money claims.
personality to file this suit and the extra-judicial foreclosure of the
MMIC assets wrongful, it shall make an award in favor of the There is absolutely no evidence that the DBP and PNB agreed, expressly or
PLAINTIFFS (excluding DBP), in an amount as may be impliedly, to the proposed FRP. It cannot be overemphasized that a FRP, as a
established or warranted by the evidence which shall be payable contract, requires the consent of the parties thereto. 47 The contract must bind both
in Philippine Pesos at the time of the award. Such award shall be contracting parties. 48 Private respondents even by their own admission recognized
paid by the APT or its successor-in-interest within sixty (60) days that the FRP had yet not been carried out and that the loans of MMIC had not yet
from the date of the award in accordance with the provisions of been converted into equity. 49
par. 9 hereunder. . . . . The PLAINTIFFS' remedies under this
Section shall be in addition to other remedies that may be However, the Arbitration Committee not only declared the FRP valid and effective,
available to the PLAINTIFFS, all such remedies being cumulative but also converted the loans of MMIC into equity raising the equity of DBP to
and not exclusive of each other. 87%. 50

On the other hand, in case the arbitration committee finds that The Arbitration Committee ruled that there was "a commitment to carry out the
PLAINTIFFS have no capacity to sue and/or that the extra-judicial FRP" 51 on the ground of promissory estoppel.
foreclosure is valid and legal, it shall also make an award in favor
Similarly, the principle of promissory estoppel applies in the thousands of stockholders will be suppressed and rendered
present case considering as we observed, the fact that the nugatory. 53
government (that is, Alfredo Velayo) was the FRP's proponent.
Although the plaintiffs are agreed that the government executed As a rule, a corporation exercises its powers, including the power to enter into
no formal agreement, the fact remains that the DBP itself which contracts, through its board of directors. While a corporation may appoint agents to
made representations that the FRP constituted a "way out" for enter into a contract in its behalf, the agent should not exceed his authority. 54 In
MMIC. The Committee believes that although the DBP did not the case at bar, there was no showing that the representatives of PNB and DBP in
formally agree (assuming that the board and stockholders' MMIC even had the requisite authority to enter into a debt-for-equity swap. And if
approvals were not formal enough), it is bound nonetheless if only they had such authority, there was no showing that the banks, through their board
for its conspicuous representations. of directors, had ratified the FRP.

Although the DBP sat in the board in a dual capacity — as holder Further, how could the MMIC be entitled to a big amount of moral damages when
of 36% of MMIC's equity (at that time) and as MMIC's creditor — its credit reputation was not exactly something to be considered sound and
the DBP can not validly renege on its commitments simply wholesome. Under Article 2217 of the Civil Code, moral damages include
because at the same time, it held interests against the MMIC. besmirched reputation which a corporation may possibly suffer. A corporation
whose overdue and unpaid debts to the Government alone reached a tremendous
The fact, of course, is that as APT itself asserted, the FRP was amount of P22 Billion Pesos cannot certainly have a solid business reputation to
being "carried out" although apparently, it would supposedly fall brag about. As Atty. Sison in his separate opinion persuasively put it:
short of its targets. Assuming that the FRP would fail to meet its
targets, the DBP — and so this Committee holds — can not, in Besides, it is not yet a well settled jurisprudence that corporations
any event, brook any denial that it was bound to begin with, and are entitled to moral damages. While the Supreme Court may
the fact is that adequate or not (the FRP), the government is still have awarded moral damages to a corporation for besmirched
bound by virtue of its acts. reputation in Mambulao vs. PNB, 22 SCRA 359, such ruling
cannot find application in this case. It must be pointed out that
The FRP, of course, did not itself promise a resounding success, when the supposed wrongful act of foreclosure was done, MMIC's
although it raised DBP's equity in MMIC to 87%. It is not an credit reputation was no longer a desirable one. The company
excuse, however, for the government to deny its commitments. 52 then was already suffering from serious financial crisis which
definitely projects an image not compatible with good and
Atty. Sison, however, did not agree and correctly observed that: wholesome reputation. So it could not be said that there was a
"reputation" besmirched by the act of foreclosure. 55
But the doctrine of promissory estoppel can hardly find application
here. The nearest that there can be said of any estoppel being The arbiters exceeded their
present in this case is the fact that the board of MMIC was, at the
time the FRP was adopted, mostly composed of PNB and DBP authority in awarding damages
representatives. But those representatives, singly or collectively,
are not themselves PNB or DBP. They are individuals with to MMIC, which is not impleaded
personalities separate and distinct from the banks they represent.
PNB and DBP have different boards with different members who as a party to the derivative suit.
may have different decisions. It is unfair to impose upon them the
decision of the board of another company and thus pin them down
on the equitable principle of estoppel. Estoppel is a principle Civil Case No. 9900 filed before the RTC being a derivative suit, MMIC should
based on equity and it is certainly not equitable to apply it in this have been impleaded as a party. It was not joined as a party plaintiff or party
particular situation. Otherwise the rights of entirely separate defendant at any stage of the proceedings. As it is, the award of damages to
distinct and autonomous legal entities like PNB and DBP with
MMIC, which was not a party before the Arbitration Committee, is a complete debts and liabilities, something which cannot be legally done in
nullity. view of section 16 of the Corporation Law . . .;

Settled is the doctrine that in a derivative suit, the corporation is the real party in (3) the filing of such suits would conflict with the duty of the
interest while the stockholder filing suit for the corporation's behalf is only a management to sue for the protection of all concerned;
nominal party. The corporation should be included as a party in the suit.
(4) it would produce wasteful multiplicity of suits; and
An individual stockholder is permitted to institute a derivative suit
on behalf of the corporation wherein he holds stock in order to (5) it would involve confusion in a ascertaining the effect of partial
protect or vindicate corporate rights, whenever the officials of the recovery by an individual on the damages recoverable by the
corporation refuse to sue, or are the ones to be sued or hold the corporation for the same act. 58
control of the corporation. In such actions, the suing stockholder is
regarded as a nominal party, with the corporation as the real party If at all an award was due MMIC, which it was not, the same should have been
in interest. . . . . 56 given sans  deduction, regardless of whether or not the party liable had equity in
the corporation, in view of the doctrine that a corporation has a personality
It is a condition sine qua non that the corporation be impleaded as a party because separate and distinct from its individual stockholders or members. DBP's alleged
— equity, even if it were indeed 87%, did not give it ownership over any corporate
property, including the monetary award, its right over said corporate property being
. . . Not only is the corporation an indispensable party, but it is also a mere expectancy or inchoate right. 59 Notably, the stipulation even had the effect
the present rule that it must be served with process. The reason of prejudicing the other creditors of MMIC.
given is that the judgment must be made binding upon the
corporation in order that the corporation may get the benefit of the The arbiters, likewise,
suit and may not bring a subsequent suit against the same
defendants for the same cause of action. In other words the exceeded their authority
corporation must be joined as party because it is its cause of
action that is being litigated and because judgment must be a  res
ajudicata  against it. 57 in awarding moral damages

The reasons given for not allowing direct individual suit are: to Jesus Cabarrus, Sr.

(1) . . . "the universally recognized doctrine that a stockholder in a It is perplexing how the Arbitration Committee can in one breath rule that the case
corporation has no title legal or equitable to the corporate property; before it is a derivative suit, in which the aggrieved party or the real party in
that both of these are in the corporation itself for the benefit of the interest is supposedly the MMIC, and at the same time award moral damages to
stockholders." In other words, to allow shareholders to sue an individual stockholder, to wit:
separately would conflict with the separate corporate entity
principle; WHEREFORE, premises considered, judgment is hereby
rendered:
(2) . . . that the prior rights of the creditors may be prejudiced.
Thus, our Supreme Court held in the case of  Evangelista v. x x x           x x x          x x x
Santos, that "the stockholders may not directly claim those
damages for themselves for that would result in the appropriation 3. Ordering the defendant to pay to the plaintiff, Jesus S.
by, and the distribution among them of part of the corporate assets Cabarrus, Sr., the sum of P10,000,000.00, to be satisfied likewise
before the dissolution of the corporation and the liquidation of its from the funds held under escrow pursuant to the Escrow
Agreement dated April 22, 1988 or to such subsequent escrow the cause of action pertains only to the corporation (MMIC) and
agreement that would supersede it, pursuant to paragraph (9), that they are filing this for and in behalf of MMIC.
Compromise and Arbitration Agreement, as and for moral
damages; . . . 60 Perforce this has to be so because it is the basic rule in
Corporation Law that "the shareholders have no title, legal or
The majority decision of the Arbitration Committee sought to justify its award of equitable to the property which is owned by the corporation (13
moral damages to Jesus S. Cabarrus, Sr. by pointing to the fact that among the Am. Jur. 165; Pascual vs. Oresco, 14 Phil. 83). In Ganzon & Sons
assets seized by the government were assets belonging to Industrial Enterprise vs. Register of Deeds, 6 SCRA 373, the rule has been reiterated
Inc. (IEI), of which Cabarrus is the majority stockholder. It then acknowledged that that "a stockholder is not the co-owner of corporate property."
Cabarrus had already recovered said assets in the RTC, but that "he won no more Since the property or assets foreclosed belongs [sic] to MMIC, the
than actual damages. While the Committee cannot possibly speak for the RTC, wrong committed, if any, is done against the corporation.  There is
there is no doubt that Jesus S. Cabarrus, Sr., suffered moral damages on account therefore no direct injury or direct violation of the rights of
of that specific foreclosure, damages the Committee believes and so holds, he, Cabarrus et al. There is no way, legal or equitable, by which
Jesus S. Cabarrus, Sr., may be awarded in this proceeding." 61 Cabarrus et al. could recover damages in their personal capacities
even assuming or just because the foreclosure is improper or
Cabarrus cause of action for the seizure of the assets belonging to IEI, of which he invalid. The Compromise and Arbitration Agreement itself and the
is the majority stockholder, having been ventilated in a complaint he previously elementary principles of Corporation Law say so. Therefore, I am
filed with the RTC, from which he obtained actual damages, he was barred by res constrained to dissent from the award of moral damages to
judicata from filing a similar case in another court, this time asking for moral Cabarrus. 64
damages which he failed to get from the earlier case. 62 Worse, private
respondents violated the rule against non-forum shopping. From the foregoing discussions, it is evident that, not only did the arbitration
committee exceed its powers or so imperfectly execute them, but also, its findings
It is a basic postulate that a corporation has a personality separate and distinct and conclusions are palpably devoid of any factual basis, and in manifest
from its stockholders. 63 The properties foreclosed belonged to MMIC, not to its disregard of the law.
stockholders. Hence, if wrong was committed in the foreclosure, it was done
against the corporation. Another reason is that Jesus S. Cabarrus, Sr. cannot We do not find it necessary to remand this case to the RTC for appropriate action.
directly claim those damages for himself that would result in the appropriation by, The pleadings and memoranda filed with this Court, as well as in the Court of
and the distribution to, him part of the corporation's assets before the dissolution of Appeals, raised and extensively discussed the issues on the merits. Such being
the corporation and the liquidation of its debts and liabilities. The Arbitration the case, there is sufficient basis for us to resolve the controversy between the
Committee, therefore, passed upon matters nor submitted to it. Moreover, said parties anchored on the records and the pleadings before us. 65
cause of action had already been decided in a separate case. It is thus quite
patent that the arbitration committee exceeded the authority granted to it by the WHEREFORE, the Decision of the Court of Appeals dated July 17, 1995, as well
parties' Compromise and Arbitration Agreement by awarding moral damages to as the Orders of the Regional Trial Court of Makati, Branch 62, dated November
Jesus S. Cabarrus, Sr. 28, 1994 and January 19, 1995, is hereby REVERSED and SET ASIDE, and the
decision of the Arbitration Committee is hereby VACATED.
Atty. Sison, in his separate opinion, likewise expressed befuddlement to the award
of moral damages to Jesus S. Cabarrus, Sr.: SO ORDERED.

It is clear and it cannot be disputed therefore that based on these Romero, J., Please see dissenting opinion.
stipulated issues, the parties  themselves have agreed that the
basic ingredient of the causes of action in this case is the wrong Purisima, J., Concur and also with the separate concurring opinion of Justice
committed on the corporation (MMIC) for the alleged illegal Pardo.
foreclosure of its assets. By agreeing to this
stipulation,  PLAINTIFFS  themselves (Cabarrus, et al.) admit that
Pardo, J., With separate concurring opinion.

 
3. MABUHAY HOLDINGS CORPORATION, PETITIONER, VS. SEMBCORP Pursuant to Article 13 of the Agreement, Mabuhay and IDHI voluntarily agreed to
LOGISTICS LIMITED, RESPONDENT. jointly guarantee that Sembcorp would receive a minimum accounting return of
US$929,875.50 (Guaranteed Return) at the end of the 24th month following the full
DECISION disbursement of the Sembcorp's equity investment in WJNA and WJSC. They
TIJAM, J.: further agreed that the Guaranteed Return shall be paid three (3) months from the
This is an appeal from the Decision[1] dated November 19, 2013 and the completion of the special audits of WJSC and WJNA as per Article 13.3 of the
Resolution[2] dated June 3, 2014 of the Court of Appeals (CA) in CA-G.R. CV No. Agreement.[10]
92296, reversing and setting aside the Decision of the Regional Trial Court (RTC)
[3]
 of Makati City, Branch 149, in SP Proc. No. M-6064. The Agreement included an arbitration clause, viz:
Article XIX. APPLICABLE LAW; ARBITRATION
Facts of the Case
19.1 This Agreement and the validity and performance thereof shall be governed
Petitioner Mabuhay Holdings Corporation (Mabuhay) and Infrastructure by the laws of the Republic of the Philippines.
Development & Holdings, Inc. (IDHI) are corporations duly organized and existing
under the Philippine Laws.[4] 19.2 Any dispute, controversy or claim arising out of or relating to this Agreement,
or a breach thereof, other than intra-corporate controversies, shall be finally settled
Respondent Sembcorp Logistics Limited (Sembcorp), formerly known as by arbitration in accordance with the rules of conciliation and arbitration of the
Sembawang Maritime Limited, is a company incorporated in the Republic of International Chamber of Commerce by one arbitrator with expertise in the matter
Singapore.[5] at issue appointed in accordance with said rules. The arbitration proceeding
including the rendering of the award shall take place in Singapore and shall be
On January 23, 1996, Mabuhay and IDHI incorporated Water Jet Shipping conducted in the English Language. This arbitration shall survive termination of
Corporation (WJSC) in the Philippines to engage in the venture of carrying this Agreement. Judgment upon the award rendered may be entered in any court
passengers on a common carriage by inter-island fast ferry. On February 5, 1996, having jurisdiction or application may be made to such court for a judicial
they also incorporated Water Jet Netherlands Antilles, N.Y. (WJNA) in Curasao, acceptance of the award and an order of enforcement, as the case may be.[11]
Netherlands.[6] Their respective shareholding percentage are as follows:[7] On December 6, 1996, Sembcorp effected full payment of its equity investment.
Special audits of WJNA and WJSC were then carried out and completed on
  WJSC WJNA  
January 8, 1999. Said audits revealed that WJSC and WJNA both incurred losses.
[12]
Mabuhay 70% 70%  
On November 26, 1999, Sembcorp requested for the payment of its Guaranteed
IDHI 30% 30%  
Return from Mabuhay and IDID. Mabuhay admitted its liability but asserted that
On September 16, 1996, Mabuhay, IDHI, and Sembcorp entered into a since the obligation is joint, it is only liable for fifty percent (50%) of the claim or
Shareholders' Agreement[8] (Agreement) setting out the terms and conditions US$464,937.75.[13]
governing their relationship in connection with a planned business expansion of
WJSC and WJNA. Sembcorp decided to invest in the said corporations. As a result On February 24, 2000, Sembcorp sent a Final Demand to Mabuhay to pay the
of Sembcorp's acquisition of shares, Mabuhay and IDHI's shareholding percentage Guaranteed Return. Mabuhay requested for three (3) months to raise the
in the said corporations were reduced, as follows:[9] necessary funds but still failed to pay any amount after the lapse of the said period.
[14]
  WJSC WJNA  

Mabuhay 45.5% 45.5%   On December 4, 2000, Sembcorp filed a Request for Arbitration before the
International Court of Arbitration of the International Chamber of Commerce (ICC)
IDHI 19.5% 19.5%   in accordance with the Agreement and sought the following reliefs:
(1) payment of the sum of US$929,875.50;
Sembcorp 35.0% 35.0%  
(2) alternatively, damages;
absolute ownership over the aforesaid shares. Moreover, Mabuhay argued that the
(3) interest on the above sum at such rate as the Arbitral Tribunal deems fit and appointment of Dr. Chantara-Opakorn was not in accordance with the arbitral
just; clause as he did not have the expertise in the matter at issue, which involved
application of Philippine law. Finally, Mabuhay argued that the imposition of twelve
(4) cost of the arbitration; and percent (12%) interest from the date of the Final Award was contrary to the
Philippine law and jurisprudence.[21]
(5) Such further and/or other relief as the Arbitral Tribunal deems fit and just.[15]
On April 20, 2004, a Final Award[16] was rendered by Dr. Anan Chantara-Opakom Ruling of the RTC
(Dr. Chantara-Opakorn), the Sole Arbitrator appointed by the ICC. The dispositive
portion of the award reads: In a Decision[22] dated May 23, 2008, the RTC dismissed the petition and ruled that
The Sole Arbitrator hereby decides that the Sole Arbitrator has jurisdiction over the the Final Award could not be enforced.
parties' dispute and directs [Mabuhay] to make the following payments to
[Sembcorp]: The RTC ruled that the "simple contractual payment obligation" of Mabuhay and
IDHI to Sembcorp had been rescinded and modified by the merger or confusion of
1. Half of the Guaranteed Return or an amount of US$464,937.75 (Four Hundred the person of IDHI into the person of Sembcorp. As a result, said obligation was
Sixty Four Thousand Nine Hundred Thirty Seven and Point Seventy Five US converted into an intra-corporate matter.[23]
Dollars);
The RTC also ruled on the issue of the lack of expertise of the Sole Arbitrator.
2. Interest at the rate of 12% per annum on the said amount of US$464,937.75 Thus, the dispositive portion of its Decision reads:
calculated from the date of this Final Award until the said amount of WHEREFORE, premises considered, this court finds in favor of the defendant
US$464,937.75 is actually and completely paid by [Mabuhay] to [Sembcorp]; and Mabuhay Holdings Corporation, hence it hereby DISMISSED the petition for the
recognition and enforcement of the subject Arbitral Award for the simple reason
3. A reimbursement of half of the costs of arbitration fixed by the ICC Court at that it was issued in violation of the agreement. Moreover, this court cannot
US$57,000 or the aggregate half of which amount to US$28,500 together with an recognize the Arbitral Award because it was not the work of an expert as required
interest at the rate of 12% per annum calculated from the date of this Final Award under the agreement. Finally, the payment obligation in interest of 12% per annum
until the said amount is actually and completely paid by [Mabuhay] to [Sembcorp]. on the US Dollar Amounts ($464,937.75 and $28,500) as ordered by the Sole
[17]
Arbitrator is contrary to law and existing jurisprudence, hence void. Thus, it cannot
Consequently, on April 14, 2005, Sembcorp filed a Petition for Recognition and be enforced by this Court.
Enforcement of a Foreign Arbitral Award[18] before the RTC ofMakati City, Branch
149.[19] Cost de oficio.

Mabuhay filed an Opposition citing the following grounds for non-enforcement SO ORDERED.[24]
under Article V of the 1958 Convention on the Recognition and Enforcement of Aggrieved, Sembcorp appealed to the CA via a Notice of Appeal under Rule 41 of
Foreign Arbitral Awards (New York Convention): (1) the award deals with a conflict the Rules of Court.[25]
not falling within the terms of the submission to arbitration; (2) the composition of
the arbitral authority was not in accordance with the agreement of the parties; and Ruling of the CA
(3) recognition or enforcement of the award would be contrary to the public policy
of the Philippines.[20] On November 19, 2013, the CA promulgated its Decision[26] reversing and setting
aside the RTC Decision.
Mabuhay argued that the dispute is an intra-corporate controversy, hence,
excluded from the scope of the arbitration clause in the Agreement. It alleged that The CA noted that the Final Award already settled the factual issue on whether
on March 13, 1997, Sembcorp became the controlling stockholder of IDHI by Sembcorp acquired the adverted shares of stock in IDHI. Thus, RTC's contrary
acquiring substantial shares of stocks through its nominee, Mr. Pablo N. Sare findings constituted an attack on the merits of the Final Award. In sum, the CA held
(Sare). Mabuhay thus claimed that it has already been released from the joint that the court shall not disturb the arbitral tribunal's determination of facts and/or
obligation with IDHI as Sembcorp assumed the risk of loss when it acquired interpretation of the law. It recognized the Final Award and remanded the case to
the RTC for proper execution.[27] Sections 19 and 42 of the ADR Act expressly provided for the applicability of the
New York Convention and the Model Law in our jurisdiction, viz:
Undaunted, Mabuhay moved for the reconsideration of the CA Decision but the SEC. 19. Adoption of the Model Law on International Commercial
same was denied in a Resolution[28] dated June 3, 2014. Arbitration. - International commercial arbitration shall be governed by the Model
Law on International Commercial Arbitration (the "Model Law") adopted by the
Hence, this petition. United Nations Commission on International Trade Law on June 21, 1985 (United
Nations Document A/40/17) and recommended approved on December 11, 1985,
Issue copy of which is hereto attached as Appendix "N'.

The core issue for resolution is whether the RTC correctly refused to enforce the x x x x
Final Award. Stated differently, was Mabuhay able to establish a ground for
refusing the enforcement of the Final Award under our applicable laws and SEC. 42. Application of the New York Convention. - The New York Convention
jurisprudence on arbitration? shall govern the recognition and enforcement of arbitral awards covered by the
said Convention.
Our Ruling The recognition and enforcement of such arbitral awards shall be filled (sic) with
regional trial court in accordance with the rules of procedure to be
We deny the petition. promulgated by the Supreme Court. Said procedural rules shall provide that the
party relying on the award or applying for its enforcement shall file with the court
I. Governing Laws the original or authenticated copy of the award and the arbitration agreement. If the
award or agreement is not made in any of the official languages, the party shall
An assiduous analysis of the present case requires a prefatory determination of supply a duly certified translation thereof into any of such languages.
the rules and other legal authorities that would govern the subject arbitration
proceedings and award. The applicant shall establish that the country in which foreign arbitration award
was made is a party to the New York Convention.
The arbitration proceedings between the parties herein were conducted in
Singapore and the resulting Final Award was also rendered therein. As such, the x x x x (Emphasis ours)
Final Award is a "foreign arbitral award" or an award made in a country other than Five years after the enactment of the ADR Act, the Department of Justice issued
the Philippines.[29] the ADR Act's Implementing Rules and Regulations (IRR)[35], and the Supreme
Court issued the Special Rules of Court on Alternative Dispute
The Philippines is among the first signatories of the 1958 Convention on the Resolution[36] (Special ADR Rules). These two rules, in addition to the ADR Act
Recognition and Enforcement of Foreign Arbitral Awards (New York Convention) incorporating the New York Convention and the Model Law, are our arbitration
and acceded to the same as early as 1967.[30] Singapore, on the other hand, laws.
became a Contracting State in 1986.[31] The New York Convention aims to provide
common legislative standards for the recognition of arbitration agreements and In addition to our arbitration laws, our courts, in recognizing or enforcing a foreign
court recognition and enforcement of foreign and non-domestic arbitral awards. arbitral award, shall also take into consideration the laws applied by the arbitral
Thus, the New York Convention primarily governs the recognition and enforcement tribunal. These may comprise the substantive law of the contract and the
of foreign arbitral awards by our courts.[32] procedural rules or the rules governing the conduct of arbitration proceedings.

In addition, as a member of the United Nations Commission in International Trade As agreed upon by the parties herein under the arbitral clause in their Agreement,
Law (UNCITRAL), the Philippines also adopted the UNCITRAL Model the substantive law of the contract is the Philippine law and the procedural rules
Law[33] (Model Law) as the governing law on international commercial arbitrations. are the ICC Rules. During the filing of the request for Arbitration, the ICC Rules in
Hence, when the Congress enacted Republic Act No. 9285 or the Alternative effect was the ICC Rules of Arbitration 1998[37] Considering that the essence of
Dispute Resolution Act of 2004[34] (ADR Act), it incorporated the Model Law in its arbitration is party autonomy, the Court shall refer to the said Rules for purposes of
entirety. examining the procedural infirmities raised by the parties to the arbitration.
II. Jurisdiction
b. Erred in upholding a final order or decision despite the lack of jurisdiction of the
Mabuhay argues that the CA seriously erred in not dismissing outright the appeal court that rendered such final order or decision;
of Sembcorp as it had no jurisdiction to act on the appeal. Mabuhay's argument
hinges on Rule 19.12 of the Special ADR Rules, as follows: c. Failed to apply any provision, principle, policy or rule contained in these Special
Rule 19.12. Appeal to the Court of Appeals. - An appeal to the Court of ADR Rules resulting in substantial prejudice to the aggrieved party; and
Appeals through a petition for review under this Special Rule shall only be
allowed from the following final orders of the Regional Trial Court: d. Committed an error so egregious and harmful to a party as to amount to an
undeniable excess of jurisdiction.
x x x x The mere fact that the petitioner disagrees with the Court of Appeals'
determination of questions of fact, of law or both questions of fact and law, shall
k. Refusing recognition and/or enforcement of a foreign arbitral award; (Emphasis not warrant the exercise of the Supreme Court's discretionary power. The error
supplied) imputed to the Court of Appeals must be grounded upon any of the above
prescribed grounds for review or be closely analogous thereto.
xxxx
Mabuhay thus contends that filing a petition for review and not a notice of appeal is A mere general allegation that the Court of Appeals has committed serious and
the proper remedy to contest the RTC's refusal to enforce the Final Award. substantial error or that it has acted with grave abuse of discretion resulting in
substantial prejudice to the petitioner without indicating with specificity the nature
The Court notes, however, that the Special ADR Rules took effect in 2009. of such error or abuse of discretion and the serious prejudice suffered by the
Sembcorp's notice of appeal was filed only in 2008. The ADR Act, which was petitioner on account thereof, shall constitute sufficient ground for the Supreme
already in effect at that time, did not specify the proper remedy of appeal from the Court to dismiss outright the petition. (Emphasis ours)
RTC to the CA. It merely provides that "a decision of the regional trial court In relation to the applicable standard or test for judicial review by the CA in arriving
confirming, vacating, setting aside, modifying or correcting an arbitral award may at its decision, the Special ADR Rules further provide:
be appealed to the CA in accordance with the rules of procedure to be Rule 19.20. Due course. - If upon the filing of a comment or such other pleading or
promulgated by the Supreme Court."[38] documents as may be required or allowed by the Court of Appeals or upon the
expiration of the period for the filing thereof, and on the basis of the petition or the
The Special ADR Rules shall retroactively apply to all pending cases provided that records, the Court of Appeals finds prima facie that the Regional Trial Court
no vested rights are impaired or prejudiced.[39] In this case, Sembcorp filed a notice has committed an error that would warrant reversal or modification of the
of appeal in accordance with Section 2 of Rule 41[40] as it is the only applicable rule judgment, final order, or resolution sought to be reviewed, it may give due course
existing at that time. Sembcorp had a vested right to due process in relying on the to the petition; otherwise, it shall dismiss the same.
said rule. Consequently, the CA had jurisdiction to act on Sembcorp's appeal.
x x x x
We now discuss the Court's jurisdiction to entertain the instant petition. The Court's
review of a CA Decision is discretionary and limited to specific grounds provided Rule 19.24. Subject of appeal restricted in certain instance. - If the decision of the
under the Special ADR Rules. Thus: Regional Trial Court refusing to recognize and/or enforce, vacating and/or setting
Rule 19.36. Review discretionary. - A review by the Supreme Court is not a matter aside an arbitral award is premised on a finding of fact, the Court of Appeals may
of right, but of sound judicial discretion, which will be granted only for serious and inquire only into such fact to determine the existence or non-existence of the
compelling reasons resulting in grave prejudice to the aggrieved party. The specific ground under the arbitration laws of the Philippines relied upon by
following, while neither controlling nor fully measuring the court's discretion, the Regional Trial Court to refuse to recognize and/or enforce, vacate and/or
indicate the serious and compelling, and necessarily, restrictive nature of the set aside an award. Any such inquiry into a question of fact shall not be resorted to
grounds that will warrant the exercise of the Supreme Court's discretionary for the purpose of substituting the court's judgment for that of the arbitral tribunal
powers, when the Court of Appeals: as regards the latter's ruling on the merits of the controversy. (Emphasis ours)
a. Failed to apply the applicable standard or test for judicial review Here, Mabuhay did not specifically raise any of the grounds under Rule 19.36
prescribed in these Special ADR Rules in arriving at its decision resulting in above in its petition before this Court. Nonetheless, considering the dearth of
substantial prejudice to the aggrieved party; jurisprudence on enforcement of foreign arbitral awards and the fact that the CA
reversed the RTC decision, the Court exercises its discretion to review the CA (c) The award deals with a difference not contemplated by or not falling
decision solely for purposes of determining whether the CA applied the aforecited within the terms of the submission to arbitration, or it contains decisions on
standard of judicial review. matters beyond the scope of the submission to arbitration, provided that, if the
decisions on matters submitted to arbitration can be separated from those not so
III. Grounds for Refusing Enforcement or Recognition submitted, that part of the award which contains decisions on matters submitted to
arbitration may be recognized and enforced; or
We now delve into the core of the issue - whether there is a ground for the RTC to
refuse recognition and enforcement of the Final Award in favor of Sembcorp. (d) The composition of the arbitral authority or the arbitral procedure was not
in accordance with the agreement of the parties, or, failing such agreement,
Our jurisdiction adopts a policy in favor of arbitration.[41] The ADR Act and the was not in accordance with the law of the country where the arbitration took place;
Special ADR Rules both declare as a policy that the State shall encourage and or
actively promote the use of alternative dispute resolution, such as arbitration, as an
important means to achieve speedy and impartial justice and declog court dockets. (e) The award has not yet become binding on the parties, or has been set aside or
[42]
 This pro-arbitration policy is further evidenced by the rule on presumption in suspended by a competent authority of the country in which, or under the law of
favor of enforcement of a foreign arbitral award under the Special ADR Rules, viz: which, that award was made.
Rule 13.11. Court action. - It is presumed that a foreign arbitral award was 2. Recognition and enforcement of an arbitral award may also be refused if the
made and released in due course of arbitration and is subject to enforcement competent authority in the country where recognition and enforcement is sought
by the court. finds that:
(a) The subject matter of the difference is not capable of settlement by arbitration
The court shall recognize and enforce a foreign arbitral award unless a ground to under the law of that country; or
refuse recognition or enforcement of the foreign arbitral award under this rule is
fully established. (b) The recognition or enforcement of the award would be contrary to the
public policy of that country. (Emphasis ours)
The decision of the court recognizing and enforcing a foreign arbitral award is The aforecited grounds are essentially the same grounds enumerated under
immediately executory. Section 36[43] of the Model Law. The list is exclusive. Thus, Section 45 of the ADR
Act provides:
In resolving the petition for recognition and enforcement of a foreign arbitral award SEC. 45. Rejection of a Foreign Arbitral Award. - A party to a foreign arbitration
in accordance with these Special ADR Rules, the court shall either [a] recognize proceeding may oppose an application for recognition and enforcement of the
and/or enforce or [b] refuse to recognize and enforce the arbitral award. The court arbitral award in accordance with the procedural rules to be promulgated by the
shall not disturb the arbitral tribunal's determination of facts and/or Supreme Court only on those grounds enumerated under Article V of the New
interpretation of law. (Emphasis ours) York Convention. Any other ground raised shall be disregarded by the
Under Article V of the New York Convention, the grounds for refusing enforcement regional trial court. (Emphasis ours)
and recognition of a foreign arbitral award are: In Our jurisdiction, We have incorporated the grounds enumerated under the New
1. Recognition and enforcement of the award may be refused, at the request of the York Convention in our arbitration laws. Article 4.36, Rule 6[44] of the IRR and Rule
party against whom it is invoked, only if that party furnishes to the competent 13.4[45] of the Special ADR Rules reiterated the exact same exclusive list of
authority where the recognition and enforcement is sought, proof that: grounds.
(a) The parties to the agreement referred to in article II were, under the law
applicable to them, under some incapacity, or the said agreement is not valid After a careful review of the case, We find that Mabuhay failed to establish any of
under the law to which the parties have subjected it or, failing any indication the grounds for refusing enforcement and recognition of a foreign arbitral award.
thereon, under the law of the country where the award was made; or We discuss the grounds raised by Mabuhay in seriatim:

(b) The party against whom the award is invoked was not given proper notice of A. The arbitral authority, composed of Dr. Chatara-Opakorn as the sole arbitrator,
the appointment of the arbitrator or of the arbitration proceedings or was otherwise was constituted in accordance with the arbitration agreement.
unable to present his case; or
The first ground raised by Mabuhay is Article V(l)(d) of the New York
Convention, i.e., that the composition of the arbitral authority was not in arbitral proceedings." The procedure to be followed on the appointment of
accordance with the agreement of the parties. Mabuhay and Sembcorp stipulated arbitrator are among the procedural rules that may be agreed upon by the parties.
in their Agreement that the sole arbitrator must have "expertise in the matter at
issue". Since they also agreed that the validity and the performance of the Moreover, under Rule 7.2 of the Special ADR Rules, a challenge to the
Agreement shall be governed by the Philippine law, Mabuhay argues that the appointment of an arbitrator may be raised in court only when the appointing
phrase "expertise in the matter at issue" necessarily means expertise in the authority fails or refuses to act on the challenge within such period as may be
Philippine law. Dr. Chatara-Opakom, a Thai national, does not possess any allowed under the applicable rule or in the absence thereof, within thirty (30) days
educational degree or training in Philippine law. from receipt of the request, that the aggrieved party may renew the challenge in
court. This is clearly not the case for Mabuhay as it was able to challenge the
The Agreement provides, however, that the arbitrator with expertise in the matter appointment of Dr. Chantara-Opakom in accordance with Article 11 of the ICC
at issue shall be appointed in accordance with the ICC Rules. The ICC, thus, is the Rules, but the ICC Court rejected the same.[48] As such, the Court shall not
appointing authority agreed upon by the parties. The "appointing authority" is the entertain any challenge to the appointment of arbitrator disguised as a ground for
person or institution named in the arbitration agreement as the appointing refusing enforcement of an award.
authority; or the regular arbitration institution under whose rule the arbitration is
agreed to be conducted.[46] Where the parties have agreed to submit their dispute At any rate, Mabuhay's contention that the sole arbitrator must have the expertise
to institutional arbitration rules, and unless they have agreed to a different on Philippine law fails to persuade. If the intent of the parties is to exclude foreign
procedure, they shall be deemed to have agreed to procedure under such arbitrators due to the substantive law of the contract, they could have specified the
arbitration rules for the selection and appointment of arbitrators.[47] same considering that the ICC Rules provide for appointment of a sole arbitrator
whose nationality is other than those of the parties.
The pertinent rules in the ICC Arbitration Rules of 1998 provide:
Article 9 - Appointment and Confirmation of the Arbitrators B. The dispute is not an intra corporate controversy, hence, included in the scope
of disputes submitted to arbitration.
x x x x
Under Article V(l)(c) of the New York Convention, the court may refuse
3. Where the Court is to appoint a sole arbitrator or the chairman of an Arbitral enforcement of a foreign arbitral award when the award deals with a difference not
Tribunal, it shall make the appointment upon a proposal of a National Committee contemplated by or not falling within the terms of the submission to arbitration.
of the ICC that it considers to be appropriate. If the Court does not accept the Mabuhay argues that the dispute is an intracorporate controversy which is
proposal made, or if the National Committee fails to make the proposal requested expressly excluded from the scope of disputes submitted to arbitration under the
within the time limit fixed by the Court, the Court may repeat its request or may Agreement. In essence, Mabuhay attacks the jurisdiction of the arbitral tribunal to
request a proposal from another National Committee that it considers to be hear the dispute as it did not fall within the terms of submission to arbitration.
appropriate.
The CA correctly applied the Kompetenz-Kompetenz principle expressly
x x x x recognized under Rule 2.2 of the Special ADR Rules, viz:
The Special ADR Rules recognize the principle of competence competence, which
5. The sole arbitrator or the chairman of the Arbitral Tribunal shall be of a means that the arbitral tribunal may initially rule on its own jurisdiction, including
nationality other than those of the parties. However, in suitable circumstances any objections with respect to the existence or validity of the arbitration agreement
and provided that neither of the parties objects within the time limit fixed by the or any condition precedent to the filing of a request for arbitration.
Court, the sole arbitrator or the chairman of the Arbitral Tribunal may be chosen The Special ADR Rules expounded on the implementation of the said principle:
from a country of which any of the parties is a national. (Emphasis ours) Rule 2.4. Policy implementing competence-competence principle. The arbitral
In accordance with the aforecited rules, Dr. Chantara-Opakom was appointed tribunal shall be accorded the first opportunity or competence to rule on the issue
upon the proposal of the Thai National Committee. of whether or not it has the competence or jurisdiction to decide a dispute
submitted to it for decision, including any objection with respect to the existence or
It bears stressing that the pro-arbitration policy of the State includes its policy to validity of the arbitration agreement. When a court is asked to rule upon issue/s
respect party autonomy. Thus, Rule 2.3 of the Special ADR Rules provides that affecting the competence or jurisdiction of an arbitral tribunal in a dispute brought
"the parties are free to agree on the procedure to be followed in the conduct of before it, either before or after the arbitral tribunal is constituted, the court must
exercise judicial restraint and defer to the competence or jurisdiction of the arbitral tribunal's findings.
arbitral tribunal by allowing the arbitral tribunal the first opportunity to rule
upon such issues. (Emphasis ours) Even granting that the court may rule on the issue of whether the dispute is an
To recall, the Agreement provides that "(a)ny dispute, controversy or claim arising intra-corporate controversy, Mabuhay's argument is premised on the factual issue
out of or relating to this Agreement, or breach thereof, other than intra-corporate of whether Sembcorp indeed acquired the shares of IDHI. Mabuhay failed to
controversies, shall be finally settled by arbitration..." establish such fact before the arbitral tribunal. The RTC, on the other hand,
concluded that Sembcorp acquired the subject shares but failed to explain the
Among the issues settled in the Final Award is whether the dispute is an intra- basis for such conclusion. In the absence of sufficient evidence that Sembcorp
corporate controversy. Dr. Chantara-Opakom ruled in the negative. The pertinent acquired the shares of IDHI, the Court finds no cogent reason to disturb the arbitral
portion of the Final Award is reproduced as follows: tribunal's ruling in favor of the latter's jurisdiction over the dispute.
x x x Indeed, during the cross-examination of Mr. Chay, he admitted that there
was no transfer of shares from IDHI to the Claimant [p. 130 of Transcript of C. Enforcement of the award would not be contrary to public policy of the
Proceedings]: Philippines.

x x x x Under Article V(2)(b) of the New York Convention, a court may refuse to enforce
an award if doing so would be contrary to the public policy of the State in which
During the re-examination of Mr. Chay by the Respondent's counsel, he again enforcement is sought. Neither the New York Convention nor the mirroring
admitted that the transfer of the shares from IDHI to the Claimant has not taken provisions on public policy in the Model Law and Our arbitration laws provide a
effect [p. 155 of Transcript of Proceedings]: definition of "public policy" or a standard for determining what is contrary to public
policy. Due to divergent approaches in defining public policy in the realm of
x x x x international arbitration, public policy has become one of the most controversial
bases for refusing enforcement of foreign arbitral awards. [52]
It is clear that the Claimant's claim is neither premised on allegations of
mismanagement of WJNA and WJSC, nor on who manages or controls or who has Most arbitral jurisdictions adopt a narrow and restrictive approach in defining public
the right to manage or control WJNA and WJSC, nor is it a claim to effect the policy pursuant to the pro-enforcement policy of the New York Convention. The
transfer of the share, nor an action for registration of the shares transfer [sic] public policy exception, thus, is "a safety valve to be used in those exceptional
already transferred from IDHI to the Claimant in the books of WJNA and WJSC. circumstances when it would be impossible for a legal system to recognize an
The nature of the Claimant's claim is not intrinsically connected with the regulation award and enforce it without abandoning the very fundaments on which it is
of the corporation. The Claimant's claim in this arbitration is straightforward: that based."[53] An example of a narrow approach adopted by several jurisdictions[54] is
the Respondent agreed, under a contract, to make payment of certain amount of that the public policy defense may only be invoked "where enforcement [of the
money to the Claimant upon the occurrence of a specified event; that the said award] would violate the forum state's most basic notions of morality and
event occurred but the Respondent refused to pay such amount of money to the justice."[55] Thus, in Hong Kong, an award obtained by fraud was denied
Claimant; that the Claimant filed the Request in order to enforce the payment. enforcement by the court on the ground that fraud is contrary to Hong Kong's
Accordingly, the Sole Arbitrator is of the opinion that the dispute in this "fundamental notions of morality and justice."[56] In Singapore, also a Model Law
arbitration is not an intra-corporate controversy, and, hence, it is not country, the public policy ground is entertained by courts only in instances where
excluded from arbitration under Article 19.2 of the Shareholders' Agreement. upholding the award is "clearly injurious to the public good or... wholly offensive to
[49]
 (Emphasis ours) the ordinary reasonable and fully informed member of the public."[57]
Again, the Special ADR Rules specifically provides that in resolving the petition for
recognition and enforcement of a foreign arbitral award, the court shall not disturb In Our jurisdiction, the Court has yet to define public policy and what is deemed
the arbitral tribunal's determination of facts and/or interpretation of law.[50] contrary to public policy in an arbitration case. However, in an old case, the Court,
through Justice Laurel, elucidated on the term "public policy" for purposes of
Yet, the RTC, in its decision dismissing the petition of Sembcorp, declared that "it declaring a contract void:
is undisputed that the shares of stocks of IDHI in WJNA and WJSC were actually x x x At any rate, courts should not rashly extend the rule which holds that a
owned by [Sembcorp] before the filing of the request for arbitration" [51] without contract is void as against public policy. The term "public policy" is vague and
providing any factual basis for such conclusion which directly contradicts the uncertain in meaning, floating and changeable in connotation. It may be said,
however, that, in general, a contract which is neither prohibited by law nor
condemned by judicial decision, nor contrary to public morals, contravenes no At any rate, Mabuhay's contention is bereft of merit. The joint venture between
public policy. In the absence of express legislation or constitutional prohibition, a Mabuhay, IDHI, and Sembcorp was pursued under the Joint Venture Corporations,
court, in order to declare a contract void as against public policy, must find that the WJSC and WJNA. By choosing to adopt a corporate entity as the medium to
contract as to the consideration or thing to be done, has a tendency to injure the pursue the joint venture enterprise, the parties to the joint venture are bound by
public, is against the public good, or contravenes some established interests corporate law principles under which the entity must operate.[62] Among these
of society, or is inconsistent with sound policy and good morals, or tends principles is the limited liability doctrine. The use of a joint venture corporation
clearly to undermine the security of individual rights, whether of personal allows the co-venturers to take full advantage of the limited liability feature of the
liability or of private property.[58] (Emphasis ours) corporate vehicle which is not present in a formal partnership arrangement. [63] In
An older case, Ferrazzini v. Gsell[59], defined public policy for purposes of fine, Mabuhay's application of Article 1799 is erroneous.
determining whether that part of the contract under consideration is against public
policy: ii. Imposition of interest
By "public policy," as defined by the courts in the United States and England, is
intended that principle of the law which holds that no subject or citizen can Mabuhay argues that the twelve percent (12%) annual interest from the date of the
lawfully do that which has a tendency to be injurious to the public or against Final Award is also contrary to the Philippine law and jurisprudence. To reiterate,
the public good, which may be termed the "policy of the law," or "public policy in the only ground for refusing enforcement of a foreign arbitral award is when
relation to the administration of the law." Public policy is the principle under which enforcement of the same would be contrary to public policy.
freedom of contract or private dealing is restricted by law for the good of the public.
In determining whether a contract is contrary to public policy the nature of the Mere incompatibility of a foreign arbitral award with domestic mandatory rules on
subject matter determines the source from which such question is to be solved. interest rates does not amount to a breach of public policy. However, some
(Emphasis ours and citation omitted) jurisdictions refused to recognize and enforce awards, or the part of the award
In light of the foregoing and pursuant to the State's policy in favor of arbitration and which was considered to be contrary to public policy, where they considered that
enforcement of arbitral awards, the Court adopts the majority and narrow approach the awarded interest was unreasonably high.[64] In this case, the twelve percent
in determining whether enforcement of an award is contrary to Our public policy. (12%) interest rate imposed under the Final Award is not unreasonably high or
Mere errors in the interpretation of the law or factual findings would not suffice to unconscionable such that it violates our fundamental notions of justice.
warrant refusal of enforcement under the public policy ground. The illegality or
immorality of the award must reach a certain threshold such that, enforcement of IV. Attorney's Fees
the same would be against Our State's fundamental tenets of justice and morality,
or would blatantly be injurious to the public, or the interests of the society. Mabuhay avers that the dispositive portion of the CA Decision failed to include its
finding that Mabuhay is not liable for attorney's fees and exemplary damages. The
We now discuss the pertinent claims of Mabuhay in relation to public policy. pertinent portion of the CA Decision is reproduced as follows:
Turning now to Sembcorp's prayer for the award of attorney's fees and exemplary
i. Violation of partnership law damages, We find the same bereft of legal and factual bases. Article 2208 of the
Civil Code allows attorney's fees to be awarded if the claimant is compelled to
Mabuhay contends that it entered into a joint venture, which is akin to a particular litigate with third persons or to incur expenses to protect his interest by reason of
partnership, with Sembcorp. Applying the laws on partnership, the payment of the an unjustified act or omission of the party from whom it is sought, there must be a
Guaranteed Return to Sembcorp is a violation of Article 1799[60] of the Civil Code, showing that the losing party acted willfully or in bad faith and practically compelled
as it shields the latter from sharing in the losses of the partnership. Ergo, the claimant to litigate and incur litigation expenses. Meanwhile, in order to obtain
enforcement of the Final Award would be contrary to public policy as it upholds a exemplary damages under Article 2232 of the Civil Code, the claimant must prove
void stipulation. that the assailed actions of the defendant are not just wrongful, but also wanton,
fraudulent, reckless, oppressive or malevolent.
The restrictive approach to public policy necessarily implies that not all violations of
the law may be deemed contrary to public policy. It is not uncommon for the courts Indeed, Sembcorp was compelled to file the instant appeal. However, such fact
in Contracting States of the New York Convention to enforce awards which does alone is insufficient to justify an award of attorney's fees and exemplary damages
not conform to their domestic laws.[61] when there is no sufficient showing of MHC's [Mabuhay] bad faith in refusing to
abide by the provisions of the Final Award. To Us, MHC's [Mabuhay] persistent
acts in rejecting Sembcorp's claim proceed from an erroneous conviction in the
righteousness of its cause.[65]
We affirm the aforecited findings of the CA. However, We find no conflict between
the fallo and the ratio decidendi of the CA Decision. The fallo of the CA Decision
includes "[n]o pronouncement as to cost." The CA also reversed and set aside the
RTC Decision in its entirety. As such, even the pronouncement of the RTC as to
costs is set aside. Accordingly, We find no merit in Mabuhay's prayer for a
statement in the dispositive portion expressly stating that it is not liable for
attorney's fees and exemplary damages.

On a final note, We implore the lower courts to apply the ADR Act and the Special
ADR Rules accordingly. Arbitration, as a mode of alternative dispute resolution, is
undeniably one of the viable solutions to the longstanding problem of clogged court
dockets. International arbitration, as the preferred mode of dispute resolution for
foreign companies, would also attract foreign investors to do business in the
country that would ultimately boost Our economy. In this light, We uphold the
policies of the State favoring arbitration and enforcement of arbitral awards, and
have due regard to the said policies in the interpretation of Our arbitration laws.

WHEREFORE, the Petition is hereby DENIED. The November 19, 2013 Decision


and the June 3, 2014 Resolution of the Court of Appeals in CA-G.R. CV No. 92296
are AFFIRMED.

SO ORDERED.

 
 

You might also like