To evaluate the performance of a three-phase, Dyn11, 11/0.415 kV, 250 kVA distribution transformer, nine tests must be performed according to IEC-60076 and other relevant standards: measurement of turns ratio, vector group, winding resistance, insulation resistance, no-load loss and current, impedance voltage and load loss at 75C, dielectric withstand, transformer oil dielectric, and temperature rise. A report must be prepared explaining the procedures for each test and including necessary diagrams.
To evaluate the performance of a three-phase, Dyn11, 11/0.415 kV, 250 kVA distribution transformer, nine tests must be performed according to IEC-60076 and other relevant standards: measurement of turns ratio, vector group, winding resistance, insulation resistance, no-load loss and current, impedance voltage and load loss at 75C, dielectric withstand, transformer oil dielectric, and temperature rise. A report must be prepared explaining the procedures for each test and including necessary diagrams.
To evaluate the performance of a three-phase, Dyn11, 11/0.415 kV, 250 kVA distribution transformer, nine tests must be performed according to IEC-60076 and other relevant standards: measurement of turns ratio, vector group, winding resistance, insulation resistance, no-load loss and current, impedance voltage and load loss at 75C, dielectric withstand, transformer oil dielectric, and temperature rise. A report must be prepared explaining the procedures for each test and including necessary diagrams.
To evaluate the performance of three-phase distribution transformers, following
tests are usually performed as per IEC-60076 and other relevant standards.
1. Measurement of turns ratio test
2. Vector group test 3. Measurement of winding resistance 4. Measurement of insulation resistance 5. Measurement of no-load loss and no-load current 6. Measurement of impedance voltage and load loss at 75oC 7. Dielectric withstand test/ High voltage test 8. Dielectric test of transformer oil 9. Temperature rise test
Consider a three-phase, Dyn11, 11/0.415 kV, 250 kVA distribution transformer.
Prepare a report by explaining the procedures of conducting the above tests as
per IEC-60076 and other relevant standards. Also, include the necessary diagrams.