You are on page 1of 22

SubSea Offshore Limited Prepared By: C.

Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

SUBSEA OFFSHORE LTD

ALLSEAS MARINE CONTRACTORS


BRITISH GAS TRINIDAD LTD
DOLPHIN GAS FIELD DEVELOPMENT PROJECT

DOLPHIN A SPOOLPIECE
INSTALLATION PROCEDURE

SSOL DOC. NO. AB-D-PR-03007


ALLSEAS DOC. NO.E086-08
©Copyright

Copy No.

Distributed to: W.P. No. DPR03007

Revision Description Date Prep Check Approved


SSOL Client
0 Issued for Comment 15/9/95 CM DM AM
1 Issued for Approval 28/9/95

Document No.: AB-D-PR-03007 Page: 1 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

AMENDMENTS

0. ISSUED FOR COMMENT 15 / 9 / 95

1. ISSUED FOR APPROVAL 28 / 9 / 95

Document No.: AB-D-PR-03007 Page: 2 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

CONTENTS

AMENDMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1.1 Scope of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4


1.2 Spoolpiece Installation Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.3 Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.4 Responsibility . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.5 Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.6 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

2.0 PROJECT OVERVIEW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

3.0 HAZARD IDENTIFICATION AND MANAGEMENT . . . . . . . . . . . . . . . . . . . . 7

3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.2 Hazard Identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.3 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.4 Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

4.0 SPOOLPIECE INSTALLATION OPERATIONS . . . . . . . . . . . . . . . . . . . . . . 9

4.1 Initial Situation on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9


4.2 Method of Deployment ......................................................................... 9
4.3 Preparatory Works . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
4.4 Dolphin A Spoolpiece installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

Document No.: AB-D-PR-03007 Page: 3 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

5.0 CONTINGENCY MEASURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

5.1 Seabed Conditions................................................................................ 16

6.0 EQUIPMENT LIST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

APPENDICES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

1.0 INTRODUCTION

1.1 Scope of Work

The following procedure describes the work required to install the tie in spoolpiece, in two
sections, between the Dolphin A platform riser and the 24” Dolphin gas pipeline.

1.2 Spoolpiece Installation Summary

On completion of the installation of 24” Gas Pipeline (approx. 40 miles long) from the NGC
Platform to the Dolphin Platform by Allseas, SSOL shall mobilise the DSV Discovery to
install the 24” riser, riser guard , 3 No side tap protection covers and associated expansion
spools at the NGC and Dolphin platform.

1.3 Objectives

The purpose of this procedure is to ensure that all parties are familiar with the scope of
work and that personnel are aware of their respective tasks and the essential interfaces
for a safe and efficient operation.

Document No.: AB-D-PR-03007 Page: 4 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

The procedure provides “step by step” details for performing the works.

Drawings and sketches are included to illustrate the works, and identify the sequence of
activities.

1.4 Responsibility

The Project Manager is responsible to the SSOL Operations Director for the completion of
the work.
On the DSV the Project Engineer will be responsible for the overall supervision of the
works, and ensuring that the installation is performed in accordance with the procedures.
He will be responsible for ensuring that all the project equipment is checked on mobilisation
and that the appropriate personnel are familiarised with its operation.
The Project Engineer will also be responsible for checking that all rigging equipment is
correctly installed and in date certification is available offshore in respect of all project
rigging and equipment. The certification will be available in the Mobilisation Manual, DOC
No: AB-D-MA-03004 which will be onboard the vessel.

1.5 Definitions

The following definitions are used in this Procedure

COMPANY British Gas Trinidad Ltd, hereafter called British Gas


CLIENT Allseas Marine Contractors A.S.
CONTRACTOR Subsea Offshore Ltd
CONTRACT L2368
PROJECT Dolphin Gas Field Development Project - Provision of Diving
Services

Document No.: AB-D-PR-03007 Page: 5 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

1.2 Abbreviations

The following abbreviations are used in this Procedure

DSV - Dive Support Vessel


ROV - Remotely Operated Vehicle
BGT - British Gas, Trinidad
ALLSEAS - Allseas Marine Contractors S.A
SSOL - SubSea Offshore Limited
CPI's - Company Provided Items
CTW - Constant Tension Winch

2.0 PROJECT OVERVIEW

Allseas have been contracted by British Gas Trinidad Ltd to fabricate and install a 24” gas
export pipeline from the Dolphin platform to the NGC platform, Offshore Trinidad.

SSOL have been contracted by Allseas to complete the following work along the proposed
pipeline route:-

- 1 off 24” riser, to be retro-fitted (with clamps and riser guard ) to the NGC
Platform
- 1 off 24” riser top, to be installed on the Dolphin Platform
- 1 off L-shaped spoolpiece to be installed at the NGC Platform
- 1 off Z-shaped spoolpiece to be installed, in two sections, at the Dolphin
Platform
- 1 off 24” Side Tap protection structure to be installed over the pipeline
- 2 off 16” Side Tap protection structure to be installed over the pipeline
- Stabilisation of pipeline crossings and expansion spools using grout bags and
concrete mattresses

Document No.: AB-D-PR-03007 Page: 6 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

3.0HAZARD IDENTIFICATION AND MANAGEMENT

3.1 Introduction
This section references the safety aspects associated with the installation of spoolpieces to be carried out
during this project.

Decisions on environmental conditions affecting operations defined by this procedure will be left to the
discretion of the Diving Superintendent and Vessel Master

3.2 Hazard Identification

3.2.1 Environmental Limitations

Due consideration must be given to limitations due to weather, including tidal parameters and limited
visibility.

3.2.2 Rigging

The Project Engineer will ensure that all items of project rigging used throughout the
project are correctly specified and that the test certification is in date for the duration
of the project. Copies of all certificates are to be available on board in the
Mobilisation Manual.

Document No.: AB-D-PR-03007 Page: 7 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

3.2.3 Lifting

Prior to use the Project Engineer will check that all rigging equipment is correctly
installed and fit for purpose

3.3 Safety

All vessel personnel will comply with the safety requirements list in Document No. AB-V-
MA-00201 Marine Safety Manual CLDSV Discovery.
In addition the requirements of Document No. AB-S-PR-00046 , SSOL Project Safety plan,
will be implemented.

3.4 Documentation

The Project Engineer will ensure that in date certification and relevant procedures,covering
all aspects of the project, are available on the DSV.

Document No.: AB-D-PR-03007 Page: 8 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

4.0 SPOOLPIECE INSTALLATION OPERATIONS

This section covers the setting out and installation of the tie in spoolpiece at the Dolphin
A platform.

4.1 Initial Situation at Site

Prior to the deployment of the spoolpiece the installed 24” pipeline will have been flooded
and final metrology completed.

The Dolphin A spool is constructed in two parts, Spoolpiece North and Spoolpiece South,
for subsequent connection on the seabed.
Spoolpiece North requires the final length adjustments to be carried out on deck prior to
deployment, these adjustments are dependant on the results from final metrology and are
described in more detail on sketch No. 03007 / 01.

The spoolpieces will arrive on the transit barge, spoolpiece North in three separate pieces
and spoolpiece South completed and fitted with lift clamps, ready for transferring to the
DSV deck for stowage. The individual pieces will be lifted onboard the Discovery in
readiness for final measurement , cutting and welding out to complete the spoolpiece
according to the metrology.

Further details of Metrology and spool make-up can be found in the relevant procedures.

Document No.: AB-D-PR-03007 Page: 9 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

4.2 Method of Deployment

The Dolphin A Spool is to be deployed in two sections.

Spoolpiece South , connecting into the existing jacket riser flange, will be the first
spoolpiece deployed and will be installed by means of a guide wire attached to a clump
weight at the outboard end. The spoolpiece will be deployed to the seabed and pulled in
to mate the flanges at the riser connection.

Spoolpiece North will then be deployed and installed by use of the pre-installed guide wire
at the spoolpiece South end and a flange catcher on the mating pipeline end.
Details of the guide wire follower and flange catcher may be found in the appendix to this
document.

4.3 Preparatory works

- Spoolpiece South to have blind flanges , gaskets and existing stud bolts removed, If
fitted. Temporary flange protection is to be attached to protect the flange faces from
damage or contamination.

- Spoolpiece lift clamps to be pre-rigged ready for lifting.


(Ref. Spoolpiece South Lift Rigging Layout Dwg. No. OCE-0184-002-02 )

- ROV to be deployed to riser flange to determine mudline level relative to spool


connection point.

Document No.: AB-D-PR-03007 Page: 10 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

- Any seabed remedial works required as a result of ROV survey to be carried out .
( see contingency measures in section 5.0 )

- Guidewire follower bracket to be fitted to spoolpiece outboard end .


(Ref. Dwg. No. OCE-0184-022-03 )

- Spoolpiece North to be cut to length, all as described in sketch No. 03007 / 01, and
prepared for welding . If fitted, blind flanges , gaskets and existing stud bolts to be
removed. Temporary flange protection is to be attached to protect the flange faces from
damage or contamination.

- Individual sections of spoolpiece to be welded out, NDT carried out and pipe coating
repaired in work areas .

Lift clamps to be fitted, aligned and fully tightened all in accordance with the positions
and orientations quoted on the spoolpiece North rigging layout.
(Ref. Spoolpiece North Lift Rigging Layout Dwg. No. OCE-0184-002-01 )

- Spoolpiece lift clamps to be pre-rigged ready for lifting.

- Flange catcher assembly to be fitted to spoolpiece North, pipeline end.


(Ref. Dwg. No. OCE-0184-022-03)

- Guidewire follower / flange catcher bracket to be fitted to spoolpiece North, inboard end
.
(Ref. Dwg. No. OCE-0184-022-03)

- Clump weight to be deployed.


See sketch No. 03007 / 02 for positioning and orientation.

Document No.: AB-D-PR-03007 Page: 11 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

- Confirm alignment of positioned clump weight and, if within tolerance, proceed to deploy
spool.

- Riser support bracket to be removed in accordance with sketch 03007 / 03.


For details of temporary riser supports during installation period, refer to Topsides
Preparation procedure.
Divers to check that riser has been flooded prior to removing flange bolts. If flange bolts
have been pretensioned , bolt tensioning spread will be required for removal.

4.4 Dolphin A Spoolpiece installation

- Vessel to set up on DP over spoolpiece South work site at Dolphin Platform.


Ref. sketch 03007 / 06 for details.

- ROV to be deployed to work location and carry out video survey of pipeline end, riser connection flange
and seabed along length of spool.

Note: ROV survey to pay particular attention to any damage to the pipeline end
connection, the jacket riser flange and any debris in the vicinity of the pipeline and the
proposed location of spool installations.

- Deploy divers to working depth, diver to check installation site for debris and clear as necessary.

- Diver to return to bell and standby.

- Deck crew and project engineer to check spoolpiece South rigging arrangement against rigging layout
drawing prior to subsea deployment.

- Guide wire, connected to CTW ,to be fitted through eye on follower bracket on spoolpiece South, outboard
end.

- Weights and light sticks to be attached to end of guidewire and approx 15m slack paid out from CTW.

- Release spoolpiece South from seafastenings.

- Pick up slack on rigging and ensure hook correctly positioned above load.

- Check each of the spoolpiece rigging lines for correct alignment under tension to ensure that the spool

Document No.: AB-D-PR-03007 Page: 12 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

will land on the seabed with a level orientation.

- When the spoolpiece is clear of the seafastenings, continue picking up to clear all obstructions and slew
crane to deploy spool over side.
(Ref. Dwg. No. OCE-0184-003-02)

- Pay out guidewire and deploy diver to secure to attachments on clump weight.

- When the spoolpiece assembly is in the water, pick up any remaining slack in guide wire and engage
constant tension facility on winch .

- Lower spoolpiece to within 10m of seabed.

- Deploy divers to each end of the spoolpiece.

- Whilst monitoring descent by diver, lower spoolpiece to seabed.


Disconnect rigging from the crane hook.

- Divers to rig Tirfor line, from spoolpiece to Jacket, and pull spoolpiece flange in under
riser flange .
(see sketch No. 03007 / 04 for details of Tirfor rigging arrangement)

- Install flange puller to riser connection and bring spoolpiece end up to mate with riser
flange.

- Loose fit bolts and new oval gasket in readiness for tightening with bolt tensioning
equipment spread. All bolts to be hand tightened and flanges aligned with uniform gap.

- Confirm satisfactory laydown of spoolpiece by ROV at both ends. Examine rigging


arrangement in preparation for release.

- Flange connection to be completed using bolt tensioning equipment, all in accordance


with bolt tensioning procedure.

- Deploy divers to outboard end of spoolpiece.

- Divers to disconnect guidewire from clump weight

- Guidewire follower bracket assembly to be removed and retrieved to deck.

Document No.: AB-D-PR-03007 Page: 13 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

- Vessel to set up on DP over spoolpiece North work site at Dolphin Platform.


Ref. sketch 03007 / 06 for details.

- Prepare spoolpiece North in readiness for lifting.

- Deck crew and project engineer to check spoolpiece North rigging arrangement against
rigging layout drawing prior to subsea deployment.

- Guide wire, connected to CTW ,to be fitted through eye on follower bracket on
spoolpiece inboard end.

- Weights and light sticks to be attached to end of guidewire and approx 15m slack paid
out from CTW.

- Release spoolpiece North from seafastenings.

- Pick up slack on rigging and ensure hook correctly positioned above load.

- Check each of the spoolpiece North rigging lines for correct alignment under tension to
ensure that the spoolpiece will land on the seabed with a level orientation.

- When the spoolpiece is clear of the seafastenings, continue picking up to clear all
obstructions and slew crane to deploy spoolpiece over side.
(Ref. Dwg. No. OCE-0184-003-01)

- Pay out guidewire and deploy diver to secure to attachments on clump weight
previously deployed on the seabed

- When the spoolpiece assembly is in the water, pick up any remaining slack in guide
wire and engage constant tension facility in winch .

- Lower spoolpiece to within 10m of seabed. Deploy divers to each end of the spoolpiece.

- Whilst monitoring descent by diver, lower spoolpiece to seabed ensuring correct


engagement of flange catchers to end of pipeline and to spoolpiece South flanges.

- Confirm satisfactory laydown of spoolpiece at both ends. Examine rigging arrangement


in preparation for release.

Document No.: AB-D-PR-03007 Page: 14 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

- Disconnect rigging from the crane hook.

- Deploy divers to jacket end connection ( spoolpiece South )

- Divers to install flange puller to spoolpiece South connection and bring spoolpiece North
end in to mate. Should distance to flanges be too great for flange puller connection,
close distance by pulling in with Tirfor rig prior to attachment.

- Loose fit bolts and new oval gasket in readiness for tightening with bolt tensioning
equipment spread. All bolts to be hand tightened and flanges aligned with uniform gap.

- Divers to disconnect guidewire from clump weight

- Guidewire follower bracket assembly to be removed and retrieved to deck.

- Flange connection to be completed using bolt tensioning equipment, all in accordance


with bolt tensioning procedure.

- Repeat operations at outboard end to mate and connect the flanges of the spoolpiece
and pipeline.

- Flange catcher assembly to be removed and retrieved to deck.

- Deploy divers to remove each of the lift clamps, all clamps are fitted with M30 bolts
requiring a 46mm AF spanner set for removal.

- Retrieve lift clamps and rigging to DSV deck and disconnect.

- DSV to reposition and recover clump weight to deck.

- On completion of spoolpiece installation activities R.O.V. to perform and video "as built"
survey .

5.0 CONTINGENCY MEASURES

5.1 Seabed Conditions

Document No.: AB-D-PR-03007 Page: 15 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

Prior to deployment of the spoolpieces an ROV survey of the worksite is to be


conducted. Depending on the results of this survey certain remedial works may have to
be carried out to ensure correct alignment of the installed items.
These contingency actions are summarised below :

5.1.1 Seabed level high at jacket riser location

If the results of the survey indicate that seabed is high at riser location, provision must
be made for dredging the area local to the spoolpiece installation.
In dredging, sufficient clearance must be provided under the riser flange for the
spoolpiece flange to clear, when pulled in. In addition, depending on the depth to be
removed, dredging may be required along the installed line of the spoolpiece to prevent
hogging of the spoolpiece.

Where the seabed is cleared local to flanges for access purposes, reinstatement is to
be carried out at the completion of the works.

5.1.2 Seabed level low at jacket riser location

If the results of the survey indicate that seabed is low at riser location, provision must be
made for installing sandbags in the area local to the spoolpiece installation to enable the
spoolpiece flange to mate with the riser flange.

5.1.3 Pipeline orientation

If the results of the survey indicate that the orientation of the pipeline is not suitable for
connection of the spoolpiece, provision must be made to correct the position of the pipeline.

In this instance it will be necessary to deploy the H Frame to move the pipeline to an
acceptable position, all in accordance with the “ Pipeline Moving Contingency
Procedure”.

Document No.: AB-D-PR-03007 Page: 16 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

6.0 EQUIPMENT LIST

Description Quantity

Constant tension winch 5Te Capacity 1 No.


Guide Wire (spooled on winch) 5 Te capacity x 400 Lg.
Clump Weight 1 No. x 3 Te Submerged weight
Flange catcher assembly 2 No. for 24” PCF coated pipe
Flange catcher assembly / Guidewire follower 1 No. for 24” PCF coated pipe
Guidewire follower assembly 1 No. for 24” PCF coated pipe
Rigging set for Clump weight 1 No.
Bolt type Anchor Shackle 1 No. x 4.75 Te

Tirfor 2No. x Type T-532


Tirfor line 2No. x 20m to suit Type T-532

Lift Clamps For 24” PCF coated linepipe 6 No.


Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 19200 Lg.
Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 16150 Lg.
Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 20445 Lg.
Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 14709 Lg.
Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 12609 Lg.
Lift sling 38 Dia. IWRC Wire rope w/ 500 Soft eyes 1 No. x 15057 Lg.

Bolt type Anchor Shackle 6 No. x 25 Te


Stud Bolts (Teflon Coated) 80 No Dia 21/2” x 28” Lg
Nuts (Teflon Coated) 160 No. for Dia 21/2” bolts
Washers (Teflon Coated) 160 No. for Dia 21/2” bolts
Gaskets (Oval S/S) 4 No. R78 S/S Type 316
46mm AF Spanner 4 No.

Description Quantity

Document No.: AB-D-PR-03007 Page: 17 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

Welding Spread
Welding Consumables
Cutting Spread
Cutting Consumables
Concrete Saw
FBE Coating Spread
Shrink Wrap Sleeves 12 No. Type KLO-N-610-12VLBL

Bolt Tensioning spread Hold Type


Flange Puller spread Hold Type

Light Sticks

Dredging Spread
Sand Bags
Deployment Net

APPENDICES

Appendix A Company Supplied Drawings

Document No.: AB-D-PR-03007 Page: 18 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

Appendix B SSOL Supplied Drawings

Appendix C Equipment Data Sheets and Procedures

APPENDIX A

Document No.: AB-D-PR-03007 Page: 19 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

Company Supplied Drawings

Drawing Title Drawing Number


Spool Piece Details at Dolphin Platform “A” BG/TRI/DO1/PIP/CN/04/02/404
Overall Field Layout BG/TRI/DO1/PIP/CN/02/01/401

Document No.: AB-D-PR-03007 Page: 20 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

APPENDIX B

SSOL Supplied Drawings

Drawing Title Drawing Number


Dolphin A-Spoolpiece North-Lift Rigging Layout OCE-0184-002-01
Dolphin A-Spoolpiece South-Lift Rigging Layout OCE-0184-002-02
Dolphin A-Spoolpiece North-Lift Elevation from DSV Deck OCE-0184-003-01
Dolphin A-Spoolpiece South-Lift Elevation from DSV Deck OCE-0184-003-01
Spoolpiece Installation Aids-G.A. and Details OCE-0184-022-03
Final Dimensions of Dolphin A Spoolpiece Sketch 03007 /01
Clump Weight - Positioning and orientation Sketch 03007 /02
Riser bracket removal Sketch 03007 /03
Tirfor Rigging Arrangement Sketch 03007 /04
Vessel Positioning during Deployment-Spoolpiece South Sketch 03007 /05
Vessel Positioning during Deployment-Spoolpiece North Sketch 03007 /06

Document No.: AB-D-PR-03007 Page: 21 of


22
Revision Number: 1 Date: August 29, 1996
SubSea Offshore Limited Prepared By: C.Mynott
Title: Dolphin A Spoolpiece- Installation
Approved
Procedure
By: A. Mcwhirter
Project No.: L2368

APPENDIX C

Equipment Data Sheets and Procedures

1. Bolt Tensioning Equipment

2. Flange Pulling Equipment

HOLD

Pending Contract Award

Document No.: AB-D-PR-03007 Page: 22 of


22
Revision Number: 1 Date: August 29, 1996

You might also like