HEMANTH KRISHNA RAI


Feb 09, 2009 at 10:11 AM

PP-PS integration
1453 Views
0

Follow RSS
Feed

Hi PP GURUS,

NEED SOME GYAAN!!

What are the major integration settings for a typical PP-PS scenario.

Ellaborate answers will be rewarded

THNX in Advance

HKR
Add a Comment | Alert Moderator

Assigned Tags

MAN Production Planning (PP)

PLM Project System (PS)

Similar Questions 
SAP PP-PS step-by-step process flow.
thiru jack Nov 22, 2019

Production Order in PP/PS Integration Project


Aditya S Nov 23, 2019

2 Answers

Sort by: Votes | Newest | Oldest

Best Answer

Former Member
Feb 09, 2009 at 03:44 PM

Hi Hemanth
2
with respect to your query i want to give brief overview reg PP ps

while creation of BOM (wbs/material) with tcode cs01 and cs71 you have to select usage as 3

you have to create project with tcode cj20n and assign budget and cost planning is to be done

activity is to be assigned to net work

once it is done you have to run Project Mrp with tcode as MD51 select for mrp paramters enter Project and WBS element as well

whenever you are going to convert material bom to wbs bom you have to use t code cn33 for bom transfer

this scenario will be useful where project execution is going on but the requirements comes through project mrp it will be convert planned order
to production order (md04) as well as purchase requisitions

i hope this will clarify you an overview relates to PP and PS integration

thanks

shaik

Add a Comment | Alert Moderator | Share

Former Member
Feb 09, 2009 at 10:40 AM

Hi,
0
As i know

1)

BOM should be created with BOM usage 3(Universal). Because these BOM transfer to required project.
2)

In the project, below project two components WBS and Network, you can attach components(Raw materials) to WBS as well as Network.

If u attach the components to WBS these components are planned with respect the project system.

Run the MRP at project level. The material procured(attached to WBS) are resever against the project showing as project stock.

3)

The component which are attached to network are planned at plant level. the components are plant stock.

Regards

Vijay

Add a Comment | Alert Moderator | Share

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more
information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the
solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.

Rules of Engagement 

Know someone who can answer? Share a link to this question.

You must be Logged in to submit an answer.

Please provide a distinct answer and use the comment option for clarifying purposes.