Professional Documents
Culture Documents
Training Crawler Exc 7 (A)
Training Crawler Exc 7 (A)
R110LC-7(-A) R140LC-7(-A)
R160LC-7(-A) R180LC-7(-A)
R210LC-7(-A) R250LC-7(-A)
R290LC-7(-A) R320LC-7(-A)
R360LC-7(-A) R450LC-7(-A)
R500LC-7(-A)
R800LC-7A
REMARK
All technical explanation in following chapters are also applicable
for the “A” models excavators, unless explicitly mentioned.
The “A” models excavators are equiped with TIER III engines, which
are listed on previous page.
C page 3
2. GENERAL SYSTEM
CLUSTER
TRAVEL
LEVERS &
PEDALS
JOYSTICKS
BOOM CYLINDERS
PUMP ASSEMBLY MAIN CONTROL VALVE (= MCV)
ARM CYLINDER
BUCKET CYLINDER
SWING MOTOR
TRAVEL MOTORS
C page 4
3. MAIN PUMP ASSEMBLY
3.1 STRUCTURE
REG 1
M REG 2
F2=NEG CONTROL
EPPR Pressure
EPPR Valve
35 bar
P1 P2 Pilot Pump
C page 5
3.2 SECTIONAL VIEW
REGULATOR REGULATOR
max
C page 6
3.3 PUMP REGULATING SYSTEM
C page 7
Regulating Circuit 3B
1.5B
(11~36ton exc)
FOOT RELIEF FOOT RELIEF
VALVE 1 VALVE 2 air breather
(0.5/0.3B)
1.5B
F1=NEG CONTROL SIGNAL 1.5B
35
bar Power Boost PUMP POWER
Solenoid
Max flow Max flow SETTING
Cut off Cut off 0...35 bar
C page 8
3.4 REGULATOR: “FLOW” CONTROL SYSTEM
When operating the excavator equipment, the negative control pressure Fi inside
regulator 1 or 2, drops, which results in displacement of the pilot piston and
increasement of the pump flow.
PILOT PISTON NEG CONTROL
ADJUST SCREW
PRESSURE PRESSURE PILOT SPRING
Pm=FLOW CUT OFF Fi=NEG CONTROL
STOPPER
Pm
PISTON Fi
FLOW
C page 9
Flow Control Signals
MAX FLOW
solenoid
MAX FLOW CUT-OFF SIGNAL
(CN137)
(35 bar ON / 0 bar OFF)
35 bar
NEG CONTROL NEG CONTROL
SIGNAL FOR P1 SIGNAL FOR P2
( ±5 <-> ±45 bar) ( ±5 <-> ±45 bar)
C page 10
3.5 REGULATOR: “POWER” CONTROL SYSTEM
By changing the mode (H,S,M,U) the CPU varies the current towards the EPPR valve (Electric Proportional Pressure
Reducing Valve). This results in varying EPPR pressures, which work (together with P1 & P2 pressure) on the power piston
inside each regulator. The power piston & pilot piston are situated near each other and control the swash plate angle.
See p.35 for all EPPR values.
In case of significant drop of engine speed, the CPU will automatically increase the current, in order to lower the pump power,
and it will do this until the engine speed reaches the set-value again !!!
EPPR PRESSURE REGULATOR 1 REGULATOR 2
PEPPR PEPPR
0…35 bar =
SERVO PRESSURE Pi
35 bar P2 P1
P1 P2
REGULATOR 1
A OUPUT
T
REGULATOR 2 Power Piston
(Compensating
Piston)
24V INPUT
fuse
CPUpin EPPR-
(or CPU pin EPPR+)
EPPR Valve = Pf (Power Shift ) Valve
CURRENT
0…700 mA
Neg sig = 40...45 bar P1, P2 = low (in 125 ...330 bar area)
C page 11 - 1
Flow Pressure Chart R210LC-7 The flow pressure chart of the pump depends on the active program version of the cluster
See p.41 for setting the program version.
400 R210LC-7(standard) 400 R210LC-7(standard)
R210LC-7, default ( = version 1.X) R210LC-7, other case ( = version 2.X)
350 350
300 300
118K
92K 105K
Flow Rate(l/min)
Flow Rate(l/min)
250 92K 206L 161K 250
92K 161K
2100rpm 217L 217L217L
217L Emergency mode
215L 215L
200 200 H mode
2000rpm H mode 93K H mode
150 S mode 150
207L 190K
S mode
Emergency mode 246K S mode
Emergency mode 246K
113L
111L 111L
100 177K 100
202K 175K177K 202K
114L 177K
107L 110L 114L 107L
50 50 114L
0 0
0 50 100 150 200 250 300 350 0 50 100 150 200 250 300 350
Delivery Pressure(kgf/cm2) Delivery Pressure(kgf/cm2)
EPPR (bar) EPPR (bar)
H 0 H 18
S 13 S 22
Emergency 15 Emergency 15
F2 = NEG CONTROL
REG 2
PEPPR
P2
Drain
P1
Pilot Pump
Pi
F1 F2
Remark
The pump assembly of R210NLC-7 is similar to above pump
For more detailed information, refer to service manual.
C page 13
3.6 MAIN PUMP R500LC-7 (& R450LC-7(#464~)) Servo assist port (Pi)
PEPPR
(≈ R800LC-7A)
A. MAIN PUMP
PILOT F1(neg)
PRESS
Psv1
P1
F1=
F2
Psv2 P2
FRONT VIEW 45/50 ton
F2(neg)
PEPPR
Drain 1
BOTTOM VIEW
C page 15
Check valve
STRUCTURE TRAVEL
Mp
LEFT
BOOM 1
Lb1
Lb2
ARM2
OPTION
(1 side) EXTRA A (OPTION)
BUCKET Power
& ARM
SEC. boost
REGENERATION
RELIEF
V/V BM
(Piston side) L01
K1
SEC.
RELIEF V/V
BUCK K1
(Piston side) Zm
Qr
(Regeneration)
Zm K3
K4
Lb1 L01
OPTION K3
PLUG
DRAIN PORT K4
SWING Mp
PLUG
PORT
Lb2
C page 15 - 1
STRUCTURE
DOZER OPTION
(EXTRA B) (EXTRA C)
HANIL-MCV (1 piece block)
OPTION
ARM1
BOOM2
BOOM2
ARM1 &
SWING SWING SWING
PRIORITY
TRAVEL
DOZER
RIGHT
STRAIGHT
TRAVEL
SEC. Qr
RELIEF V/V (REGENERATION)
ARM
(Rod Side)
Q1
Q2 (SUMM)
V3 PLUG
Q2 summation
line for arm
PO (PILOT OIL (arm 2)
ENTRANCE)
Ks
PLUGS
Q1
p 2-25
Ks
p 2-23
PLUG
Orifice +
filter (FO3) Orifice in FO3 FO4
straight
travel valve
(FO4) C page 15 - 2
STRAIGHT TRAVEL SPOOL
for crawler excavator
(at entrance of
pilot signal
hose)
HOLE
for wheel excavator: (in this case, spool is in "fixed position" no straight travel function)
HOLE
(at entrance of
pilot signal
hose) C page 15 - 2a
HANIL-MCV (2 pieces block)
Work PS CD7
(NO, auto decel)
Remark for next models with Hanil MCV's : R290(N)LC-7A, R140LC-7(A) (Except -7 S/N E1602 to E2679), R140W-7(A),
R110-7(A), R160LC-7(A), R180LC-7(A), R170W-7(A)
When using arm & breaker at the same time, the breaker can receive double pump flow , due to the arm-2 spool
which delivers oil to different spools in the block. To avoid this, exchange load check valve ass'y with other parts
see SB–2009–005 for detailed information
C page 15 - 3
MCV R140LC-7, TOSHIBA (1/5)
ARM
1 CYL
10 11
15
9
ARM1 ARM2
13
2 7
BOOM2 BOOM1
(OPT)
14
BOOM
HOLDING
BUCKET VAVLE
TANK
SWING
17
STRAIGHT
3 4
TRAV V/V
12 TRAVEL RIGHT
16
TRAVEL
RIGHT OPTION Power
BUCKET F1 signal (Fl)
Boost
BOOM 1 Signal
ARM 2
FOOT RELIEF
VALVE (10)
XAk2
SEC. SEC. FOOT RELIEF
RELIEF V/V RELIEF VALVE (11)
BUCK V/V BM Ck1
(Piston side) (Rod side)
Drain Px Py
F2 signal (Fr) Arm Holding
Valve (9) auto decel
press switches Pilot Oil
Entrance
RETURN
Pa L LINE
signal
P1 P2
FLOW FLOW
auto decel
Boom Holding orifices (16)
Valve
Drain
SEC.
RELIEF
5Pi
V/V BM
(Piston side)
C page 15 - 5
MCV R140LC-7, TOSHIBA (3/5)
SEC.
RELIEF
Center by pass
V/V BM
spool (1)
(Rod side)
XAk2= summation
bucket in signal
stroke limiter
signal not in use :
linked to tank
LEFT BACK VIEW
BOTTOM VIEW
ARM 1
XBa1 SEC.
RELIEF
SWING
V/V ARM
(Rod side)
SEC. SEC.
RELIEF RELIEF V/V
V/V BM BUCK
(Piston side) (Rod side)
Priority
Check Straight Travel
Valve (6) Pilot Valve (4)
Arm Regeneration
Valve (2)
C page 15 - 6
page 15 - 7
ARM1
MAIN 12
RELIEF
SEC. RELIEF
VALVE
V/V
15
STRAIGHT RTAV
PILOT V/V 4
6
PRIORITY
CHECK
VALVE
ARM
HOLDING V/V FOOT 10
9 CENTER RELIEF
ARM BYPASS VALVE
HOLDING SPOOL 1
PILOT V/V
2
SEC. RELIEF
V/V 15
STROKE
LIMITER
ARM1
SPOOL
page 15 - 8
17
SEC. RELIEF
BUCKET
V/V
13 14 SUMMATION
AUTO CHECK V/V
16
DECEL
ORIFICES
CHECK
8
VALVE
FOOT
RELIEF V/V
11
SEMI PARALEL
SPOOL
(CHECK V/V SPOOL)
5
BOOM
HOLDING V/V
SEC. RELIEF
V/V
13 14
BOOM
SUMMATION
CHECK V/V
7
4.2 MCV KAWASAKI
page 16
R210/250/290/320LC-7
(~#1176)
C
(Only R210/250LC-7A)
SHUTTLE TEE
FROM SWING
PNS
CS1&2
PUMP2
Nzy
Nzx
PUMP1
STRUCTURE R210/250/290/320LC-7
(~#1176)
Drain 4
Drain
FRONT VIEW
Main Relief
Valve P1
DRAIN FLOW
SWING work ps CD7
(auto dec) P2
PORT Straight Travel
Drain 3 FLOW
Valve (TS)
Pa L signal
Ccb Pilot Oil
Entrance
Arm Holding LCa1 Drain
Valve (HV)
Csp Power Boost
(PG)
Signal
(PH)
Nzx R
Drain 1 Drain 1
P2 Drain
Nzy
Drain Check Valve BY PASS
CMR 1 trav ps CD6 valve BP
(auto dec) F1 signal(Fl)
Pns P1
Check Valve FOOT RELIEF F2 signal(Fr)
Boom
CMR 2 VALVE 1
priority valve 3 AUTO DECEL
(= Swing reducing valve) ORIFICES
Boom Holding
Pilot Valve PRV-BOOM PRV-ARM
TRAVEL OPTION BOOM 1 BUCKET ARM 2 (Piston side) (Rod side)
RIGHT
Pb L signal
Drain 4 PRV-BUCKET
(Piston side)
Boom Holding
Valve (HV)
C1 FRONT
LC0 LCk
C2
R290LC-7
BOTTOM VIEW
PRV-BOOM PRV-BUCKET
(Rod side) (Rod side)
Swing Priority
Spool SP:
(only in use on
R210/250LC-7A) R210LC-7
FRONT
to Swing
neg. brake (PRV = PORT RELIEF VALVE) R290LC-7
PRV-ARM
(Piston side)
C page 18
R210/250/290/320LC-7
(~#1176)
TRAVEL PS
CD6 (auto dec)
PH
C page 19
page 19 - 1
MCV R290LC-7, HANIL (#1177~) 1/4 (SMALL MODIF's AS FROM SN. E0401:
SWING TANK SEE PARTS MANUAL)
RETURN
RIGHT SIDE MCV !! !! LEFT SIDE MCV
C
saf v/v
Gp
BUCKET
OPTION
Pd4o ARM REGEN.
ARM1 & EXTRA A
Qr
O2
Q1
K1
ARM2
BOOM2
saf v/v
BOOM1 Pa2o
SWING
Mp
TRAVEL
RIGHT TRAVEL
LEFT
STRAIGHT
TRAV V/V
page 19 - 2
VIEW A (BOTTOM)
ARM REGEN.
& EXTRA A
Boom Holding
Valve (BHV) NEGATIVE
BUCKET RELIEF
VALVE 1
Pb21
SEC REL
V/V ‘s
BOOM1
Dr1 TRAVEL
ARM2 LEFT
Main Relief
SEC REL Valve
V/V ‘s ARM
REGENERATION
travel ps CD6
(auto dec)
work ps CD7
NEGATIVE (auto dec)
RELIEF
VALVE 2
Power
Boost
Signal
Pilot 02
Check
valve Mp
Pn2
Pn1
RIGHT LEFT
Option
MCV
port B4 chek v/v ‘s
BLOCK
MR
Swing MACHINE
drain Qr DIRECTION
load check v/v buck
line
Parallel passage
Center passage
VIEW A (BOTTOM) Ck2
(Check valve for
bucket summ line)
page 19 - 3
C
MACHINE (cap on swing
priorrity)
DIRECTION
page 19 - 4
11
10
12
12
C page 20
B] STRUCTURE (1/3) RIGHT BLOCK R360LC-7(A)
3 BOOM PRIORITY
ORIFICE BOOM HOLDING 5
VALVE
SINGLE LOAD
SECUN. RELIEF V/V
CHECK V/V
DOUBLE LOAD
CHECK V/V
CENTER BY-
PASS V/V ASS
Orifices 12
Auto Decel
FOOT RELIEF V/V
SECUN. RELIEF
V/V
PY
1
PX
BOOM RIGHT MIDDLE LEFT
Press Sw
BUCKET
Auto Decel MCV
TRAVEL BLOCK
RIGHT
Arm out (a)
Arm in (c)
MACHINE
DIRECTION
C page 21
B] STRUCTURE (2/3) MIDDLE BLOCK R360LC-7(A)
BUCKET
SUMMATION
CHECK VALVE
1 MAIN RELIEF V/V
C page 22
B] STRUCTURE (3/3) LEFT BLOCK R360LC-7(A)
LOAD CHECK
V/V SW
dr SWING PRIORITY
ORIFICE 4
4PC
SWING
ARM
12
OPTION DOUBLE LOAD
FOOT RELIEF V/V CHECK V/Vs
TRAVEL CENTER BY-PASS
LEFT SECUN. RELIEF V/V ASS
Buck in (b)
Boom up (d)
V/V
C page 23
MCV R360LC-7A(#170~#442), KAWASAKI
page 23 - 1
R360LC-7A
CUT -2
C
(BUCKET
"BUCKET -IN SIG." SUMMATION)
CUT -1
(OPTION
CONFLUENCE SUMMATION)
C-2
ARM
HOLDING (OPEN)
VV. ASS''y
CONFLUENCE
C-1
(CLOSE)
ARM1
ARM2
Signal for
changing
pressure
setting
"STROKE
LIMITER
BUCKET
OPTION
SIGNAL FROM PRESS. SW.
Px TO OPEN THE NEG
SWING BRAKE (SH)
BM UP SIG
BOOM
HOLDING
VV. ASS''y
SHUTTLE TEE
FROM SWING
BOOM2 BOOM1
SWING
PRIOR
SPOOL
TRAVEL
SWING RIGHT
SWING
RESTRICTION
VALVE
STRAIGHT
TRAV V/V
Px
TRAVEL POWER
LEFT BOOST
MCV R360LC-7A(#170~#442), KAWASAKI
BOOM
HOLDING
VALVE
Main relief valve
CUT-2 Spool (at right side of
"R4" (from Mu -Swing)
STRAIGHT
(Bk summation) straight trav valve)
TR RIGHT
ARM HOLDING
TR LEFT
BM1
BK
VALVE
ARM2
SW
BM2
OPTION
ARM1
Neg. Relief swing restriction
valve-2
valve & sign "Pns"
CONFLUENCE
C-1
"BUCKET -IN
SIG." for flow summ.
Sign. to open
ARM HOLDING
swing prior spool VALVE
(below BM2) &
signal "Psp"
CONFLUENCE
C-2
C page 23 - 2
limiter signal
MCV R360LC-7A(#170~#442), KAWASAKI VIEW FROM RIGHT SIDE for boom-down
(not piloted) - TOP -
- BOTTOM -
P2 P1
boom up VIEW
VIEW sign FROM
FROM FRONT
Tank
REAR
- BOTTOM -
- TOP -
BOOM 1
BUCKET
limiter signal
for bucket -in
MAIN (operated at
RELIEF boom up)
with PB - TOP -
- BOTTOM -
on top
bucket-out
signal
auto decel
press
- REAR- switches
VIEW VIEW FROM LEFT SIDE VIEW FROM BOTTOM
FROM - REAR-
TOP
- BOTTOM -
- TOP -
Neg rel.
Neg rel. v/v 2 v/v 1
adjustable
- FRONT -
setting for CUT-1 Spool
CONFLUENCE CUT-2 Spool rel. v/v option CONFLUENCE
- FRONT - spool
C page 23 - 3
C-1 C-2
MCV R360LC-7A(#170~#442), KAWASAKI CONFLUENCE
C-1
Neg rel.
v/v 2
Neg rel.
v/v 1
CONFLUENCE
C-2
1e SECTIONAL VIEW
FROM FRONT
C page 23 - 4
page 23 - 5
8 8
7 7
5
supplementary
outside pipe
connection for ARM2
(only R800LC-7A)
6 10
( ) ( )
P2 P1 C page 24
B] STRUCTURE (1/3) RIGHT + LEFT BLOCK R450/500LC-7(A) & R800LC-7A
B] STRUCTURE (1/3)
FOOT RELIEF V/V 8
P1
T1
ARM REGEN. V/V
6
F1 (PS2) F2 (PS1)
DR1
RIGHT LEFT
P2
Pa11
MCV
BYPASS CUT SPOOL
T4 BLOCK
7
T3
BUCKET SUMM.
SIGN. MACHINE
BYPASS CUT SPOOL DIRECTION
7
C page 25
B] STRUCTURE (2/3) RIGHT BLOCK R450/500LC-7(A) & R800LC-7A
ARM 2
BM-1 HOLD VALVE 4
BUCKET
PC2
DR2
BOOM 1
TRAVEL
STRAIGHT
TRAVEL 2
C page 26
B] STRUCTURE (3/3) LEFT BLOCK R450/500LC-7(A) & R800LC-7A
ONLY
R800LC-7A 11
BM-2 HOLD ARM 1
PP (PILOT
VALVE
PRESS) MAIN RELIEF SERVICE
1 PC7
VALVE
DR7 BOOM 2
PH (POWER
BOOST) SWING
TRAVEL
PA
0 bar (normal)
35 ~40 bar (heavy duty mode)
DR1 ORIFICE+ 3
SMALL LOAD CHECK V/V
DR3
PC1
C page 27
5. CAPO SYSTEM
5.1 SYSTEM DIAGRAM
CAPO =
The accel dial permits in
COMPUTER an easy way to set a
AIDED desired RPM in H, S & M
POWER mode.
OPTIMIZATION
In U mode (or MI, MII)
SYSTEM
however, the RPM is fixed.
H, S
M, U (Not R110LC-7)
(MI, MII)
C page 28
5.2 JOYSTICK BUTTONS
B A D C
1 3
2 4
1 3
LEFT RIGHT
LEFT RIGHT
2
4
1 3 HORN
C page 29
5.3 MONITORING SYSTEM COLOURED MENU TYPE (-7A)
Priority / Breaker
C page 30
1.B CLUSTER CHECK PROCEDURE
C page 31
1.C WORKING OF COLOURED MENU TYPE CLUSTER
When pushing on button nr. “ 5”, you enter into the menu:
C page 31 - 1
C page 31 - 2
C page 31 - 3
C page 31 - 4
COLOURED MENU TYPE (-7A):
3. R110LC-7/-7A similar as previous pages R110LC-7
3.A MONITOR PANEL
CLASSIC DISPLAY TYPE (-7)
Via select switch it is possible to show sequencially:
RPM / TIME / EPPR pressure / CPU model &
F program version
P
HIGH POWER
STANDARD POWER
LIGHT POWER ( ONLY ON -7)
Brown
Black
Yellow
Blue
C page 31 - 5
page 31 - 6
C page 32
5.4 MODE SELECTION SYSTEM
1) GENERAL (NOT R110LC-7) First generation machines have 2 fixed power modes (H,S) and 2 user modes (MI, MII)
Second generation machines have 3 fixed power modes (M,H,S) and 1 user mode (U)
Find at page 35 the table with RPM & EPPR values for H, S, (& M) modes
A. POWER & USER MODES
MI = User Mode I M
MII = User Mode II U U = User Mode
R140LC-7 & R290LC-7 with Hanil MCV’s (not -7A) R210LC-7<->R320LC-7 In this case a pilotable restriction is placed in the
with Kawasaki MCV’s entrance line of the swing spool.
ARM1
BM, ARM
BM, ARM
BOOM2
SWING
PRIORITY
VALVE
swing prior sig. SWING SWING
R140LC-7 boom prior sig.
arm regen. (arm regen.
cut signal cut signal)
R140LC-7
R290LC-7
PRIORITY BOOM
PRIORITY PRIORITY
SOLENOID
SOLENOID VALVE
CN133
CN133
35 PRIORITY 35 PRIORITY
bar SOLENOID bar SOLENOID
HEAVY OFF HEAVY ON
GENERAL ON GENERAL OFF
☜
S Standard power 2100 1900 290 8 340 11
Auto decel Engine deceleration 1200 - 670 31 see left 670 31
TO EPPR
One touch decel Engine quick deceleration 850 - 670 31 670 31
Key start Key switch start position 850 - 670 31 670 31
valve
410 15 410 15
Emergency
(50 Ohm) (50 Ohm)
C page 35
3) RPM & EPPR SETTINGS FOR FIXED POWER MODES (2/9) (EXCAVATORS WITH 2 FIXED POWER MODES H, S
& 2 USER MODES MI, MII
R210LC-7, ~#1000 (TIER I engine)
Mode Application Pow er shift by EPPR valve
C page 38
M = OLD “H” value
4) RPM & EPPR SETTINGS FOR FIXED POWER MODES (5/9) H = OLD “S” value
B] FOR EXCAVATORS WITH 3 FIXED POWER MODES (H, S, M) & 1 USER MODES (U) S = “H” - 100 rpm
PROGRAM
M-mode H-mode S-mode Auto Key
(MAXIMUM) (HIGH) (STANDARD) DEC start
mA mA mA
Signification RPM EPPR (bar) RPM EPPR (bar) RPM EPPR (bar) RPM RPM
standard program
setting M
U
option program
setting (see p.41 for
more info)
(Tier-II)
FIRST SERIE OF
PROGRAM
CONFIGURATIONS
(Stand & Option) :
(Tier-II)
C page 39
(EXCAVATORS WITH 3 FIXED POWER MODES H, S, M
& 1 USER MODES U
Adaptation - (Low noise, 2nd level marked with “ S” in below table) (6/9)
(#491~) (#1520~) (#542~) (#659~)
( ) ( ) ( ) ( )
M
U
C page 39 - 1
4) RPM & EPPR SETTINGS FOR FIXED POWER MODES (7/9) (EXCAVATORS WITH 3 FIXED POWER MODES H, S, M
R160/180LC-7 (TIER II engine) & 1 USER MODES U
Mode Default (1.x) Other case (2.x)
Emergency
C page 39 - 2
4) RPM & EPPR SETTINGS FOR FIXED POWER MODES (8/9) (EXCAVATORS WITH 3 FIXED POWER MODES H, S, M
& 1 USER MODES U
-7A EXCAVATORS TIER III ENGINES
C page 39 - 3
4) RPM & EPPR SETTINGS FOR FIXED POWER MODES (9/9) (EXCAVATORS WITH 3 FIXED POWER MODES H, S, M
& 1 USER MODES U
-7A EXCAVATORS TIER III ENGINES
R800LC-7A
R110LC-7A (TIER III engine) MODE Ver RPM RPM PUMP EPPR
Mode Default (3.x) Other case (4.x) UNLOAD LOAD mA bar
M 1800 1750 230 4
RPM RPM EPPR RPM RPM EPPR
Standard H 5.1 1800 1750 330 10
UNLOAD LOAD mA bar UNLOAD LOAD mA bar
S 1700 1650 330 10
H 1900 1800 230 4 1900 - 100 0
S 1800 1700 290 7 1900 - 290 7 M 1800 1750 150 0
L 1700 1600 340 10 1800 - 340 10 Option H 6.1 1800 1750 230 4
Auto decel - - - - - - - - S 1700 1650 330 10
One touch decel 900 - 700 35 900 - 700 35 Auto decel 1150 - 700 35
Key start 900 - 700 35 900 - 700 35 One touch decel 800 - 700 35
Key start 800 - 700 35
Emergency
Emergency 491 15
C page 39 - 4
REMARK Throtlle % values for QSB/QSC/QSM-Tier II engines
Percentage of Cummins power, used by Hyundai excavator. This Percentage is stored in the Hyundai Controller and is recognised by
Cummins controller via CAN BUS system. The value can be seen when working with the Cummins software (“Insite”)
b. Working
The system operates by means of 2 or 3 pressure switches (Px Py Pz ) situated on the main control valve.
Operating pressure : ± 10 bar
Find more information regarding this in “290-7MCV.pdf”
C page 40
HOW TO CHANGE THE PROGRAM VERSION (1.X <-> 2.X) ON THE CLUSTER
(5.X <-> 6.X)
(…)
By changing the program version of the MCU, the EPPR valve pressure and/off
engine RPM changes for the 3 power modes (S, H, M) simultaneously. These
alternative values are shown in the tables at pages 35<->39 - 4.
• To change the current program version on the system menu: CHANGING PROGRAM VERSION VIA
Select “Settings” -> “Dual Mode” -> “OK” to change
BUZZER STOP & TRAVEL SPEED SWITCH
C page 41
4) USER MODE SELECTION SYSTEM (NOT ON R110LC-7)
1] CLASSIC DISPLAY TYPE (-7/-7A)
The first type of excavators had 2 memory modes (MI & MII) ; the later machines have only 1 memory mode:(U).
Via this modes, the operator can configure a fixed pump power & engine power
OLD NEW
OLD NEW
U
M
U
(U)
(U)
CHANGING “GROUP”
DISPLAY VIA
BUZZER STOP & SELECT
SWITCH
Remark: add. group 1: AP --> Ambient pressure (kpa) (only TIER2,3 engine)
add. group 3: ol --> Overload pressure switch (on or off)
C page 43
2) ERROR CODES TABLE After ignition on, push 2 times the buzzer stop & select
A. MACHINE ERROR CODES LIST (HYUNDAI) switch simultaneously, to get into the error code group.
(OPTION) (OPTION)
(Not on QS eng.)
(OPTION)
(OPTION)
(OPTION)
(OPTION)
(OPTION) (= Co Err) (Not all error codes are applicable for
the R110-7/-7A)
C page 45
B1. ENGINE ERROR CODES LIST FOR R290/360LC-7 (CUMMINS QSB5.9/QSC8.3) NO High Pressure Common Rail (2/3)
285
The ECM expected information from a At least one multiplexed device will not
285 multiplexed device but did not receive it operate properly.
soon enough, or did not receive it at all.
C page 46
B1. ENGINE ERROR CODES LIST FOR R290/360LC-7 (CUMMINS QSB5.9/QSC8.3) NO High Pressure Common Rail (3/3)
C page 47
B2. ENGINE ERROR CODES LIST FOR “-7A” R210/250/290/320/360 (CUMMINS QSB6.7/QSC8.3/QSL9) all with High Pressure Common Rail (1/5)
C page 47 - 1
B2. ENGINE ERROR CODES LIST FOR “-7A” R210/250/290/320/360 (CUMMINS QSB6.7/QSC8.3/QSL9) all with High Pressure Common Rail (2/5)
C page 47 - 2
B2. ENGINE ERROR CODES LIST FOR “-7A” R210/250/290/320/360 (CUMMINS QSB6.7/QSC8.3/QSL9) all with High Pressure Common Rail (3/5)
C page 47 - 3
B2. ENGINE ERROR CODES LIST FOR “-7A” R210/250/290/320/360 (CUMMINS QSB6.7/QSC8.3/QSL9) all with High Pressure Common Rail (4/5)
C page 47 - 4
B2. ENGINE ERROR CODES LIST FOR “-7A” R210/250/290/320/360 (CUMMINS QSB6.7/QSC8.3/QSL9) all with High Pressure Common Rail (5/5)
C page 47 - 5
B3. ENGINE ERROR CODES LIST FOR R450/500LC-7(A) (CUMMINS QSM11) (1/3)
C page 48
B3. ENGINE ERROR CODES LIST FOR R450/500LC-7(A) (CUMMINS QSM11) (2/3)
C page 49
B3. ENGINE ERROR CODES LIST FOR R450/500LC-7(A) (CUMMINS QSM11) (3/3)
C page 50
B4. ENGINE ERROR CODES LIST FOR R800LC-7A (CUMMINS QSX15) (1/4)
C page 50 - 1
B4. ENGINE ERROR CODES LIST FOR R800LC-7A (CUMMINS QSX15) (2/4)
C page 50 - 2
B4. ENGINE ERROR CODES LIST FOR R800LC-7A (CUMMINS QSX15) (3/4)
C page 50 - 3
B4. ENGINE ERROR CODES LIST FOR R800LC-7A (CUMMINS QSX15) (4/4)
C page 50 - 4
C. ENGINE ERROR CODES LIST FOR R110/140/160/180LC-7A (MITSUBISHI D04FD-TAA)
- View active and logged diagnostics (once the ECM software has been updated)
- View events where irregularities occurred and were logged by the ECM
- View the status of a group of parameters simultaneously
(temperatures, pressures, etc.)
- Record and log performance data
- Graph a group of status parameters
- View the current configuration of an ECM
- Change ECM configurations
- Perform diagnostic tests DR-Tool
- Perform calibrations Diagnostic
- Print reports and diagnostic results Plug
HRDT
Diagnostic
for more info & purchase, contact service dept. Plug CN126
- View HYUNDAI & CUMMINS (QSB/QSC/QSM) Error Codes (actual & memorised)
with full explanation & trouble shooting steps
- View elemental monitoring information on (Hyundai/Cummins)
- Record different Pressures during sample time
& store in graph/table
- View Hour Counter for remaining maintenance interval time
- View history of switches activation & others....
(Cummins
Diagnostic
find more info in Service Bulletin HHIE-SB-2007-007
Plug CN148)
C page 52/53
5.6 MALFUNCTION OF CLUSTER OR MODE SELECTION SYSTEM
• Check display of cluster first 5 sec after ignition on: CLUSTER
All lamps should light up, with buzzer sound POW (IG) brown
GND black
• If nothing appears, check on cluster: - Feed line (Brow ) 24 V RX yellow
TX blue
- Ground line (Black) GND
In case of no feed voltage: check fuse for cluster, power relay, wiring
• If display is blurred or some lamps do not lighten up replace cluster (or light board inside)
• Check Rx & Tx Voltage on cluster: - Serial- (Rx) line, input (Yellow) 12V
- Serial+(Tx) line, output (Blue) 4V
In case of no voltages: check wiring (Rx & Tx lines)
In case of voltages: replace CPU
Other types of
• Check LED’s on CPU: communication errors:
070 / 071 / 072
• Green: Normal condition see list at p.44
• Yellow & Green: Communication problem = “Co Err” Yellow: (Line) failure at cluster
CPU
• Check CHECK warning light on cluster
Emergency
Resistor
CN19 CN47
CN19
&
CN19B
CN19A
Plugging in the emergency resistor assures setting of fixed Eppr pressure, which results in machine operation, equal to “S-mode”
ACTUAL SYSTEM OLDER MACHINES SYSTEM WITH CN47 & EMERG. SWITCH OLDER MACHINES SYSTEM WITH ONLY “CN47”
EMERGENCY EMERGENCY
RESISTOR RESISTOR
CN47
24V 24V 24V EMERGENCY
Fuse CN47 Fuse CN47 Fuse RESISTOR
ON
+ +
- - OFF -
CPU CPU EPPR CPU
EPPR EMERGENCY VALVE EPPR
SWITCH
VALVE VALVE
NORMAL (OFF)
EMERGENCY (ON)
C page 55
Emergency Procedure, in case of faulty CPU (=MCU) (2/2)
- ASSURING ENGINE SPEED CONTROL - ASSURING STARTING OF MACHINE
For B3.9, B5.9, C8.3, M11, S6S, S4K engine:
- DISCONNECT accelerator cable from injection pump lever (CN96A for wheel exc)
- CONNECT emergency (Push-pull) cable on injection pump lever CN92
So, in this case MANUAL control of RPM is possible
(SEE NEXT PAGE)
CN92
For QSB, QSC, QSM, D04FD engine: (CN96B for wheel exc)
In emergency, engine control is ONLY possible via ACCEL DIAL: ALL EMERGENCY CONNECTORS: NEAR CPU
NORMAL
* CLUSTER (S, H, M)
* CLUSTER AUTO DECEL BUTTON
* AUTO DECEL PRESS. SW’S
* QUICK DECEL BUTTON Emergency
ON JOYSTICK CAN BUS Resistor
* .... CONNECTION
CPU
ECM
NORMAL
STOP SCREW
HIGH IDLE
(PRE-SET)
STOP SCREW
LOW IDLE
(PRE-SET)
ENGINE ACCEL
ACTUATOR
(DC-MOTOR) EMERGENCY
Adjustment of RPM:
THROTLLE see page 59
CABLE
C page 57
3) ACCEL ACTUATOR
C page 58
R110LC-7
TYPE B (R110LC-7 / R140LC-7, SN 1001and up) / R140W-7)
C page 58 - 1
4) ACCEL ACTUATOR CABLE SETTING PROCEDURE
SETTING SCREW
C page 59
5.8 ENGINE SPEED SENSOR (not for excavators with QS-engines)
C page 60
5.9 ELECTRIC COMPONENT LOCATION For exact location of
components,refer to service
manual
CN148: J1939
(3-PIN)
Diagnosis for
Cummins ECM on
QSB,QSC,QSM eng
(R210LC-7)
Box with:
- fuses
- CPU
- relays
13 (R290LC-7, R140LC-7) - emergency resistor
(and/or emergency switch)
- connectors for Hyundai &
Cummins diagnosis &
software updating
R210LC-7
CPU
Ry Head Lamp
(CR13)
Ry Breaker CR – 36
(CR62)
The Safety Relay has an anti-restart
function: see next page
C page 62
5.11 ANTI - RESTART FUNCTION
“START-SIG”
(CN96 for
wheel exc.)
= START RELAY
C page 63
5.12 FUEL WARMER SYSTEM
Pushing this switch activates the heater element
- On R160LC-7/R170W-7/180LC-7 at bottom side of fuel filter
- On -7A models
Activation (ON/OFF)
controlled by Hyundai CPU:
(start from "key-on") - Control of Ry by CPU -
Actuation of relay: When
coolant temperature is below
10 degree
Release of relay: When
operation time is over
30minutes or coolant
Remark temperature is over 60
R450LC-7A(#0084~), degree, whichever comes
R500LC-7A(#0045~), first.
R800LC-7A have other
type of filter (-7) with (info "Pre heating system" see "Engine bulletins") C page 63 - 1
heater at the bottom
6. ELECTRIC COMPONENT SPECIFICATION
TABLE 1/4
C page 64
TABLE 2/4
C page 66
TABLE 4/4
C page 67
7. BREAKER / DOUBLE FUNCTION PIPING
The option spool in the MCV can be used for either breaker (single function),
either clamshell, shear (double function)
B. OPERATION
Push on the breaker (or double function) switch BREAKER / DOUBLE FUNCTION
at right hand side. At that time the foot pedal can SOLENOID CN66 (see p. 70)
be operated for opening the “ option” spool
inside the MCV. (depend on model)
MAIN
CONTROL
VALVE
P2 P1
C page 69 - 1
8. SOLENOID BANK
8.1 ALL MODEL (NOT R110LC-7/-7A)
The solenoid bank is situated in the main pumps compartment
A1 A2 A3 A4 A5
C page 70
8.2 R110LC-7/-7A
A2 SECOND SPEED
SOLENOID (CN70)
A1 SAFETY SOLENOID
(CN68)
BREAKER SOLENOID
PRESSURE CHECK
PORT
(neg. control signal for
breaker operation)
C page 70 - 1
9. SWING MOTOR
All excavators have a similar swing device
Reactionless valves
Relief valves
SW left,
to MCV
(R290LC-7)
SW left,
(35 bar) from joystick SH
signal
SW right,
to MCV
SW right,
from joystick
Shuttle valve
SH
Relief valves
PG
Make up valve
Reactionless valves
Swing brake
pressure can be
measured on
this place
R290LC-7 R290LC-7 C page 71 - 1
Swing bearing grease
⅓H
½L ½L
L
Grease Amount (liter) 4.4 6.9 9.2 11.6 11.2 12.8 15.6
C page 71 - 2
10. TRAVEL MOTOR REFER ALWAYS TO THE NAMEPLATE ON
THE TRAVEL MOTOR TO IDENTIFY THE
10.1 TRAVEL MOTOR R110LC-7/-7A CORRECT TYPE!!!!! (Mind also that "LCM
" or "NLC" models can have different
types of travel motors > see parts book
D1 D2
P1 P2
7
8
P3 5
Orifice second
speed (back of Filter parking 6 6
cover) 7 brake (back of
cover) 8 2
4
4
DRAIN PISTON 3
B A B
OVERLOAD RELIEF
VALVE
2
P2 GAUGE
A SECOND SPEED
5
SPOOL
P1 GAUGE
PARKING 2-SPEED-CONTROL
BRAKE
RELEASE PORT (P)
PRESS
GAUGE (P3)
OVERLOAD RELIEF
VALVE
2
Remark
CHECK VALVE This travel motor shifts automatically in 1e speed,
CHECK 1 4 at a pressure of 290 bar and up.
(BALL)
VALVE
C page 72
TRAVEL MOTOR Tong Myung "Modified" R250LC-7(#473~) R180LC-7 (#372~#468)
(type B)
R250LC-7A R180LC-7A(~#0085)
valve parking
(2 pieces)
brake control
Orif. (297)
Orif. (297)
CV (227)
CV (227)
2e Sp spool
spool (263)
valve 2e speed (263) CV (227)
parking
brake pin
control
CV 2e sp
(268)
NPTF1/16
PARKING BRAKE
PRESSURE GAUGE
PORT
press reducing valve
for parking brake
C2
CV 2e sp
(268)
CV (227)
P3 C page 72 - 1
TRAVEL MOTOR Jeil R210LC-7(#2079 - #4493) R180LC-7(#469~) Part nr (Assy) 31N6-40050 (for 20ton)
R210LC-7A R180LC-7A(#0086~)- 31N5-40081BG (for 18ton)
(check name plate:
(check name plate: Jeil or Jeil or Tong Myung)
Tong Myung) !!!!
OVERLOAD RELIEF
VALVE
DRAIN
(T1,2)
SECOND
SPEED
SPOOL P1
Pm1
2-SPEED-
CONTROL
PORT (Ps) P2
NPTF 1/16
PLUGS
Pm2
OVERLOAD RELIEF
VALVE
COUNTER
BALANCE SPOOL
ORIFICE
PCH
NEG. BRAKE
PCH
C page 72 - 2
JEIL, 2e speed spool
P1 P2
SPOOL 59
ORIFICE 60
CH press
ORIFICE 60 V
Q (to shift into
ORIFICE 61 2e SPEED) ORIFICE 61
C page 72 - 3
JEIL
FOR THE ORIFICES BEHIND PORTS SW1,SW2:
!!!!!
A CH press
pilot
B
C
D
CH press SW2
(ORIFICE) Q
(P1)
CH SW2
V
SW 1 passage (P2)
passage
passage hole
hole
hole
SW1
(ORIFICE)
CH press
SW2
(ORIFICE)
page 72 - 4
JEIL
CH SW 2
passage passage
hole hole
SW 1
passage
hole
ORIFICE 26
to reduce (or 4 mm)
pressure for
opening neg.
brake
page 72 - 5
JEIL
Orifices
Remark
The travel motor shifts automatically in
1e speed, at a pressure of 270 bar
and up.
C page 73
TRAVEL MOTOR Jeil R290LC-7 (#1215~) & R290LC-7A Part nr (Assy) 31N8-40050
R320LC-7 (#0456~) & R320LC-7A) Part nr (Assy) 31N9-40020
C page 73 - 1
TRAVEL MOTOR Jeil R290LC-7 (#1215~) & R290LC-7A Part nr (Assy) 31N8-40050
R320LC-7 (#0456~) & R320LC-7A) Part nr (Assy) 31N9-40020
C page 73 - 1
10.4 TRAVEL MOTOR Kawasaki R360LC-7 (- #0741) -Part nr (Assy) 31NA-40010-
C page 74
10.4 TRAVEL MOTOR Tong Myung R360LC-7 (#0742~) & R360LC-7A -Part nr (Assy) 31NA-40020-
Pb
Pa (351)
(531)
steel ball(543)
C page 74 - 1
10.4 TRAVEL MOTOR Tong Myung R360LC-7 (#0742~) & R360LC-7A -Part nr (Assy) 31NA-40020-
(Orif. 703)
in brake
piston
Pressure
release valve
(flow control
valve, 351)
(Orif. 703)
(Orif. 545)
Pressure
release valve
(flow control
valve, 351)
(Orif. 704)
C page 74 - 1
10.4 TRAVEL MOTOR Tong Myung R360LC-7 (#0742~) & R360LC-7A -Part nr (Assy) 31NA-40020-
C page 74 - 1
10.5 TRAVEL MOTOR Rexroth R450/500LC-7(A) valve
pressure
control
2e SPEED
SIGNAL "X"
OVERLOAD
RELIEF
VALVE
MA
MB CHECK PORT
FOR PARKING
BRAKE PRESS
"Bre" 25BAR
25 bar OVERLOAD
RELIEF
VALVE
C page 75
10.5 TRAVEL MOTOR Rexroth R450/500LC-7(A)
valve
pressure For releasing parking brake
control spec. 25 bar
valve
pressure
control
control
valve for
2e speed 2e speed
sign.
(35bar)
control
valve for
2e speed
C page 75 - 1
10.6 TRAVEL MOTOR KYB R800LC-7A
Drain line
OVERLOAD RELIEF
VALVE
G1
2-SPEED-
CONTROL
PORT (Pi)
G2
OVERLOAD RELIEF
VALVE
C page 75 - 2
11. SAFETY VALVES (Oil Control)
Find more detailed information in TRAINING-SAFVV.pdf
C page 76
VIEW SAFETY VALVE
MCV
SPOOL
BOOM UP
T
Pi
TANK (T)
PILOTING (Pi)
BOOM CYL
CYL PORT C2
C page 77
SAFETY VALVE R800LC-7A
(RH boom cyl)
Relief valve C
2 cartridges
VIEW A
Check valve
C page 77 - 1
12. SYMBOLS & ABBREVIATIONS
The requiered circuits can be found in next books:
ON HYDRAULIC CIRCUITS:
Technical Handbook (ed. 2007-> -7 & -7A) part nr. 91E2-30907
MCV Main Control Valve Electric Circuit Handbook (-3 & -7): part nr. 91E2-30990
MR Main Relief Valve Hydraulic Circuit Handbook (-3 & -7): part nr. 91E2-30980
RCV Remote Control Valve
(Joystick/Pedal)
F1,2 (Pn1,2 , Pi1,2 ) Negative Pump Control Signal
SH Shuttle Joystick Pressure for Swing Brake
PG, PH Standby Pilot Pressure (35b)
Dr Drain
EPPR v/v Electro Proporional Pressure Reducing Valve
Pi Pilot Pressure (35b)
Px,Py Auto Decel Pressure Switches
Pz Power Boost Signal (35b)
Pk Second Speed Signal (35b)
Pm1,2 Max Flow Cut off Signal (35b)
ON ELECTRIC CIRCUITS:
CN Connector BZ Buzzer
NC Not Connected ILL. Illumination
Ry Relay INT Intermittent Signal (Wiper Mot)
CR Relay Connector ACC Acceleration
AC Air Conditioner SOL Solenoid
COMP Compressor ACT Actuator
GND Ground CPU Central Processor Unit
I (IG) Ignition ECM Electronic Control Module (Cummins)
S Start OEM Original Equipment Manufacturer = Hyundai
E Earth PCB Printed Circuit Board
B+ Battery Plus LH Left Hand Side
SW Switch RH Right Hand Side
PS Pressure Switch
C page 78
13. PRESSURE SETTINGS MEASURE CONDITION:
-Hyd Temp. ±50°C
-Power mode = “M-mode”
- Auto decel OFF ( high idle)
110LC-7 140LC-7 160LC-7 180LC-7 210LC-7 250LC-7 290LC-7 320LC-7 360LC-7 450LC-7(A) 800LC-7A
UNIT: BAR (A) (A) (A) (A) (A) (A) (A) (A) (A) 500LC-7(A) (=*)
MAIN CONTROL MAIN RELIEF 330 330 330 330 330 330 330 330 330 330 330
VALVE POW ER BOOST 360 360 360 360 360 360 360 360 360 360 360
PORT RELIEF 380 380 380 380 390 390 390 390 390 390 380
SWING MOTOR RELIEF PRESS 240 240 240 240 240 275 265 265 260 285 260
290
BRAKE RELEASE PRESS 35 35 35 35 35 35 35 35 35 33 - *35 40
BRAKE RELEASE SPEC. 33~50 30~50 20 20 33~50 33~50 29~32 26 30 20~50 30~50
TRAVEL MOTOR RELIEF PRESS 330 330 330 330 330 330 330 330 330(kawa) 345 350
360(Tong M)
35
EXCEPTION SPEC >> (at 2000 rpm) (at 2000 rpm) (at 2000 rpm) (at 2000 rpm) (at 2000 rpm) (at 2000 rpm) (at 1800 rpm) (at 1800 rpm) (at 1800 rpm) (at 1000 rpm) (at 1800 rpm)
Note: The indicated swing motor presssures are measured at a lab-stand with ±30 l/min PUMP PRESSURE 40 ±5 Bar (11t~45t)
pump flow. The real pressures (measured at relief, with M mode selected) are ± IN NEUTRAL: 45 ±5 Bar (450LC-7A & 50~80t)
20~30 bar “higher” then the indicated values !
C page 79
C