Professional Documents
Culture Documents
Running Head: Chapter One, Two, and Three
Running Head: Chapter One, Two, and Three
Oman
Contents
Abstract ........................................................................................................................................... 3
Variation Orders and Project Delivery Systems ........................Error! Bookmark not defined.
Introduction ............................................................................................................................... 32
Interviews .............................................................................................................................. 34
Questionnaire ......................................................................................................................... 34
Qualitative Methodology........................................................................................................... 35
Quantitative Methodology......................................................................................................... 37
Validity .................................................................................................................................. 39
Reliability .............................................................................................................................. 40
References ..................................................................................................................................... 42
Chapter One, Two, And Three 4
Abstract
Variations in orders are one of the main issues in most projects related with construction. The
basic aim of this study is to research in-depth the adverse causes and effects of variation in
orders on government construction projects in Oman. Objectives of the study are the following:
(1) what causes variation in orders to occur in construction projects of Oman; (2) what are the
adverse impacts of variation in orders on construction projects; and (3) lastly to provide
recommendations to help mitigate and effectively eliminate the issue of variation in orders.
Extensive reviews will be done of previous literature focused on the same specific research area.
Interviews and questionnaires will be the techniques used to collect data both in the quantitative
and qualitative form. Interpretations will be made through statistical analysis of the collected
data which will help in providing a conclusion to all stakeholders of Omani construction firms as
to why variation in orders occur and what are the ways to prevent it.
Chapter One, Two, And Three 5
CHAPTER # 1: Introduction
Study Background
variability. There are clauses in contracts included by parties allowing them to make changes and
giving them the freedom of initiating variation in orders without changing the terms of the
contract (Gokulkarthi and Gowrishankar 2015). The scope of the contract is likely to change
even if it is planned carefully as the construction industry can be very volatile (Assbeihat and
Sweis 2015).
It is a common sight to see variations and conflicts between parties in during the course
of a construction project. Whether they decrease or increase the venture’s schedule or cost, any
deletion, addition or any other revision to the terms of the project is known as variation in orders
(Assbeihat and Sweis 2015). Alteration of building works, project programs, project aspects
caused by modifications of preexisting assumptions, requirements, conditions and design are all
known as changes or variations in orders with regards to a construction project (Gokulkarthi and
Gowrishankar 2015).
It has been revealed by several studies that variation in orders is one of the main reasons
for cost overruns in projects. A research focused on the adverse effects caused by variation in
orders revealed that every time variation in orders occurred in a construction project the project
had the issue of cost overrun as well. The studies also revealed that the variation of orders in
project almost always increased the cost and time period of the project (Kikwasi 2013).
Developing countries such as Oman need to effectively eliminate this issue from the construction
sector as the country cannot afford delays and cost overruns in the governmental projects with
any value being added to the project. Oman’s construction sector is considered as an integral
Chapter One, Two, And Three 6
sector with regards to Oman’s economy. Although, this sector has faced great issues since its
establishment such as variation in orders which have not allowed it to reach its full potential
Overall costs and the management aspects were mainly focused on in the previous studies related
to variation in orders. Two principles underlying the theory of waste reduction were revealed
through a study conducted by (Islam, Trigunarsyah, Hassanain, and Assaf 2015). Time
compression and reduction of variability were the two principals involved which led to
minimizing waste. Variation in orders is referred to when using variability when on the issue of
the construction sector. The counterpart of waste reduction can be identified as variation in
orders. Increasing of waste is imminent when variation in orders occurs as the variation will take
more time of the project as well as contribute to heavier cost and damages which could also lead
to cost overrun (Larsen, Shen, Lindhard, and Brunoe 2015). The fact that variation in orders is
common in construction project has been identified by researchers and investigators; however,
the adverse effects it has on construction projects have been completely ignored and overlooked.
However, many projects have been subjected to variation in orders and have been put on
hold due to reasons such as increase in resource cost, construction material shortage, lack of
skilled manpower and shortage of modern construction equipment, all of which are a great
problem to Oman’s construction sector. Hence, the primary goal of this thesis will be to study the
adverse impacts and causes of these undesired variations in orders and also provide
recommendations on how to effectively eliminate this plague from the construction industry of
Oman.
Chapter One, Two, And Three 7
Problem Statement
According to Han, Love, and Peña-Mora (2013), Variations are unavoidable in projects
related to construction. There are several factors like changes to the market conditions might
alter the requirements and needs of the client related to the projects, it can happen wither during
designing phase or construction phase. Also, novel technologies have an effect and transform the
project’s development. Above mentioned factors might cause an effect on the architectural
designs which will consequently root modifications to the engineering design that result in
variations. Moreover, mistakes in design caused by engineers and all through construction are
going to oblige changes to the construction projects. In addition, the price of the contract is
increased if there are variations found in the document of the contract and drawings. The
contractual disputes possibilities are further increased because of variations (Almahmoud, Doloi,
and Panuwatwanich 2012). On the whole, problems are caused by variations for everybody who
is concerned with the project. There could be several factors causing the variation relevant to the
building projects. The process of the construction could be affected by exceedingly altering
variables and random factors that can come from diverse sources. These sources containing those
factors include the construction parties’ performance, resources availability, and participation of
other parties, contractual relations, and ecological conditions. The result of these sources is that
the project’s construction might come across variations that can cause hindrance in the
Variation in orders has now become too common in the construction sector of Oman
which is adversely affecting the sector and the economy of the country. Changes made to
construction projects to alter or modify the scope of the construction project are known as
variation in orders. Variation in orders of construction projects can cause countless problems
Chapter One, Two, And Three 8
such as disputes, delays and conflicts between parties involved in the project. However, no
technique or method has been developed yet to prevent the issue of variation in orders from
negatively impacting construction projects of Oman. Although, studying the causes that directly
contribute to the occurring of variation in orders of construction projects, will help in developing
effective techniques to eliminate the problem. The variation in orders of a governmental project
can hinder the success of that project and identifying the causes of these variations can help in
effectively eliminating the problem while simultaneously improving the performance of the
construction project.
Research Objectives
Research Questions
Considering the study objectives, designing and answering the research questions
Oman currently has many different projects that are currently underway in the country.
The scope would be too extensive to handle considering the area to cover and the number of
projects to review. Hence, Muscat which is the capital of Oman will be focused on by this study
as the city has a number of public buildings currently under construction. Due to limitation of
schedule and budget for the study, this scope limitation arises. Those projects which have been
initiated since July 2017 and the structure being built is G+2, will be considered and reviewed
Since the factor of variation in orders has many adverse effects that can endanger a
project in the construction industry, its causes and what influences variation in orders is vital
information which needs to be identified, as well as how construction companies can minimize
the risk of variation in orders. The study will try to determine remedial processes that can
effectively eliminate the problem of variation in orders while supporting the governmental sector
of construction of Oman. This study aims to be a guideline and aims to be helpful to the Omani
government in assessing the damages of variation in orders as well as the causes which cause this
Ethical Considerations
Anonymity will be provided to all construction firms and participants of the study so that the
information provided by them does not have any effects on their personal lives as well as
encouraging honesty among participants. There will be no compensation or benefits given to the
Chapter One, Two, And Three 10
participants so that an uninfluenced and unbiased opinion can be obtained. The following aspects
Data capturing done through accurate and precise means, for good quality of data.
Chapter # 1: Introduction – First chapter of this research will comprise the research background,
statement of the problem, research objectives, and research questions, scope of the study,
Chapter # 2: Literature Review – The second chapter of this research explores earlier studies
concerning the effects of variation orders. In this chapter, the definition, origin, causes and effect
Chapter # 3: Research Methodology, Results and Findings – The third chapter will elaborate the
methods and tools to be used for the collection of data, and their results and findings.
Chapter # 4: Analysis - This chapter will analyse the results and findings of the gathered data.
be made upon the analysis of the data, relating them to the statement of the problem, and
research objectives.
Chapter One, Two, And Three 11
A mission undertaken to create a unique service, facility or product in the specified time, cost,
quality and resources, is known as construction project. However, most construction projects can
face countless issues such as delays, cost overruns and conflicts due to the issue of variation in
orders.
An inevitable issue in construction projects is the variation of the scope which may occur even
before the phase of the contract. The issue of variation is undeniable in construction projects
(Ndihokubwayo 2009). The possibility of variation in a construction project is always high due
to the large number of factors that can positively or negatively influence a project. Variation may
still inevitably occur despite the best efforts of administration, planning and implementation of
the contract, by all personnel participating in the project. If all participants don’t recognize the
immense problem of variation, the project may subsequently fail (Sweis et al. 2014). Variations
due to unexpected conditions faced in the construction field or variation due to change of scope
of work are the major variations that usually occur in all projects. Factors such as subsurface
conditions, terrain and existing utilities can cause two buildings with similar design and building
structure to be different in other factors. The contract administration process however, still
allows for the variation of orders.
Predictions towards the human behavior of all participants involved in the project,
towards the contract can also not be made. Changes in the mind or heart of participants involved
in contracts are another major cause of variation in construction projects. The clients or
contractors are usually the people that initiate the variation in orders (Ijaola and Iyagba 2012).
There were four main root causes of variation in orders revealed by a study focused on
construction projects (Alzahrani and Emsley 2013). Contractors, consultants, unspecified
“others” and clients were the four main root agents that caused variation in orders in construction
projects.
Chapter One, Two, And Three 12
Introduction
Creating a unique and desired structure in the allocated funds, time and area is known as
a construction project. However, in reality due to poor workmanship or poor use of funds and
other incidents cause projects to have cost overruns and also influence variation in the plan of the
It is a fact that variation in orders will undoubtedly occur in projects sometimes even
before the contract is signed. Variations are an inevitable reality for all construction projects
(Almahmoud et al 2012). During the course of a construction project, the only constant aspect is
that of variations. Variation will almost certainly occur, despite all the best efforts of the
well as the contract. If not considered and monitored by all personnel collectively, the variation
and variation in orders can greatly affect a project (Hanif et al 2016). Variations in the scope of
the project caused due to the unexpected conditions of the field of the project are the most
common type of variations in a construction project. Factors such as surface area, existing
utilities and terrain are very important as they can be the difference between two completely
same structures. In simpler terms the construction industry has accepted the major problem of
variation in orders as a process of the contract administration phase (Alzahrani and Emsley
2013).
Definition of variation order; contractual provisions relative to variation orders; type and
nature of variation orders; will all be included in this section as the literature review will contain
Definition of Variation
Variation cannot be defined by one single definition. The definition of variation is more
or less similar even though it differs in the various literatures on the issue. A definition of a
variation in terms of specific activities and actions will usually be included in any standard form
of building contract. Additions, omissions or alterations in materials, working hours, work space,
work etc. are known as variations, as defined by the building contract dictionary.
An instruction given by the engineer, who will result in variation of the work, is known
FIDIC (1998).
Assbeihat and Sweis (2015) described that variation in a construction project simple
meant any alterations or changes to the project that were not agreed upon or discussed in the
original contract. Variations not only change the type or effectiveness of work but also bring
Variation can be any one of these or all of the following as defined by (Larsen et al 2015):
The modification or alteration of the quantity, design or quality of the works, as referred
to or described in the contract bills and shown upon the contract drawings, and includes
the omission, substitution and addition of any work, the modification of the products,
utilities and materials to be used for the building of the project, are all included as
Modifications of instructions related with the work’s nature are also particularly named
Alteration to the contract or one of its clauses with the consent and agreement of both
parties after signing of the original contract, are also known as variation in orders in
The contract sum adjusted to accommodate all labours and utilities will also be included
Every change in the quantity or quality of the project from the originally spelled or
Every sort of divergence such as addition, omission or modification, other than mentioned in
contract concerning the contract specifications, drawings or bills of quantities are called
variations (Sunday 2010). According to the researchers the modification or alteration of the
quality of works, design, as mentioned in the contract drawings, specifications and/or are known
When the initial scope of the work will be altered due to change in any clauses of the
approve a variation order is only in the hands of the owner while the variation is implemented by
the contractor. It is explained by Koushki, Al‐Rashid and Kartam (2005) that the owner has the
authority to influence a variation in the contract by only subtracting and adding specific features
that are within the scope of the project. A supplementary agreement is required for variations
the contract, its works and its clauses are generally referred to when discussing variation in terms
of construction projects. For modification of the original contractual agreement, a variation order
is issued which is collectively complied with all the documents of the project (Ijaola and Iyagba
2012). Only with the agreement and consent of the owner will a variation order be issued to the
contractor.
actions and utilities of which the results cannot be predicted. It is argued that variation in orders
is inevitable in construction projects and cannot be avoided (Kikwasi 2013). Jawad et al (2009)
explained that the inclusion of variation clauses in modern construction contracts prove that no
construction project can be completed without variation. As the work progresses, no matter how
much planning has gone into the project there may be minor changes that will result in
substantial variations. The researchers also revealed that due to the limitations of time and
money for planning and the uniqueness of each project, variation occurs. The commonness of
variation orders in construction projects is argued by many investigators, researchers and authors
Rao and Joseph Camron (2014) explained that due to the complexity of construction
construction process or the plans itself. Reasons ranging from aesthetic, geological, weather
documents, product improvement, finance and design are all responsible for variation in orders
(Kikwasi 2013). Additionally, the behavior of the humans towards the contract and with honesty
can also not be predicted which can be another cause of variation. Change of heart or minds of
the parties involved may also result in a change of contract or even in extreme cases the
dissolution of the project. Contractors and clients both have the power to initiate variation in a
Given the volatile nature of the construction industry and its complex natures, it is
necessary to now include variation clauses in contracts. Since the prediction and visualization of
the end-product is very tough in this field, accommodations should be made for changes and
variations Measures for variations should be included in contracts for unseen conditions that may
arise with the gradual progression of the project (González, González, Molenaar, and Orozco
2013). Although, there are also disadvantages of these variation clauses as the architects may
keep a much lazier hand in finalizing the plans for the projects as they know that through
utilizing these variation clauses they can finalize the plans at any time of the project.
as the engineers and architects are much more free in their approach as they can leave critical
decisions until the last possible moment of the project. However, critics argue of another
disadvantage of variation clauses which make clients much more confused about the project and
embark prematurely only to find themselves backing out utilizing these clauses and wasting
much resources and time (Enshassi et al 2010.). Durability, optimality and functionality are
traditionally the three major requirements of a client from a project. Advice on optimum design
and use of resources to achieve these objectives, clients hire consultant and advisory teams.
Contractors on the other hand focus mainly on managing and effectively reducing the cost of a
Chapter One, Two, And Three 17
specific project. Agents and clients may be sources of higher construction costs which is
completely overseen and ignored. Using multiple variation orders can result in great cost
overruns in a project which can sometimes be forgotten by clients and their agents/consultants.
An example of this would be if the client wants the project to be completed at a specific date,
they may initiate the construction phase before the design phase is properly completed which
may result in design flaws and other discrepancies for the project in terms of the long run. As a
result, some works are put on hold and others are subject to abortion or demolition.
Aborted works are usually classified as wastage of resources which are typically billed to
A study by Skoyles and Skoyles (1987) revealed that lack of awareness is one of the
major reasons for costs of a project to increase. The fact that reduction of variation in orders can
reduce construction costs is not understood or believed by the construction industry. Ibbs (1997)
also proved this fact through a study which stated that changes will have many adverse effects on
variations” are the two types of variations. Emergent variation arises spontaneously and are not
originally intended or anticipated. On the other hand, anticipated variations are planned in
advance and occur as intended. Necessity is another basis on which variation can be reviewed
and studied. “Required variations “and “elective variations” can be the two types of variation
Chapter One, Two, And Three 18
according to this basis. A study by Ming et al. (2004) revealed that a required variation is where
there is no option but to make the variation; while an elective variation is where one may choose
whether or not to implement. There will be variations in a project before completion, no matter
how much planning goes into it. According to Ndihokubwayo (2009) both the reasons for their
effect and subsequent occurrences can be used as a basis to determine the types of variation that
occur in a construction project. (Arain & Pheng, 2005) classified variation orders into two,
Hanif et al (2016) described in their study that, an order issued to reduce cost, schedule,
and degree of difficulty in a project or improve the quality standard is known as a beneficial
variation order. As a result, this type of order will reduce the cost of the project; while also
eliminating unnecessary costs, which can better help the client. Value analysis is the main
purpose of initiating beneficial variation orders, to realize a balance between the functionality,
durability and cost aspects of a project for the satisfaction of the clients. An organized approach
used to identify and eliminate unnecessary costs which are costs that provide neither life, nor
quality, nor customer features, nor appearance, nor use, is known as value analysis (Sunday
2010).
The study by Ndihokubwayo (2009) also gave us the definition of detrimental variation
orders, which are orders that negatively impact the project’s performance and the client’s value.
Chapter One, Two, And Three 19
An example of a detrimental variation order is that if a project has gone into cost overruns and
the client is low on investment he will make a variation in utilities from high standards to lower
cheaper ones which will inevitably and adversely impact the project and its value. The client’s
Many considerable and adverse impacts may be had on projects due to variation in orders
which can occur due to a number of reasons, at any stage of the project and are very common in
construction projects in not only Oman but worldwide. Re-estimation of work statement, extra
demands of materials, labor, overtime, equipment and consecutive delays in project schedule
may all be caused due to critical variations in the project. Chances of a Project failing are very
high when variation occurs during the construction phase or contract signing phase as these
differences and variations can not only affect the schedule and cost of projects but also change
the perspective or the parties and clients involved. Marzouk and El-Rasas (2014) summarized
The employer is enabled to issue the contractor orders of variation in the project or the
contract through specific clauses included in the contract. The variations clause usually provides
the introduction of different materials, revised timing and sequence, and a change in shape of the
scheme. Usually a provision for altering and accommodating the completion date is provided
while a mechanism to evaluate the potential effects and damages of variation is also included. A
variation in the works of the project will be made quite difficult for an employer without these
specific clauses. Some difficulties in variations without these clauses may be contractor
problems in refusing to carry out the work or insisting for an advance payment. Payment in
excess of contract rates may be required for the extra work required to implement any type of
variation in a project.
The usual bases upon which contracts are drafted in the Omani construction industry are
taken from the Ministry of Urban Development and Construction (MUDC), Public Procurement
(PPA) and Federation Internationale Des Ingenieurs Conseils (FIDIC). The guidelines for
contract administration, they consequentially alter variation of construction works unless and
otherwise they are replaced or deleted by other words or sentences in the specific conditions of
Chapter One, Two, And Three 21
contract for a project and the duties and responsibilities of the parties involved in the contract are
Origin Agents
Client
From completion way back to the inception phase, the most critical and important
participant related to the project is the owner as the initiator of the project. Therefore, the
the owner’s decisions. The projects scope establishment, predicting future needs and
requirements of the project and ensuring top quality of work as well as material is all done by the
client/owner. There are various reasons due to which variation orders are initiated in a project by
the owner or clients. Rao and Joseph Camron (2014) revealed that a change in requirements was
the primary reason due to which clients were influenced to initiate variation in a project, for
example, the client may have a change of heart about the purpose of the structure being built.
There are two categories of clients which are those with little to no construction experience or
those who know the field and industry well. The design team can also be aided through a more
professional and direct idea of the design with an owner who has experience in the construction
industry. Continuous change during the critical phase of construction can be avoided through this
experienced approach. Since the clients have knowledge about the workings of the construction
industry they will be enabled to have a more elaborate and personal hand in the design process
Chapter One, Two, And Three 22
which will minimize chances of confusion and changes later on (Han, Love, and Peña-Mora
2013).
Consultant
Architects who would overlook the site of the project and would have a pivotal role in the
design of the structure were initially heavily relied on by inexperienced clients. In the modern
construction industry, rather than a single entity representing the needs of the client, there is a
greater need of a much more elaborate consultant team which can handle the design, construction
and workings of the project, exactly according to the clients need to minimize the chances of
variation in a project. Architects, designers, specialist engineers, project managers and cost
consultants are all included in this elaborate consultant team. Upon consent with the client and
on their behalf, the consultant team has full right to initiate variation orders in the construction
projects.
It is the duty of the consultant team to come up with effective and remedial solutions in
case of a conflict in any phase of the contract may it be construction, inception or even
discrepancies in the drawings or the paperwork of the project. If an ambiguous situation develops
during the project the contractor is not permitted to continue operations. Resources may be
wasted due to idle plant or labor due to the ambiguity of the consultant in implementing the
variation order. Han et al (2013) revealed that understanding of the overall goals and scope of the
project, offering specific suggestions when it makes sense and understanding the deliverables is
an important job for the consultant. Without a negative effect on the productivity of the project
Chapter One, Two, And Three 23
all these processes need to be carried out swiftly and without delay by the contractor. However,
the critical requests of a contractor may be ignored by the consultant due to a false sense of pride
Contractor
The origin of variation orders is usually through the contractors. González et al (2013)
advised in their study that all problems should be closely monitored by all participants of a
project. The accuracy of the information provided by the consultant should not be relied on by
any party involved with the project. Whenever a technical issue or problem occurs during the
project, it is the job of the contractor to convey the problem and influence a variation in the
project through the consultant. A study by Ndihokubwayo (2009) revealed that obvious
contractors after which they would communicate with the architect in fixing the problem, while
also agreeing on a price for the additional cost required to effect the change in the project and the
finally initiating the variation order. Whenever a technology is deemed unfit by a contractor to
complete the required efficiency in the project, he is permitted to implement other methods or
techniques based on his experience. The Omani industry has experienced discrepancies in
projects due to the design team which resulted in roof leakage in a school in which case the
contractor is required to be adaptive and experienced to handle such problems and discrepancies
Throughout the whole duration of the project from inception to occupancy, project
delivery systems are deployed to successfully achieve the purpose of the construction project
efficiently. Various contracting formats may be employed by these project delivery systems to
successfully deliver up to the standards of the target. An important decision which determines
how the construction project is to be built and designed has to be made at a very initial stage of
the project by the owner (Odabasi et al., 2003). Particular systems designed for the delivery of
the projects have been developed to cover specific requirements of owners according to the
changing and modernizing construction industry as well as the fluctuating prices of the market.
The advanced Integrated Project Delivery (IPD) and Design-Build (DB) are some of the modern
project delivery systems used in the current construction market. Due to the objective of the
study to provide a clear understanding of the concept, the Integrated Project Delivery (IPD)
system is mentioned in the study even though it has been used quite rarely in projects.
Design-Build (DB)
the oldest approach. An influential figure known as the master builder was instilled with the
entire responsibility of the project from design to construction in ancient times. This tradition
was followed up till recently in the late 19th century when science discovered the architect and
Apolot, and Tindiwensi 2013). In this type of delivery method, the contractor is usually assigned
with the job to hire suitable designers and constructers to effectively and successfully deliver the
project.
Chapter One, Two, And Three 25
Hanif et al (2016) revealed in a study that, a DB team is contracted by the owner, that
subcontracted entity with a team led by a designer, a single firm capable of performing both
construction and design, or a designer and a contractor. Usually the lead members of such teams
are contractors as they have the ability to sacrifice on corporate capital in completing projects.
The process when a proprietor employs a developer, that brings its own contractor and
designer partners, is also a slightly different variant of the same DB team structure formula
which is known as fee-paid developer. No matter in which way the team is designed, the
complete designing of the project usually based on a preliminary scope of design provided by the
owner, will be conducted by the DB team. A prescribed process will be used by the DB team
during a specific stage of the project in which they will determine their fee for the designing of
the project. All coordination between construction and design as well as the whole responsibility
of the construction of the project will be on the DB team once the project is initiated.
Not many projects have been contracted using this method as this method is relatively
new to the construction industry of Oman. A multiparty agreement among the prime players
which includes at least the designer, builder and owner and can go to the extent of the important
sub-contractors of the project, in the construction and design process is required by this
The processes to realize the completion of a construction project as well as its nature are
both very complex things. Hence, construction projects are commonplace for variations to take
place. Contract instructions are usually used to issue variation order. After the work is carried out
according to a variation in the working of a project, the dues used in this work to implement the
Oldapo (2007) reveals that how variation orders can be initiated through contractual
clauses. Every case involves oral instruction being transcribed into physical writing or physical
writing instructions in implementing variation orders in a project (Oldapo 2007; Sunday 2010;
Kikwasi 2013). Since oral instructions are not required to be followed by the contractor, hence
each and every oral instruction is needed to be confirmed in black and white by the contractor
or/and the consultant. The document must be confirmed by the consultant through a signature if
the document is drafted by the contractor. The works and operations will proceed as planned if
Alnuaimi et al. (2010) studied about the variations in the construction projects of Oman,
the study also investigated the variation causes, broke down their effect on the projects,
recognized helpful destinations and offered devices to relieve related issues. Concerning comes
about on the effect of the change arrange, it was presumed that the most vital impact of the
change was the "finish of undertaking delay" in the two cases, that is, include or dispense with.
The postponement on account of the total is very self-evident, and on account of an oversight,
Chapter One, Two, And Three 27
this is because of the customer's aim to utilize the sum put something aside for the extra work,
which at times should be finished. This impact will be added to the cases and question, which
The principle factors that reason delays in ventures in Oman, poor administration and
programming temporary workers illustrations fumble contract based workers postpone the
members Ruqaishi et al. (2015). The reason for this examination is to explore the reasons for
delays in development ventures at oil and gas refineries in Oman. Audit of the writing and of a
study led among the invested individuals of the oil and gas industry, it has been demonstrated
that the postponements in the undertaking were caused by the bureaucratic arrangement of the
administration and the span of the venture endorsement process, the poor outline group task of
ineptitude, insufficient offering rehearses and delays in execution. inner proprietor endorsement
strategies.
ought to be shown by the significance of each of them, utilizing the Likert size of 5 focuses.
Variables that reason delays in oil and gas operations are referenced in the demand: reasons
related with the customer, for reasons identified with contractual workers reasons identified with
the advisor, reasons related with the materials, causes and contract reasons identified with
business related gear, and outside causes. The polls were sent to 210 undertaking directors, a
specialist and a temporary worker in a few associations. The aggregate number of respondents
was around 59, which is 28%. In this examination, Cronbach's alpha used to confirm the
Chapter One, Two, And Three 28
legitimacy of the poll, Kruskai-Wallis used to test the invalid theory and the middle was utilized
As indicated by Al Khalil and Al-Ghafly (1999), the most imperative tasks that are
deferred from the temporary worker's perspective are those that have a place with the proprietor
of the organization, which are not willing to collaborate with the contractual worker, which
Implementation. the liquidation of temporary worker guarantees by the proprietor and the
inordinate administration in the administration of the proprietors. The reason for this
examination was to distinguish the fundamental driver of postponements out in the open
administration extends in Saudi Arabia, and particularly in the water supply and sanitation
extends that were completed in the Eastern Province and in the Province of Riyadh. KSA In this
investigation it was discovered that the three gatherings (customer, experts and contractual
workers) concur that the most vital reason is the absence of budgetary liquidity and the money
related challenges of the temporary worker, the troubles in getting licenses and the prerequisite
Another investigation led by El-Razek et al. (2008) means to recognize the primary driver
of deferrals in development extends in Egypt. Its goal is to distinguish the reality of the
explanations behind the deferrals in the tasks from the point of view of the expert, the customer
and the temporary worker, and also to analyze the union of these gatherings as far as the
significance of these reasons. The most critical reason was the financing of the contractual
worker amid development. This was exhibited as an understanding between all gatherings to the
venture this is the most critical explanation behind the deferral in Egypt. The following three
The principle purpose behind the deferral in lodging ventures in Jordan is the money
related troubles looked by the temporary worker, as on account of studies directed by Sweis et al.
(2008) The second most imperative purpose behind the deferral in this investigation is that there
are an excessive number of changes in the proprietor's request. Studies have additionally
demonstrated that atmosphere and changes in government directions are of minor significance.
The conclusion of the research had was that all the parties agreed on the importance of
the main delay causes. The owners rated cash flow problems during the construction as a very
important cause of delay and schedule of subcontractors, whereas the contractors rated more
importance to the contractual relationship. The A/E firms agreed on the reasons related to project
If effective strategies are used to counter the effect of variation orders, the adverse
impacts of this issue can be effectively decreased. It was suggested by Sweis et al (2014) that
effective planning during the design stage can substantially reduce chances of variation in a
project. For the ultimate benefit of the owner and successful completion of the project, effective
control systems should be employed by projects to control the impacts of variations. It was
concluded by Gokulkarthi and Gowrishankar (2015) that if all parties are involved and in
knowledge of all preliminary work of the project, the chances of variation can be effectively
minimized to almost zero. If designers address their workload before scoring new projects,
through effective designing the plague of addition and omissions can also be reduced but cannot
be completely eliminated (Doloi et al 2012). In Hence, in simpler words the designers should
Chapter One, Two, And Three 30
take a reasonable amount of workload which they can easily handle so that they can provide a
sound and effective design plan which does not require changes or alterations in the long run
which lead to variations. Recommendations to reduce variation orders were given by (Enshassi,
Arain and Al‐Raee 2010). Other researchers including Jawad et al (2009) also provided input to
these strategies which can effectively minimize the chances of variation orders occurring in
construction projects.
Several researchers have proposed different strategies to minimize variation orders, some
of them are mentioned below (Jawad et al 2009.; Doloi et al 2012; Islam et al 2015; Hanif et al
2016).
Before work is started on site, adequate awareness and planninng is required by all
A concluding, sound and decisive design and contract should be provided by the
consultant;
A clear breif of the scope of work should be provided by clients to the contractor;
Unpredictable and uncommon situations should also be prepared for by all parties;
During the design stage closer coordination is required with the consultant;
All parties involved should be proactive at all times with enhanced communications;
Budget should be planned carefully to accommodate all plans and scope of work;
Detail site investigation such as soil testing etc. should be done at an initial stage of the
project;
Land purchase c=should be completed before the offer of any sort of contract;
No changes to the specification should be made once the tender has been awarded; and
Knowledgeable and experienced architects and engineers employed for effective and
successful completion of the project with least amount of variations and effective levels
of productivity.
Chapter One, Two, And Three 32
Introduction
The different methods, tools and techniques used in conducting this study and collecting
data for it is identified by this methodology section, in the study. the organization of all of the
tasks of the study in a practical way is done by this methodology (Creswell and Clark 2007). A
plan of action for what techniques will be used for collecting information, how this information
will be applied to formulate effective rectifications and the different actions that can be taken to
solve the problems highlighted by the study are known as the methodology. Throughout the
For the identification of the method utilized to analyze the data and the type of data
required by the study will be easily done after a problem statement is formulated for the research
(Leahey 2007). The discrepancies and adverse impacts on the Omani construction industry due
to variation in orders is the main problem statement of this study. The identification of the causes
of these variations is vital in order to eliminate this plague from the construction industry of
Oman and especially in order to better the quality of construction projects in Oman.
Research Approach
All the factors of a research ranging from conclusions, values, validity to analysesare
greatly influenced by the techniques and methods used to collect the data for the study.
Understanding people's perceptions of the world and gaining insights is the main objective of the
qualitative approach, as viewed from a theoretical context. Both quantitative and qualitative
methods can be employed in the case of this research. The perception on variation orders, of the
stake holders in construction projects in Oman, influence the qualitative factor in this study.
Chapter One, Two, And Three 33
Specific public building projects in Muscat, Oman were chosen for the desk studies. Project
participants' opinion, the exploration of the physical works and the observation of site documents
Measurementsof the variables (such as: seldom and often, different and similar, low and
high) also make this study quantitative, as these measurements are key to understanding variation
orders and also for answering the formulated questions of the study.
For surveys, literature and desk study the triangulation technique was employed, in order
to improve the reliability and effectiveness of the findings of the study. The quantitative and
qualitative methods combined and strengthened with the literature review are the main function
of this technique.
A non-probability sampling technique was used due to the large extent of the study as
well as the nature of the data to be collected. The population of this study was selected by a
The projects which were G+3 and may or may not include a basement, which have
commenced since July 2017 and have been approximately 60 percent completed, were selected
in the area of Muscat, Oman, with the number of projects selected as the population for the study
totaling to thirty-two projects. The study will use data from all of the thirty-two projects.
Questionnaires were distributed to the other population of the study which involved high
officials in the Omani government, related to the construction sector such as project managers
and executives, clients and consumers and stakeholders. The amount of exposure to any of these
Data Collection
Several different techniques such as the desk study, interviews and questionnaire were
Desk Study
Monthly performance reports and project payments were used for the extraction of useful
data for the purposes of the problem statement presented by the study. Differences between
actual practices performed in construction projects and theories is made much easier to
differentiate through this. There was a worthy amount of data discovered for the study through
Interviews
face manner. Collection of data which may not be achievable through the process of a
questionnaire can be achieved through the much more intimate and personal technique of an
interview. Information on the impacts and causes of variation orders were obtained for the study
through interviews conducted with Senior Project Managers, Senior Executive Managers and
other executive personnel involved in the selected construction projects in the Muscat region of
Oman.
Questionnaire
An easy method used in the cases of gaining information from large number of
respondents is known as the questionnaire (Creswell and Clark 2007). The main purpose of the
questionnaire was to gain information on the current projects in the city of Muscat through
formulating questions based on the variables involved in all of these projects and then
Chapter One, Two, And Three 35
distributing this questionnaire throughout all high executives involved in the construction
industry of Oman. At the end of each section there was also space provided for the respondents
Part A: Four questions were involved in this section which were related to the role of the
respondent in the organization and the category or department the respondent was part of while
Part B: This section included opinion of the respondents towards the causes that influenced
variation orders in the public building projects of Muscat Oman. A total of thirty-eight responses
Part C: The purpose of this section was to get the opinion of the respondents on the adverse
impacts that variation orders may have on a construction project. A total of fifteen questions
Part D: This section was for the participants to provide their opinions on some effective methods
which can be used to minimize the variation orders and what the participants think can be done
to effectively eliminate this plague. This final section also included a total of fifteen questions.
Qualitative Methodology
Understanding people's perceptions of 'the world' and gaining insights is the main
understanding, opinions, views and beliefs of people are the main functions involved in the
qualitative approach (Östlund et al 2011). The perception on the impact of variation orders on
construction projects of Oman, of the major stakeholders in the construction industry of Oman is
Chapter One, Two, And Three 36
a major objective the study hoped to accomplish through the qualitative method of research.
Qualitative Data
Instead of the outcome or the product, the process is the main focus in the qualitative
approach of research. Through interaction with influential site personnel the research aimed to
understand and identify the influences and elements of every case in every particular project,
Qualitative data is collected at a first basis and is then grouped rather than being collected
inductive way (Creswell and Clark 2007). The opinion of stakeholders on the influential topics
of cost, time, consultants, contractors and project managers was achieved through open-ended
The qualitative approach has an influential factor which is vital to its existence, which is
known as meaning. Meaning is necessary for a qualitative research.The aim of the research
would be to understand the personal experience of all the participants in the different cases of the
Quantitative Methodology
Amounts and measurements (smaller and larger, seldom and often, different and similar,
less and more) of the events that the researcher studies and the characteristics displayed by the
people, is the main focus of the qualitative technique of researching. The following is included in
Quantitative data:
suggested by the name, is concerned with the data that could either be quantified or counted, and
typically utilises the information and data collected from experiments and surveys to study its
Quantitative approach in a research is generally taken to classify the factors which have
an influence on the outcome, or in order to test a explanation or a theory. The issue is typically
intensively covered by other scholars, and the objective is to establish researcher’s own theory
particularly when the participants or the respondents are in huge numbers. The researcher who is
carrying out the study can send questionnaires or data sheets in huge numbers to be filled by
different parties, in this case mostly consultants, contractors, clients, and project managers.
Moreover, the researcher does not need to keep an eye on the completion of the survey or
questionnaire because of the huge quantity of surveys or questionnaire sent out, the surveys or
Chapter One, Two, And Three 38
the questionnaire which are filled and completed would generally be sufficient enough sample
(which precisely reflects the sample population) for the study purpose. Though, because of the
limitations of the data sheets or survey questions, this research approach doesn’t offer depth into
For instance, respondents in this research are asked to specify the causes and effects of
variation orders utilizing a scale which show important (5) to unimportant (1). The quantitative
data will be collected through the questionnaire which will able to calculate how many
respondents gave all the answers, but knowing how many established a cause unimportant
The following table summarises the disadvantages and advantages of the two above
The required data for this research should meet the requirements mentioned below:
Chapter One, Two, And Three 39
With the aim to establish causes of variation orders and its effects on the government
numbers.
Validity
other type of version is referred to as validity (Leahey 2007). Concerning the procedures of
measure (Creswell and Clark 2007). Indeed, this research study is investigating a hypothesised
established, inferences are made regarding the sample population and, possibly, a range of
conditions in which the established relationship might be applied further than those of thespecific
Thus, validity is hypothesized on the postulation that issue under study could be captured
or measured, and seeks out to verify the accuracy and truth of the captured and measured data,
and also the accuracy and truth of conclusions or findings established from the collected data
(Leahey 2007).
Chapter One, Two, And Three 40
Reliability
Reliability is usually supposed on the view that there is some sort of standardization or
uniformity in the data that is being measured, and that the selected research method must
constantly capture the topic that is being explored (Leahey 2007). A research instrument is
verified as reliable only if it gives the similar results on recurring trials. A tool is considered as
reliable only if it is stable and consistent, and, therefore, accurate and predictable.
Phone discussions: making phone calls were critical ways for communication as they authorized
Short Message Service: the upside of utilizing the SMS was that a specialist could send messages
to the respondents' cell phones in the event that their calls were unanswered or inaccessible.
Messages: this sort of correspondence turned out to be productive as the analyst could make
Online Questionnaire: After designing the questionnaire on Google Docs, link was sent tot he
participants of research to complete the questionnaire. This method saved a lot of time and
travelling.
Chapter One, Two, And Three 41
The required data is collected regarding a variety of construction projects, which is going
to be analysed after this chapter with the intention of satisfying the objectives of this research.
Previous literature was reviewed in order to find relationship amongst causes and effects
of variation orders.
Several research methodologies were considered and a then a research approach was
A sample size of 100 was collected with the applicable information to justify the research
questions.
The result of the data analysed will be compared with the findings of the previous
literature.
References
Al-Khalil; Mohammed I. and Al-Ghafly; Mohammed A., (1999). Important Causes of delay in
Almahmoud, E.S., Doloi, H.K. and Panuwatwanich, K., 2012. Linking project health to project
Alnuaimi; Ali S., Ph.D.; Ramzi A. Taha, Ph.D.; Mohammed Al Mohsin, Ph.D; and Ali S. Al-
Harthi, M.Sc., 2010. Causes, Effects, Benefit, and Remedies of Change Orders on Public
Alzahrani, J.I. and Emsley, M.W., 2013. The impact of contractors’ attributes on construction
Assbeihat, J.M. and Sweis, G.J., 2015. Factors Affecting Change Orders In Public Construction
Creswell, J.W. and Clark, V.L.P., 2007. Designing and conducting mixed methods research.
Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in
pp.479-489.
Chapter One, Two, And Three 43
Enshassi, A., Arain, F. and Al‐Raee, S., 2010.Causes of variation orders in construction projects
in the Gaza Strip. Journal of Civil Engineering and Management, 16(4), pp.540-551.
Construction Projects.
González, P., González, V., Molenaar, K. and Orozco, F., 2013.Analysis of causes of delay and
Han, S., Love, P. and Peña-Mora, F., 2013.A system dynamics model for assessing the impacts
pp.2044-2053.
Hanif, H., Khurshid, M.B., Lindhard, S.M. and Aslam, Z., 2016. Impact of Variation Orders on
Ijaola, I.A. and Iyagba, R.O., 2012. A comparative study of causes of change orders in public
construction project in Nigeria and Oman. Journal of Emerging Trends in Economics and
Islam, M.S., Trigunarsyah, B., Hassanain, M. and Assaf, S., 2015, October.Causes of delay in
Jawad, R.S., Abdulkader, R. and Ali, A.A.A., 2009. Variation orders in construction
Kikwasi, G., 2013, February.Causes and effects of delays and disruptions in construction
Koushki, P.A., Al‐Rashid, K. and Kartam, N., 2005. Delays and cost increases in the
Larsen, J.K., Shen, G.Q., Lindhard, S.M. and Brunoe, T.D., 2015. Factors affecting schedule
delay, cost overrun, and quality level in public construction projects. Journal of
Leahey, E., 2007. Convergence and confidentiality? Limits to the implementation of mixed
Marzouk, M.M. and El-Rasas, T.I., 2014.Analyzing delay causes in Egyptian construction
Ndihokubwayo, R., 2009. Variation Orders on Construction Projects: Value adding or Waste?
Oladapo, A.A., 2007. A quantitative assessment of the cost and time impact of variation orders
Östlund, U., Kidd, L., Wengström, Y. and Rowa-Dewar, N., 2011. Combining qualitative and
Rao, P.B. and Joseph Camron, C., 2014. Causes of Delays in Construction Projects-A case
Ruqaishi; Mohammed and Bashir; Hamdi A., (2015). Causes of Delay in Construction Projects
in the Oil and Gas Industry in Gulf Cooperation Council Countries: A Case Study.
Journal of construction Engineering and Management [online]. Vol. 31(3), pp. 831-841.
Sunday, O.A., 2010, September. Impact of variation orders on public construction projects.
Sweis, R.J., Bisharat, S.M., Bisharat, L. and Sweis, G., 2014. Factors Affecting Contractor
Sweis; G., Sweis; R., Hammad; A. Abu, Shboul; A., (2008). Delays in construction Projects: The