Professional Documents
Culture Documents
Insert OHL name here from annex “D” Insert Circuit name here
from annex “D”
Client : TRANSCO
Contractor : Inabensa SA
1
ABENGOA
Table of contents
S. No CONTENTS
1 Objective
2 Scope
6 Reference documents
8 Resources
9 Responsibilities
10 Detail Procedure
12 Control measures
13 Emergency Instructions
Annex ‘A’ Risk assessment and control measures
List and circuit details of towers for replacement of Single Suspension strings
Annex ‘B’
to Double Suspension strings.
Annex ‘C” Tool box format
2
ABENGOA
1. Objective:
This Method statement establishes the procedure to replace the single Suspension strings
with Double suspension strings on existing Towers, crossing the highways/roads as pre-
determined by TRANSCO.
The procedure covers all the activities involved in replacing the Insulator strings from
dismantling the Single Suspension string, ground assembly of the new Double suspension
string to lifting of the strings in a safe manner by taking shutdown on each OHL circuit for
a limited time period.
2. Scope:
Scope of work for this method statement is replacing the single suspension strings with
new Double suspension strings complete including all the necessary fittings and Insulators
on the existing 400 and 220 kV OHLs in Western region, Abu Dhabi and Northern Emirates
region.
The names of the OHL and its corresponding Towers and circuits is mentioned in the
annexure ‘B”.
Scope involves:
1. Dismantling the existing single suspension strings complete from the Twin/Quad
bundled conductors and lowering to the ground.
2. Packing the old single suspension strings (insulators and fittings) in boxes and
transporting back to INABENSA/TRANSCO store.
3. Inspection of the existing hinge attachment bracket on cross arm with respect to
width, diameter of hole, bolt size and length of the bolt.
4. Transporting to site and assembling new Double suspension strings with new
Insulators and fittings.
5. Lifting of assembled double suspension string upto the cross-arm level to connect
with hinge
6. Clamping in position the conductors with suspension clamps, armor rods and
complete fittings.
This document gives due consideration to Inabensa HSE requirements and TRANSCO HSE
System safety rules with the objective to follow the good HSE practice to perform this
works safely without any incidences at site.
3
ABENGOA
The overall project activities are scheduled to commence from 24.11.2019 and expected
completion by 14.04.2020 as cited in the shutdown schedule included under annexure
“D”.
The tentative starting and finishing dates for each circuit is indicated in the Shutdown
schedule but exact date for receiving the outage and commencement of works is
dependent on the document approval process and approval of the PTW by TRANSCO/
LDC.
Competent person: {Insert the competent person name with mobile number}
Type of Permit: Permit to work
Any change in the outage schedule will be brought to the notice of TRANSCO.
CICPA passes /GHQ approval to be obtained for personnel, machinery and equipment’s
before attending to the towers falling under CICPA and Military zones.
CP-Competent Person
PTW-Permit to work
PM-Project Manager
CM-construction Manager
PPE- Personal protective equipment
HSE- Health, Safety & Environment
Ckt- Circuit
4
ABENGOA
Portable Earth: To discharge the induced voltage from OHL. The Portable Earth
must be minimum 95 Sq.mm Copper conductors and applied both sides of
working Area.
6. Reference Documents:
As this activity is limited to the individual tower locations within TRANSCO network, no
other inter phase points are envisaged. However, care shall be taken to identify if
any new modifications are carried out by TRANSCO on existing old lines by close
coordination with TRANSCO O&M Engineers. Further as the insulator replacement work
involves OHLs networks interconnected to different substations in northern Emirates,
TRANSCO will ensure the coordination with other utilities while issuing the permit to
work. Necessary safety documents are to be obtained from CICPA, GHQ, other
agencies while trespassing the OHL route.
8. Resources:
Project Manager 1
Construction Manager 1
Site Engineer/competent person 1
Supervisor 2
Storekeeper 1
6
ABENGOA
9. Responsibilities:
• Project Manager: Overall control and management of all activities at Project level.
Distribution of resources & finance, Review and implement procedure for meeting
statutory and quality requirements. Co-ordination with construction team and
client, consultants, sub-contractors, local statutory bodies and shall have the final
responsibility on HSE.
• Site Engineer: for ensuring all the activities are undertaken and implemented as per
the drawings, coordinates for necessary work permits, all approved QC
requirements are met by the construction team and ensure that all necessary
resources are available to meet the schedule targets. Reporting to the construction
manager.
• Competent person: To receive and clear the necessary safety document from
TRANSCO. The competent person must be present at the working area full time.
Reporting the progress of work to the Authorized person. To ensure proper
barricading of the safe working area and implement the safety precautions laid
down by TRANSCO systems safety rules and the safety document.
• Storekeeper: To control the receipt and dispatch of materials in and out of store,
coordination with the transportation of materials from store to site and record
keeping of all returnable dismantled line materials to store. Arranging the material
dispatches according to the request from the site crew.
10.1 General
• Before starting the activity, the towers where Suspension string has to be
replaced shall be identified.
• Slings , pull lifts and ropes attached to the towers shall be covered with
heavy duty flexible plastic pipes or gunny sacks to avoid damage to the
galvanized/painted tower parts.
• All equipment and hardware fittings shall be transported from store to the
work site and stacked with proper care.
• As Polymer new insulators are used in the line, care shall be taken while
hoisting the insulators and during overall operations. Technicians will use
clipping ladders for reaching the conductor position on suspension
insulator strings. Utmost care shall be taken so that no metal part will rub
the insulator sheds. The insulator shall be placed on plastic/canvas sheets
while assembling the hardware fittings on the ground. Before hoisting,
the Insulator shall be cleaned with cotton cloth for removing dust/foreign
particles deposited.
• After availing outage on an existing OHL ckt, which will be availed one
circuit outage at a time as listed in the shutdown schedule, live circuit will
be demarcated with Red flag and warning tape at ground level.
• All works shall be carried out under strict supervision of site Engineer
/Supervisor in coordination with competent person. The Competent
person will be in the site full time and supervise all activities.
• If there is provision to drill hole on the existing bracket and if the size is
suitable to accommodate the proposed new hinge, then hole will be
drilled to accommodate the second hinge bolt maintaining the correct
spacing between the suspension insulators as shown in the drawings.
8
ABENGOA
• If the existing hinge attachment bracket is not suitable for the proposed
type of double suspension string, then a new bracket will be studied and
fabricated in workshop to match its fitting on the existing cross arm
members.
• Incase no modification is required then the works will continue following
the below procedure which is also applicable to towers with correct
double suspension string attachment provision.
10.2 Removing and lowering down the existing Single Suspension String
• After receipt of the PTW from TRANSCO and once the portable earths are
installed on the phase conductors, 3 to 4 Technicians will climb the tower
using the life line and double hook lanyards. Another 4 technicians will
remain at the ground. A vehicle will be available on standby at the tower
location.
• Raise the rope ladders to the cross-arm Level with the help of P.P. rope. All
required tools will be lifted with use of Single sheave pulley using PP rope
handled by technicians on the ground.
• Fix the Ladder on the cross arm and 2 Technicians will reach to the
conductor level with the help of ladder to enable releasing of the
conductors from the suspensions clamps.
• Fix the clipping fixture (nylon endless round rope and yoke plate) on the
conductor and attach the one end of 6-Ton Pull lift to cross arm with the
help of 1 m. wire rope slings and D-Shackles. Other end of the Pull lift will
be connected to clipping fixture. 2 sets of clipping fixture and 6T pull lift
will be used to suspend the phase conductors on either side of the
insulator string.
• A single sleeve pulley shall be attached to the cross arm of the tower and
a 20 mm dia P.P rope shall be passed through the same. Fasten the yoke
plate and top end cap of the Insulator with the PP rope which will pass
through the single sheave pulley on the cross arm and the other end of
the PP rope will be passed through another sheave pulley attached at pile
cap level. The rope will be firmly held by technicians on the ground.
• Lift the conductors upward by tightening the 6T pull lift in order to free
the conductor load from the insulator string. After tightening the chain
pulley, the insulator string will become loose.
9
ABENGOA
• After ensuring the insulator string is gripped firmly by the PP rope, the
technicians will then open the bottom suspension clamp to release it from
the conductors and the unbolt the hinge connection from the tower cross
arm, transferring the entire weight of the insulator string on the PP rope.
• By releasing the P.P. rope slowly, the insulator string will be lowered to the
ground and the dismantled insulator and the HW fittings will be stored in
wooden boxes and transported back to Inabensa store for later handing
over to TRANSCO store.
• The new Double suspension string will be kept completely assembled and ready
on the ground as per the approved drawings.
• By using the same rope pulley arrangement and with the PP rope fasten to the
top yoke plate, the new double suspension string will be lifted to the cross-arm
level to attach the hinge.
• Armor rod will be placed around the conductor and the suspension
clamps will be fasten over the armor rod ensuring verticality of the
insulator.
• Lower the conductors downwards by releasing the load from the 6T pull
lift to transfer the load of the conductor on to the double suspension
Insulator string.
10
ABENGOA
• All site crew shall be provided with safety helmets, hand gloves & safety
shoes and Linesmen who will work on the towers shall be provided with
double hook safety lanyards.
• Great care shall be taken for anchoring the machines & temporary
anchoring of conductor.
• Pulling and lifting devices shall be well maintained in order to keep the
tools & plants site worthy.
12. Control Measures: Refer Task Based Risk assessment – Annexure -1.
• Usage of Hot sticks and Insulated Gloves (33kV Rating) during applying
and removal of Portable Earths.
11
ABENGOA
If you notice an emergency (accident, fire or incident), proceed in the following manner:
• Verbally inform others still in the area.
• Give the alarm signal calling the Head of Emergencies.
• If you have contacted the Head of Emergencies, follow his/her instructions.
• If you have not contacted the Head of Emergencies, inform the appropriate emergency
service.
Never put yourself at risk of bodily harm. If there is such a risk, evacuate the area and
gather at the Meeting Point, which will be located near the scene of the emergency in a
danger-free zone.
Alarm and Evacuation Team Robiano Diaz Tel: +971 5062 14551
12
ABENGOA
Emergency Services
Centre Telephone Centre Telephone
When calling the emergency number, please remember to state your name, the nature of the
accident, address of the emergency and how serious the situation is. And remember to provide
them the telephone number you are calling from. Remain calm and provide the paramedics with
clear information so they can supply the necessary help.
13
HAZARD IDENTIFICATION
RISK ASSESSMENT AND RISK CONTROL MEASURES
PROJECT NO.: N-16418
SEVERITY (S) PROBABILITY (P) LEGEND RISK MATRIX
1 Negligible {P -Slight Injury or Health Effects} {A-Slight Damage} A - IMPROBABLE High Risk: Unacceptable high
{E-Slight Effect} {R-SlightImpact} Action must be taken immediately to towe the risk P R O B A B I L I T Y
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Workers
Project mobilization at
Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
the site
R.E R.L Residue R.R
S/No. Activity Hazard Cause of Hazard Consequences and Impacts Recommended Controls Measures Acceptable?
S P H/M/L S P RL
1. Proper housekeeping.
2. Put area demarcation and barricades and warning signs
1. Minor body injury 3. Ensure suitable PPE footwear is worn, warn of risks by
2. Major body injury due to using.
Mobilization of Un-even Ground Slip, Trip and Fall on Level fall in level ground & hit 4. Place equipment to avoid cables crossing pedestrian
3 3 C M 1 A L YES
workers Level Ground hard object. routes and use cable guards to cover cables where
3. Fatality due to fall on required.
sharp object
HAZARD IDENTIFICATION
RISK ASSESSMENT AND RISK CONTROL MEASURES
PROJECT NO.: N-16418
SEVERITY (S) PROBABILITY (P) LEGEND RISK MATRIX
1 Negligible {P -Slight Injury or Health Effects} {A-Slight Damage} A - IMPROBABLE High Risk: Unacceptable high
{E-Slight Effect} {R-SlightImpact} Action must be taken immediately to towe the risk P R O B A B I L I T Y
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
S E V E R I T Y
2 Marginal {P-Minor Injury or Health Effects} {A-Minor damage} B - REMOTE Medium Risk: Acceptable but must be managed at ALARP A B C D E
{E-Minor effect} {R-Minor Impact} Low Risk: Acceptable without further action 5 HIGH RISK
3 Critical {P-Major Injury or Health Effects}{A-Local Damages} C - OCCASSIONAL ALARP As Low As Reasonable Practicable 4
{E-Localised Effect}{R-Considerable Impact} R.L Risk Level 3 MEDIUM RISK
4 Severe {P-Single Fatality or Permanent total disability} D - PROBABLE R.E Risk Evaluation 2 (ALARP)
{A-Major Damage} {E-Major Effect}{R-National Impact} R.R Risk Rating 1 LOW RISK
5 Catastrophic {P-Multiple Fatalities or Permanent Local Dissabilities} E - FREQUENT Assessor: Ericson Reviewed by: P - People E- Environment
{A- Extensive Damage}{E-Massive Effects}{R -International Impact} Date of Assessment: 14/10/2019 Due for Review: A - Assets R - Reputation
Project Activity: Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD, WR, NE Regions
14
ABENGOA
15
INABENSA Tool Box Record Page 1 of 3
1. General Data
Project: N16418
Ref. HS Plan/MS&RA
Work to be carried
Location:
2. Theoretical content
3. Speakers/Competent Person:
-
-
4. Evaluation certification
The workers whose names are listed have successfully attended this specific training activity, they
have understood hazards and precautions related on the activities to be carried-out.
FORMG-211-09.00.E00 POG-211-02
INABENSA Tool Box Record Page 2 of 3
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Emirates ID:
Completion of form:
Upon issuance of the registry sheets for the training activity to the attendees, they shall be instructed to clearly and legibly complete the boxes in their
entirety, indicating the company to which they belong, the division and department, both last names and first name (in that order), signature and VAT ID
FORMG-211-09.00.E00 POG-211-02
INABENSA Tool Box Record Page 3 of 3
Important
Mandatory PPEs and other HSE requirements to be provided and to be
followed prior and during the to work.
1. Full body harness with double lanyards and shock absorber, with valid 3rd party
certificates. It should be 100 percent tie-off while working on heights everytime.
2. 2 Lifelines to be installed on each tower having a working at height activity, for
the safe ascending and descending of workers on the tower, with valid third party
certificates.
3. Each workers must be having rope-grab with valid third party certificates.
4. Rescue kits must be provided in each working at heights activity (this is very
important, our client Transco is very strict on this), with valid third party
certificates.
5. First Aider must be available on site along with first aid box with valid contents.
6. Fire warden must be available at site along with DCP fire extinguisher at least
6kg.
7. Stand-by vehicle must be on site always during the execution of work and the
seating capacity of it must be equal/ appropriate to the number of workers.
8. Tool Box talks must be conducted by the competent person on a daily basis, with
specific topics related to the activities (workers must be aware and understand
all the precautions against all the hazards indicated/written in approved RA and
PTW.)
9. Appropriate Signages to be installed in each work places as an administrative
control.
10. Bottom of the tower must be barricaded no person is allow to stand/ cross on the
barricaded area. (it must be discussed to all workers through PPEs.
11. Follow safety clearance, work only on the area which is allowed written on the
permit.
12. Follow Transco SSR.
13. All the safety requirements needed e.g. documents and materials written on this RA must be
followed and must be provided prior to start the work. To avoid any unwanted events that may
hinder us towards the completions of the project.
FORMG-211-09.00.E00 POG-211-02
ABENGOA
16
INABENSA SHUTDOWN SCHEDULE TRANSCO O
Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD , WR , NE Regions
1 of 2
INABENSA SHUTDOWN SCHEDULE TRANSCO O
Replacement of single Suspension String Composite Insulators by New Double string composite suspension insulators on Road Crossing Towers at Coastal Area at AD , WR , NE Regions
2 of 2