INSPECTION OF PIPING INSULATION ( CHILLED WATER)

COASTAL
PROJECT : COASTAL GUJARAT POWER LIMITED - 4000MW (800 MW X 5) THERMAL GUJARAT
STERLING & POWER LIMITED
POWER PROJECT, MUNDRA KUTCH
WILSON PVT.
LIMITED DOCUMENT NUMBER:SW-CGPL-HVAC-QCP-11
Report No. : Date:
Drawing no : AREA:
Equip. tag no : QTY:
Description : MRI NO:
Model : RFI No
WITNESS
Item no DESCRIPTION
S&W CGPL
1 Check whether the pipe is cleaned properly before application of primer.

2 Check whether the Hot bituminous primer 0f 85/25 0r 85/40 is applied uniformly

3 Check density of thermocole to be applied.

4 Check covering of thermocole with RP Tissue Paper and finally wrapped with GS
wire netting

5 Check thickness of sand sement plaster covering the thermcole (min. 15 mm)

10

11

12

Remarks : - ACCEPTED
REJECTED
ACCEPTED SUBJECT TO ATTENDING PUNCH LIST

WITNESS S&W CGPL

Signature

Date

Name