722 CIVIL EXCAVATION WATER TANK/ZONE 11 NEED APPROVAL MECHANICAL DRAWINGS TECHNICAL
719 IRRIGATION INSTALLATION MAIN LINE/ZONE 10/L2 NEED UPDATE DRAWING TECHNICAL
706 CIVIL EXCAVATION SHRUBS PLANTER AREA/Z00/L1 NEED APPROVED DRAWING TECHNICAL
707 CIVIL EXCAVATION SHRUBS PLANTER AREA/Z00/R1 NEED APPROVED DRAWING TECHNICAL
708 CIVIL INSTALLATION RIYADH LIME STONE/Z11/L4 NEED ACTION FROM SITE TEAM CONSTRUCTION
709 IRRIGATION SAND BEDDING/Z10/R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
758 IRRIGATION SAND BEDDING/Z10/R2 NEED ACTION FROM SITE TEAM CONSTRUCTION
610 IRRIGATION SECOND LAYER BACKFILL/Z10/L4 NEED ACTION FROM SITE TEAM CONSTRUCTION
611 CIVIL EXCAVATION FOR RIYADH STONE/Z10/R2 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
612 CIVIL EXCAVATION FOR RIYADH STONE/Z10/R3 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
742 IRRIGATION EXCAVATION MAIN LINE/Z14/R1 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
743 CIVIL EXCAVATION FLUSH KERB/Z11/L4 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
540-541 LANDSCAPE PLANTING TREES /Z12/R2 R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
286 LANDSCAPE INSTALLATION RIYADH LIME STONE/Z12/L3 NEED ACTION FROM SITE TEAM CONSTRUCTION
431/432 LANDSCAPE INSTALLATION INTERLOCK/Z12/L3/R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
329/328 LANDSCAPE INSTALLATION FLUSH KERB/R2/R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
180/147 LANDSCAPE INSTALLATION RIYADH STONE R2/R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
386 IRRIGATION ISOLATION VALVE/Z11/R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
542- 543 -544 CIVIL WOODEN TREE STAKE/Z12/L2 R2 R3 NEED ACTION FROM SITE TEAM CONSTRUCTION
549 CIVIL GRAVEL MULCH(25-60MM)/L2/Z12 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
548 CIVIL GEOTEXTILE PLANTING AREA/Z12/L2 NEED ACTION FROM SITE TEAM/SURVEYOR CONSTRUCTION
555 CIVIL EXCAVTION SHRUBS GROUNDCOVER/Z10/L2 NEED ACTION FROM SITE TEAM CONSTRUCTION
457 CIVIL GEOTEXTILE PLANTING AREA/Z12/R2 NEED ACTION FROM SITE TEAM CONSTRUCTION
347 CIVIL GRAVEL MULCH(25-60MM)/R2/Z12 NEED ACTION FROM SITE TEAM CONSTRUCTION