You are on page 1of 8

Private & Confidential Updated 15/08/2019

Take Stock Meeting No: 28. 26th July 2019. Location: Plot H, GG

Present: Teh Teck Seong (TTS), Leong Tat Fatt (LTF), Lim Kee Yik (LKY), Aloysies Arrokiam
Nathan (AAN), Kevin Ng Seng Lee (NSL), Syerifaizal (SF), Nelson Lee Kim Tan (LKT),
Goh Seng Ong (GSO), Mohamad Nazri (MN), Neo Kian Seng (NKS), Poh Soon Ping
(PSP), Yeo Siang Chuan (YSC), Melissa Nee Kah Yen (NKY), Yusthieles (YUS), Lim Hui
Yan (LHY), Kingsley Chieng Chew Hui (CCH), Foong Choi Wan (FCW), Goh Poi Ann
(GPA), Vernon Wong Kam Fei (VW), Lim Jia Jun (LJJ)
Apologies: Szeto Wai Loong (SWL), Loh Kye Li (LKL), David Kong (DK), Lee Chan Kit (LCK),
Muhammad Afiq (MA), Mohd Sobrie (MSO), Steven Lo (SL), Goh Kong Beng (GKB),
Ng Hon Song (NGS), Yong Kok Lim (YKL)

Matters Arising/Issues Actionee Status/Feedback/Next Steps

1. GE Structure and Business


Unit/5 Year Business Plan

1.1 TTS briefed on status of GBV. Every Info TTS & LTF have prepared a
Business Unit is to come up with a Business Plan
strategy to reach their respective order
book.

1.2 TTS briefed that BU is actively Info


participating in a few outride tenders
which are on final stage and likely to
secure by this year:
1. Hicom Gamuda RSKU Super • Pending issuant of LOA
Structure

1.3 GL Project that have been awarded to Info


GE for 2019:
1. CO4 (KK257) • LOA received
2. Plot H (Gamuda Garden) • LOA received
3. Hicom Gamuda RSKU Sub • LOA received
Structure

1.4 Projects in the pipeline: Info


1. Ikan Emas (Retro group) • Tender closed.
2. Bandar Malaysia • Under negotiation
3. TRX Residence • Tender closing on 20/8
4. TA3 & TA4 – TA Global • Tender closing on 20/10

1
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps


1.5 TTS informed that according to QMM Info Next QMM targeted on 8/8/19
period ending 31/12/18, the following
Project have recorded cost overrun:
i. KJHP
ii. SCM
iii. PB
TTS reminded it is important for every
SPM to have a tight control of cost
spend within the budget. The cost
centre that need attention are:
i. Staff overhead
ii. Plant & Machineries
iii. General Labour
iv. Material wastage

1.6 TTS informed all to be more cautious Info


when selecting subcontractor not
working with GBU before. Study their
respective back ground and
performance of past Projects. GBU
need to have a group of capable and
experience subcontractors to work with
in order to avoid unnecessary work
delay and poor quality of works.

1.7 Build up adequate team to run the All As table below


targeted project. TTS informed that
recruitment of staff is temporary
stopped as KJHP staff are anticipated to
gradually demob by beginning of April
19. Except for staff with certain skill set
that GBV still lacking will be considered
such as SPM, CM and Architecture Head
and supervisor.

Headcount (as of 1st June 2019) To be updated by LTF


Description Required Present Shortfall
Project Manager 10 9 1
Construction Manager 16 14 2
Safety Manager 13 9 4
Other 213 154 59
Total 255 186 69

1.8 C&C to present the payment status of FCW


projects and AF for KJHP and Stonor by
next meeting.

2
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps

2 Develop Our People

2.1 For future staff promotion, SDOC All Committee members: -


discussions have to be carried out. To LTF, LKY, LCK, GPA, GSO, LKT &
form a committee to develop people PSP lead by TTS. All SPM/PM to
under SDOC. The committee will meet assign 2019’s Project and
half yearly to monitor the performance Individual KPI for their staff by
of the candidates and those with 15th June 2019. LKY, PSP and
potential to be discussed. NSL have submitted. NKS & LKT
to submit by 5th July 2019.

2.2 LTF presented the Management All All SPM/PM to nominate staffs
Programme for the Management
Programme

3 Building BU OST

3.1 Tracking of Order Book

Gamuda Building Order Achieved Balance


Venture Book
‘RM billion’
Conventional 0.5 0 0.5

3.2 Project Financial analysis was presented Info To analyse every 3 months.
by FCW FCW to present by next
meeting.

4 KPI Weightage (2019)

4.1 The weightages are as below: - Info Instruction not to participate


Order Book : 70% conventional tender only focus
on IBS Tender.
Earning : 30%
Profit Margin 8%

3
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps

5 DIGITAL WORK
TANSFORMATION

5.1 BIM
Training & Accreditation
1. All BIM staff to attend training AAN M&E – Course is in June and
with MyBIM Centre by CIDB to Oct. RM1,500 per person (has
be accredited by end of 2019 been approved by Dato’ Ubull)
C&S staff to attend.

2. To fully implement BIM on Info Projects with BIM: -


client-initiated projects. 1. SCM2
2. GG (Plot H)
3. C04

All PM/SPM’s to send their


logistic plan to AAN to check
using BIM.

3. Setup BIM team AAN BIM team recruitment in


progress as table below.

Project Require Hired Remaining


Base
BIM Coordinator 1 1 0
Planner 4 3 1
BIM Engineer – C&S 4 4 0
BIM Engineer – Arch 1 1 0
BIM Engineer – M&E 3 3 0
TOTAL 13 12 1
*Hardware & Software purchases will be done concurrently.
5.2 TTS requested Safety Department to MN Completed 3 modules – Plan to
embark on BIM to identify hazards at conduct Practical assignments
site and come out with preventive for project using BIM System:
action. MN to find out how BIM can
assist QSHE 1. Logistic and Safety
Planning Using BIM
Module.
2. Course Module - Online
Navisworks Beginners
3. Course Module -
Navisworks Manage –
Intermediate.

4
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps


5.3 FieldView Info MA presented Fieldview
Implementation Status
(covering Site diary and NCR
closure) of respective projects.

YSC/MA YSC and LHY informed that pre-


discussion is conducted for
setting up Defects
Management Status Tracking
and Update (Before Handover
to Client) in FieldView.
Further discussion will be
carried out for the design of the
Presentation in Tableau.

YSC/MA YSC informed that Panel


Inspection Checklist
(Communication between GE
and GIBS only) is prepared and
ready to be used in Fieldview.
Further discussion with GIBS
team will be conducted for
minor amendment.

5.4 BIM Training Info BIM Team to conduct training


on Fundamentals of BIM and
Basic Revit to Site Operations
Staff on 6th August 2019.

6 QSHE

6.1 QLASSIC Assessment to be conducted SF 1. New propose date for


at RSKU Bandar Kundang QLASSIC Assessment is on
16th August 2019.

6.2 QLASSIC (Info) SF Works Ministry to make


Qlassic certification
mandatory to all upcoming
developments by 2020 as
outlined in the National
Housing Policy 2.0
(NHP2.0).

5
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps


6.3 IBS Joint Treatment QAQC Control SF 1. SOP developed for IBS
Mechanism installation works.

6.4 IBS Installation Accreditation Training MN Next training plan focus to all
by CIDB for GE-BU staffs update until IBS Installer Sub Contractors
June 2019. and GE Staff Target date mid of
Sept (Later will inform by CIDB).
Target 30 participants –
RSKUPB (2), KKC04 (5), IBS
Banting (20) & subcon-ASN (3).

6.5 CIDB start to do enforcements in Info All Sub-contractors under GE


accreditation skill works exp. Site are advisable to attend the
supervisor and other skills work trade. training conducted by CIDB.
Mr. Teh reminded to C&C
Department to looks on this.

SHASSIC assessment by CIDB


for RSKUPB had been
conducted on 20/6/2019-Result
received from CIDB on
5/8/2019 achieved Result 5
Stars (90%).

6.6 GBU standard for setting up project LTF Hand book stating common
standards of practise in BU for
the following:
a. Site Office Building Set up
b. Document
c. Tool & Equipment
d. Construction accessories
e. List of machineries
LTF to setup committee and
arrange for workshop on 28th
August 2019.

6.7 Safety management in IBS Construction Info The briefing will conduct once a
month during SHE Committee
meeting.

1. 1st workshop 18/6


2. 2nd workshop 18/7

6
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps


6.8 FSC (Federal Safety Commissioner) MN FSC Site audit target date on
accreditation audit. Our achievement of Mid of September 2019 at
FSC Accreditation determines RSKU Cyber Valley for 4 days.
GAMUDA’s ability to be awarded with To check on physical site
projects in Australia. compliances and site document
implementation.

Selected RSKU Selangor Cyber Valley to RSKUCV FSC site audit target
be audited. date on 2nd September 2019

6.9 IBS - Installation Requirement. LTF, LKT, NKS LTF, LKT & NKS to prepare write
up on IBS Installation
Requirement for tower
crane/crawler crane.
To present by next meeting.

6.10 IBS - Management of Panels. All LHY informed all PM/SPM’s to


monitor the number of panels
being installed and keep GIBS
inform toward the end of
installation work to check the
balance available stock is
adequate.

6.11 IBS – C&C to include cost for defects NKS NKS to give a write up by 2nd
repair in project budgets and double August 2019
handling.

6.12 IBS – TTS reminded that storage of IBS Info TTS informed that the IBS
panels at site should be clean and neat. storage yard has to register for
safety

6.13 Annual QSHE Management Review SF SF presented the findings of the


Annual QSHE Management
Review

6.14 IOI Quality Standard GPA GPA to arrange for site visit to
study IOI Quality Standard.

7
Private & Confidential Updated 15/08/2019

Matters Arising/Issues Actionee Status/Feedback/Next Steps

7 HR
7.1 Personnel Requisition Form (PRF) All NKY informed that all request
NKY highlighted that HRBP are not for personnel are to be done
aware on the hiring as this only go thru through HRBP and not direct to
the recruitment team. Recruitment.

To submit PRF through GES. Will


nominate the representative if
the SPM/PM unable to raise the
PRF via GES.

7.2 Staff Resignation All NKY highlighted, resignation


shouldn’t be submitted to HR
last minute as HR is unable to
prepare the necessary in time.

7.3 Performance Assessment All NKY reminded that the


Performance Assessment will
begin next month

7.4 NKY mentioned that interns were All To follow the company policies.
requested to work longer hour as well as
work on weekend and line manager
suggested to compensate the intern in
allowance instead of replacement leave.

7.5 NKY informed that there is a staff will be All NKY will talk to the staff before
demobbed by 1 Aug 2019 from PDP SBK. arrange the meet up with LTF.
Suggested to arrange to meet up the TTS emphasized that staff who
staff in person to gauge his suitability. transferred to building unit
should stay longer.

8 Others
8.1 Double Handling of IBS & Skim product NKS NKS to present the cost of
double handling of IBS
elements and skim products for
IBS joints by next meeting.

The next meeting will be on 29th August


2019, 2:00 pm at Cyber Valley.