Professional Documents
Culture Documents
Date : 14.03.2024
Revision : R0
SS JT SVG
2. PURPOSE:
The purpose of generating this method statement is to define the procedure step by step to
implement the correct practices for Cable Laying & Termination.
3. ABBREVIATIONS:
Project : NAV2 DC02, NTT, Mumbai
Client : NTT
Contractor : ELECTROMECH INFRAPROJECTS PVT. LTD.
MEP - Mechanical, Electrical & Plumbing
MS - Method Statement
ITP - Inspection & Test Plan
ICL - Installation Checklist
CCL - Commissioning Checklist
4. REFERENCES:
Project Plan
Contract Technical Specifications
Approved Technical Data Sheets
Approved GA drawings
Design Intent Drawings & Approved Shop Drawings
Manufacturer’s Catalogues & Recommendations
7. SAFETY PROCEDURE:
Strictly followed as per the manufacturer’s Health and Safety recommendations for handling
and use of the materials. Ensure all involved personnel shall be aware of the same.
8. OPERATIONAL PROCEDURE:
8.1 Preparation Work
Before the commencement of laying the cables, the following to be carried out:
The Material received from Client shall be stored in designated area of the
Store/storage facility.
Arrangements shall be made to protect the cable drums against effects of weather
and environment.
Material inspection will be carried out to ascertain that no damage has occurred to
the Cables.
In case of any damages common inspection and report will be issued.
Cable shall be tested on cable drums prior to removal and work site with a 1000 V
insulation tester (5KV for MV Cables).The values will be noted for Core to Core and
Armour.
After the test, the end of the cable shall be sealed to prevent the ingress of moisture.
Store material requisition shall be made.
The material shall be transported in their original packing to location.
The cable drums shall be off-loaded at the site locations as identified by the site
engineer.
It shall be ensured that there is no obstruction to movement of vehicles or any
hindrance to works of other companies.
Check that all the allocated cable routes are ready with the cable trenches/trays and
they are free from blockage.
Necessary cable rollers/skids or crowbar shall be kept ready for smooth laying.
Mobile crane or Tower crane shall be arranged along with operator.
Check work area is clean and safe.
METHOD STATEMENT FOR LV & HV CABLE Page 4 of 5
LAYING & TERMINATION
Prior to installation, refer to the approved drawings and specifications related to the
area of installation and ensure that required materials are available at site.