You are on page 1of 2

SME Annual Meeting

Feb. 28-Mar. 03, 2010, Phoenix, AZ

Preprint 10-058

COMMISSIONING AND OPERATION OF THE MINERAL PARK CONCENTRATOR

M. Gorman, Mineral Park Inc., Golden Valley, AZ, USA


K. Leader, Mineral Park Inc., Golden Valley, AZ, USA
C. Smith, Mineral Park Inc., Golden Valley, AZ, USA

ABSTRACT
The Mineral Park Mine is an open pit copper-molybdenum mine
located in northwestern Arizona, approximately 74 miles southeast of
Las Vegas, Nevada. The property has been owned by the Duval
Corporation, Cyprus Mining Company and Equatorial Mining of
Australia. Mercator purchased Mineral Park from Equatorial in 2003.
Mineral Park commissioned a 25,000 tpd copper and
molybdenum concentrator in November and December of 2008.
The process includes two stage milling (SAG and Two Ball Mills)
fed by primary crushed ore. Metals are recovered in a copper-
molybdenum flotation circuit consisting of mechanically agitated
roughers and cleaners. The copper- molybdenum flotation concentrate
is thickened and further processed in the molybdenum flotation circuit
which separates the copper and molybdenum minerals into salable
concentrates. The molybdenum circuit also uses mechanically
agitated cells.
This paper describes the plant and some of the highlights of the Figure 1. The Mineral Park Copper/Moly concentrator process
commissioning process. flowchart.

DESIGN Crushing and grinding


Run-of-Mine ore is transported to an in-pit crushing plant with 100
The Mineral Park Copper/Moly concentrator is a facility designed ton haul trucks and dumped into a 200 ton crusher feed hopper. An
to process 25,000 tpd of copper and molybdenum ore grading 0.25% apron feeder delivers ore to a vibrating grizzley screen, the oversize
Cu and 0.025% Mo. Mineral Park produces both copper and material feeds a 56" x 72" Traylor Jaw Crusher. Undersized and
molybdenum concentrates which are transported off site by truck. crushed material is conveyed to a crushed ore stockpile via a 54” fixed
stacker. The crushing plant product is approximately 80% passing 6 to
The facility is located on engineered fill in the barren core of this
8 inches. This unconventional equipment selection was based on
porphyry copper deposit. The plant uses the existing permitted tailings
optical evaluation of actual broken faces in the exposed and developed
dam that once served Duvall’s Mineral Park operations.
pit, where material from the pit was determined to run 80% minus 8” in
Construction on the facility commenced in 2007 with the mine ROM condition. A second identical in-pit crushing facility will be
preparation of engineered backfill for the Grinding section. The facility incorporated in Phase II.
was commissioned in November 2008 as construction was being
Crushed ore is reclaimed using two 60” belt feeders located
completed.
underneath the stockpile. The crushed ore drops onto a 54” conveyor
The plant is unique because of this “fast track” approach: that feeds the SAG mill.

• It was built without a completed detailed engineering phase The SAG mill is a 32’diameter x 14’ long, fixed speed mill driven
• No engineering group for construction management. The by two 3,000 hp motors. The SAG discharges to a vibrating screen
construction process was managed by Mineral Park fitted with 3/8” screen panels. Screen oversize is recycled to the SAG
personnel mill and screen undersize is split between two ball mill discharge
• Much of the procurement was done by Mineral Park sumps. The SAG mill is steel lined with 48 row, single height lifter
personnel design and charged with 5” balls.
• SAG mill was refurbished on site Each ball mill discharge sump feeds a cluster of 26” cyclones.
• Much of the detail work was completed in the field during The cyclone underflow feeds two 20’ diameter x 28’ long ball mills each
construction driven by a 7,000 hp synchronous motor. The cyclone overflows feed
• The milling facility and rougher flotation is outdoors in a the rougher flotation plant. The ball mills are rubber lined and charged
mostly temperate climate with 3” balls.
• The grinding mill and rougher flotation use a single tower
crane for maintenance The cyclone overflow is typically 70% passing 140 mesh.
• The plant was started with very few experienced operations Currently flotation collectors and milk of lime are added to the
people SAG mill feed. Frother is added to the cyclone overflow.
OPERATION Flotation
The process is described in Figure 1. Mineral Park flotation includes rougher flotation, copper/moly
cleaners and moly flotation.
1 Copyright © 2010 by SME
SME Annual Meeting
Feb. 28-Mar. 03, 2010, Phoenix, AZ
3
The rougher flotation plant consists of five, 9,070 ft mechanically 1. Need to revise piping during commissioning. The gravity
agitated Wemco Cells. The flotation concentrates are combined and tails line sloped uphill for several hundred feet from the tails
pumped to the copper/moly cleaners. Rougher tailing are combined launder. We saw that the pipe looked wrong but we
with scavenger tailings and flow by gravity to the high-rate tails assumed that it was an optical illusion and the pipe grade
thickener. was designed properly. Trying to get the tails to flow uphill
caused a great deal of frustration at startup.
Copper/moly cleaner flotation includes regrinding to 80% passing 2. Features found in modern operating plants, such as column
325 mesh in a 14’ diameter x 43’ tall Vertimill charged with 1 1/2 “ cells for molybdenum cleaning, were not included in the
balls, followed by cleaning, recleaning and scavenging in sixteen, 300 Mineral Park design.
3
ft Wemco cells. 3. Fresh water requirement was underestimated even though
The recleaner concentrate is pumped to a copper/moly thickener. historic raw water demand for Arizona flotation mills was well
The scavenger tails are combined with the rougher tails and flow by known.
gravity to the tails thickener. 4. Equipment placement not ideal. Vertical pumps were placed
in pump boxes that are inaccessible by forklift or overhead
Thickened recleaner concentrate is conditioned with NaHS and crane. The pumps are too long to be lifted out the pump box
processed in the moly flotation circuit. The moly roughers are two due to a lack of clearance between the box and the next
3
banks of ten, 100 ft covered Wemco cells. Normally, the plant uses deck up.
only one bank of moly roughers. The rougher concentrate is combined 5. Protracted arguments with motor supplier for the SAG mill
and further cleaned; the moly rougher tails is the final copper regarding their refurbishment quality control.
concentrate. This concentrate is thickened and fed to our copper 6. Access to work areas is not ideal due to lack of stairs and
concentrate filter press. walkways. Many decks could only be accessed from one
location causing people to walk all the way down stairs to get
The moly rougher concentrate is conditioned again with NaHS upstairs on the other end of the building.
and cleaned in a single bank of first cleaners. The first cleaners are a 7. The cooling systems were designed to mine supplied raw
3
bank of ten, 100 ft covered Wemco cells. The first cleaner water temperatures that proved inadequate for outdoor use
concentrates are combined and further cleaned; the first cleaner tails in the summer.
are recycled to the moly rougher feed. 8. The tower crane was purchased used and took several
The first cleaner concentrate is conditioned again with NaHS and months to get it reliable.
cleaned in a bank of second cleaners. The second cleaners are a 9. Long, costly period of time for operators to get trained while
3
bank of ten, 100 ft covered Wemco cells. The second cleaners are operating. The inexperienced operators made errors that
divided up into second re-cleaners (four cells), second cleaners (three were not anticipated by experienced supervisors. Examples
cells) and second cleaner scavengers (three cells). The concentrate include filling and overloading a down ball mill with sand
from each stage is fed forward. The final concentrate is fed to the twice and damaging the discharge end bearings and
recleaner circuit, the tails recycled to the first cleaner feed. jumpering out interlocks on a concentrate thickener and
damaging its drive.
3
The moly recleaners are two banks of ten 24 ft Quinn cells, and
two 30” column cells. All four sets of equipment operate in parallel. Lessons learned about the process include
The Quinn Cells are divided into four stages of cleaning where the 1. The effect of acidic ore on the mill’s performance was never
concentrate is fed forward. The column cells operate as single stages fully considered.
of flotation. a. The acidic material contains oxide copper and
molybdenum, forcing ore control to blend for sulfide
The Quinn cell tails are recycled to the first cleaners. The column minerals instead of total copper and molybdenum.
cell tails are recycled to the moly rougher feed. b. The acidic material froths significantly causing
operational problems.
Tails
c. The acidic material consumes a great deal of lime,
The plant tailings are thickened to 50% solids and disposed of by
impacting economics.
gravity through ceramic chokes to the tailings dam. Reclaimed and
2. Ore types impact performance but little ongoing classification
thickener overflow water is pumped back to the mill.
was done to prior to start up help describe problems. The
OPERATING EXPERIENCE ore is reported by the pit and elevation even though different
rock types (gneiss, schist…) are present; not tracking ore
We have learned a great deal about the consequences of the types prevents us from knowing how the mill will perform
design and the process itself since commissioning. prior to receiving ore.
3. Consultants were valuable early in the operation. Once
Consequences of the design
Mineral Park process people understood the plant, the
The benefits of skipping much of the detailed engineering were:
consultants were more useful for brainstorming than actually
1. Save money and time allowing the plant to be completed for providing fixes. This is to be anticipated because most of
$154 million in less than two years. the obvious mistakes were fixed quickly and we were left
2. Allowed the Mineral Park Concentrator to survive the recent with problems that were more difficult.
down turn in copper and moly prices when similar operations 4. Column cells are preferred over Quinn cells to reach a
cut back production or shut down altogether. molybdenum grade reliably in excess of 48% Mo.

The benefits of Mineral Park construction management are:


1. Mineral Park people know intimately how the equipment is
installed
2. Modifications to make the plant operator friendly that had to
be put off were being planned and discussed prior to
commissioning
3. There were few layers of management hindering the
commissioning process
Problems have included:

2 Copyright © 2010 by SME

You might also like