Professional Documents
Culture Documents
1.1 Sec. 12 of the Manual on the New Government Accounting System, Volume II
provides that Subsidiary Ledger (SL) is a book of the final entry containing the
details or breakdown of the balances of the controlling account appearing in the
General Ledger (GL).
Account Balance
Due to BIR 7,365,330.47
Due to GSIS 546,758.47
Due to PAG-IBIG 32,051.71
Due to PHILHEALTH 152,177.19
Total 8,096,317.84
1.3 In the verification of the supporting schedule of the subsidiary ledger records of the
above mentioned accounts, we noted the existence of negative accounts and the
inclusion of amounts that have no details as follows:
26
1.4 It was noted in the course of random verification of the subsidiary ledgers that there
were remittances posted in the SL without corresponding deductions resulting in
negative balances.
1.5 The existence of negative balances in the subsidiary ledgers is a manifestation that
these records are not being monitored. Abnormal balances are required to be
investigated or analyzed so that necessary correction/s could be made. There is also
laxity in the preparation of list of remittances that resulted in remittances without
corresponding deductions. The Chief Accountant who certified the correctness of the
remittances has not also checked the deficiencies noted. As a result, said deficiency
affected the correctness of the account balance.
1.6 Moreover, there is an unreconciled amount of P603,599.99 of which details are still
to be identified by the Accounting Division. The amount had been existing in prior
years, hence affecting the correctness of the ending balance of the accounts.
a. the Accounting Division to strictly monitor the Due to BIR, Due to GSIS, Due to
PAG-IBIG and Due to PHILHEALTH accounts so that negative balances will be
analyzed and correspondingly corrected/adjusted;
b. the personnel in charge of preparing the List of Remittances to always see to it
that only those officials and employees who have deductions are included in the
list; and
c. the Chief Accountant to exert effort to determine the details of the amounts that
are still subject for reconciliation to ensure that balances of said accounts
appearing in the general ledger are correct.
2. Of the P718,902.83 balance of the Tax Refunds Payable account, the amount of
P429,707.07 or 59.77 per cent were stale checks and unpaid tax refunds since the
payees were already separated from service or could no longer be contacted; thus,
had been outstanding for two years or more but were not reverted to the retained
operating surplus as required in COA-DBM Joint Circular No. 99-6.
2.1 In the course of our verification and analysis of the Schedule of the Tax Refunds
Payable as of December 31, 2011, we noted that it included payables to former
27
employees of the Court that have been outstanding for two years or more. Aging of
the tax refunds payable is shown below:
2.2 COA-DBM Joint Circular No. 99-6 dated November 13, 1999 prescribed the
guidelines on the reversion of accounts payable to the cumulative result of operation
of the national government which have been outstanding for two years or more
pursuant to Executive Order No. 109. The guidelines were issued due to proliferation
of dormant and outstanding accounts payable in the books of accounts of agencies
that hamper the national government efforts to establish a more realistic cash
program.
2.3 Our verification showed that some of the checks for tax refunds issued to the former
CA employees were not received by them and became stale, hence accumulated as
outstanding tax refunds payable. Other recorded tax refunds payable remained
outstanding since payees are no longer connected with the Court due to retirement,
resignation, transfer to other offices and termination of appointment. Details are as
follows:
2.4 The amount of P429,707.07 which is 59.77 per cent of the balance of the Tax
Refunds Payable account was not reverted to the retained operating surplus as
required in the abovementioned COA-DBM Joint Circular.
2.5 We recommended that management require the Chief Accountant to revert all tax
refund payables that have been outstanding for two years or more.
2.6 In response to our audit recommendation, the Chief Accountant will undertake the
reversion of all tax refunds payable particularly for years 2009 and below while tax
28
refunds payable set up in 2010 will be further verified and payees will be notified in
writing of their unclaimed tax refunds
3.1 The construction of the transformer vault room was recommended by the
Maintenance and Utility Section due to electrical problems being experienced by the
Court. The transformer vault room will provide electrical supply for the Annex I
Building which at present is connected to the Main Electrical Room which supplies
power in all the buildings except for the Centennial Building which has its own
transformer.
3.2 The Court entered into a contract on October 23, 2008 for the said project in the
amount of P2,404,572.80 with a Notice to Proceed received by the contractor on
December 18, 2008 for 45 calendar day completion of the project.
3.3 The contractor submitted its accomplishment report as of February 28, 2009 which
was equivalent to 89.34 per cent and requested for 1st Partial Payment in the amount
of P2,148,245.34. Officials from the General Services Division issued a certification
of verification and inspection and payment was approved by the agency head.
3.4 On June 1, 2009, the Project Coordinator reported delays in the completion of the
project due to requirements of the Electrical Division of the Manila City Hall on
signed copies of electrical load of the Annex I Building, requirements and approval of
MERALCO, and coordination work with Maynilad for adjustment of existing water
meter that affects the Steel Louver Door of the Transformer Vault Room.
3.5 Inquiry from the Project Coordinator revealed that the requirements and approval of
MERALCO was only complied with in early 2012. We noted however, that
contractor still have remaining works to be done which is equivalent to 10.66 per cent
to complete the project for a remaining project cost of P256,327.46 enumerated as
follows:
29
Cleaning, Testing & Turnover 0.85
Total 10.66
3.6 Also, as provided under Article XVIII, Section 18.1 of the Agreement, the contractor
is required to submit to the Court the following upon completion of the project:
3.7 According to the Project Coordinator the completion of the project was delayed by
more than two (2) years due to the inability of the contractor to coordinate with him
despite of several notices for the compliance of the requirements of City Engineer’s
Office of Manila on the contractor’s license, electrical permits including signatories
to the revised electrical plans. Thus, benefits that can be obtained from the project
of avoiding the risk of overloading has not been achieved.
3.8 We recommended that management coordinate with the contractor for the
completion of the project so that the intended purpose of the project can benefit the
Court. Otherwise, apply the provisions of the Agreement particularly Article X on
contract time, completion date, extension and liquidated damages and Article IX on
Owner's option to take over.
3.9 In reply to our audit observation, the Technical Working Group (TWG) commented
that the delays on the execution of the project were attributed to changes of the
requirements of the City Engineer's Office of Manila from contractor's licenses
(PCAB), electrical permits including signatories to the revised electrical plans. The
inability of the contractor to coordinate with the Project Coordinator, although several
notices were served for him, was contributory to the delay in the early compliance
with the said requirements and became a setback in the project where a revised
30
schedule would have been done to cope with its completion. The project coordinator
is now in close coordination with the contractor and pressing them for the immediate
completion of the project. The TWG will also ask assistance from the Management
Audit and Accounting Divisions for the computation of penalties, if any, that should
be imposed on the contractor for the delay in the completion of the project.
4.1 Section 31 of the General Appropriations Act of 2011 provides that the GAD plan
shall be integrated in the regular activities of the agencies, which shall be at least five
percent of their respective budgets. The Court's appropriation for the year was
P902,303,000.00, thus five percent or P45,115,150.00 should be budgeted to GAD
projects.
4.2 For calendar year 2011, the agency allocated P5,000,000.00 for the following planned
projects/activities which is more than last year’s budget but less than the five percent
requirement:
4.3 Meanwhile, the agency implemented several projects and spent P2,014,125.49 as
follows:
31
of the Philippines
c. Annual Program/Budget Planning Conference of 144,598.01
CA-GAD Focal Point
d. Conducted second Breast Cancer Awareness 11,118.70
Lecture and free Clinic Breast Examination
e. Printed 70 copies of Book on Laws, Rules, 17,500.00
Issuance for cases involving family, domestic
relations, women and children
f. Conducted on the Spot Essay Writing Contest with 26,021.00
the theme “Celebrating Nation's Quest for
Development Towards the New Millennium”
g. Conducted four seminars on CEDAW and Gender 1,184,977.93
Sensitivity for CA-Manila, CA- Cebu and CA
Cagayan de Oro City
h. Intensive Training Workshop for CA-GAD Focal 169,772.55
Point
i. Conducted seminar on First Aid with CPR and free 13,650.70
hand, facial spa and eye refraction check-up
Total P2,014,125.49
4.4 The Audit Team noted that not all proposed projects were accomplished by the GAD
Focal Point during the year. Of the 16 Gender Awareness and Gender Sensitivity
Seminars planned, only four were conducted while only one intensive training
workshop was held for CA-GAD Focal Point instead of two.
4.5 According to CA-GAD Focal Point, the planned activities were not fully
accomplished due to resignation of the Chairperson and co-chairperson in June 2011.
The new Chairperson took over only in November 2011, hence the insufficient time
within the year to fulfill all the proposed plans.
4.6 Moreover, the agency did not deemed it practical to appropriate the full amount
required for the GAD Focal Point as the Court has other priority programs and plans
in accordance with its mandate. It, however, increased the allocation for the year to
implement more GAD projects in compliance to the previous audit recommendation
of the Audit Team.
32
5. Implementation of Programs/Projects for Senior Citizens and the Differently-Abled
for CY 2011
5.1 Sec. 32 of the General Appropriations Act provides that the plans, programs and
projects intended to address the concerns of senior citizens and differently-abled
persons shall be integrated in the regular activities of the agencies, which shall be at
least one percent (1%) of their respective budgets.
5.3 Nevertheless, the Audit Team observed that the agency has constructed in previous
years’ access paths for disabled persons to facilitate mobility to different buildings of
the Court. As part of medical services, all employees including senior citizens and
personnel with disability were given vaccines for flu and pneumonia. The Court is
also strengthening its medical and dental services benefiting all personnel thru
acquisition of medical equipment, medicines, and dental supplies to cater the health
and welfare of its employees.
6.1 For the year 2011, the adjusted withheld taxes from various suppliers, contractors,
salaries and other compensation of their officials and employees amounted to
P79,175,965.96 of which P71,810,635.49 was remitted to the Bureau of Internal
Revenue (BIR) leaving a balance of P7,365,330.47 as of year end. Of the balance,
P6,598,169.81 was remitted on January 16, 2012 while the amount of P767,160.66 is
subject to further verification before remittance to BIR.
7.1 The balance of notice of suspensions in the total amount of P287,360.00 were settled
during the year, leaving no unsettled balance as December 31, 2011. Details are as
follows:
33
Notice of 0 0 0 0
Disallowance
Notice of Charge 0 0 0 0
Total P287,360.00 0 P287,360.00 0
34