Professional Documents
Culture Documents
Class Note Pkroy
Class Note Pkroy
• Introduction of FOBs
• Inspection & Maintenance of FOBs
• Design, Planning, Construction, fabrication & Quality
control
• RDSO & other Drawings
• Precautions for Launching & De-launching
• Innovations & best practices
• Case studies
1- Introduction of FOBs
Introduction
• Foot over bridges over the Indian Railways are used by
pedestrian traffic to cross the Railway track safely.
• Foot Over Bridges are subjected to the static loads unlike
the railway bridges which are subjected to dynamic loading
also.
• Due to the non critical nature of the structures from the
fatigue considerations, the maintenance of the foot over
bridges is not often done to the desired standards.
• Population of FOBs in Mumbai suburban is 321 (CR-198, WR-
123)
Types of common Railway Foot over Bridges
• At a time only
one person can
climb and
inspect/repair.
•The work is
carried out in
limited traffic and
power block
which results in
slow progress.
•Difficulty in welding
work due to frequent
vibrations of the
ladder.
• Aged staff fear to
work at such
conditions.
• Difficult to ensure
Quality of welding
work.
Bridge Inspection & Repair IMPROVED METHOD
• It provides larger
working area for
inspection and repair.
• More people can
reach at the required
working area.
• More FOBs on same
track can be
inspected/repair at
one block.
Bridge Inspection & Repair ADVANCED METHOD
DEFECTS IN FOUNDATIONS
• Spalling/cracking of concrete
in foundations
• Loose or corroded holding down bolts
• Looseness of nuts of holding down
bolts.
• Accumulation of water and lack of
cleanliness near bed plates/
holding down bolts
CARE TO BE TAKEN DURING INSPECTIONS AND MAINTE
DEFECTS IN COLUMNS
• Verticality of columns.
• Cracks in welding.
• Bends or damage in
secondary members such
as bracing, gussets etc.
• Condition of painting and
extent of corrosion,
especially near the junction
of the truss and column
DEFECTS IN COLUMNS
CARE TO BE TAKEN DURING INSPECTIONS AND
MAINTENANCE
DEFECTS IN STAIRCASE
• Spalling of concrete from
bottom side of stairs.
• Nosing angle and flooring.
DEFECTS IN FLOORING
• Excess wear in wearing coat/ tiles.
• Damage due to wear in floor slab.
CARE TO BE TAKEN DURING INSPECTIONS AND
MAINTENANCE
GENERAL DEFECTS
• OHE protection sheet,
covering sheeting,
covering sheet truss,
hand railing etc.
• Pockets having
drainage problems.
• Damage due to
corrosion in
reinforcement of
floor slab
CARE TO BE TAKEN DURING INSPECTIONS AND MAINT
TOP DIAGONA
MEMBE L MEMBER
R
1
0 2 3 4 5 6 7 8 9
BOTTOM VERTICAL
Detail 'A' MEMBER MEMBER
Diagonal
Vertical
Member
Member
GUSSET
BOOTOM PLATE
MEMBER
CROSS GIRDER
DETAIL AT 'A'
Analysis of truss:
Design standards:
The truss members are designed as per IRS: steel bridge code (SBC).
The members of truss considered as hinged joint for analysis. Although the members
are connected by gusset plate as fixed joint. This assumption not only differ negligible
results but also give more conservative result than actual value.
Camber: The open web steel girders for railway loading are designed with camber to
counteract the secondary stresses. In the case of foot over bridges, camber from these
considerations is not required, but some upward deflection in geometrical shape is
provided to facilitate the drainage in the girders.
Deflection: The ratio of deflection to length of the girder shall not exceed 1/600 in case
of Rly loading bridges where as this ratio relaxed for foot over bridges up to 1/325.
(SBC para 4.17)
Tension members: The ratio of unsupported length to the least radius of gyration shall
not exceed to 250 in case of railway loading bridges where as this ratio relaxed for foot
over bridges up to 300. (SBC para 6.7.3)
Stage wise analysis and observations
Stage I:
Steel floor system (under side) Steel floor system (top view)
Axial force/stress: As per stadd output the comparative distribution of axial force/stress.
The bottom and diagonals are tension members and top and vertical members are compression members.
The stress in top cords and bottom cords is maximum at central panels and
Stress in vertical and diagonals members are maximum at end panels.
Top and bottom members are more critical at centre & diagonals and vertical members are more critical at ends.
Hence during inspection and maintenance more attention is required in these critical members.
The max. deflection is in middle top member is 34.6 mm where as permissible deflection is 77.7 mm.
Stage II-
The truss analyzed by reducing section of bottom cord member and
observed the behavior of truss. we analyze this truss when the one angle
out of two angle ISA 100X100X10 is not in function due to corrosion.
Max. tension Max. stress bottom Max. defle.
Condition bottom cord (kg) cord (kg/mm2) (mm)
Live Load =500kg/m2 38099 20.0 43.353
Live load=0 22065 11.6 25.139
Observations:
The maximum stress in bottom cord is 20 kg/m2 which is higher than
permissible tensile stress (15.4 kg/m2). Hence structure is fail in tensile
stress where as safe in deflection.
The structure is still in function because of factor of safety where the
yield stress is 26 kg/m2.
Stage II- cont.
The structure is safe when there is no live load. Hence one angle can be
open and replaced by closing foot over bridge from users.
This analysis gives realistic stress level of member to decide the
condition of structure and repair methodology. The maintenance
engineer got confidence in opening of joints and providing temporary tie
during repairing of tension member.
The corroded structure life can be increased by replacing RCC
flooring system to steel flooring system by reducing floor dead load.
The bottom angle intact with concrete floor gets more corroded than
other bottom angle. Hence a clear gap between bottom angle and floor
slab shall be plan at design and construction stage.
Stage III- Non destructive test by instrumentation
The truss analyzed for various live load and studied variation in maximum
stresses and deflection.
Observations:
The maximum stress in bottom cord with various Live load plotted on
graph as shown in fig-8.
stress increased constantly with respect to increase in live load.
4
0 100 200 300 400 500 600
Floor Live Load (kg/m2)
Stage III- cont.
The above two observations are very useful for assessing strength of
truss by non destructive test.
• Case-one:
• Severe corrosion in the junction of the truss with the flooring.
• The section reduced the by more than 50 %
• In one of the nodes, the connection of the truss had broken, leading
to sag by almost 100-125 mm in the truss at first node point.
• Inspection:
excessive corrosion was responsible for the sag .
View before repair
0 1 2 3 4 5 6 7 8 9
Flooring
Detail at 'A'
Case-one: cont.
• Rehabilitation Scheme:
• Truss action restored with the use of large size gussets,
covering the corroded parts of the truss members .
• The flooring was dug up, and the new gussets were
provided at all node points.
• There was very less corrosion in the members other
than at the contact with the flooring,
• The repairs done at site, and ignoring the sag,
View after repair
View after repair
Case-two:
A Foot Over Bridge at a Station, bottom members badly corroded
Inspection:
The horizontal flange of the bottom angle of the truss had got
corroded and almost eaten away in a length of 10 m near the middle
of the span.
The reason for the loss was the corrosion due to the water from
the floor of the foot over bridge, and the non painting of the
members due to OHE area.
The load carrying capacity of the truss was suspect due to the severe
loss of section in the bottom flange.
Rehabilitation Scheme:
• The first activity to be done was to splice the corroded angle. The
angle could only be spliced from the underneath but the length of
damage was so long that the effectiveness of the splice was in
doubt. The welding work in the particular condition was even more
suspect.
• However, this did not give adequate confidence. To strengthen the
truss, it was decided to provide extra tension flange area. It was
decided that the area be provided at a level higher than the existing
bottom flange. This took care of the loads, and we had a truss of
slightly lesser overall depth, but a structure that inspired
confidence in its load carrying capacity.
0 1 2 3 4 5 6 7 8 9
26m
OHE OHE
ADDITIONAL
COVER PLATE
2 3 4 5 6 7 8
HORIZONTAL LEG OF ANGLE MISSING DUE
TO ACUTE CORROSSION
VIEW A-A
NEW
NEW ANGLES
ANGLES WELDED
WELDED TO PROVIDE
TO PROVIDE
BOTTOM
BOTTOM FLANGE
FLANGE
AREA
AREA
INTACT
INTACT BOTTOM
BOTTOM
FLANGE
FLANGE ANGLE
ANGLE
CORRODED
CORRODED BOTTOM
BOTTOM
FLANGE
FLANGE ANGLE
ANGLE WITH
WITH MISSING LEG BOTTOM SPLICE PLATE
View after repair
Bridge Rule
• The live load due to pedestrian traffic shall be treated as
uniformly distributed over the footway.
• Live load including Dynamic effect- 4.8 kPa (490 Kg/m²)
• No allowance need be made for dynamic effects.
• Parapet force on Railing-lateral horizontal force and a vertical force of
1.47 kN/m (150 kg/m) applied simultaneously at the top of the railing
or parapet.
• Wind pressure- 0.74 kN/m2 (75 kg/m2)
Design provisions for FOB
Before During
fabrication fabrication After fabrication
Before Fabrication :
• Quality Assurance Plan - prepared and got approved.
• Raw material inspection, Rolling Mark Certificates .
• Lamination, piping, pitting rolling defects and
Straightness of be checked before fabrication.
• Consumables such as, rivets, welding electrodes
and paints etc. are as per standard specification.
• Welding Procedure Specifications need to be approved.
• Welders approval as per Welding Procedure Specification.
During Fabrication :
• Lay out, jigs and fixtures and profile to be checked.
• Welding by qualified welders as per approved WPSS.
• Welding parameters are to be set & checked during
welding.
• Riveting by qualified and skilled personal with approved
work instructions.
After Fabrication :
• Verify rolling Mark number of steel sections used for
fabrication, from Certificate issued by manufacturer.
Check the register maintained by firm.
• Surface defects shall be checked visually.
• Qualify of welds with respect to specified sizes, length
and any visual defects.
• Quality of rivets to be checked visually and with the
help of riveting hammer.
• Dye Penetration Test for Welds
• Leading dimensions i.e. overall length, hole
dimensions, end finishing etc. shall be checked.
Prepare detail measurement sheet.
Connection Details
brication of FOBs girder through other than RDSO approved
(Rly Bds.No. 2017/50/CE-III/BR/FOB dt 18.12.2018)
• Since the FOBs are not subjected to dynamic loads unlike the Railway
Bridges and hence, the stringent conditions of expertise, experience
etc. as required in fabricating Railway Bridge girders, might not be
mandatory for FOB fabrication.
• Accordingly, it has been decided that fabrication of FOBs can be
done through firms other than RDSO approved firms.
• However, to ensure quality of fabrication, QAP has to be prepared in
each case which is to be approved by officer not below rank of JAG.
Staircase
Ramp
RDSO
DRG
of
Ram
p
Escalators
Construction of FOB: Challenges and Best practice
Barricading of site
Cables During Excavation
Protection of cables
Raft concreting
Treamie concreting of columns
SAW welding and DPT test
DPT Testing of Steel welding
Fabrication Yard
4-RDSO & other Drawings
RDSO Drawings
Constraints of RDSO standard Drawings
• Available Only for 3.0m & 6.0m wide FOB
• Applicable only for vertical clearance 6250mm
• Splice connection by using welding
• Foundation details are limited/standard.
• Girder spans are for 2,3 & 4 line crossing on mainland
platform i.e. 19.93, 25.28, and 30.60m only.
• No details for multiple spans.
• More nos. of columns in RDSO drgs restricting space
for passenger movement.
• Welded splice
Sample drawing of a conventional FOB
3D
v
DOUBLE DISCHARGE STAIRCASE
V
LIFTING HOOK
Borivali Deck Layout Plan 350 m x 10.5 m
127
Borivali – Elevated Deck
Deck in Evening
131
Three Link Ways
58
WHAT NEXT ?