CABLE LAYING INSPECTION REPORT

COASTAL GUJARAT
PROJECT : COASTAL GUJARAT POWER LIMITED - 4000 MW POWER LIMITED
STERLING & WILSON (800 MW X 5) THERMAL POWER PROJECT, MUNDRA, KUTCH
PVT. LIMITED DOCUMENT NO: SW-CGPL-HVAC-QCP-22
REPORT NO. : S & W ORDER No.: DATE:

PAGE: 1 OF 1
System No.
System Description
Subsystem No.
DRAWING NO. Area / Location
Cable Trench / Rack /
Tray/ JB/PB No.
Results
Item No. Description
Accepted N/A Rejected
1 Cable trench is as per the spec. and ready for cable laying.
2 Cable tray installation completed and accepted.
3 Inspection of cable type, size and rating.
4 Insulation resistance test before installation completed.
Cable installation method is correct and bending radius is as per
5
specification
Cable pulling tension restricted as recommended by the
6
manufacturer.

7 Cable tag are correct through transits and at each end completed

Cable trays & under ground cable dressing, tagging as per


8
specification.
9 Segregation, spacing and depth are maintained.

10 Road crossing duct sealed and sufficient spare space left in ducts.

11 Cable dressing clamping and tagging has done properly.


12 Cable route markers are installed as per drawing.
Cable tested for insulation resistance and continuity before back
13
filling and after back filling cut ends are sealed.
14 Cables are free from visible damage.

15 Cable trench back filling and tilling are completed as specified.

16 Approved construction material are used.


17 Record resistance of gland body to earth. Maximum 0.1 Ohm
18 Core identification at each end completed
19 Cable chase sand filling completed as specified
All pipe sleeves are properly sealed using fire proof/water proof
20
seal after installation of cables
Note : Attach cable schedule for the routes
Remarks :

EQUIPMENT / SYSTEM MECHANICAL COMPLETION ACCEPTED :