PROJECT: PHNOM PENH CAMBODIA TEMPLE

SPUN PILE FABRICATION SCHEDULE FOR ANNEX (MASS PILE)


Monitoring contents Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue
TOTAL
(segments)

3/15

3/16

3/17

3/18

3/19

3/20

3/21

3/22

3/23

3/24

3/25

3/26

3/27

3/28

3/29

3/30

3/31

4/10

4/11

4/12

4/13

4/14

4/15

4/16

4/17

4/18

4/19

4/20

4/21

4/22

4/23

4/24

4/25

4/26

4/27

4/28

4/29

4/30
4/1

4/2

4/3

4/4

4/5

4/6

4/7

4/8

4/9

5/1

5/2

5/3
Building Casting date

Generator +
Shoe Segment L8 6 6
Transformer

End Segment L7 27 40 40 40 40 42 60 60 5 354


Annex Building
Shoe Segment L8 27 20 20 20 20 18 125

Con'c test
14days
Segments
Con'c test
14days

0
Segments
Con'c test
14days

0
Segments
Con'c test
14days

89271
PLANING
Concrete strength test 14days

Pile Delivery Schedule

TOTAL per day (segments) 60 60 60 60 60 0 60 60 60 5

Accumulation (segments) 60 120 180 240 300 300 360 420 480 485 485
Percentage % 12% 25% 37% 49% 62% 62% 74% 87% 99% 100%