Professional Documents
Culture Documents
CE 308 Construction Technology and Management: Dr. Santu Kar Department of Civil Engineering
CE 308 Construction Technology and Management: Dr. Santu Kar Department of Civil Engineering
Lecture 5
Counter claim is a cross claim, and it can be raised as a defense to claim but may not be so in a
number of situations and can be a substantive claim against the claimant which could have rooted
as independent action.
❑ What is dispute?
A dispute implies on assertion of a right by one party and repudiation thereof by another. Hence a
mere claim without repudiation cannot be a dispute and a claim cannot be adjudicated unless it
becomes a dispute.
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 3
Reasons of Disputes
Incorrect ground data
Contracts containing faulty and ambiguous provisions
Deviations
Suspension of works
Hindrances due to other contractors working on site
Owners not handing over site on dates agreed
Defaults by contractor
Levy of compensation for delay
Delay in payment of bills
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 4
Mediation and conciliation
❑ An informal process in which the parties are assisted by one or more
neutral third parties in their efforts towards settlement
❑ Mediators advise and consult impartially with the parties to assist in
bringing about a mutually agreeable solution to the problem
❑ Mediators have no power to impose an outcome on disputing parties
❑ The parties participate in their own free will
❑ The process is private, confidential and conducted without prejudice to
any legal proceedings
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 5
Mediation and conciliation
❑ Process of mediation and conciliation
– Agree to mediate
– Information gathering
– Facilitating negotiation
– Settlement
– Recording agreements
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 7
Arbitration
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 8
Arbitration (cont…)
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 9
Selection of Arbitrator
Technical person with special knowledge of subject matter under dispute
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 10
Duties of Arbitrator
Call for a preliminary meeting to familiarize himself of the issues and disputes or send notices to
parties asking them to forward statement of case along with supporting documents
Should not receive any evidence in the absence of the other party
Should not examine a witness in the absence of any of the parties and should not make private
enquires at the back of any party
Must adhere to time schedule laid down for making and publishing the award
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 11
Arbitration (Case Study)
❑ Project description
Supply and commissioning of coal handling plant (CHP) by L&T at Maharashtra for
Maharashtra State Electricity Board (MSEB)
Details of contract -
LOI issued on 19/04/1988
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 12
Arbitration (Case Study)
❑ Background of the claims ▪ Arbitrators
▪ L&T filed its claims on October 1994 o Mr. X (Appointed by L&T)
o Mr. Y (Appointed by MSEB)
▪ L&T raised 14 claims worth Rs. 26,84,65,023
o Mr. Z (Institution of Engineer)
▪ MSEB strongly opposed the claims and raised
counterclaims
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 13
Case Study – Claim No. 1
Description: Additional cost of hand railing on all the walkways along the conveyor
instead of providing only for the central walkway
❑ Claimant (L&T)
❑ Respondent (MSEB)
MSEB drawing for this work shows both
side handrailing on all the walkways
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 14
Case Study – Claim No. 1 (Cont…)
❑ Claimant (L&T)
❑ Respondent (MSEB)
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 15
Case Study – Claim No. 1 (Cont…)
L&T MSEB
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 16
Case Study – Claim No. 1 (Cont…)
Arbitrators
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 17
Case Study – Claim No. 2
Description: Compensation for extra work carried out for repair of conveyor and
structure due to damage caused by oversized boulders of coal.
❑ Claimant (L&T)
▪ Coal of 600 mm size and below was expected
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 18
Case Study – Claim No. 2
❑ Respondent (MSEB)
▪ We have specified that the grid should be adequate to pass coal of 600 mm
size and below
▪ Instead of making diagonal of grid 600 mm, L&T made 600 mm x 600 mm size
grid, which allowed bigger size of coal lumps up to 848 mm size to pass
through
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 19
Case Study – Claim No. 2
❑ Claimant (L&T)
▪ The design was approved by MSEB
❑ Respondent (MSEB)
▪ When L&T submitted the design, our interest was only to get coal of 600mm size
and below
▪ This 600 mm size grid was considered by L&T, now the diagonal becomes 848 mm
L&T MSEB
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 20
Case Study – Claim No. 2 (Cont…)
Arbitrators
Dr. Santu Kar, Assistant Professor, Department of Civil Engineering, IIT Guwahati 21
Thank You