Professional Documents
Culture Documents
Preprint 10-033
PRACTICAL FINAL PIT DEPTH CONSIDERING THE FUTURE UNDERGROUND MINING- A CASE STUDY
Technical considerations of the underground option Economical considerations of the open-pit and underground
In order to assess the option of underground mining for this options
deposit, certain assumptions have been made to offer a low cost and A) Estimation of the annual incomes:
productive method for ore extraction. These assumptions are [10]: The actual production of the processing plant was determined to
• Backfilling of openings will not be economically viable; therefore be equal to 6 Mt/year considering a loss of 5% of concentrate to dust in
mining will be by room and pillar or open stoping methods. the plant. Therefore, in order to produce the actual targeted 6 Mt of
concentrate, the annual tonnage of processed ore will be in the range
2 Copyright © 2010 by SME
SME Annual Meeting
Feb. 28-Mar. 03, 2010, Phoenix, AZ
of 8.7 Mt. The price for concentrate is US$0.235 per Fe unit in Final open-pit depth considering the underground option
concentrate based on US$16/t at 68% Fe. The related data with the According to the method that is used to determine final open-pit
annual incomes achieved from open-pit and underground options is depth with considering to an underground option, it is first necessary
summarized in Table 1 [10]. identifying several scenarios of combined mining on the basis of the
benches height of 15-m in open-pit. Each scenario includes three
Table 1. Annual incomes achieving from open-pit and underground components of open-pit, a crown pillar, and underground. Crown pillar
mining. stability will be dependent on numerous parameters including rock
Characteristic Open-pit underground type, rook quality, rock strength, overburden depth, water influence, in-
Annual concentration (ton) 6000000 6000000 situ rock stress, and pillar geometry. At the north end of the ore body
Price of Fe unit (US$) 0.235 0.235 where the ore zone outcrops at bedrock surface, ore will have to be left
Annual income 96585000 96585000 as a crown pillar beneath approximately 100 m of overburden.
B) Estimation of the costs: Then, through the economical comparison between the scenarios,
the most profitable one can be selected and its final open-pit depth will
The operating costs are based on estimated productivity for each be the optimum transition depth for the case. It is notable that the main
type of mine equipment, on costs for consumables and maintenance assessment is done according to the constructed economical block
material and on the anticipated workforce. In this regard, the total models of open-pit and underground mining.
operating cost was estimated to be equal to 554.65 (US$ million).
As it shown in Fig. 3, with take into account a discount rate of
It is notable that here operating cost is divided into three groups of 12%, a net present value of 63 (US$ million) is achieved due to the
mining, processing, and general and administration. Among the related scenario of open-pit depth of 285 m. It means that the optimal
operating cost groups, processing cost as well as general and final open-pit depth considering the room and pillar mining to be equal
administration cost are the same in both open-pit and underground. An to 285 m achieving a 63 (US$ million) of net present value.
average process operating cost for Area 3 was estimated to be US
$3.00/ton per feed ore, based on a processing rate of 8.1 Mt/a of
undiluted ore resulting is 6 Mt/a of concentrate. In addition, general
and administration cost was estimated to be equal to 2.3 (US$
million/year). Therefore, the operating cost of processing plant for
open-pit and underground mining is calculated to be 26.17 and 24.7
(US$ million/year), respectively.
It is evident that with increasing open-pit depth and consequently
the removable waste rocks (stripping), stripping costs will be
increased. For the reason, ascendant trend of operating cost per each
tonnage of produced ore in regard to different open-pit mine sizes, is
assessed using whittle 4-X software (Fig. 2). As it is clear in Fig. 2, in
relation to an open-pit mine including 130 Mt of ore, mining operating
cost is US$2.28 per each tonnage of produced ore. This operating cost Figure 2. Mining operating costs of open-pit and underground.
is considered only during production years of open-pit, whereas, during
the three years of overburden removal, operating cost of mine is taken
into account to be equal to US$0.4 per each tonnage of overburden
removal. Therefore, before ore production and during development
stage mining cost will be 13.666 (US$ million/year). Generally, capital
cost of open-pit mining is determined regarding to the mine size. In this
relation, on the basis of an open-pit mine with maximum production
capacity of 130.87 Mt of ore capital cost is considered to be 100.712
(US$ million).
It was planned that a period of 4-years is essential for the
development and accessing to the desired ore deposit in the
underground mining. An estimation of the underground mine capital
cost and mine operating costs, in addition, the direct, underground
operating and maintenance labour requirements and the type, sizes
and number of major pieces of underground equipment has been
done. All estimates are in US dollars, using 2002 prices, and have an
error of estimate of 25%. A 15% contingency has been added to all Figure 3. Net present values of the combined mining scenarios with a
cost estimates. discount rate of 12%.
Capital costs are those costs incurred during the first years of CONCLUSION
construction and prior to mine production. The capital costs include:
124.962 (US$ million) for underground mobile mining equipment, 17.34 Due to the significance of determining the optimal open-pit depth
(US$ million) for miscellaneous mine equipment, 36.453 (US$ million) considering an underground option for Gol-e-Gohar Area 3 ore body,
for shaft development and installations, 33.119 (US$ million) for mine an effective method was used. In this regard, according to the benches
development, 2.2 (US$ million) for mine construction, 2.919 (US$ height of 15-m several scenarios of combined mining of open-pit and
million) for miscellaneous mine operating, 5.23 (US$ million) for staff room and pillar were initially considered. Then, with considering a
and labour. discount rate of 12% the related NPV of each scenario was
determined. After that, during an economical comparison between the
As it shown in Fig. 2, the total operating cost for direct operating scenarios, the most profitable one was selected. In this relation, the
and maintenance supplies and labour for stope and production optimal open-pit depth was assessed to be equal to 285 m, which
development, room and pillar mining has been estimated to be equal to achieves a total NPV of 63 (US$ million).
4.47 (US$/ton, Milled). Therefore, mining cost of the room and pillar
will be 36.9 (US$ million/year). On the basis of the room and pillar REFERENCES
mine with maximum production capacity of 122.455 Mt of ore capital
cost is considered to be 208.142 (US$ million). 1. Fuentes S. S. (2004), "Going to an underground (UG) mining
method", Proceedings of MassMin Conference, Santiago, Chile,
3 Copyright © 2010 by SME
SME Annual Meeting
Feb. 28-Mar. 03, 2010, Phoenix, AZ
pp.633-636.
2. Chen J., Guo D. and Li, J. (2003), "Optimization principle of
combined surface and underground mining and its applications",
Journal of Central South University of Technology, Volume 10,
Number 3 / September, pp. 222-225.
3. Fuentes S. S. and Caceres S. (2004), "Block/panel caving
pressing final open pit limit", CIM Bulletin, September, No 97,
pp.32-34.
4. Arancibia E. and Flores G. (2004), "Design for underground
mining at Chuquicamata Ore body-Scoping Engineering Stage",
Proceeding of Massmin Conference, Santiago, Chile, pp. 603-
609.
5. Flores G. (2004), "Geotechnical challenges of the transition from
open pit to underground mining at Chuquicamata Mine",
th
Proceeding of 4 International Conference on Mass Mining
(August 22 –25), Santiago, Chile, pp. 591-602.
6. Kuchta M., Newman A. and Topal E. (2003), "Production
scheduling at LKAB’s Kiruna Mine using mixed integer
programming", Mining Engineering, April, pp.35-40.
7. Abdollahisharif J., Bakhtavar E. and Shahriar K. (2008), "Open-pit
to underground mining- where is the optimum transition depth?",
st
Proceedings of 21 WMC & Expo 2008, Sobczyk & Kicki (eds),
Taylor & Francis Group, London, UK, pp. 189-196.
8. Nilsson D. (1982), "Open Pit or Underground mining",
Underground Mining methods Handbook (Section.1.5), AIME,
New York, pp. 70-87.
9. Nilsson D. (1992), "Surface Vs. Underground Methods", SME
Mining Engineering Handbook (Section 23.2), edited by Hartman,
H.L., pp. 2058-2068.
10. ADC (Acres Davy Consultants). (2000), "Prefeasibility study of
Gol-e-Gohar Iron Ore Mine (Mine Area 3)", Project No.171700,
175 pages.