Professional Documents
Culture Documents
PROCEDURE
17/1.0/16.07.14/PCPDOC-238-1411
Laying of High-Voltage Cables
CON TE N T
0 Modifications ........................................................................................................... 3
1 General ................................................................................................................... 4
2 Safety ...................................................................................................................... 4
3 Documentation ........................................................................................................ 4
4 Equipment ............................................................................................................... 5
5 Communication ....................................................................................................... 5
6 Preparation for Cable Laying................................................................................... 5
6.1 Advance Information ............................................................................................... 5
6.2 Position of Cable Drum ........................................................................................... 6
6.3 Pulling Winch and Rope .......................................................................................... 7
6.4 Calibration ............................................................................................................... 7
6.5 Pulling Head and Pulling Stocking .......................................................................... 8
6.6 Cable Pushing Device ............................................................................................. 8
6.7 Preparation of the Cable Route ............................................................................... 8
7 Cable Pulling ........................................................................................................... 9
8 Final Placing of the Cable ..................................................................................... 10
9 Sheath Testing after Cable Laying ........................................................................ 10
10 Summary of Important Points ................................................................................ 11
11 References ............................................................................................................ 11
12 Drawings ............................................................................................................... 11
0 MODIFICATIONS
Rev.
00 first issue (German only)
01 additions and modifications in all sections
1 GENERAL
The purpose of this document is the provision of an overview concerning important
factors to be considered during cable pulling and laying.
The most common method for laying of high-voltage cables is the so-called "nose-
pulling" method. The pulling rope is fixed to the head of the cable. This can be
done at the pulling head which is directly installed on the cable conductor. More
often a pulling stocking is used to which the rope is connected.
The advantage of the pulling stocking is that it can be used again. During cable
pulling care shall be taken that pulling forces and sidewall pressures are kept to a
minimum. This is of special importance in the case of long cable lengths and high
cable weights.
Special laying techniques, for example laying of cables in deep tunnels or the
bond-pulling method, are not covered by this document.
2 SAFETY
Danger to persons and environment must be prevented under all circumstances.
Health and safety regulations must strictly be adhered to. The personnel involved
have to be instructed accordingly and shall dispose of the appropriate certificates.
Additional project-related requirements are to be observed as well. The cable
laying contractor is fully responsible for all activities in this respect. Any works
made in advance by third parties are to be carefully checked before making use of
it. Those are for example switched-off status of equipment, jointing pits, installation
scaffolds and the like.
3 DOCUMENTATION
Proper documentation is of high importance. Position and laying process of each
cable length shall be recorded in a cable laying report which shall comprise as a
minimum:
o name of cable connection and stations
o power cable type
o project or order number
o identification of cable section (location)
o phase identification
o cable identification by drum number or cable code number
o pulling direction
o cable length
o diameter of calibre (if used in pipes)
o date of cable laying
PRC0016_R01_cable_laying_gb.docx ENG0000 R06 08.2012
4 EQUIPMENT
It is essential that the cable laying company uses appropriate and reliable devices
to ensure laying works without problems and to avoid damage to personnel, to
cables or to equipment. Defective tools and equipment are to be replaced
immediately. The equipment to be employed has to be checked according to
relevant rules (VDE, TÜV ...). Labels on the equipment shall indicate the
compliance.
5 COMMUNICATION
During cable laying good communication is important. Usually this is done by radio
(walkie talkie). Communication facilities shall be used at all important locations.
These include the person at the drum, at the winch, at the cable head as well as at
other important places, e.g. road crossing, vertical section or the like. The laying
company has to provide a communication device to the Site Manager of nkt cables
in order to keep him informed during all stages of the cable pulling process.
made according to IEC 60229 with 10 kV DC for 1 minute. The cable ends must
be accessible for carrying out the test.
Before pulling the cable, it is to be checked and ensured that the cable ends are
properly sealed. Accordingly, the cable ends are always to be closed again when
the cable is cut, for example by using heat-shrinkable caps. The caps must have
glue inside to prevent ingress of water into the cable.
6.4 Calibration
In the case of pulling cables into protection pipes, the complete pipeline is to be
calibrated after backfilling and compaction of the ground. This is to ensure that
there are no obstructions, for example deformed pipes, which will cause problems
during pulling of the cables. The diameter of the calibre shall be such that
constrictions and damages are likely to be detected. The diameter of the calibre
shall be at least 85 % of the inner diameter of the pipe.
Furthermore, it shall be possible to blow auxiliary ropes into the pipe sections.
Pollution and debris must be removed by using appropriate brushes.
Usually a pulling head (Figure 1) is already installed in the factory. Before start of
cable pulling tightness of the pulling head is to be checked. In case of damages, a
newly installed pulling head may be required. The installation is to be done in
accordance with the installation instructions provided by nkt cables.
Pipes through which the cables shall be pulled must be clean and smooth and free
from any obstacles. The ends of the pipes shall be free over a distance of 50 cm.
This is to prevent ingress of stones and ground material which can block the cable
or damage its oversheath. On top of that the free end is advantageous for sealing
of the pipe.
The proper quality of the pipes must have been demonstrated by the installer
before cable laying. To protect the pipe it is recommended to install a bell mouth at
the pipe's entry and exit. An example is shown on drawing EHP 0784/2.
The pulling rope shall be guided in such a way that damage to the pipe is
prevented. The pulling rope shall be lubricated every time before use.
Cable lubricants can be used to reduce friction. The lubricant is evenly applied to
the cable sheath during pulling. A suitable lubricant is water soluble and
environmentally compatible.
When the cable is laid in an open trench sufficient numbers of cable rollers and
corner rollers shall be provided for guiding the cable along the route. For straight
sections normal cable rollers, e.g. according to drawing EHP 9704a, shall be used.
They are placed at intervals of maximum 3 m. For heavy cables the spacing may
be reduced to keep the friction load component lower.
For bends angle rollers (corner rollers) similar to what is shown on drawing
EHP 9690a are needed. Especially at the bends the rollers are to be securely
fixed, so they can withstand the pulling forces. Details of fixing and positioning of
rollers is to be decided on site to take into consideration the actual conditions
found there. For preparation of a bend several rollers are connected as shown on
drawing EHP 9690a. Care has to be taken that the rollers are evenly distributed
and that the cable is not overbent at the edges.
The minimum permissible bending radii of the cable shall be observed. The
minimum value should be considered as an exception and the bends shall be
made with the largest radius possible.
For exact guidance of cables during pulling, e.g. at the entrance in building or into
a pipe, guide rollers (drg. EHP 8636/2a) are used. One roller is removable so that
the cable can be taken out after pulling.
The roller close to the drum must be extra wide. This is because the cable is
wound over the width of the drum and its position will change during pulling
accordingly. This special roller is about 1.5 m wide. A construction with two rollers
is shown on drawing EHP 8637/2a.
7 CABLE PULLING
High-voltage cables must have a sufficiently high temperature before cable laying
to ensure the required flexibility. When the cable temperature is lower than the
minimum permissible value, the cable must be heated before laying. The minimum
permissible temperature depends on the cable type. Heating can be done by
keeping the complete cable drum warm under a tarpaulin using appropriate heater
or by storing the drum indoors. Under such circumstances the cable must be laid
as soon as possible to avoid undue cooling of the cable.
When pulling starts it shall be checked whether the pulling rope will have contact
with adjacent objects and may cause damage to them. If necessary, additional
guiding rollers shall be installed.
The minimum temperatures for cable laying are:
o -5°C for XLPE cables with PVC sheath
o -20°C for XLPE cables with PE sheath
A breaking device must be available at the cable drum to avoid over-running which
means that the drum must never run faster than the cable is being pulled out.
The cable should preferably be pulled continuously into its final position. Stop and
re-start results in higher stresses. A cable length should be pulled preferably
without interruption.
11 REFERENCES
BAE008 Handling of Cable Drums
IEC 60229 Tests on cable oversheaths which have a special protective
function and are applied by extrusion
12 DRAWINGS
EHP 9695a Cable Drum Hydraulic Jacks
EHP 9697a Capstan Winch for Cable Pulling
EHP 8616/2b Cable Pulling Grip with Swivel
EHP 9704a Cable Roller
EHP 9690a Cable Angle Roller
EHP 8636/2a Cable Guide Roller
EHP 8637/2a Cable Run-out Roller
EHP 0784/2 Lead-In Tube for Conduits
Kabel-Spillwinde
Capstan Winch for Cable Pulling
Maßst./Scale :
EHP 9697a
with Swivel
Cable Pulling Grips Maßst./Scale :
Ah
Hk
Hü
Für diese Zeichnung behalten wir uns alle Rechte vor. All rights reserved.
A4H3DE1 09.2002 Zeichnung wird bei Änderungen nicht eingezogen. Drawing will not be recalled in case of revisions.
Cable Rollers
Kabel-Verlegerolle Maßst./Scale :
Hk
Hk
Hü
Für diese Zeichnung behalten wir uns alle Rechte vor. All rights reserved.
A4H3DE1 09.2002 Zeichnung wird bei Änderungen nicht eingezogen. Drawing will not be recalled in case of revisions.
Kabel-Eckrollen
Cable Angle Rollers
Maßst./Scale :
EHP 9690a
Ah
Hk
Hü
Für diese Zeichnung behalten wir uns alle Rechte vor. All rights reserved.
A4H3DE1 09.2002 Zeichnung wird bei Änderungen nicht eingezogen. Drawing will not be recalled in case of revisions.
Ah
Hk
Hü
Für diese Zeichnung behalten wir uns alle Rechte vor. All rights reserved.
A4H3DE1 09.2002 Zeichnung wird bei Änderungen nicht eingezogen. Drawing will not be recalled in case of revisions.
Gepr./Check. : 01.03.05
Gez. / Drawn : 01.03.05
EHP 0784/2
Hk
Hü