Professional Documents
Culture Documents
- Upon completion of cadastral survey acopy of the public notice compliance before the final lot survey shall be
forwarded to the
Sangunian Barangay
- Land surveys affecting barangay road in a certain municipality, a notice and consultation be made on the
widths and center line of the office of
Court
- No cadastral lot pending registration shall be amended or subdivided by geodetic engineer without order from
the
RA 7160
- Provincial boundaries disputes shall be settled in accordance with procedures in Local Government Code
1/20,000
- New survey technology, the Primary Control relative error shall not be greater
1/10,000
- Secondary Control relative error using new survey technology shall not be greater
1/5,000
- Tertiary Control relative error using new survey technology shall not be greater
5 cm per km
- Primary control linear error using new survey technology, shall not exceed
10 cm per km
- Secondary control linear error using new survey technology, shall not exceed
20 cm per km
- Tertiary control linear error using new survey technology shall not exceed.
2 traverse if no mention
Question: standard accuracy for Primary control the number of observation position with one second theodolite.
1 traverse if no mention
Question: Standard Accuracy for secondary control the number of observation position with 1 second
theodolite is
5 cm per km
Question: Standard accuracy for primary traverse using conventional instruments, the lines error of closure not
to exceed
10 cm per km
Question: Standard accuracy for secondary traverse using conventional instruments, the lines error of closure
not to exceed
20 cm per km
Question: Standard accuracy for Tertiary Traverse using conventional instrument, the linear error of closure not
to exceed
1"
Question: Standard Accuracy for conventional instruments in surveying. The azimuth reading for the Primary
traverse is
10" to 15"
Question: Standard Accuracy for conventional surveying instruments. The azimuth reading for Secondary
traverse is
30" to 1 minute
Question: Standard Accuracy for conventional surveying instruments. The azimuth reading for tertiary is
1"
Question: Standard accuracy for conventional surveying instruments. In Primary traverse the theodolite least
reading is
1"
Question: Standard accuracy for conventional surveying instruments. In Secondary traverse, the theodolite least
reading is
1 minute
Question: Standard accuracy for conventional surveying instruments. In tertiary transverse, the engineers'
transit least reading is
20" to 30"
Standard accuracy for conventional surveying instruments. In primary traverse, the engineers' transit least
reading
20" to 30"
Standard accuracy for conventional surveying instruments. In secondary traverse, the engineers' transit least
reading is
8 or 4
Standard accuracy for conventional surveying instruments. In astronomical observation if primary traverse, the
number of series in the morning is
4
Standard accuracy for conventional surveying instruments. In astronomical observation of primary traverse, the
number of series in the evening is
LMS
- In delimitation of reservations parks and other protected areas processed data and other survey returns shall be
submitted for verification and approval of the plan to the
LMS
- in delimitation survey of the forest reserves area done by the authorized private geodetic engineers, processed
data and other survey returns shall be submitted verification and approval
to
Is order by Regional Executive Director and Regional Technical Director for Lands until final approval of the
survey returns
- The survey of cadastral project shall be considered as in progress from the data the survey
12 months
- In mineral land survey authority or order issued valid for
30-day notice
- After completion of notification of lot claimants, a public notice shall be posted conspicuous places in the
locality and municipality building known as
60 days
-From the date of issuance of Cadastral project survey order, geodetic engineers shall submit a list of their
survey in progress inside the project to the Chief of Cadastral project
within
1 to 999
- The corners of public Land Subdivision lots shall be marked standard concrete monuments engraved on the
top by a letter in alphabetical order starting from "A" followed by number
from
Four months
- Isolated surveys within the cadastral project must be submitted to the Land Management Sector for
verification through the Chief of Cadastral project within
Need to be accounted
- Tertiary for each cadastral project shall be numbered consecutively. Numbers 1 to 1000 be assigned to one
geodetic engineer for his use; 1001-2000 to a second; 2001-3000 to be a
third and so forth. The unused numbers
Duplicate card
- During the lot survey, for completion of the sketch and survey card, the geodetic engineer shall carry the
3 Copies
- The survey claimant shall be shall be furnished by the geodetic engineer concerned the approved narrative
technical description of at least
Above it
- Field notes containing erasures of field data shall not be accepted. If erroneous data have been entered, shall
be crossed out with pencil line and the correct data be written
Municipalities
- Sketch plan on political boundary dispute shall be prepared for settlement. A heavy full lines base on tax
declaration, shall be represent the division between
1Barangay
- After lot sketching, the project shall be divided into cadastral cases in which one case shall be composed of
Intervisible
- in other survey, forest delimitation, when such boundary lines past through mountains or hills or rolling areas,
the intervals between consecutive monuments shall be
Uniformly
- In primary control traverse, the angular error azimuth closure shall be distributed among the angles between
the azimuth line
Space uniformly
- Where the ground slope is uniform, the contour lines are
Horizontal Control
- generally, in the topographic survey the first step is to establish
As a Separate lot
- portion of patented, leased, or decreed which form part of river, estero, arroyo, creek during cadastral project
shall be surveyed
As a separate lot
- portion of previous surveys not patented leased or decreed which form part of river, estero, arroyo or creek
during cadastral project shall be survey and
Separate lot
- When a claimant insist upon her rights to be taken by a road of way the area shall be surveyed with other
portion of the claim as
As separate lot
- when advance claimants do not design a surveys of the claim undergoing survey shall be indicated the plan
and surveyed
As separate lot
- When the applications of the property undergoing survey does nor accept the corner of previous survey
untitled as common to his property, the boundary line as pointed to by
hint be monumented and surveyed and the conflict area shall be indicated
in the latter, the survey shall
Be only one
- Due to limited funding cadastral survey of the municipality may be awarded by cadastral case, cadastral
survey number for a certain municipality.
Hard pencil or Permanent Waterproof ink
-All survey field data shall be recorded in the field notes by the geodetic engineer or his authorized assistant
and be written clearly.
Geodetic Surveying
- Involve large areas and take into account the earth's curvature.
Plane Surveying
- Cover limited areas and earth curvature neglected
Erecting eyepiece
- Consist of four plano-convex lenses placed in eyepiece slide
Inverting eyepiece
- Composed of two plano-convex lenses placed in eyepiece slide
Topographic survey
- Determining the shape of the surface of the ground and the location of natural and artificial features on it.
Pantograph
- A device use to enlarge or reduce the scale.
Profile Leveling
- The elevation of the ground surface along a definite line desired.
Began prior to the date of the order for the cadastral project
-After 30days from the date of order for survey of cadastral project, no other survey shall be undertaken within
the project except when the isolated land survey.
Cadastral Case
- Boundary Dispute between municipalities not settled before the completion of the field work of the cadastral
project shall be surveyed and be treated as separate.
By inspection method
- it is an interpolation method of contour line which is mentally traced by moving clockwise observing that it
will join only all points of same elevation until it closes upon itself.
Grid azimuth
- Astronomical observation for azimuth in the lines of the man control of cadastral project, other than live
BLLMN to 2, shall be used to check on the carried.
Grid Azimuth
- The azimuth in cadastral project is known as;
Numerical file
- The sketch and survey card shall be duplicate and the duplicate card shall be placed in the
Alphabetical file
- the sketch and survey record card shall, after completion the place in the
Segregation survey
- It is a kind of survey for the purpose of segregating twenty percent or less of area of previously surveyed large
tract of public land.
Resurveys
- It is a survey of a previously surveyed tract of land for the purpose of voiding the original approved but
undecreed survey due to failure to include all the areas claimed by the
applicants.
Resurvey
- During cadastral lot survey, titled and leased properties with technical descriptions do not form closed
polygon shall be subject to
Resurvey
- During cadastral lot survey, titled and leased properties without technical descriptions from magnetic surveys
shall be subject to
Relocation survey
- It is a survey made of reestablishment of corners or boundary lines using the bearing distance, and area stated
in the previously approved plan or written in the lease or Torrens title.
Relocation survey
- Geodetic Engineers who are commissioned by the owner /developers on a property to be developed into
housing subdivision project, he shall first conduct in the area of