Professional Documents
Culture Documents
Copies to:
1. Sonny Salvacion (DCI)
Meeting Summary MeetingAction
Minutes Due
Item
Officer Date
Action Due
Item Meeting Summary
Officer Date
The meeting was called to order at exactly 01:00 PM
1. Review and confirmation of the previous meeting minutes
1.1. Upon review of the previous meeting minutes, all items were
deemed correct based on the confirmation of all concerned.
4. Scope Management
4.1. Construction Management
4.1.1. CP02A Site Development Update
FODC presented actual project status for the site
development works including highlights and relevant issues
and events. (See Attached Annex “A” FODC Presentation as
of July 5, 2019).
a. Construction Update
10 Jul
09 Jul
a. Design Update
b. Construction Update
See attached Annex “A” (FODC Presentation as of July 5,
2019 pp.9-15) for the accomplishments on erection works.
FODC presented the option for the curved roof termination.
PTG agreed to have FODC to do a mock up for two (2) options
to fulfill the architectural intent for the project. More so, FODC
shall proceed with the construction of the roofing (GL C to I)
per original intent since this is not part of the curved roof.
Roll form equipment expected to be here on site within the
week. FODC informed that they will start roofing works on 15
July 2019 as committed.
See attached Annex “A” (FODC Presentation as of July 5,
2019 pp.7-8,16-18) for the accomplishments on SOG
concreting works and CHB laying.
See attached Annex “A” (FODC Presentation as of July 5,
2019 pp.19-21) for the accomplishments on MEPFS utilities.
FODC to expedite activities which includes hanger and support
installation for MEPF utilities at Utility building and ensure
material resources availability.
OSM/E Delivery Update
DCI informed that fuel storage tank by CUMMINS was
delivered on 08 July 2019, already lifted and positioned to
its containment. CUMMINS committed to complete works
from mounting of the bracket until testing on 20 July 2019.
Also, they have mentioned that generator set ETA on site is
on Friday, 12 July 2019 and asked assistance from FODC
for the clearing of area for access.
NEW BAC informed that ETA on site of the cooling tower is
22 July 2019, to schedule an ocular inspection next week.
112. Quality Management
DCI reminded FODC to close all pending NTC and invite DCI for joint
inspection and transmit the responded document for closing. (Refer to
Annex “B” DCI Presentation pp. 11-14) NTC tabulation is as follows:
13 Jul
Pending COP mentioned above with negative variances will be
submitted by FODC on 13 July 2019.
156.3. DCI advised FODC that contract is subject for amendment to
reflect cost implications of approved change order proposals which is
processed by YLF.
179. Risk Management
179.1. No risk register has been discussed.
Meeting Summary MeetingAction
Minutes Due
Item
Officer Date
19 Jul
DCI informed that SUMO-CP02-SNR-037 (additional toilet facilities) is
for compliance of FODC until next week.
180.2. DCI presented the observations last safety walkthrough – PPE of
workers painting on the perimeter of Tempfacil and provision of
access ladders on scaffolds. (See Attached Annex “B” DCI
Presentation p. 29). FODC to note these items to prevent any
incidents to happen at site.
199. Other matters
199.1. DCI presented a drone video of the entire project site in
coordination with BMB.
The above shall be deemed as an accurate record of the meeting unless written notice to the contrary
is received within three (3) days from receipt of these documents
Prepared by:
JONABEL CUASAY
Construction Project Engineer – M.E.
Meeting Secretary
Noted by:
Meeting Summary MeetingAction
Minutes Due
Item
Officer Date