SPECIAL MEETING
10 August 2019, ABT Office Conference Room
Action
Due Date
Officer
The meeting was called to order at exactly 08:30 AM
1. Review of current status of NO BIA and S-UMMO projects
1.1. NO BIA
Based on the contract, the project is awarded 472 days to complete
the project, which would end by 28th of February 2020. As end of
April 2019, FODC has spent 260 days, which is 55.08% of the
contract time. This means FODC has 212 days (44.92%) left.
Regarding accomplishment percentage, based on the approved
schedule, the target is 67.49%, while the actual accomplishment is
only at 63.83%. The project is delayed by 3.66% which is equivalent
to 14 days. Note that the penalty clause is Php.590,000 per day.
Penalty 590M As of July Accomplishment Delay
28Feb’20 2019
Php.590,000 Days 472 260 55.08% Target 67.49 3.66%
per day %
Bal. 212 44.92% Actual 63.83 14 days
%
ABDM reminded the PMT that they should not depend on the
claim for extension of time, instead work towards meeting the
given deadline.
1.2. S-UMMO
Based on the contract, the project is awarded 365 days to complete
the project, which would end by 21st of January 2020. As end of April
2019, FODC has spent 192 days, which is 52.60% of the contract
time. This means FODC has 173 days (47.40%) left. Regarding
accomplishment percentage, based on the approved schedule, the
target is 51.12%, while the actual accomplishment is only at
46.77%. The project is delayed by 3.72% which is equivalent to 16
days. Note that the penalty clause is Php.619,000 per day.
Penalty 619M As of July Accomplishment Delay
21Jan’20 2019
Php.619,000 Days 365 192 52.60% Target 51.12 3.72%
per day %
Bal. 173 47.40% Actual 46.77 16 days
%
Approved by:
______________________
ABDM