Professional Documents
Culture Documents
Saic D 2002
Saic D 2002
00 30-Jun-16
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Schedule Q
Delivered vessel showed no signs of improper handling and no physical
A3 Attachment IV
damage.
Para 7.1
Unless otherwise specified on the data sheet, the minimum projections for
nozzles and manway necks, as measured from the outside surface of the
shell or head to the face of a flange, shall meet the following reqmts:
a) 6 inches for NPS 6 nozzles and smaller.
b) 8 inches for NPS 8 nozzles and larger and manways necks. 32-SAMSS-004,
A7
c) For insulated vessels, projection shall be sufficient to allow Par. 8.1.2
bolting of studs without interference with the insulation.
d) For vessel drain connections and other connections, where a
process stream is likely to be stagnant, the projection shall not
exceed three times the connection nominal diameter.
32-SAMSS-004,
A3 Type of head used is ASME 2:1-Ellipsoidal or ASME Hemispherical. Design
Par. 7.10.2
One piece construction is used for heads of vessels with wall thickness
32-SAMSS-004,
A4 greater than 50 mm, and for heads of vessels in cyclic, hydrogen or lethal Design
Par. 7.10.4
services.
32-SAMSS-004,
A body flange shall be constructed of a single-piece forging. Nozzles shall
A9 Par. 8.1.4 Par. Design
not be less than 2-inch NPS. Only flanged nozzles shall be used.
8.1.5 Par. 8.1.6
Vessels in services other than air and water shall be provided with a 32-SAMSS-004,
A10 Design
minimum 2-inch NPS flanged steam-out connection Par. 8.1.8
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
All manways are circular. The manway covers shall be hinged or provided
32-SAMSS-004,
A12 with handling davits as specified on the data sheet and shown in approved
Par. 8.4.2
drawings.
1/4-inch telltale vent holes drilled and tapped for 1/8-inch NPT shall be
provided in reinforcing pads for welded attachments, including nozzles
and manways, per the following: 1) one hole in a single piece reinforcing
32-SAMSS-004,
A13 pad. 2) where a pad is split, each segment shall have at least one hole.
Par. 13.2.7
Tell tale holes in reinforcing pads for external welded attachments shall be
plugged with grease or other materials adequate for the operating
temperature but not capable of retaining pressure.
All supports and structural attachments (clips) are continuously welded to 32-SAMSS-004,
A14
the vessel. 10.1.4
The anchor bolt holes on the sliding-end saddle are slotted. 32-SAMSS-004,
A18
Par. 10.3.5
Anchor bolts shall straddle vessel centerlines on the north-south, east- 32-SAMSS-004,
A19
west axes. Par. 10.4.2
32-SAMSS-004,
A20 Anchor bolts shall not be less than 19 mm minimum nominal diameter.
Par. 10.4.3
A davit for the lifting of equipment shall be supplied when specified on the 32-SAMSS-004,
A23
data sheet & shall be in accordance with PIP VEFV1100. Par. 11.6
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Support for insulation system shall be according to the data sheet. The 32-SAMSS-004,
A28 Vessel Manufacturer shall supply and install supports required for Par. 11.2.1 & Par.
insulation 11.2.2
The bottom heads of vertical vessels that are externally insulated are
32-SAMSS-004,
A29 provided with 12 mm blank nuts. Blank nuts are welded on edge and
Par. 11.2.3
located on 300 mm square centers.
For Vessels that were insulated, insulations are not damaged and meets
the following:
a) Stainless steel, galvanized steel, or aluminized steel jackets
for insulation systems that require fireproofing
b) Aluminum metal jackets for non-fire hazardous areas within SAES-N-001,
A30
process plant battery limits. Par. 7.7.2
c) Elastomeric coatings used for weatherproofing on plastic foam
and cellular glass when there is no requirement for metal
jackets.
d) Corrugated jacketing shall not be used to cover cold insulation.
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
All metallic protrusions through insulation systems are caulked with a SAES-N-001,
A33
sealant. Par. 7.4.4
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-005, Safety Instruction Sheet (21 March 2010)
2- 32-SAMSS-004 -- Manufacture of Pressure Vessels,(29 June 2015)
3- SAES-W-010 -- Welding Requirements for Pressure Vessels, (15 May 2016)
4- SAES-N-001 -- Basic Criteria, Industrial Insulation, (6 September 2008)
5- SAES-H-001 --Coating Selection and Application Requirements for Industrial Plants and Equipment (5 April 2016)
6- ASME -- Section VIII, Applicable Edition as per Equipment Drawing's Design Data
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: