Professional Documents
Culture Documents
CDT
Exam
Study
Workbook To be used with the Project Delivery Practice Guide
Answers
The information in this Study Workbook is only about the “Subject Matter Areas” listed in the
Candidate Handbook. It does not cover the entire Project Delivery Practice Guide.
It should also be noted that even though this Study Workbook includes True-False questions, the
CDT Examination is all Multiple Choice questions. The True-False questions are included for the
purpose of helping the candidate learn the information.
Acknowledgements
This Study Workbook would not have been possible without the dedicated efforts of the 2012 CSI
Education Committee consisting of the following members:
June 1, 2012
Introduction | Page 1
This page intentionally blank
Introduction | Page 2
STUDY MODULE NO. 1
Introduction to Project Delivery
Knowledge Item No. 1-3: Stages of facility life cycle with associated activities and documents.
Understand the definitions of the stages of the life cycle of a facility, the activities and
documents produced during each stage, and the team member responsible for each.
Knowledge Item No. 1-4: Project stages with associated activities and documents.
Understand the factors that make each project unique, the attributes that the documents used
for projects describe, and the basic cost that projects include.
Understand the activities associated with each of these phases, as well as the roles of the
participants and the documents produced.
Reading List
Knowledge Item No. 1-1: Job roles and responsibilities of the four project teams.
PDPG 2.1 through 2.5
Knowledge Item No. 1-3: Stages of facility life cycle with associated activities and documents.
PDPG 3.4
Knowledge Item No. 1-4: Project stages with associated activities and documents.
PDPG 8.8
Key Terms
Knowledge Item No. 1-1: Job roles and responsibilities of the four project teams.
Owner Team. Establishes the design requirements, budget, and time constraints for the
project. As the ultimate purchaser of installed products, the owner may have significant input
on equipment and finish selections and may require information on product operation,
maintenance, and warranties. (PDPG 2.2)
Contractor Team. Agrees to construct the facility for the owner with the contractor’s
management and labor forces and services of subcontractors. The contractor contracts with
the owner to successfully complete the project in accordance with the documents prepared by
the design team. (PDPG 2.4)
Instruments of Service. The work product of architects and engineers that includes a seal
attached to the documents. (PDPG 2.3)
Partnering. A concept of “team work” or “team building” that attempts to make all team
members partners in the process of executing the work and completing the facility. The
ultimate goal is a project constructed on time, on budget, and meeting the owner’s
requirements. (PDPG 2.7)
Team Approach. Cumulative and coordinated efforts of owner, A/E, and contractor, during
design and construction, are the means that produce the end: the completed project. The
success of the project is dependent on how well the participants understand their roles and
responsibilities and those of others, how well they carry out those roles, and how they meet
the expectations of other participants. (PDPG 13.2.1)
Knowledge Item No. 1-3: Stages of facility life cycle with associated activities and documents.
Facility Life Cycle. The life cycle of a facility, from concept through construction to use and
eventual deconstruction (demolition), follows a number of stages:
Project conception
Project delivery methods
Design
Construction documents
Bidding/negotiating/purchasing (procurement)
Construction
Facility management
(PDPG 3.4)
Project Conception. Stage in the facility life cycle in which an owner’s needs and
requirements are identified, preliminary studies are performed, a site is selected, and a
preliminary budget and schedule are established. (PDPG 3.4.1)
Project Delivery Methods. Stage in the facility life cycle when owner determines the project
delivery method to be used:
Design-bid-build
Design-negotiate-build
Design-build
Design. Stage in the facility life cycle when A/E transforms the owner’s program into
graphic and written documents that can be used to produce bidding and pricing documents in
a subsequent stage. The two commonly recognized phases of design are schematic design and
design development. (PDPG 3.4.3)
Construction Documents . Stage in the facility life cycle where written and graphic
documents prepared or assembled by A/E from owner-approved design development
documents for communicating the project design for construction and administering the
contract. Construction documents consists of two major types of documents: procurement
documents and contract documents. During this stage, the A/E prepares documents, that will
be used to file for permits and approvals from AHJ’s and to obtain prices upon which a bid or
negotiated contract can be based. (PDPG 3.4.4 and 3.4.6)
Construction. Stage in the facility life cycle where owner’s project is constructed. Involves
cost estimating, procurement, coordination of construction activities, and the physical
construction. Much construction is performed by specialists in many different trades. These
specialists are usually employed by the contractor as subcontractors. (PDPG 3.4.6)
Facility Management. The longest stage in the facility life cycle when the facility is
accepted and put into use by the owner for its intended purpose. (PDPG 3.4.7)
Knowledge Item No. 1-4: Project stages with associated activities and documents
Facility. The completed project is a facility, which is a constructed entity or space to perform
a certain function. (PDPG 1.5)
Quality. The factors of extent, time, and cost will establish the quality of the project and its
component parts. (PDPG 7.1.2.4)
Extent. The magnitude, form, function, and complexity of the project will have a direct
bearing on the project delivery method and the number of participants. Generally, the greater
the magnitude of the project, the greater the number of participants, the more the construction
process is compounded. (PDPG 7.1.4)
Cost. Number of different methods are used for determining and stating amounts of cost or
compensation within agreements. When contract is bid or negotiated, the basis of payment
that will be used in the contract is clearly stated in bidding documents or request for proposal.
When the contract is executed the bid or negotiated basis of payment is included in the
contract. (PDPG 7.1.6)
Design Stage. The AIA defines design as occurring in three distinct phases: schematic
design, design development, and construction documents. EJCDC defines design in two
phases: preliminary design and final design phase, which includes construction documents.
CSI defines design as having two phases: schematic and design development phases. (PDPG
3.4.3)
Schematic Design. Site plan and area relationships may be defined, the general size, shape,
and massing of building elements are determined, elevations and exterior finishes established,
and conceptual design criteria for structural, mechanical, and electrical systems identified.
Written documents usually consist of preliminary project descriptions and preliminary cost
projections. (PDPG 8.8.3)
Design Development . Follows the owner’s acceptance of the schematic stage and any
necessary program or budget adjustments. Emphasis shifts from overall relationships and
functions to more technical issues of constructability and integration of systems and
components. Aesthetic concerns move from massing and arrangement to materials, surfaces,
and details. Design development documents fix and describe the size and character of the
entire project, including architectural, structural, mechanical, and electrical systems.
Documentation includes more precise and specific drawings, physical or electronic models,
and outline specifications. (PDPG 8.8.4)
Master Planning . The design of multiple projects with integrated and complementary
functions on the same site or contiguous sites to fulfill the requirements of an extensive
program. (PDPG 8.8.1.1)
Prototype Design. Single design developed for multiple projects on different sites.
Establishes a consistent project identity and purpose that is readily identified by facility users.
Each project is site adapted to a particular site and requirements of the authorities having
jurisdiction. Can enhance the efficiency of design, construction, and facility management
stages of the project life cycle. (PDPG 8.8.1.2)
Conceptual Design. Concepts are mental representations of an abstract object that are
creatively given shape, form, and meaning. The creative design process is similar to the
process of solving problems and starts with an original idea called a concept. Documentation
includes drawings of basic information, physical or electronic models, and narrative
descriptions. (PDPG 8.8.2)
Integrated Project Delivery (IPD) . The progression of project delivery methods has
evolved into the integrated project delivery method. In its simplest form, this project delivery
method is reducible into two groups of individuals and companies: those who decide, design,
and determine, and those who supply, construct, and install. The operative component in
integrated project delivery is the integration of these two broad activities to capitalize on the
unique contributions each individual and company can make to the delivery process. A first
Four C’s of Communication. The four C’s for effective communication are: CLEAR, use
proper grammar and simple sentences construction to avoid ambiguity; CONCISE, eliminate
unnecessary words, but at the expense of clarity, correctness, or completion; CORRECT,
Present information accurately and precisely; COMPLETE, do not leave out important
information. (PDPG 11.3.5)
Specifications. Define the quality requirements for products, materials, and workmanship
upon which the contract is based and requirements for administration and performance of the
project. Generally written for each subject as sections and organized by divisions under
MasterFormat® or categories in UniFormatTM. (PDPG 11.1.4)
GreenFormat. Web based tool, developed by CSI that allows manufacturers to accurately
report product sustainability properties. Provides designers, constructors, and building
operators with basic information to help meet “green” requirements. (www. greenformat.com)
Knowledge Synopsis
Knowledge Item No. 1-1: Job roles and responsibilities of the four project teams.
2.1 Introduction
The design and construction of a project that, upon completion, becomes a facility,
requires the merging of the collective needs, ideas, talents, knowledge, and services of a
widely diverse group of individuals and businesses that provide specialized services.
Owners frequently require the services of others to assist with their role and
responsibilities:
• Financial institutions
• Attorneys
• Insurance companies
• Real estate agents
• Appraisers
• Marketing companies
2.2.4.1 Surveyors
2.2.4.2 Environmental Engineers
2.2.4.3 Geotechnical Engineers
2.2.4.4 Hazardous Materials and Abatement Consultants
2.2.4.5 Traffic Engineers
2.2.4.6 Sustainability Consultants
2.2.4.7 Wetlands Biologists
2.2.4.8 Wildlife Biologists
2.2.4.9 Design Engineers
2.2.4.10 Testing and Inspection Agencies
2.2.4.11 Commissioning Authority
2.2.5 Occupants
The owner arranges and contracts for the various public and regulated private
utility providers that will furnish electrical power, natural gas, domestic water,
sewerage removal, stormwater control, and communications services to the
completed facility.
The design team works with the owner to deliver a facility meeting the owner’s vision
and requirements. The process of transforming the owner’s vision and requirements, as
expressed in the decisions and conclusions composing the project conception, from
original concepts, visions, and ideas to the documentation required for construction,
requires various disciplines of aesthetic and technical design services.
Using specialized design skills, the design team is usually responsible for the following
services:
Traditional design services typically include the following broadly defined design
services that can be used with any of the project delivery methods:
The design team is universally referred to as the A/E (architect/engineer). The terms
architect, engineer, and consultant reflect the education and specialized training,
governmental licensure, and sphere of design in which they practice.
Construction services may be combined with design services or may be obtained during
or after the design process.
Project management services may be utilized early in the project delivery process to
complement design services. These management services may simply involve
establishing construction costs of the design or may be more formally established as
project management or construction management.
2.4.1 Contractor
The term contractor is used universally to refer to the entity that constructs a
facility. The contractor uses their management abilities to gather the various
labor forces, subcontractors, and material, product, and equipment suppliers
required to construct the facility.
2.4.2 Subcontractor
The supplier team is composed of a wide variety of companies that are part of the
delivery method simply because they will furnish the materials and products for the
facility to be constructed.
A project team that functions together and works toward mutual goals can be greatly
improved by the concepts of partnering and collaboration. The success of any project is
Knowledge Item No. 1-3: Stages of facility life cycle with associated activities and documents.
The life cycle of a facility, from concept through construction, to use and eventual
deconstruction (demolition), follows a number of stages. Arrange the following stages in
the correct sequential order:
The duration of each stage depends on the extent of the project, the number of
participants involved, and the efficiency the participants apply to their respective
contractual responsibilities.
At some point in the process, the owner needs to determine the project delivery
method to be used. Factors affecting the decision include the owner’s
____________________, ____________________, and __________; the
____________________ __________; and the ____________________
____________________.
3.4.3 Design
Primary participants:
Deliverables in each phase include graphic and written design documents and
estimates of project cost.
Deliverables include:
Deliverables include:
Acceptance of the contractor’s bid or negotiated sum and other conditions will
result in award of a contract and commencement of work.
3.4.6 Construction
Knowledge Item No. 1-4: Project stages with associated activities and documents.
All projects proceed through multiple stages from conception to facility management.
Design is defined as having two phases: schematic design and design development. At
the conclusion of each design phase, the A/E will deliver design documents that express
the progress of the design and updated cost estimates to ensure that the design is
consistent with the owner’s ____________________ ____________________ and
____________________.
8.8.1.1 Master Planning. The design of multiple projects with integrated and
complementary functions on the same site or contiguous sites to fulfill
the requirements of an extensive program.
8.8.1.2 Prototype Design. A single design developed for multiple projects on
different sites that establish a consistent project identity and purpose
that are readily identifiable by facility users.
The design development phase follows approval of the schematic design and
any necessary program or budget adjustments. Documents fix and describe the
size and character of the entire project, including architectural, structural,
mechanical, and electrical systems.
A. Design
B. Facility management
C. Project permitting
D. Project conception
E. Procurement
F. Project delivery
G. Construction
H. Construction documents
3. True or False: The A/E is required to determine the project delivery method.
4. True or False: Sustainability consultants can only be retained by the design team.
5. True or False: It is not uncommon for a governing agency to dictate the design and
construction process of any of the project delivery methods by their own rules or regulations.
6. The design stage of a project includes all of the following except which one?
A. Design development
B. Schematic design
C. Feasibility studies
D. Outline specifications
7. True or False: The primary construction project team components are the Owner Team,
Design Team, Contractor Team, Supplier Team, and the authorities having jurisdiction.
8. True or False: AIA Design Phases include schematic design, design development, and
construction documents.
A. Increased productivity
B. Reduced project costs
C. Earlier project completion
D. Fewer meetings
Knowledge Item No. 2-2: Feasibility and impact studies and facility evaluations .
Understand the definitions and purposes of feasibility studies, impact studies, physical
evaluations, site studies, and studies of other issues that may influence a project.
Reading List
Knowledge Item No. 2-1: Programming, planning, and pre-design.
PDPG 6.2
Knowledge Item No. 2-2: Feasibility and impact studies and facility evaluations.
PDPG 3.4.1.1 and 6.3
Key Terms
Knowledge Item No. 2-1: Programming, planning, and pre-design.
Programming. During project conception stage, starts with defining the problem and
concludes with requirements for developing solutions. (PDPG 6.2)
Facility Programming. A two-phase process that proceeds from general to particulars and is
associated with the schematic design and design development phases of design, attributed to
William M Pena’s book, Problem Solving: An Architectural Programming Primer –
schematic programming and program development. Problem Seeking indicates that there are
four considerations that need to be identified:
Function
Form
Economy
Time
Problem Solving also lists five consecutive steps to programming progress:
Establish Goals – What does the Owner want to achieve?
Collect and analyze facts – What is known?
Uncover and test concepts – How are goals achieved?
Determine Needs – What is needed and how much will it cost?
State the Problem – What is the direction the design should take?
(PDPG 6.5)
Knowledge Item No. 2.2: Feasibility and impact studies and facility evaluations.
Due Diligence Investigations. Owner may conduct several studies to determine the potential
project’s viability. These investigations are carried out by the owner, independently or in
consultation with a development consultant and other specialists, to identify the conditions
and influences that will shape the project concept and clarify the owner’s values and goals.
Whether purchasing or leasing real estate, the owner must take care to perform due-diligence
Financial Studies. Evaluates the various aspects of an owner’s vision. If the vision is not
financially viable, the project will probably not be feasible with modification. Includes
evaluating the following:
Owner’s financial condition
Life cycle cost
Value of existing facilities
Available funding
Timing
(PDPG 6.3.1)
Community Impact Studies. A project is directly related to the impact it will have on the
project site and surrounding community. A proposed development or project may affect
public facilities and utilities, which may need to be modified to accommodate the impact of
the project. Includes:
Operations
Relocation
Environmental impact
Public facilities and utilities impact
Economic impact
(PDPG 6.3.2)
Site Studies. Key activity of the project conception stage. A site study evaluates the
likelihood that a particular location will be able to support the facility throughout its cycle. A
thorough site study is a series of coordinated investigations by qualified participants to
determine a site’s suitability for its intended purposes. Site studies include:
Environmental issues
Hazardous material surveys
Land use restrictions
Subsurface conditions
Archeological surveys
Foreign governments
Surrounding conditions
(PDPG 6.3.3)
Other Governments. Some projects may address the implications of planning projects on
sites governed by other governments. This may involve Native American tribes or foreign
embassies within our country. (PDPG 6.3.3.5)
Existing Facility Evaluations. If an existing facility will be part of the project concept, an
investigation will help determine its suitability for adaption to the owner’s needs and goals.
Such an evaluation may include the following evaluations:
Functional
Facility systems
Structural
Environmental
(PDPG 6.3.4)
Site Selection. The site should be located in a setting that is conductive, suitable, and fitting
to the purpose for the facility. Choosing a site is an important consideration for a facility
because for as long as the facility exists, it will be on one site and in one neighborhood or
community. (PDPG 6.4)
Zoning. Defines the permitted and conditional uses of land by regulating the type and size of
a facility, its use, its function, and the density of improvements. (PDPG 6.4.2)
Project Budget. Includes projections of all the costs associated with the entire project. A
project budget may consider initial construction cost only or may include projected cost of
operation. Including the operations and maintenance costs in a project budget will provide a
better understanding of the total life cycle costs. (PDPG 6.7.2)
Construction Budget . Accounts for the biggest portion of the project budget. Includes the
cost of bonds, insurance, products and systems, and labor both to construct the facility and to
Project Schedule. A well-prepared project schedule can make the difference between a
project that progresses smoothly and one that is characterized by delays and other problems.
It serves as a road map, plotting out a logical succession of steps, from which a series of
smaller, more specific tasks emanate. It also serves as a script showing interactions of key
project participants. (PDPG 6.8)
Gantt Chart . The simplest form of a schedule which is a type of bar chart. (PDPG 7.1.5.2)
Critical Path Method Schedule. Determines activities that are dependent upon each other
and the longest path for completion of those activities. In this approach, the schedule is
dictated by the activities that are on the critical path to the completion date of the project. The
goal is to establish the sequence of activities that constitute the shortest path through all of the
activities. (PDPG 6.8)
Knowledge Synopsis
Knowledge Item No. 2-1: Programming, planning, and pre-design.
Project conception is the stage of the facility life cycle in which the project is planned and
is characterized by the following activities:
• A clear understanding of project values and goals, which become the basis of many
decisions
• Specialists in concept development who can prioritize the values and goals, integrate
them with the facts provided by preliminary studies, and make recommendations
6.3 While envisioning the future facility as the beginning of a project, the owner may
conduct a series of due diligence investigations to determine its viability.
Financial studies should provide the owner with a clear understanding of the
financial restrictions affecting the project’s size and material requirements by
evaluating the following:
The feasibility of a project is directly related to the impact it will have on the
project site and surrounding community. Community impact studies address:
6.3.3.2 Hazardous Material Surveys. Structures built before 1970 may contain
mate reveal the materials that are presently considered health hazards
3.4.1.3 Site Selection. Site selection and analysis may include specific studies
of environmental impact, zoning restrictions, governmental regulations,
pedestrian or vehicular accessibility, available utilities, and soil
conditions.
6.4.1 Location
• Natural features
1. The buyer submits an offer. The conditions of the offer are based on
receiving information from an evaluation of the site or facility that satisfies
the buyer’s requirements.
2. On the basis of receiving a favorable evaluation that favors the buyer’s
requirements, the purchase is completed.
6.5 The book Problem Seeking, An Architectural Programming Primer defines programming
as a process that starts with defining a problem and concludes with the requirements for
developing a solution to the problem.
Problem Seeking proposes that facility programming is a two-phase process that proceeds
from general to particulars and is associated with the following:
_____ Form B. What will the facility look like and feel like?
Problem Seeking indicates there are five consecutive steps to the programming process;
arrange the following steps in the correct sequential order:
State the problem (What is the direction the design should take?)
A/Es need to know and understand the owner’s goals and values, in addition to
the basic project needs. The goals need to be quantifiable and measurable.
Every project is a combination of various needs and influences, including:
The facility program document must be a clear, simple statement of the problem
and include organized and edited information, free from irrelevance. The
owner’s values and goals statements should be expressed in quantitative and
qualitative terms that describe the essence and uniqueness of the facility.
Once the functional needs (the program) have been established by the owner and
the preliminary studies have been collected and analyzed, a project budget can
be formulated.
The project schedule developed during project conception differs from the construction
schedule. The construction schedule is just one part of the overall project schedule.
Refer to 7.1.5.2 under Knowledge Item No. 3-3 in Study Module No. 3.
8.7 Sustainability
10.5.4.4 Sustainability
A. Relocation
B. Commissioning
C. Due diligence studies
D. Design fees
E. Topographical surveys
2. True or False: There is no difference between the construction schedule and the project
schedule.
3. All of the following activities are associated with the project conception stage except which
one?
A. Predesign
B. Planning
C. Commissioning
D. Programming
5. True or False: As a project proceeds through the project delivery process (time), the ability to
influence the cost is high at the beginning, but decreases as the project advances through the
various stages.
A. Unit price
B. Cost per measured unit
C. Systems
D. Component cost
7. True or False: The EPA’s definition of a green building covers all three primary aspects of
the built environment, siting, design and construction.
8. Green buildings are designed to reduce the overall impact of the built environment on human
health and the natural environment by:
A. Environmental issues
B. Hazardous material
C. Subsurface conditions
D. Archeological Surveys
E. Other governments (Native Peoples)
F. A site survey
G. A, C, D, and E
H. All of the above except F
I. All of the above
Project Delivery
Knowledge Item No. 3-2: Tripartite relationships among owner, contractor, and A/E.
Understand tripartite relationship for a traditional bid or negotiated contract.
Knowledge Item No. 3-3: Factors affecting project delivery (e.g., extent, time, and cost).
Understand that extent, time, and cost are the primary factors that establish the quality of a
project and its component parts.
Understand the definitions of terms relating to extent, time, and cost and the basic
considerations that go into the decision-making process relating to each.
Understand the effects of decisions on the documentation process.
Reading List
Knowledge Item No. 3-1: Design and construction services and documentation required.
PDPG 2.3 and 2.4
Knowledge Item No. 3-2: Tripartite relationships among owner, contractor, and A/E.
PDPG 5.2
Knowledge Item No. 3-3: Factors affecting project delivery (e.g., extent, time, and cost).
PDPG 7.1
Key Terms
Knowledge Item No. 3-1: Design and construction services and documentation required.
Design Team. Refer to Knowledge Item No. 1-1 in Study Module No. 1.
Contractor Team. Refer to Knowledge Item No. 1-1 in Study Module No. 1.
Knowledge Item No. 3-2: Tripartite relationships among owner, contractor, and A/E.
.
Tripartite Relationship. Relationship among the owner, contractor, and A/E. This
relationship is created by obligations to third parties to the contract. For example, the owner-
A/E agreement may require certain duties of the A/E acting on behalf of the owner. The
contractor has the right to rely on the proper performance of these duties. The A/E, similarly,
relies on the contractor to perform certain duties identified in the owner-contractor agreement,
even though the A/E is not a party to that contract. The A/E relationship to the contractor in
the owner-contractor agreement is a third-party relationship. These third-party relationships
create the third side of the triangle in the construction process. (PDPG 5.2)
Knowledge Item No. 3-3: Factors affecting project delivery (e.g., extent, time, and cost).
Project Delivery. Refer to Knowledge Item No. 1-3 in Study Module No. 1.
Owner’s Capability. The success of the delivery of a project depends heavily on the owner
having a good understanding of the many decisions required to direct and guide the design
and construction process. Owners experienced with one or more of the project delivery
methods will be in a position to effectively direct, administer, and manage the complex
delivery process. Owners with little or no experience will either place their trust and
protection of their interests in the design and construction professionals that participate in the
delivery process, or will retain a construction management firm to assist with directing and
administering the various stages, phases, and individual activities. (PDPG 7.1.3)
Extent of Work. Refer to Knowledge Item No. 1-3 in Study Module No. 1.
Sequencing. Performing work, one portion prior to another portion, in a predetermined order.
(PDPG 7.1.5.1 and 13.10.4)
Fast Track. Process of overlapping activities to permit portions of construction to start prior
to completion of the overall design. (PDPG 7.1.5.3)
Stipulated (Lump) Sum. An agreed amount for a defined extent of work based upon
complete or partially complete construction documents. This is the simplest method of stating
the basis of payment wherein a single amount is agreed upon for completion of entire
contract. (PDPG 7.1.6.1)
Unit Price. Payment is made at a stipulated sum multiplied by the quantity completed. Unit
prices are used in cases where the exact extent or quantity of work cannot be calculated
accurately or otherwise determined in advance of actually performing the work. Commonly
used for civil engineering projects where the types of work, such as unstable soil or rock
excavation, can be identified during the design of the project but the actual quantities of such
work items can be only be estimated. (PDPG 7.1.6.2)
Cost-Plus Fee. Usually used with negotiated contracts. The contract calls for compensation
for the actual cost of direct expenses, plus an additional fee for overhead and profit. The fee
is usually a percentage of the direct expenses, but also may be a fixed-fee amount. (PDPG
7.1.6.3)
Cost-Plus Fee with Guaranteed Maximum Price (GMP). Added to the cost-plus fee, a
guaranteed maximum price may be negotiated when project design is in the early design stage
such as design development and may be only sufficiently complete to allow for adequate
project definition. A contingency amount in the project budget should be included to allow
for the inevitable changes and a resulting increase to the guaranteed maximum price. (PDPG
7.1.6.3)
Penalty/Bonus Clause. A clause providing a penalty of a daily amount for not completing
the work in the allocated time or by the agreed-upon date can be included in the contract.
However if there is penalty clause in the contract, it should be accompanied by language that
pays the contractor a bonus/incentive amount for early completion. Usually, the per-day
amount for penalty and bonus/incentive are the same amount. (PDPG 7.1.6.4)
Shared Savings. A shared savings provision can be utilized to reduce initial costs and may
be used with a guaranteed maximum price. With this form of shared savings, payment is
made based on an agreed-upon portion of the difference between the original cost (stated or
agreed) and the actual amount of proposed changes or substitutions. The savings are shared
on a percentage basis between the parties to the agreement. (PDPG 7.1.6.5)
Design-Bid-Build (D-B-B). A delivery method, that is the traditional method for moving a
project from concept to completion. It is a linear sequence of activities generally occurring in
the following order:
Project conception
Design (including schematic and design development)
Construction documents
Competitive bidding
Construction
The basis of this delivery method is that design is completed prior to bidding/pricing and
construction. (PDPG 7.2)
Competitive Bidding . Most effective method of determining the least cost for constructing
the work that is described and defined by the bidding documents. Competitive bidding
creates an environment where bidders at every level, contractor, subcontractor, and supplier,
must carefully and seriously consider every aspect of their bid in the attempt to be awarded
the work by providing a lower price than any of the other bidders. A bid states, or stipulates,
the price the bidder will charge to perform the work (including overhead and profit) and may,
if requested by the bidding documents, include the length of time required to complete the
work. The project design is developed and bidding documents prepared by the A/E for the
owner that are then made available to bidders. (PDPG 7.2.2)
Stakeholders and Participants. Those involved with the project either by contract or no
contract with the owner. These include the owner, A/E, contractor, construction manager,
subcontractors, suppliers, and product representatives. (PDPG 7.2.3, 7.3.3, 7.4.5, 7.5.3, and
7.6.3)
Design-Build (D-B). A project-delivery method, the owner contracts with a single entity for
the complete design and construction of a project. The design-builder may consist of one or
more firms associated in a variety of ways. Regardless of its composition, the design-builder
provides complete design service and performs the construction under a single contract with
the owner. (PDPG 7.5)
Integrated Project Delivery (IPD). Refer to Knowledge Item No. 1-4 in Study Module No.
1.
Team Selection Process. Participants are brought together by agreements that should be
compatible, depending on the relationships established by the project delivery method
selected. Each contract under a delivery method most likely will have a subset of contracts
Request for Qualifications (RFQ). May be issued before the request for proposal or at the
same time. The information received in response to the request for qualifications, helps the
owner discern the qualifications of those who may be considered for a project. The owner
may want to have this information before the request for proposal is sent. This may help to
narrow the field as the request for proposal is sent only to those who have been approved or
prequalified. (PDPG 2.6.2.2)
Proposal. An offer from one entity to another, of terms and conditions with reference to
some work, which if accepted can form a contract. A proposal implies an opportunity for
more consideration by the recipient and is sometimes utilized when project cost or other
conditions will be determined by negotiation. A proposal is usually in response to a request
for proposal. (PDPG 11.4.2)
Direct Selection. Those with previous experience in design and construction may use direct
selection as their primary means of obtaining design services. To the A/E, this is known as a
returning client. The direct selection process saves time and money for the participants
involved. The client saves the efforts of research, interviews, and specific documentation of
requirements. For the A/E, the process saves expenses of identifying markets, making
presentations, and assessing capabilities of consultants required for the project. Direct
selection may be the result of the A/E’s reputation in certain design types. Some A/E’s have
demonstrated creative solutions and unique use of materials in their designs. These solutions
to problems have received recognition through awards and publication. Most A/E firms
specialize in certain project types and have developed significant expertise in those markets.
(PDPG 2.6.2.1)
Total Project Commissioning. Includes validation of the project delivery process entirely
from the concept stage, including programming, through design, contract document
preparation, procurement, and construction, and into the operations and maintenance activities
of facility management. Uses a specialist known as a commissioning authority, or sometimes
agent, who is an independent entity not affiliated with the other participants on the project
team. The commissioning authority is engaged to verify the quality of the project in relation
to the owner’s project requirements. The process begins by documenting the owner’s project
requirements, the basis of the design proposed to solve those requirements, and how the
variety of systems and assemblies will work together to provide those solutions. At each
stage in the project’s life cycle, procedures can be implemented to monitor how the criteria
are being incorporated and whether the criteria will achieve results. This commissioning
continues through the design and construction process to obtain assurances and minimize
errors and omissions. (PDPG 2.8)
Knowledge Synopsis
Knowledge Item No. 3-1: Design and construction services and documentation required.
Refer to 2.3 under Knowledge Item No. 1-1 in Study Module No. 1.
Refer to 2.4 under Knowledge Item No. 1-1 in Study Module No. 1.
Knowledge Item No. 3-2: Tripartite relationships among owner, contractor, and A/E.
5.2 The simplest manner of explaining the essence of a project is that it is a collection of
relationships among three diverse groups, as illustrated in Figure 5.1, that come together
for the ______________ _______________ of focusing a wide range of talents and
abilities on the planning, design, documentation, construction, and management of a
building or other facility.
Knowledge Item No. 3-3: Factors affecting project delivery (e.g., extent, time, and cost).
7.1.1 All projects require a number of specialized individuals, firms, and companies
that participate in a vast array of complex activities to design and construct a
project.
For owners that build a project only occasionally, a lack of familiarity with the
design and construction process will in all likelihood be a
____________________.
7.1.5 Time
7.1.5.1 Sequencing
7.1.5.2 Scheduling
If projects are not completed within the time frame designated for the
work, the consequences can be onerous for all concerned.
The effort required of the A/E and owner for a fast-track project is
greater with multiple contractors because it is ____________________
more complex.
Contracts record the agreed-upon cost of the work and establish the
basis of payment. A number of different methods are used for
determining and stating amounts of cost or compensation within
contracts.
There are __________ types of project delivery methods, each of which include
a different mixture of contractual arrangements and processes. The decision to
utilize a particular delivery method affects the participant relationships and how
they will ___________ and ____________________ a project. Project delivery
requires significant decisions early in the _______________ __________
_______________.
7.2 Design-Bid-Build
7.2.1 Introduction
There are two categories of bidders, and the __________ generally determines
which category should be used for a project:
While the __________ construction cost are established with the owner
contracts with the successful bidder, the __________ costs cannot be known
until all __________ in the work are discovered and the contract is almost
complete.
The most basic relationship between the owner, the A/E, and the contractor is
known as the _______________ relationship which is first established by the
owner-A/E contract and then, second, by the owner-contractor contract. While
there is no _______________ relationship between the A/E and the contractor, a
__________-__________ relationship is established between the two by the two
contracts with the owner.
7.2.3.1 Owner
The owner contracts first with an A/E to design the project and to
prepare _______________ _______________. The owner then obtains
7.2.3.2 A/E
7.2.3.3 Contractor
When the owner enters into a contract with the selected bidder, that
bidder becomes the contractor who then enters into individual
____________________ with specialty subcontractors and
_______________ __________ with material suppliers.
The owner is entitled to __________ the contractor to construct the project for
cost that was bid and made the _______________ __________. Also, the
contractor is entitled to expect the construction documents to be
_______________ to accurately bid and construct the project.
7.3 Design-Negotiate-Build
7.3.1 Introduction
When the owner and the contractor negotiate a construction contract, the goal is
to achieve __________ _______________ to each and to avoid the inherent
__________ of a competitive environment among contractors (however,
competition still occurs between _______________ ____________________
and _______________ _______________).
The various stakeholders and participants have more opportunity to discuss the
project on a __________-to-__________ basis and work toward informed,
_______________ decisions.
7.3.3.1 Owner
The owner will select a specific contractor and then negotiate the
contract as the design and construction document process proceeds.
7.3.3.2 A/E
7.3.3.3 Contractor
In the process of negotiating with a contractor, the owner can work with the
contractor to determine the __________ of __________ that can be
accomplished with the __________ _______________.
Early participation by the contractor permits the A/E to benefit from the
contractor’s advice on the following:
One of the primary disadvantages is that the __________ cost may not be
obtained due to the __________ of competition because without bidding
competition, the possibility exists for _______________ __________.
Modifications to design documents may become __________ __________ that
affect time and cost, which are sometimes referred to as __________
__________.
7.4.1 Introduction
7.4.5.1 Owner
Because the owner will __________ with each __________ contractor,
the construction manager should review these contracts and make
recommendations to the owner.
7.4.5.2 A/E
7.4.5.4 Contractors
The following are instances where construction management may not be the
appropriate project delivery method:
When one party is advising the owner as well as constructing the project, the
potential exists for _______________ of _______________.
The use of construction management does not affect whether the contracts are
__________ or _______________.
7.5 Design-Build
7.5.1 Introduction
There are several ways an owner can utilize Design-Build, how the project
__________ is established is the principal difference in the several variations.
One way is when the owner contracts __________ with the design-builder, who
is then responsible for:
7.5.3.1 Owner
After the design-build contract is awarded, the owner may be left out of
may __________-to-__________decisions and will have __________
contact with project activities than in design-bid-build.
7.5.3.2 Design-Builder
7.5.3.3 A/E
7.5.3.4 Contractor
The primary benefit to the owner is that a single entity is responsible for design
and construction. The single-contract arrangement also offers more control over
project __________ and __________.
Because of the close coordination between the A/E and contractor during the
design phase, the contractor can influence product selections by providing
information regarding __________, ________________, and
_______________.
Because the A/E is working for the design-builder, the owner should not expect
the same level of _______________ _______________ to protect the owner’s
interest as normally performed during a ____________________ delivered
project.
7.6 Owner-Build
7.6.1 Introduction
Some large-scale real estate developers and private companies that have
experienced and qualified on-staff professionals may construct projects without
retaining an independent contractor or construction manager.
The construction contracts are executed directly between the owner and
companies that are traditionally ____________________
____________________ and material suppliers but become multiple-prime
contractors.
7.6.3.1 Owner
The owner must carefully determine how the tasks that are specified in
Division 01 - ____________________ ____________________ of the
project manual will be accomplished.
7.6.3.2 A/E
When the owner hires an independent A/E, the A/E may provide the
same services related to design of any other project. However, in most
instances the owner will handle ____________________ and
____________________ with little involvement of the A/E.
7.6.3.3 Contractors
Since contractors are in direct contract with the owner, they are
technically not considered ____________________ but are actually
____________________ ____________________.
7.6.3.4 Subcontractors
One of the primary benefits of owner-build is that the owner can achieve a
____________________ ____________________ by performing the duties that
the contractor would for other delivery methods.
7.7.1 Introduction
One of the core elements around which Integrated Project Delivery is structured
is the technological development of ___________________
___________________ ___________________, which is the basis of how
design and construction documents should be prepared and used which is
defined as: “A Building Information Model utilizes cutting edge
___________________ technology to establish a computable representation of
all the ___________________ and ___________________ characteristics of a
facility and its related project/life-cycle information, and is intended to be a
___________________ of information for the facility owner/operator to use and
maintain throughout the life-cycle of a facility.”
A prerequisite of a good project is ensuring that each team participant has the
___________________, ___________________ ___________________, and
___________________ to carry out their respective responsibilities effectively
and in concert with other team participants. An effective project team work
together ___________________ and focuses on the same goal.
The owner should keep in mind the project concept and mission when
assembling the team. The owner should consider the work that needs to be done
and skills and expertise required to perform the work.
The A/E is generally selected by the owner based on the A/E’s firm’s
___________________ in a particular type of project. There are three primary
methods for selecting an A/E.
Some owners may have prior relationships with A/E’s and other
participants.
2.6.3.2 Qualifications
2.6.3.3 Subcontractors
Once an owner decides that one of the two types of construction management
project delivery methods is appropriate for a project, the construction manager
may selected through ___________________. Construction managers may be
selected ___________________ based on an established relationship or may
submit their ___________________ in response to a request for proposal.
Prior to issuing a request for proposal, the owner may issue a request
for qualifications to solicit information about potential design-builders.
The information received in response to the request for qualifications
helps the owner discern the qualifications of those who may be
considered for the project.
2.8 Commissioning
2. True or False: There being no contractual relationship between the A/E and the contractor,
there is also no contractual relationship between the A/E and the subcontractors and suppliers.
A. Selection
B. Payment
C. Award
D. Contract
5. The nationally recognized California AIA "Integrated Project Delivery Guide" redefines the
stages of a project to include which of the following:
A. Conceptualization
B. Criteria design
C. Detailed design
D. Implementation documents
E. All of the above
7. What are the three principal types (business arrangements) of the design-build project
delivery method?
8. A limitation of the design-build project delivery method is that the owner is less involved in
the project design, including for example material selection.
Knowledge Item No. 4-5: Cost estimates and estimating techniques used during design phase.
Understand the basic types of estimates and the estimating techniques used by the A/E during
design.
Knowledge Item No. 4-6: Life cycle costs and value analysis.
Understand what is included in life cycle costs and how the concept is applied in evaluating
design choices.
Understand the potential benefits and possible drawbacks of value analysis.
Understand the types of recommendations that may result from value analysis.
Reading List
Knowledge Item No. 4-1: Schematic design documentation.
PDPG 9.3
Knowledge Item No. 4-5: Cost estimates and estimating techniques used during design phase.
PDPG 8.11
Knowledge Item No. 4-6: Life cycle costs and value analysis.
PDPG 8.12 and 8.13
Key Terms
Knowledge Item No. 4-1: Schematic design documentation.
Schematic Design Documentation. AIA B101 and EJCDC 520, which are standard forms of
agreement between the owner and the A/E, require the A/E to furnish the owner a report. The
report should include preliminary schematic drawings and a preliminary project description
(PPD) that together clearly indicate the extent and relationship of the project components.
(PDPG 9.3)
Estimate of Probable Construction Costs - Schematic Design. Uses the unit of measure
technique for the estimate of probable construction costs which are consistent with other
schematic design documents. Because the design is broadly defined, the estimate will be
similarly broad with a substantial contingency category to account for unknown factors.
(PDPG 9.3.2)
Design Development Documents. AIA B101 requires the A/E to prepare drawings and other
documents sufficient to describe the character of the project and its major elements, including
architectural, structural, mechanical, electrical systems, and materials as appropriate, along
with adjustments to the preliminary cost estimate. EJCDC E-520 requires production of final
design criteria, preliminary drawings, outline specifications, and written description of the
project along with a revised estimate of probable project costs. (PDPG 9.4)
Design Development Drawings. More detailed than schematic design drawings, but are not
suitable as construction drawings. Artist renderings are not used at this point because
stakeholders and participants are familiar with the aesthetic aspects of the design. The
emphasis during this time is shifting from aesthetics to more technical items in anticipation of
Outline Specifications. Aid in the design process and are the basis for revising cost
estimates, schedules, and value analysis studies. They also serve as a checklist for the project
team when selecting products and methods during development of the project manual. They
are a means of communication among members of the project team and between the team and
the owner. Outline specifications help control the decision-making process and encourage
clarity in the construction documents. The use of well-prepared outline specifications reduces
the potential for design changes at later stages and consequent inefficient use of design team
time. Outline specifications can also be used for the coordination of terminology between
drawings and specifications. The format of outline specifications uses MasterFormat® level
one and level two numbers in brief, concise statements. The three part Section Format is not
necessary. (PDPG 9.4.2)
Design Team Coordination. Prior to completing design development documents, the A/E
must review the design and estimate of probable construction cost information provided by
the owner and sub-consultants to ensure that the documents are coordinated and within
budget. The key to effective design team coordination is good coordination. Three
components to project design team coordination: organization, execution, and quality
assurance. (PDPG 9.4.3)
Quality. Refers to the project requirements established in the contract documents. (PDPG
8.9)
Quality Assurance. Refers to procedures for guarding against defects and deficiencies
before and during the execution of the work. (PDPG 8.9)
Quality Control. Refers to procedures for evaluating completed activities and elements of
the design for conformance with the requirements. (PDPG 8.9)
Establishing Quality. The owner establishes the basis for quality in the program, budget,
and schedule. The A/E prepares design documents to convey a physical form and materials
that should be consistent with the owner’s quality requirements. Developing phases are forms
of quality assurance/quality control. Obtaining approvals at each phase verifies the design as
a quality control. Procedures utilized by the A/E, such as uniform documentation systems,
ensure a greater degree of quality control. (PDPG 8.9.1)
Participants Affect Quality. The A/E performs quality assurance/quality control in the
design of the project, preparation of the contract documents, and administration of the
Allowance. Specified monetary sum or a specified quantity of work not otherwise defined by
the specifications and drawings, but which the contractor is required to include in the bid or
price. The contractor is asked to submit prices for work items that are undetermined at the
time of bidding, but will be determined after the agreement has been executed. (PDPG
8.14.1.1)
Cash Allowance. A monetary sum that the bidder includes as part of the contract sum to
account for certain items to be determined at a later time. (PDPG 8.14.2.1)
Quantity Allowance. A specified quantity of a product or assembly that the bidder includes
in the scope of work even though the location of the product is not defined on the drawings or
in the specifications. (PDPG 8.14.2.2)
Alternate. A defined portion of work that is priced separately and thus provides an option for
the owner in determining the final scope of the project. The alternate provides the owner with
a choice between different products or it can define the addition or deletion of a portion of the
work. (PDPG 8.14.3)
Knowledge Item No. 4-5: Cost estimates and estimating techniques used during the design
phase.
Cost Estimate. An estimate is not a price. It is an A/E’s opinion of the probable cost of
construction based on:
The cost of similar constructed projects
Input from construction participants
Economic conditions prevailing at the proposed time of construction
Contingency for inestimable factors, such as unknown details, unforeseen or hidden
construction, soil conditions, changed market conditions, and weather delays
(PDPG 8.11)
Cost against Extent. It is important to maintain a balance between the proposed design and
project budget. A change to either design extent or budget must result in a corresponding
change in the other. (PDPG 8.11.1)
Successful Project. One which the owner receives a project at a reasonable price, the A/E
sees the project originally envisioned successfully completed without having to compromise
design concepts or features, and the contractor has the work done on time and within budget
so a reasonable profit can be realized. (PDPG 8.11.1)
Order of Magnitude. Uses per unit of occupancy costs; used to provide cost information
while the project concept or program is still at its earliest stages of development or during
schematic design when projects are not yet determined, typically with a degree of accuracy of
20 to 25 percent. (PDPG 8.11.2)
Unit-of-Measure. The construction must be defined and the approximate total facility size
must be known, typically with a degree of accuracy of 15 to 20 percent. (PDPG 8.11.2)
Assemblies or Systems. Cost per unit of assembled construction is used to form the project
estimate; requires the kind of information that is developed during the design development
stage, typically with a degree of accuracy of 10 percent. (PDPG 8.11.2)
Unit Price. A price can be stipulated or quoted by a bidder or proposer for a single, specified
unit of work. Unit prices are useful where the type of work is defined, but the extent of the
work is not known or is likely to change. Unit prices are also utilized when quantity
allowances are specified, providing a means of adjusting the contract sum once the full extent
of work becomes known, typically with a degree of accuracy of 5 percent. Usually the method
used to establish the final design estimate. (PDPG 8.11.2, 8.14.1.3)
Knowledge Item No. 4-6: Life cycle costs and value analysis.
Life Cycle Costs. Life cycle costs are the estimated expenses for a project, or a specific
material, equipment, or system, including:
Design
Construction
Operation
Maintenance
Resale, demolition, or salvage
Life cycle costs are based on the total costs of ownership rather than just the initial cost.
(PDPG 8.12)
Value Analysis. Also called value-enhanced design or value engineering, is the process of
evaluating documented design to identify potential alternate methods, systems, or materials
that will benefit the owner by enhancing the life cycle value for the entire project. (PDPG
8.13)
Data-Gathering Phase. First phase of the value analysis process that compiles valuable
information regarding the project including:
Project program to understand the owner’s goals and requirements
Code analysis
Geothermal information
Energy analysis
Design documents
Construction documents
(PDPG 8.13.1.1)
Investigation Phase. Value analysis team considers potential alternates and options
applicable to the project. (PDPG 8.13.1.2)
Reporting Phase. The value analysis process is documented and recommendations are
presented to the owner for consideration and approval and the A/E prepares to implement
them accordingly. (PDPG 8.13.1.4)
Written Historical Record. The importance of a written historical record during the
performance of a contract should never be underestimated or taken lightly. (PDPG 5.10.1)
Design Considerations. Design considerations are requirements the A/E must take into
account in designing the project including regulatory and owner requirements. (PDPG 8.3)
Aesthetics. Aesthetic design incorporates components that elicit sensory responses primarily
but not exclusively visual, in anyone who may have contact with the project, with the
intention of communicating the owner’s values and the facility’s purpose. (PDPG 8.4)
Functional Requirements. The A/E must design the project elements and their relationships
in a manner that ensures proper function of the project in accordance with the owner’s
program and related authorities having jurisdiction requirements. (PDPG 8.5)
Environmental Design Tools. Many public and private groups have created design tools for
the designer to implement a sustainable project, including: BEES, Energy Star, and LEED.
(PDPG 8.7.2)
Energy Star. The Environmental Protection Agency (EPA) administers the Energy Star
program in which individual building products are rated for compliance with sustainability
criteria, based on standardized testing procedures of their energy consumption. The EPA also
enforces many regulations regarding the environment, including air quality, water quality,
emissions, and pollutants. (PDPG 8.7.2)
LEED. The U.S. Green Building Council (USGBC), a private corporation, developed the
Leadership in Energy Efficient Design (LEED) program, which certifies the sustainability of
new, remodeled, or existing facilities based on their compliance with criteria. According to
USGBC, LEED works to promote sustainable green building and development practices by
developing and applying universally accepted standards, tools, and performance criteria.
(PDPG 8.7.2)
Sustainable Design. Takes place on the product level and facility level. Energy Star rates
manufactured products, including appliances, equipment, building products, and
manufactured structures, according to energy efficiency. The BEES program evaluates
building products based on their environmental impact at each stage of the life cycle. The
LEED program evaluates whole facilities, rather than each product, including new
construction, major renovations, and existing buildings according to their theoretical
environmental performance during the facility life cycle. (PDPG 8.7.2)
Sustainability Life Cycle Analysis. Under the BEES model evaluates six impacts a product
make on the environment during each of the aforementioned stages including:
Global warming potential
Acidification
Nitrification potential
Natural resource depletion
Solid waste produced
Indoor air-quality
(PDPG 8.7.3)
Budgets. The A/E must understand and account for the owner’s budget requirements and
design the project accordingly. The owner must also be aware of the limitations that the
project budget places on design. Design and budget are ultimately tested when the project is
priced during the procurement (bidding/negotiating/purchasing) stage. Regardless of the
delivery method, the owner and the A/E must have a common understanding of how the
budget will affect the design. (PDPG 8.10)
Types of Products. The term “product” can be used to identify the following:
Manufactured units
Materials
Assemblies/fabrications
Equipment
(PDPG 10.2)
Products. Configuration of various materials that are manufactured into a self-contained unit
that has certain self-contained units that is intended for a specific purpose or function that can
be installed, applied, or incorporated into the work. (PDPG 10.2.3)
Standard Products. Products produced in quantity and stocked for shipment upon receipt of
a purchase order. (PDPG 10.2.3.1)
Evaluation and Selection Process. The process should be disciplined and thorough, and
should conclude with products that are suitable for the project design and its location. The
process includes:
Initial product identification
Establishing project criteria
Determining applicable criteria for evaluation
Attribute categories for evaluation
(PDPG 10.5)
Initial Product Identification. At the design concept for a project is developed and the
aesthetic design begins to give physical form to the desired project, products should be
identified as generic products. (PDPG 10.5.1)
Establishing Product Criteria. The unique attribute of each product should be evaluated
according to the product criteria that are established for the project. (PDPG 10.5.2)
Tests. Means of verifying conformance with performance criteria and a measure of actual or
predicted performance level. (PDPG 10.5.1)
Project Requirements. The project budget directly influences decisions by setting price
parameters. The project schedule has two basic influences: design delivery and product
delivery. Regulatory requirements also exert influence product selections. Marketplace
considerations introduce competitive influences on product selection. (PDPG 10.5.2.2)
Applicable Criteria for Evaluation. Products do not need to be evaluated according to each
and every product criterion known, but only those that apply to the specific project. (PDPG
10.5.3)
Knowledge Synopsis
Knowledge Item No. 4-1: Schematic design documentation.
AIA and EJCDC standard forms of agreement between owner and A/E require the A/E to
furnish the owner a report that should include ____________________
____________________ ____________________ and a ____________________
____________________ ____________________ that together indicate the extent and
relationship of the project components.
9.3.1 Drawings
Schematic design drawings give a more organized form to the design concept
and begin to describe the following about the project design:
9.3.2.1 Format
The other engineers and consultants usually have been developing their design
concepts for the program.
AIA standard form of agreement between owner and A/E requires the A/E to prepare
drawings and other documents sufficient to describe the ____________________ of the
project and its major elements, along with ____________________ to the preliminary
cost estimate.
9.4.1 Drawings
The drawings at this stage are __________ detailed than the schematic design
drawings, but are not ____________________ as construction drawings. The
emphasis during this time is shifting from ____________________ to the
____________________ aspects of the project design in anticipation of
producing construction drawings.
9.4.2.1 Format
9.4.2.2 Content
The ___________ establishes the basis of quality in the program, budget, and schedule.
The __________ performs quality assurance/quality control in the design of the project,
preparation of contract documents, and administration of the construction contract.
There are occasions when it will be necessary for the A/E to consider special procedures
for certain variables in a project, including:
8.14.1.1 Allowances
8.14.1.2 Alternate
Unit prices are useful where the type of work is defined, but the
_____________________ of the work is not known or is likely to
_____________________.
8.14.2 Allowances
8.14.3 Alternates
Knowledge Item No. 4-5: Cost estimates and estimating techniques used during design phase.
Knowledge Item No. 4-6: Life cycle costs and value analysis.
Life cycle costs are based on the total cost of _____________________ rather than just
the _____________________ cost.
Value analysis, also called value enhanced design or value engineering, is the process of
evaluating documented design to identify potential _____________________ methods,
systems, or materials that will benefit the owner by _____________________ the life
cycle value of the project.
8.13.2 Recommendations
The importance of the need for a written historical record during the
performance of a contract should never be underestimated of taken lightly.
Design considerations are requirements the A/E must take into account in designing the
project. The A/E must account for two types of requirements:
8.4 Aesthetics
The A/E must design the project elements and their relationships in a manner that ensures
proper function of the project in accordance with the owner’s program and related
authorities having jurisdiction requirements.
8.6 Constructability
8.10 Budgets
The A/E must understand and account for the owner’s _____________________
requirements and design the project accordingly.
The owner must also be aware of the _____________________ that the project budget
places on design.
10.1 Introduction
While there are many materials that are exposed to view and are selected based on
aesthetic decisions, there are many more that are concealed that are crucial to the
performance of the facility over its life cycle.
10.2.1 Materials
10.2.2 Commodities
10.2.3 Products
10.2.3.4 Equipment
Most manufacturers are aware that current and accurate technical information is required
for the design and construction of projects, so they have been more aggressive about
providing customer service to those that make evaluations, selections, and decisions
about products.
As the design concept for a project is developed and the aesthetic design begins
to give physical form to the desired project, products should be identified as
_____________________ products.
Design delivery
Product delivery
Activities are performed during the design phases that create a setting
for progressive decisions leading to a final product selection. These
progressive decisions begin at an elemental level in the early phases
and become more detailed as the design progresses.
10.5.4.3 Performance
10.5.4.4 Sustainability
10.5.4.6 Manufacturers
10.5.4.7 Installers
10.5.4.8 Cost
Product design
Maintenance cycles
Maintenance training
Maintenance supplies
Manufacturer or distributor support services
Knowledge Item No. 5-5: Coordination between graphic and written documents.
Understand which information should be conveyed in drawings, and which information
should by conveyed in specifications.
Understand the concept of schedules.
Understand the process of coordinating information between drawings and specifications.
Knowledge Item No. 5-6: Legal interpretations and/or conflicts of contract documents .
Understand the importance of design team coordination.
Understand the results of incomplete coordination among design team members.
Understand the rules for how contracts can be interpreted by the courts.
Reading List
Knowledge Item No. 5-1: 4C’s of communication.
PDPG 11.3.5
Knowledge Item No. 5-5: Coordination between graphic and written documents.
PDPG 11.2.9
Key Terms
Knowledge Item No. 5-1: 4C’s of communication.
Clear. Use proper grammar and simple sentence construction to avoid ambiguity.
Concise. Eliminate unnecessary words, but not at the expense of clarity, correctness,
or completeness.
Correct. Present information accurately and precisely. Carefully select words that
convey exact meanings.
Complete. Do not leave out important information.
(PDPG 11.3.5)
Construction Documents. Written and graphic documents prepared for communicating the
project design for construction and administering the construction contract. They include two
major groups of documents: procurement documents and contract documents. (PDPG 11.1.2)
Contract Documents. Describe the proposed construction (referred as the work) that results
from performing services, furnishing labor, supplying, and incorporating materials and
equipment into the construction. Contract documents consist of both graphic and written
elements and typically include the following:
Contracting forms
Project forms
Conditions of the contract
Revisions
Clarifications
Modifications
Specifications
Drawings. Graphic and textual information organized on a two-dimensional surface for the
purpose of conveying data about a specific portion of the project. Drawings convey design
intent and may show multiple views, either of the whole project or of its parts. Drawings
indicate relationships between elements and may show the following for each material,
assembly, component, and accessory:
Location
Identification
Dimension and size
Details and diagrams of connections
Shape and form
(PDPG 11.2)
Specifications. Define the quality requirements for products, materials, and workmanship
upon which the contract is based and requirements for administration and performance of the
project. They are generally written for each subject as sections and organized by divisions
under MasterFormat® or by categories under UniFormatTM. (PDPG 11.3)
Bid. An offer to perform a contract for work and labor or supply materials or goods at a
specific price. A bid is a response to a solicitation such as an invitation to bid or
advertisement for bid. (PDPG 11.4.2)
Proposal. An offer from one party to another, of terms and conditions with reference to some
work, which if accepted can form a contract. A proposal implies an opportunity for more
Invitation to Bid . Intended to attract qualified bidders and to help prospective bidders
decide whether to obtain the procurement documents. (PDPG 11.4.3)
Instructions for Procurement. The requirements with which the bidders must comply before
and during submissions of bids. (PDPG 11.4.4)
Bid Form. The bid process requires a bid form that is prepared as a document that the bidder
will submit to the owner. It contains blank spaces completed by the bidder and a place for the
bidder’s signature (and for the seal of corporate entities) to indicate that the bidder agrees to
all provisions. (PDPG 11.4.6.1)
Proposal Form. Can utilize a form offered by the proposer or can be a form required in a
procurement process. Whether the process is formal or informal, the proposal form is similar
to a bid form except it is with a chosen entity. (PDPG 11.4.6.2)
Bid Security. Guaranties that if a bid is accepted within the specified time, the bidder will
enter into a formal agreement with the owner (usually 30 to 90 days from the opening of the
bids) and will furnish the required construction performance and payment bonds. The
purpose of the bid security is to compensate the owner for damages incurred if the selected
bidder does not accept the contract award. (PDPG 11.4.3.1)
Contract. A contract between two or more parties represents a promise to be performed for
consideration. Common law has recognized performance under such contract to be an
enforceable duty. A contract may be oral or written. Oral contracts can be difficult to enforce
because there is no record of exact terms. (PDPG 5.3)
Notice of Award. The owner may issue a notice of award if preparation of the actual contract
might be delayed. This procedure is required when a challenge period is required by statute.
A notice of award establishes the beginning of the challenge period. (PDPG 11.5.2.4)
Agreement. The written document signed by each party and is the legal instrument binding
the parties to the contract. The agreement defines the relationships and obligations existing
between the parties. By reference, the agreement includes all other contract documents, such
as the drawings and specifications. (PDPG 5.4)
Project Forms. Forms used in the process of the construction of the project. Project Forms
include: bond forms, certificates and other forms, clarification and modification forms, and
closeout forms. (PDPG 11.5.3)
General Conditions. The conditions of the contract are broad clauses that define basic
rights, responsibilities, and relationships of the entities associated in the construction of the
project. General Conditions have wide applicability to almost all projects and are available as
standardized documents that are prepared by various societies such as AIA, EJCDC, and
DBIA. (PDPG 11.3.9)
Knowledge Item No. 5-5: Coordination between graphic and written documents.
Coordination. Effective coordination and quality assurance programs must start early in the
design process and depend largely on continuous and effective communication among project
team members. The level of details of the drawings should be consistent with the level of
requirements in the specifications. (PDPG 11.2.9)
Knowledge Item No. 5-6: Legal interpretations and/or conflicts of contract documents.
Project Team Coordination. Three components for project team coordination are:
Organization: Selecting team members and establishing management procedures
Execution: Project design and production of construction documents
Quality Assurance: Meetings, checklists, communication, and checking and cross-
checking construction documents
(PDPG 5.9)
Incomplete Coordination. Issues that can result from incomplete coordination are:
Duplications
Omissions
Addenda. Written or graphic instruments issued to clarify, revise, add to, or delete
information in the original procurement documents or in previous addenda. (PDPG 11.3.12.2)
Change Orders. A written instruction to the contractor issued after execution of the
agreement. It authorizes an addition, deletion, or revision to the project in consideration of an
adjustment in the contract sum, contract time, or both. A change order is used for changes to
the contract documents that affect contract sum or time. (PDPG 11.3.12.3 and 13.9.2.4)
Construction Change Directive. Directs the contractor to make a change in the project
before the owner and contractor have agreed upon the proposed changes in contract sum or
contract time. Change directives are used in the absence of an agreement between the owner
and contractor on the terms of a change order or when the value of the change directive may
or may not affect the contract sum or time, however, the change directive serves as a notice
that the change will be incorporated in a change order once the value of the work is
established. (PDPG 11.3.12.3 and 13.9.2.3)
Minor Changes in the Work. Instructions or interpretations not involving adjustment to the
contract sum or contract time. Such changes are made by the architect’s supplemental
instructions directing the contractor to make stated modifications. The architect’s
supplemental agreement does not require an owner’s signature. (PDPG 11.3.12)
Warranty. A promise that a proposition of fact is true, a promise that certain facts are truly
as they are represented to be and that they will remain so, subject to any specified limitations.
In certain circumstances a warranty will be presumed; this is known as an implied warranty
(PDPG 11.3.18.1)
Full Warranty. A warranty as to full performance covering both labor and materials. (PDPG
11.3.18.1)
Express Warranty. Any affirmation of fact or promise made that relates to the goods or
installation and becomes a part of the bargain that the goods or installation shall conform to
the affirmation of promise. (PDPG 11.3.18.1)
Guarantor. One who makes a guaranty; one who becomes secondarily liable for another’s
debt or performance in contrast with a strict surety who is primarily liable to the principle
debtor. (PDPG 11.3.18.1)
Warrantor. One who makes a warranty; any supplier or other person who gives or offers to
give a written warranty or who is or may be obligated under an implied warranty. (PDPG
11.3.18.1)
Limited Warranty. A written warranty that fails to meet one or more of the minimum
standards of a full warranty. (PDPG 11.3.18.1)
Uniform Commercial Code (UCC). Governs contracts dealing with the sale of goods and,
with minor variations, is the law in every state except Louisiana. The purpose of the Uniform
Commercial Code is to facilitate commerce by providing certainty and consistency of
commercial transactions. (PDPG 11.3.16.3)
Implied Warranties. Under the Uniform Commercial Code, there are two implied
warranties:
Implied warranty of merchantability that goods are fair, average, and medium quality
Implied warranty of fitness meaning the proposed item should be fit for its intended
purpose
(PDPG 11.3.18.4)
Insurance. A contractual relationship that exists when one party (the insurer), for a
consideration (the premium), agrees to reimburse another party (the insured) for loss to a
specified subject (the risk) caused by designated contingencies (hazards or perils). (PDPG
11.3.20.1)
All Risk Insurance. Protection from loss arising out of any fortuitous causes other than those
perils or causes specifically excluded by name. This in contrast to other policies that name
the peril or perils insured against. (PDPG 11.3.20.1)
Builder’s Risk Insurance . Covers losses during the construction phase arising from the
insured risks of fire, windstorm, collapse, and theft. The policy is designed to cover all
property that has been or will be incorporated into the project. Builder’s risk insurance is
available in a named peril or an all-risk policy. (PDPG 11.3.20.3)
Claims-Made Policy. Policies written under a claims-made basis will cover claims made
(reported or filed) during the year the policy is in force for any incidents that may occur that
year or during any previous period the policyholder was insured under the claims-made
Completed Operations. A form of liability insurance that provides coverage for bodily
injury and property damage arising out of the operations that have been completed or
abandoned provided the accident occurs away from the premises owned or rented by the
insured. (PDPG 11.3.20.1)
Comprehensive Policy. This term applies to a variety of policies that provide broad
protection. (PDPG 11.3.20.1)
Contractual Liability. Liability assumed under any contract or agreement over and above
that liability that may be imposed by law. (PDPG 11.3.20.1)
Hold-Harmless Agreement. A contract under which legal liability of one party for damages
is assumed by the other party. (PDPG 11.3.20.1)
Limit of Liability. The maximum amount that an insurance company agrees to pay in the
case of loss. (PDPG 11.3.20.1)
Loss. The basis of a claim for damages under the terms of a policy. (PDPG 11.3.20.1)
Occurrence Policy. Policies that cover claims made that arise from injury or damage that
occurs during the policy period, irrespective of when the claim is made against the insured.
(PDPG 11.3.20.1)
Subrogation. The assignment to an insurer by terms of the policy or by law, after payment of
loss, of the rights of the insured to recover the amount of the loss from one legally liability for
it. (PDPG 11.3.20.1)
Liability Insurance. Liability policies protect the named insured from losses arising out of
legal liability to others caused by the insured activities. (PDPG 11.3.20.2)
Automobile Insurance. From a contractor’s standpoint, the liability for operation of owned
and non-owned automobiles, included rented or hired vehicles, is generally secured through a
business automobile coverage form. (PDPG 11.3.20.2)
Boiler and Machinery Insurance. A policy separate from a builder’s risk policy. Insures
against loss resulting from accidents to boilers and pressure vessels identified in the policy,
including damage to others property. (PDPG 11.3.20.3)
Contractor’s General Property and Equipment Insurance. Covers the cost of loss of tools
and equipment to build the project. (PDPG 11.3.20.3)
Umbrella Excess Liability. Provides a layer of insurance above the limits carried in the
contractor’s other liability policy. (PDPG 11.3.20.3)
Construction Bonds. There are three types of bonds used in construction projects:
Bid bonds
Performance bonds
Payment bonds
(PDPG 11.3.19)
Bid Bond. The purpose of the bid bond is to protect the owner from losing the benefit of an
accepted bid. Issuance of a bid bond commits the bidder to enter into a contract and, if
required, provide performance and payment bonds. The bid bond is provided by the bidder at
the time of the bid and is submitted with the bid. The bid bond provides for a penal amount
expressed either in dollars or as a percentage of the total amount of the bid. In the event that
the selected bidder fails or refuses to enter into a contract for the price of the bid, the surety is
obligated to pay the owner’s damages, up to the penal amount of the bid bond. (PDPG
11.3.19.4)
Performance Bonds. Provides the most important protection for the owner by guaranteeing
that if the contractor defaults, the surety will either complete the contract in accordance with
its terms or provide sufficient funds, up to the penal amount of the bond, to fund the
completion. (PDPG 11.3.19.5)
Payment Bonds. The payment bond, sometimes referred to as the labor and materials
payment bond, guarantees the subcontractors, material suppliers, and others providing labor,
material, and equipment to the project will be paid. (PDPG 11.3.19.6)
Principal. The party who has the primary obligation to perform the undertaking that is being
bonded. (PDPG 11.3.19.1)
Surety. Also referred to as the bonding company, the surety is the party that guarantees the
principal’s performance. The surety agrees to be bound to the obligations of the principal’s
performance should the principal fail to perform. (PDPG 11.3.19.1)
Obligee. The obligee is the person for whose benefit the bond is written. (PDPG 11.3.19.1)
Surety Bond. The written document given by the surety and principal to the obligee to
guarantee a specific obligation. (PDPG 11.3.19.1)
Penal Amount. Bonds are written with a limit on the amount of the guarantee. This limiting
amount, frequently 100 percent of the contract amount, is called the penal sum or penal
amount of the bond. (PDPG 11.3.19.1)
Claimant. Commonly used to refer to a party that files a claim against the bond. This could
be a subcontractor or owner or supplier seeking recovery under the payment bond. (PDPG
11.3.19.1)
Lien. The legal right of a party, such as a subcontractor, to claim a security interest in the
project or have it sold for payment of a claim. (PDPG 11.3.19.1)
Knowledge Synopsis
Knowledge Item No. 5-1: 4C’s of communication.
11.1.1 Introduction
The responsibilities of the participants on the design team are determined by the
____________________ ____________________ ____________________
used.
Drawings are graphic representations of the work upon which the contract is
based. They show the ____________________ extent and relationships of
elements to one another.
11.1.4 Specifications
Figure 11.1 Arrange the following document names in the proper locations in the graphic below:
Pre-Contract Revisions
Specifications
Conditions of the Contract
Revisions, Clarifications and Modifications
Certifications
Instructions for Procurement
Project Forms
Div. 40-49 Process Equipment
Procurement Requirements
Div. 20-29 Facility Services
Clarifications and Proposals
Supplementary Conditions
Payment Bond
Addenda
Contract Modifications
Available Information
Resource Drawings
Contracting Forms
Procurement Documents
Div. 30-39 Site and Infrastructure
Project Manual
General Conditions
Performance Bonds
Contracting Requirements
Div. 02-19 Facility Construction
Contract Documents
Contract Drawings
Div. 01 General Requirements
11.4.1 Introduction
11.4.4.1 00 21 00 Instructions
There are various types of information that should be made available to bidders,
proposers, and contractors during procurement and execution of the work
however, they are not ____________________ ____________________.
The procurement requirements should contain provisions that the bidder may
conduct additional ____________________ to verify the thoroughness of
information made available to bidders.
The form of bid or proposal is based on the project delivery method and the
intended ____________________ of ____________________ for the
agreement.
The bid process requires a bid form that is prepared as a document that
the bidder will submit to the owner.
Project ____________________
Name and address of party to whom the bid is directed
____________________ submitting bid
Acknowledgments
Amount of __________ for the bids to be held open
Identification of ____________________
Prices
Combined bids
Alternates
Allowances
__________ prices
____________________ time
____________________ damages
Supplements
Closing
The proposal process can utilize a form offered by the proposer or can
be a form required in a procurement process. Whether the process is
formal or informal, the proposal forms could be similar to a bid form.
11.5.1 Introduction
Work
Contract Documents
Payments
Termination
Claims and Dispute Resolution
Knowledge Item No. 5-5: Coordination between graphic and written documents.
11.2.9.1 Drawings
11.2.9.3 Schedules
11.2.9.4 Coordination
Following are some of the issues that can result from incomplete coordination:
____________________. Violates the CSI principle of “say it once and in the right
place.” It is an opportunity for discrepancies that alter the uniform basis for
procurement and cause confusion
____________________. Defined as information concerning an element of work
that is inadvertently excluded from the construction documents
____________________ or ____________________. Conflicting information in the
construction documents can be due to the lack of knowledge by the team leader or
team members
Division 01 ____________________. Division 01 affects all divisions and requires
input from all disciplines
____________________ ____________________. Differences in the technical and
descriptive terms used on drawings and specifications
The conditions of the contract establish procedures for the A/E to issue
____________________ of contract documents and to order
____________________ modifications of the work consistent with
these interpretations. Types of modifications include the following:
11.3.18 Warranties
The insurance company agrees to pay all sums for which the
insured becomes legally ____________________ to pay as
damages.
There are two types of coverage:
Occurrence Type
Claims-Made Type
Bid bonds
Performance bonds
Payment bonds
A. Instructions to Bidders
B. Contract Documents
C. Specifications
D. Procurement Requirements
E. All of the above
4. An affirmation of fact or promise made by the seller to the buyer that relates to the goods
and becomes a part of the basis of the bargain creates _______________________ .
A. An implied warranty
B. A full warranty
C. An express warranty
D. A guarantee
A. The supplementary conditions should state that the period last a specific additional length
of time
B. EJCDC and AIA documents state correction period instead of guaranty period
C. The owner accepts any repairs after that date
D. The courts relieve the contractor of his responsibility
6. Under the AIA A201 and EJCDC C-700, who provides property insurance covering the
Work?
A. Contractor's surety
B. Owner
C. Contractor
D. Financing agency
E. None of the above
A. Maintenance bond
B. Payment bond
C. Bid bond
D. Performance bond
Knowledge Item No. 6-10: Hierarchy of general, administrative, and procedural requirements.
Understand the hierarchy of general and procedural requirements based on the General
Conditions, Division 01 - General Requirements, and Part 1 - General.
Reading List
Knowledge Item No. 6-1: OmniClassTM.
PDPG 11.3.7.1 and OmniClassTM (www.omniclass.org)
Knowledge Item No. 6-10: Hierarchy of general, administrative, and procedural requirements.
PDPG 11.3.10
Key Terms
Knowledge Item No. 6-1: OmniClass™.
MasterFormat®. An organizational structure providing numbers and titles for the variety of
subject matter necessary for the construction, operation, and maintenance of a facility.
MasterFormat® provides a system of six-digit and eight-digit numbers and titles for
organizing construction information into a standard order or sequence. By establishing a
master list of numbers and titles, MasterFormat® promotes standardization, facilitates the
placement and retrieval of information, and improves construction communication. (PDPG
11.3.7.3)
Master Guide Specifications. Used for prepared specification sections intended to be edited
and used for project specifications. (PDPG 11.3.13)
PageFormat ™. Standard page format provides an orderly and uniform arrangement of text
for each page of a specification section. (PDPG 11.3.7.5)
Performance Specifying. Specifies the required results, the criteria by which the
performance will be judged, and the method by which it can be verified. The contractor is
free to choose materials and methods complying with the performance criteria. (PDPG
11.3.6.2)
Imperative Mood. The recommended method for instructions covering the installation of
products and equipment. The verb that clearly defines the action becomes the first word in
the sentence. (PDPG 11.3.5.2)
Indicative Mood. The passive voice requires the word “shall” in nearly every statement.
This sentence structure can cause unnecessary wordiness and monotony. (PDPG 11.3.5.2)
Knowledge Item No. 6-10: Hierarchy of general, administrative, and procedural requirements.
GreenFormat™. Web-based CSI format that allows manufacturers to accurately report the
sustainability properties of their products. It provides designers, constructors, and building
operators with basic information to help meet ‘green’ requirements. Manufacturers report the
attributes of their products through a comprehensive, online questionnaire. Their entries are
then displayed through www.greenformat.com, where designers, constructors, and building
operators can search for products that fit their projects. (www.greenformat.com)
11.3.7.1 OmniClassTM
11.3.7.2 UniFormatTM
11.3.7.3 MasterFormat®
Divisions
11.3 Specifications
11.3.1 Introduction
11.3.4 Practices
Work Results Structure. The A/E must understand that neither the
____________________ ____________________ nor their
arrangement defines how the work of the project is to be assigned to
various construction trades and subcontractors.
11.3.7 Formats
11.3.7.1 OmniClassTM
11.3.7.2 UniFormatTM
11.3.7.3 MasterFormat®
11.3.7.4 SectionFormatTM
11.3.7.5 PageFormatTM
Refer to 11.2.9 under Knowledge Item No. 5-5 in Study Module No. 5.
11.3.16.4 Format
11.3.18 Warranties
Refer to 11.3.18 under Knowledge Item No. 5-8 in Study Module No.
5.
Refer to 11.3.19 under Knowledge Item No. 5-10 in Study Module No.
5.
Refer to 11.3.18 under Knowledge Item No. 5-9 in Study Module No.
5.
11.3.7.4 SectionFormatTM
11.3.7.5 PageFormatTM
There are four methods that are used for writing specifications:
11.3.5.3 Abbreviations
11.3.5.4 Symbols
11.3.5.5 Numbers
11.3.5.6 Capitalization
11.3.5.7 Punctuation
11.3.5.13 Streamlining
Knowledge Item No. 6-10: Hierarchy of general, administrative, and procedural requirements.
A. References
B. Action Submittals
C. Source Quality Control
D. Measurement and Payment
A. 05 00 00 Metals
B. 05 20 00 Metal Joists
C. 05 21 00 Steel Joist Framing
D. 05 21 19 Open Web Steel Joist Framing
5. Submittal requirements for Facility Services Divisions 21 through 28 are specified in:
A. One design team member should be responsible for overall specification coordination
B. Different document formats should be used to identify the work of the separate
consultants
C. The lead design professional should avoid the liability inherent in reviewing consultants'
work
D. Information should be collected and the project A/E assume responsibility for preparing
each section
8. An information organizing framework for the design and construction industry that assigns
built environment data into 15 discrete, coordinated tables to facilitate the organization of
project information and databases is known as:
12. The two sentence structure moods that are recommended for specifications are:
A. Mechanical Systems
B. Furnishings
C. Equipment
D. Special Construction
A. Accessories
B. Specialties
C. Equipment
D. Special Construction
15. All of the following are Articles in PART 3 - EXECUTION except which one?
A. Examination
B. Application
C. Fabrication
D. System startup
16. True or False: The OmniClass construction specification system is based on the
International Organization for Standards (ISO).
17. True or False: GreenFormatTM is a web based searchable database where users can
evaluate materials, products, and process, organized by UniformatTM.
18. Identify the level 1 UniFormatTM categories the letter designation is given:
A
B
C
D
E
F
G
Z
Reading List
Knowledge Item No. 7-1: Contract drawings - role and function.
PDPG 11.2.1 through 11.2.3
Key Terms
Knowledge Item No. 7-1: Contract drawings – role and function.
Drawings. Graphic and textual information organized on a two-dimensional surface for the
purpose of conveying data about a particular portion of a project. Drawings convey design
intent and may show multiple views, either of the whole project or of its parts. Drawings
indicate relationships between elements and may show the following for each material,
assembly, component, and accessory:
Location
Identification
Dimension and size
Details
Diagrams of connections
Shape and form
(PDPG 11.2)
Shop Drawings. Drawings that are prepared by manufacturers, suppliers, subcontractors, and
contractors to illustrate a portion of the work. Only shop drawings required by the
specifications are normally reviewed and acted on by the A/E. These drawings are not
contract documents and usually illustrate proposed details and techniques to show compliance
with the contract documents. (PDPG 11.2.3.4)
Plans. Floor plans and reflected ceiling plans are horizontal cross-section cuts taken at a
selected vertical elevation that is perpendicular to project materials and components. (PDPG
11.2.4.2)
Elevations. Show project materials and components in their vertical relationship, viewed
perpendicularly from a selected vertical plane, generally retaining their true scale, shape, and
proportion. (PDPG 11.2.4.2)
Sections. Cut vertically through and perpendicular to project materials and components and
show their detailed arrangement. Typical types of sections include the following:
Building sections
Wall sections
Site sections
Sections of specialized engineering applications
(PDPG 11.2.4.3)
Details. Show more specific information about a portion of a project component or element
than can be provided by smaller scale drawings. A detail may be shown as a plan, an
elevation, or a section view. (PDPG 1.2.4.3)
Isometric. Type of drawing that shows horizontal and vertical surfaces not in perspective but
equally foreshortened in all three dimensions. (PDPG 11.2.4.3)
Perspective. Type of drawing that illustrates objects as they appear to the eye, with reference
to relative distance and depth. (PDPG 11.2.4.3)
Scaled Views. Include orientations in the horizontal plane and in the vertical plane and
vertical cuts through the project. (PDPG 11.2.4.2)
Drawing Standards. Drawings used for construction have common conventions that
distinguish them from other types of drawings and include:
Construction-related symbols and abbreviations
Dimensions
Drawing identification
Notes or keynotes
Various types of graphic representations
(PDPG 11.2.5.1)
Dimensions. Drawings may include dimensions to delineate the actual size of an object.
They may also be used to demonstrate extent or required clearance. (PDPG 11.2.5.6)
Abbreviations. Used for construction terms on drawings and in schedules where space for
textual information may be limited. In general, the construction documents should include an
edited list of abbreviations that are tailored to the project and not the long, all-inclusive list of
widely used standard abbreviations. (PDPG 11.2.5.8)
Drawing Set Organization. Certain aspects of a project might influence the organization of
a drawing set, including:
Number of disciplines
Number of project parts (buildings)
Number of contracts
Project phase
Construction sequence
Number and extent of systems
Project delivery method
(PDPG 11.2.5.9)
U. S. National CAD Standard (NCS). Streamlines and simplifies the exchange of building
design and construction data from project development throughout the life of a facility. The
National CAD Standard is a consensus standard comprised of interrelated standards,
guidelines, and tools for uniformly organizing and presenting facility planning, design,
construction, and operation drawing information. (PDPG 11.2.7)
CAD Layer Guidelines. Provide a hierarchical organization for describing drawing layers.
The user can identify or name on the basis of the level of detail provided in each drawing
layer. The guidelines define the four data fields within layer names:
Discipline designators
Major group
Minor groups
Status
(PDPG 11.2.7.2)
Resource Drawings. These are the drawings furnished during the procurement stage that
generally show existing conditions such as roads, buildings, and current construction
circumstances. These may be drawings that were prepared for the construction of existing
facilities. Drawings of this nature rarely show exact as-built conditions and may be record
drawings from the previous contractor. Resource drawings are generally furnished for
reference only and are not contract documents. (PDPG 14.2.5.1)
Knowledge Synopsis
Knowledge Item No. 7-1: Contract drawings - role and function.
11.2 Drawings
11.2.1 Introduction
Drawings used during the design phase are primarily tools to convey
____________________ aspects of the project and show the
____________________ of space.
Construction drawings are the basis of other drawings that are produced
during construction:
11.2.4.1 Views
Typically, the first sheet in the drawing set, the cover sheet often shows
the following:
11.2.5.4 Graphics
The graphical portions of drawings are called drawing blocks and are
constructed of various types and shapes of lines.
11.2.5.5 Symbols
11.2.5.6 Dimensions
11.2.5.7 Notations
11.2.5.8 Abbreviations
Number of ____________________
Number of project ____________________
Number of ____________________
Project ____________________
Construction ____________________
Number and extent of systems
Project ____________________ method
The United States National CAD Standard (NCS) streamlines and simplifies the
____________________ of building design and construction data from project
development throughout the life of a facility.
The CSI Uniform Drawing System organizes and presents the drawings
and project information in a standard ____________________ for use
in planning, design, construction, and operation of facilities throughout
its lifecycle.
A. Contract forms
B. Closeout submittals
C. Record drawings
D. As-builts
E. Not required for private work
1. Specific requirements
2. Location
3. Quality of materials
4. Dimension and size
5. Shape and form
A. 1, 2, 3, 4, and 5
B. 2, 4, and 5
C. 2, 3, 4, and 5
D. 1 and 3
E. 3, 4, and 5
Reading List
Knowledge Item No. 8-1: Procurement process.
PDPG 12.1, 12.5, 12.7, 12.8, and 12.9
Key Terms
Knowledge Item No. 8-1: Procurement process.
Procurement. The transition from the design stage to the construction stage of a project is
the bidding/negotiating/purchasing stage called procurement. (PDPG 12.1)
Bid. An offer to perform a contract for work and labor or supply materials or goods at a
specific price. A bid is a response to a solicitation such as an invitation to bid or an
advertisement to bid. (PDPG 12.7)
Bid Depository. Receives subcontractor bids for identified units of work. The units of work
are usually significant parts of the total project. These sub-bids, depending on location, are
then either analyzed by the client agency with the selected sub-bids assigned to the general
contractor. (PDPG 12.7.1.12)
Competitive Bidding. Prospective contractors are invited to prepare and submit bids stating,
in a specified format, the sum of money required to construct the project. It is the method of
determining the lowest cost for accomplishing the work defined by the procurement
documents. The object of bidding is to ensure that the cost of the project is reasonable and
consistent with prevailing conditions of the construction industry. (PDPG 12.7.1)
Contractor Qualification. Some owners might request information regarding skills and
financial stability of prospective contractors. This is known as a request for qualifications.
(PDPG 12.7.1.2)
Negotiating. A process of dialogue, offer, compromise, and resolution between two parties’
precedent to an agreement or contract modification. (PDPG 12.8)
Prebid Meeting. A meeting, normally convened at the site, allows the owner, A/E, and
consultant to orient the prospective contractors to conditions affecting the project. (PDPG
12.7.1.6)
Pricing Documents. The documents used to obtain pricing from prospective contractors are
referred to as procurement documents. In a negotiation process the documents are referred to
as pricing documents. (PDPG 12.1)
Substitution Request. Bidders and sub-bidders may propose substitutions for most
components, subsystems, and systems during the competitive bidding stage in accordance
with the instructions to bidders. (PDPG 12.7.1.7)
Stipulated Sum (Lump Sum). An agreed amount for a described extent of work, based upon
complete or partially complete construction documents. This is the simplest method of stating
the basis of payment wherein a single amount is agreed upon for completion of the contract.
(PDPG 12.2)
Cost of Work Plus a Fee . Is usually used only with negotiated contracts. The contract calls
for compensation for the actual cost of expenses, plus an additional fee for overhead and
profit. The fee is usually a percentage of the direct expenses but also may be a fixed fee
amount. (PDPG 12.2)
Guaranteed Maximum Price. The prospective contractor’s price includes the cost of the
work as defined in the procurement documents and the prospective contractor’s fee for
administrating construction, plus overhead and profit. The contractor’s fee can be stated as a
stipulated sum (fixed fee) or as a percentage of the cost of the work. The cost of work
combined with the contractor’s fees is the guaranteed maximum price. (PDPG 12.2)
Time and Material with an Estimate of Probable Cost. An alternate to the cost of work
plus a fee when the owner and contractor agree to proceed on a time and material basis. In
the owner-contractor agreement, the contactor states the percentage of overhead and profit
that will be added to documented labor and material costs incurred while constructing the
project and an overall estimate of cost. (PDPG 12.2)
Unit Price. Refer to Knowledge Item No. 3-3 in Study Module No. 3.
Pricing. Pricing involves a comprehensive cost analysis of the project requirements, based on
the information contained in the procurement documents and other information obtained
during the period preceding bidding or formal negotiation. (PDPG 12.4)
Construction Costs. The calculable costs that the owner is required to pay. (PDPG 12.4.1)
Contingency. An estimated monetary amount to account for the risk to the prospective
contractor for performing the work. (PDPG 12.4.1)
Profit. The financial benefit realized by the contractor after all the costs have been paid and
all related claims settled. (PDPG 12.4.1)
Knowledge Synopsis
Knowledge Item No. 8-1: Procurement process.
12.1 Introduction
The _________________ from the design stage to the construction stage of a project is
the bidding/negotiating/purchasing stage collectively known as procurement.
The documents used to obtain pricing from prospective contractors are referred to as the
_________________ documents and are based on the project delivery method selected.
In a _________________ bidding process, the documents are used for bidding. In a
_________________ process, the documents are used for developing proposals.
12.7 Bidding
Specifications
Drawings
The Prebid meeting, normally convened at the site, allows the owner,
A/E, and consultant to _________________ the prospective contractors
to conditions affecting the project.
12.7.1.8 Addenda
The instruction to bidders should define the manner in which bids will
be opened and ____________________ and to whom the results will
be reported. ____________________ bid openings may be conducted
at the owner’s discretion, and bidding irregularities may be considered
or waived according to the owner’s judgment. Most
____________________ bids are required to be opened publicly, the
rules regarding irregularities strictly followed, and the results reported
to all bidders and the general public.
Negotiating is a process of dialog, offer, compromise, and resolution between two parties,
precedent to an agreement, or contract modification.
12.8.1 Participants
The documents for negotiating are similar to those required for competitive
bidding.
Following receipt and evaluation of prices, the owner might discover that the
cost of the project will exceed the established budget unless significant
____________________ changes are made. Value analysis can determine how
This pricing method is used when the contractor or owner has special
or “fixed” pricing ____________________ from the manufacturer,
distributor, or supplier.
12.9.2 Participants
12.9.3 Documents
12.9.4 Processes
____________________ a contract
Purchasing agreement ____________________
Delivery to the point of ____________________
Performance of special services at the point of performance
Stipulated Sum (also known as a Lump Sum) including Cost of the Work, and
Contractor’s Overhead and Profit. By this method, the ____________________ is
completed before pricing and the price is known by the participants before
construction begins. This pricing method is used for public and private projects that
will be ____________________ bid.
Cost of the Work Plus a Fee, sometimes, with a Guaranteed Maximum Price. The
prospective contractor’s price includes the ____________________of the
When the project is completed, the amount of work is measured or counted, usually
by a designated entity, and the contract ____________________ is calculated based
on the unit prices.
12.3 Purchasing
Cost include:
12.4.1.2 Contingency
____________________ documents
Estimated sums for ____________________ cost factors
____________________ made in pricing
Costs related to dispute resolution, legal fees, and claims against
the ____________________
12.4.1.4 Profit
Profit is the financial benefit that the contractor will realize after all
costs and claims for the project are paid.
Depending upon the owner’s and A/E’s policies, documents may be distributed
in the following forms:
The standard agreement forms contain wording that has a history of being
____________________ and ____________________ by the legal profession and the
courts, and modifications should be made with caution and not without review by an
attorney.
11.3.12.2 Refer to 11.3.12.2 under Knowledge Item No. 6-4 in Study Module
No. 6.
2. The following are all advantages gained by using standard agreement forms except which
one?
Knowledge Item No. 9-8: Site visits, observations, meetings, and inspections.
Understand the difference between observations of the progress of work and certain
inspections at key points, the A/E’s obligations in each case, and what happens as a result.
Understand the roles and responsibilities of the contractor and owner in relation to site
observations and inspection.
Understand the basic requirements for effective meetings and the types of meetings typically
held.
Knowledge Item No. 9-8: Site visits, observations, meetings, and inspections.
PDPG 13.5 and 13.7
Communication. The general conditions establish the lines of communication and describe
how the communication process is to work. The basic line of communication as identified in
the AIA and EJCDC general conditions include the following:
Between owner and contractor, through the A/E
To design consultants through the A/E
To subcontractors and suppliers, through the contractor
To separate contractors, through the owner, construction manager, or coordinating
contractor
In traditional agreements, the A/E and contractor have no contract with each other; however
their individual agreements with the owner, and the conditions of the contract make it their
duty to have certain communications. (PDPG 13.3.10)
Owner–Construction Stage. The owner typically places much of the construction contract
administration responsibility on the A/E, the owner also has important rights and
responsibilities during the construction stage:
Know the documents used in construction
Understand the role of each construction participant
Be sensitive to the expectations each participant has of the others
Communicate with each other
Understand the effect various project delivery methods have on construction contract
administration and construction project administration
(PDPG 13.3.1)
Authorities Having Jurisdiction. The authorities having jurisdiction do not have contractual
relationships with the project participants but have regulatory authority granted by the permit
process and local, state, and federal regulations and laws. (PDPG 13.3.6)
Testing Agency Inspectors. The types and quantity of tests and inspections that may be
required on a project are typically determined by the facility type and extent and materials,
and methods being utilized. (PDPG 13.3.7)
Refer to General Conditions (AIA A201, Article 8 or EJCDC C-700, Subparagraphs 1.01, A,
14; Paragraph 2.03; and Paragraph 12.02)
Substitutions after Award of Contract. Under certain project delivery methods the owner
may encourage the contractor to propose alternatives during the course of construction.
(PDPG 13.9.3.1)
Evaluation of Substitution Requests. The first and foremost item to evaluate is whether or
not the proposed substitutions meets the requirements of the contract documents. It is the
responsibility of the entity requesting the substitution to research and document the
substitution to prove equivalency. (PDPG 13.9.3.3)
Modifications. Contract modifications are required whenever a change will modify the
contract documents, whether or not the change will affect the time or cost. Change orders are
used to modify the contract documents when cost, time, or both are affected. Minor changes
in the work are issued when neither time nor cost are affected. Prior to preparation of a
change order, the contractor is usually asked to respond to a proposal request or submit a
request for proposal, in which the cost of the change and schedule impact is identified. If the
A/E is in agreement with the proposed change, cost, and time revisions submitted by the
contractor, a change order will be used. If the A/E is not in agreement with the contractor’s
proposal, a change directive may be issued. (PDPG 13.9.2)
Minor Changes. Minor changes to the project or clarifications of the contract documents are
defined as instructions or clarifications not involving adjustments of the contract sum or time.
(PDPG 13.9.2.2)
Change Directives. Change directives are used in absence of an agreement between the
owner and the contractor on the terms of a change order or when the value of a change cannot
be determined until after the work is performed. (PDPG 13.9.2.3)
Change Orders. A change order is a written instruction to the contractor issued after
execution of the agreement. It authorizes an addition, deletion, or revision to the project in
consideration of an adjustment in the contract sum, contract time, or both. (PDPG 13.9.2.4)
Knowledge Item No. 9-8: Site visits, observations, meetings, and inspections.
Progress Meetings. Progress meetings concern the progress of the work. They provide a
forum in which matters pertinent to the timely completion of the work can be discussed. The
frequency and length of progress meetings depend on the extent of the project and the project
delivery method. (PDPG 13.5.2.2)
Closeout Meetings. The closeout meeting is used to review requirements for the completion
of the contract and to obtain submittal of the necessary final documents. Separate meetings
may be required for substantial completion, final completion, and warranty reviews. (PDPG
13.5.2.5)
Site Visits, Observations, and Inspections. All participants in the construction process have
certain responsibilities for making observations and inspections. This process of monitoring
the work is basic to quality control. Dictionaries define observe as to perceive, notice, see,
whereas inspect means to examine carefully and critically, especially for defects. In
construction, the distinction between these two words has significance. Most standard owner-
A/E agreements and the condition of the contract indicates the A/E will perform construction
contract administration and will visit the site to:
Ascertain progress and quality of work
Inform the owner of known deviations from the contract documents and defects and
deficiencies observed in the work
Keep the owner informed of the progress of work
Conduct inspections to determine dates of substantial and final completion
The standard agreements between owner and contractor require the contractor to visit the site
prior to bidding or commencing work to correlate and coordinate observations with the
contract documents and report any discrepancies to the A/E. The contractor is also
responsible for continual inspection of the work to ensure that each portion is ready to receive
subsequent portions and to arrange for inspections required by authorities having jurisdiction.
(PDPG 13.7)
Substantial Completion. The date established by the A/E when the project, or a portion of
the project, is so nearly complete that the owner may use the project for its intended purposes.
(PDPG 13.7.2)
Authorities Having Jurisdiction. Federal, state, county, and city authorities oversee the
safety and welfare of the public they serve. In doing so, they verify that the code and
ordinance requirements have been met. The authorities having jurisdiction usually performs
reviews of the contract documents before issuing permits. They verify that the regulatory
requirements are being met by performing building, mechanical, electrical, elevator, fire, life
safety, health, zoning, accessibility, and critical structural inspections at the project site.
(PDPG 13.7.5)
Project Site Safety. The standard general conditions clearly establish the contractor as being
responsible for planning, maintaining, and supervising construction safety measures and
programs. Although the owner and the A/E do not participate in planning the contractor’s
safety program, they are to follow the procedures established by the contractor. (PDPG
13.7.8)
Defective and Nonconforming Work. The A/E has the authority to reject work that does not
conform to the requirements of the contract documents. Only the owner can accept
nonconforming work. The contractor has the obligation to promptly correct nonconforming
or defective work. (PDPG 13.7.9)
Stopping the Work. Standard general conditions do not give authority to the A/E to order
the contractor to stop work. The conditions of the contract describe the conditions under
which the contractor can stop work or terminate the contract and the procedures the contractor
must follow when doing so. (PDPG 13.7.9.1)
Delivery, Storage, and Protection of Products. The contractor is responsible for receiving,
unloading, and handling products delivered to the project site. Products are often stored on-
site or off-site locations being incorporated into the project. The contractor is responsible for
adequately protecting stored products. (PDPG 13.7.10)
Progress Schedule Review. The contractor is required to submit construction progress and
submittal schedules. Review of the construction progress schedule assists the A/E in
determining the percentage of project completion. Review of the construction progress and
submittal schedules helps the A/E to recall the status of submittals and to anticipate when
Record Documents. Record documents are kept in the field office and are used to record
actual construction. Division 01 specification sections specify the procedural requirements
for record documents. The documents should be maintained in a clean, dry, and legible
condition and should not be used for construction purposes. Information should be placed on
the record documents concurrently as construction progresses. The record documents should
be available for review by the A/E and owner during the entire construction stage. (PDPG
13.7.14)
Review, Analysis, and Evaluation. Regular feedback based on actual project experience is
valuable for the improvement of future documentation and project procedures. Feedback
should occur during each phase of a project, especially during the construction stage. It is the
construction stage that lessons learned should be documented, in writing, in order to improve
the project team’s corporate memory and quality management progress. (PDPG 13.7.15)
Construction Submittals. The contractor shall perform no portion of the work requiring
submittal of shop drawings, product data, samples, or other submittals until the respective
submittal has been approved by the A/E and that such work shall be in accordance with
approved submittals. (PDPG 13.6.3)
Action Submittals. Submittals requiring responsive action by the A/E, normally review and
approval. These include:
Product data
Shop drawings
Samples
(PDPG 13.6.3.1)
Shop Drawings. Drawings that are prepared by manufacturers, suppliers, subcontractors, and
contractors to illustrate a portion of the work. Only shop drawings required by the
specifications are normally reviewed and acted upon by the A/E. These drawings usually
illustrate proposed details and techniques to show compliance with the contract documents.
Shop drawings may include dimensions obtained at the project site showing how the
specialized work will be incorporated into the project. Shop drawings are not contract
documents. (PDPG 13.6.3.1)
Samples . Shows color, texture, and other appearance items, physical examples of materials,
equipment, or workmanship that illustrate functional and aesthetic characteristics of a material
or product and establish standards by which the work will be judged. (PDPG 13.6.3.1)
Informational Submittals. Submittals not requiring responsive action by the A/E. This
information deals for the most part with the verification and certification that the installed
work or portion of the work meets the specified quality requirements. These informational
submittals may include:
Coordination drawings
Certificates
Design and delegated design data
Test and evaluation reports
Manufacturer’s instructions
Manufacturer’s reports
Sustainable design reports
Qualification statements
Construction photographs
(PDPG 13.6.3.2)
Submittal Review. Submittals are reviewed and approved by the contractor to ensure that
contract document requirements have been met, to check dimensions, and to coordinate with
subcontractors. Once approved by the contractor, they are submitted to the A/E for review and
processing. The A/E’s review is not to determine the accuracy and completeness of
dimensions or quantities, these are the contractor’s responsibility. (PDPG 13.6.5)
Record Keeping. A record of submittals is necessary for checking on the status of specific
items and ensured their timely review. The submittal process should have a high priority by
each participant, whether it is preparation of submittals, assembly of information, or review.
(PDPG 13.6.7)
Quality Assurance and Quality Control. The construction stage of a project is the process
of executing the requirements of contract documents and thus providing the required quality.
Quality assurance refers to the procedures for discovering defects and deficiencies or
deviations to the contract documents before and during the execution of the work. Quality
control refers to the procedures for evaluating completed activities and elements of the work
for conformance with contract documents. (PDPG 13.8)
Participants Affect Quality. The rights and responsibilities of the owner, contractor, and
A/E are addressed in the conditions of the contract. Procedures are addressed in Division 01 –
General Requirements within 01 40 00 – Quality Requirements of the specifications. In the
course of administering a construction contract, the A/E endeavors to verify that the required
quality of work is being provided and to inform the owner of known deviations from the
contract documents, the A/E provides the continuity in the understanding of the intent of the
contract documents. The contractor’s quality assurance process begins when the contractor
visits the site to become familiar with conditions under which work will be performed. The
process continues with field measurements, coordination, scheduling, and the preparation and
review of submittals. The contractor’s quality control process originates when the contractor
assumes responsibility to supervise and direct the work using the contractor’s expertise, skill,
and attention. The contractor also assumes control over the means, methods, techniques,
sequences, and procedures for construction. (PDPG 13.8.1)
Team Approach. The responsibilities and performance of each participant affect overall
project quality. The success of a project depends upon all participants being committed to a
team approach for meeting the requirements. (PDPG 13.8.6)
Refer to General Conditions (AIA A201, Article 12 or EJCDC C-700, Article 13.)
Refer to General Conditions (AIA A201, Article 9 or EJCDC C-700, Article 14)
Measurement and Payment. Measurement means quantifying the amount of work eligible
for payment, and payment is the distribution of money proportionate to that quantity of work.
(PDPG 13.12)
Application for Payment. Most contracts specifically stipulate the requirements for
preparation and delivery of the application for payment. Most contracts require that a
schedule of values be submitted to the A/E for approval prior to the first application for
payment. (PDPG 13.12.1)
Payment Intervals. The interval between payments is normally identified in the contract
documents. Common payment intervals are as follows:
Periodic progress payments
Provisional payments
Single payment
(PDPG 13.12.2)
Periodic Progress Payments. Monthly progress payments are appropriate for most projects,
including those of long duration and high cost, where the rate of progress will vary from
month to month. (PDPG 13.12.2)
Provisional Payments. Predetermined partial amounts of the total contract sum tied to the
attainment of identifiable milestones. (PDPG 13.12.2)
Single Payment. When projects are of a size that enables the work to be completed in a short
period, a single payment of the entire contract sum may be appropriate. (PDPG 13.12.2)
Basis of Payment. The payment administration process depends on the basis of payment
identified in the contract documents for the various contract items. The three basis of
payment are as follows:
Stipulated sum
Stipulated Sum. A single price becomes the amount agreed upon for completion of the
entire contract. (PDPG 13.12.3)
Unit Price. The actual quantity of work is measured and verified as it completed and
payments are made at the agreed-up unit price rates. (PDPG 13.12.3)
Cost Plus Fee. The contractor is reimbursed the contractor’s actual cost of labor,
equipment, and material, plus a predetermined fixed fee, or percentage of costs, for overhead
and profit. (PDPG 13.13.3)
Contractual Responsibilities. The owner-A/E agreement establishes that the A/E will
certify the amounts due the contractor based on the A/E’s observations of the work in
progress and evaluation of the contractor’s application and certification for payment. The
A/E’s certification is based only on the A/E’s knowledge, information, and belief that the
work has progressed to the point indicated and the quality of work conforms to the
requirements of the contract documents. (PDPG 13.12.4)
Schedule of Values. The schedule of values is an itemization of the costs of various portions
of work, which together comprise the total contract sum. Each line has a value that is a
proportional fraction of the total value of the whole project. (PDPG 13.12.6)
Application Forms. The contractor prepares the application and certifies that the work
covered by the application conforms with the requirements of the contract documents and that
all the previous amounts paid to the contractor have been properly applied to discharge the
contractor’s obligation to others furnishing materials and labor on the project. (PDPG
13.12.7.1)
Progress Payments. Upon receiving the contractor’s application and certificate for payment
with the A/E’s certification, the owner is obligated to make payment. When the progress
payment has been made to the contractor, the owner has discharged the owner’s payment
obligation for work completed to date. (PDPG 13.12.8)
Withholding Payment. The A/E has the right, and the responsibility, to withhold payment of
the whole of any part of the payment application in order to protect the owner. (PDPG
13.12.10)
Failure to Make Payment. If there is a failure to make payment within the prescribed times,
without cause under the contract conditions, the owner may be in material breach of contract.
In this situation, the contractor is protected under the conditions of the contract and may stop
work if payment is not made within the notice period. (PDPG 13.12.11)
Substantial Completion, Partial Occupancy, Final Acceptance, and Payments. The date
of substantial completion is when the project, or a portion of the project identified by the
construction contract, is determined by the A/E to be sufficiently complete so that the owner
can use it for its intended purpose. Neither progress payments nor acknowledgement of
substantial completion or partial occupancy constitute acceptance of work not completed
according to the contract documents. (PDPG 13.12.14)
Final Payment. Final payment often requires the processing of a final change order to
balance previous payments against the final payment and final contract amount. (PDPG
13.12.15)
Refer to General Conditions (AIA A201, Article 10 or EJCDC C-700, Paragraph 6.13)
Project Site Safety. The contractor is responsible for the overall project safety and the owner
and the A/E are obligated to abide by the contractor’s safety rules when at the project site.
The owner and A/E should not direct the contractor in matters of safety, or they may be liable
for the consequences that arise from their direction. In addition to OSHA, most companies
have their own safety rules. (PDPG 13.10.13)
Refer to General Conditions (AIA A201, Article 14 or EJCDC C-700, Article 15)
Refer to General Conditions (AIA A201, Article 15 or EJCDC C-700, Article 16)
Claims and Disputes. Claims are initial requests for adjustments in contract sum or time.
Disputes are claims that cannot be resolved by the parties to the construction contract without
the intervention of an impartial third party. (PDPG 13.11)
Claims. Two sources of claims include claims by the contractor (often on behalf of their
subcontractors and suppliers) against the owner, and claims by the owner against the
contractor or the A/E. The third source is a claim initiated by someone other than a party to
the construction contract. (PDPG 13.11.1)
Owner Claims. When the owner believes the value of work received is not commensurate
with the contract price, or the owner’s costs are increased because of actions or inactions by
the contractor, the owner may initiate a claim. (PDPG 13.11.1.2)
Third-Party Claims. Injury or death to persons and property damage claims are high on the
list in terms of frequency and severity. (PDPG 13.11.1.3)
Resolving Claims. Upon receipt of a claim, the A/E or initial decision maker may request
additional information to support the claim. Once the claim is clearly documented and
understood, it may be appropriate to generate a written preliminary response summarizing the
essence of the claim, identifying any concerns requiring reconciliation, and establishing a
proposed schedule for resolving the claim. (PDPG 13.11.3)
Dispute Avoidance. Claim avoidance has become a common term applied to the
management of claims and disputes. Because a claim is defined as a request for adjustment to
the contract, it is more appropriate to think in terms of dispute avoidance. Each party
understanding the interests and limitations of the other is a first step to avoiding disputes.
(PDPG 13.11.3.1)
Disputes. Disputes often occur when the A/E’s or the initial decision maker’s decision on a
claim is not accepted by one or both parties and the claim cannot be resolved through
negotiation. When attempts at reaching a mutually acceptable settlement have been
unsuccessful, the parties are obligated under the conditions of the contract to use the specified
method of dispute resolution indicated in the contract documents. (PDPG 13.11.4)
Mediation. An extension of negotiation whereby a neutral party acts as a facilitator to aid the
parties in finding a mutually acceptable settlement of the claim. (PDPG 13.11.4)
Study General Conditions (AIA A201, Paragraph 4.2.4 or EJCDC C-700, Paragraph 8.01)
13.3.10 Communication
13.3.2 Architect/Engineer
13.3.3 Contractor
13.3.4.1 Subcontractors
13.3.4.2 Suppliers
13.3.5 Consultants
The types and quantity of tests and inspections that may be required on a project
are typically determined by the facility type and extent and materials and
methods being utilized.
13.3.10 Communications
Refer to 11.3.19 under Knowledge Item No. 5-10 in Study Module No. 5.
Study General Conditions (AIA A201, Article 8 or EJCDC C-700, Subparagraphs 1.01, A, 14;
Paragraph 2.03; and Paragraph 12.02)
13.9.3 Substitutions
Under certain project delivery methods the owner may encourage the
contractor to propose ____________________ during the course
of construction.
The first and foremost item to evaluate is whether or not the proposed
substitutions meets the requirements of the ____________________
documents.
Study General Conditions (AIA A201, Article 7 or EJCDC C-700, Article 10)
13.9.2 Modifications
Contract modifications are required whenever a change will modify the contract
documents, whether or not the change will affect the ____________________ or
____________________. ____________________ ____________________
are used to modify the contract documents when cost, time, or both are affected.
____________________ ____________________ in the work are issued when
neither time nor cost are affected. Prior to preparation of a change order, the
____________________ is usually asked to respond to a proposal request or
submit a request for proposal, in which the cost of the change and schedule
impact is identified. If the A/E is in agreement with the proposed change, cost,
and time revisions submitted by the contractor, a change __________________
will be issued. If the A/E is not in agreement with the contractor’s proposal, a
change ____________________ may be issued.
Knowledge Item No. 9-8: Site visits, observations, meetings, and inspections.
13.5 Meetings
Contractor/subcontractor meetings:
All participants in the construction process have certain responsibilities for making
observations and inspections. This process of monitoring the work is basic to
____________________ ____________________.
Most standard owner-A/E agreements and conditions of the contract indicate the A/E will
perform construction contract ____________________ and will periodically visit the
construction site to:
Typical and traditional agreements require the A/E to consult with and advise
the owner and act as the owner’s ____________________ during construction,
as provided in the general conditions. The standard agreements also require the
A/E to make site visits at ____________________ appropriate to the stage of
construction and to become generally ____________________with the progress
and quality of the contractor’s work. In addition to these requirements, the
standard agreements and general conditions state that the A/E:
A good working relationship among the owner, the A/E, and the contractor, with
the primary focus on the ____________________ of the construction, helps to
resolve problems and conflicts quickly.
The A/E has the authority to ____________________ work that does not
conform to the requirements of the contract documents. Only the ___________
can accept nonconforming work. The contractor has the obligation to promptly
correct nonconforming or defective work.
The conditions of the contract describe the conditions under which the
contractor can stop work or terminate the contract and the procedures
the contractor must follow when doing so.
13.7.10.1 Delivery
13.7.10.2 Storage
Products are often stored at on-site and off-site locations before being
incorporated into the project.
13.7.10.3 Protection
Record documents are kept in the field office and are used to record
____________________ construction. Division _____ specification sections
specify the procedural requirements for record documents.
Note: There is an omission error on page 404 in the fourth line down: insert the word “not”
between the words “are” and “contract.” Therefore, the beginning of the second sentence
should be “These submittals are not contract documents …”
These submittals are not contract documents, unless specifically identified as such in the
contract documents, and are not be used by the contractor or the A/E to
____________________ the contract. Submittals are also an important part of the
quality ____________________ for a project. They indicate how the contractor,
subcontractors, fabricators, and suppliers intend to fulfill portions of the contract
document requirements.
The rights and responsibilities of the owner, contractor, and A/E are addressed
in the ____________________ of the ____________________. Procedures are
addressed in Division 01 - General Requirements within 01 40 00 - Quality
Requirements of the specifications.
The contractor’s quality control process originates when the contractor assumes
responsibility to ____________________ and ____________________ the
work using the contractor’s expertise, skill, and attention. The contractor also
assumes control over the ____________________, ____________________
techniques, sequences, and procedures for construction.
Before actual execution of the work, quality assurance activities help to ensure a
common ____________________ of the contract documents and prevent future
problems. Examples of early quality assurance activities are:
Study General Conditions (AIA A201, Article 12 or EJCDC C-700, Article 13)
Study General Conditions (AIA A201, Article 9 or EJCDC C-700, Article 14)
13.12.5 Measurement
Upon receiving the contractor’s application and certificate for payment with the
A/E’s ____________________, the owner is obligated to make payment. When
the progress payment has been made to the contractor, the owner has discharged
the owner’s payment obligation for work completed to date.
The conditions of the contract usually stipulate that progress payments do not
constitute ____________________.
13.12.9 Retainage
The A/E has the right, and the responsibility, to withhold __________________
of the whole or any part of the payment application in order to protect the
owner.
If there is a failure to make payment within the prescribed times, without cause
under the contract conditions, the owner may be in material ________________
of contract. In this situation, the contractor is protected under the conditions of
the contract and may ____________________ work if payment is not made
within the notice period.
13.12.12 Liens
Study General Conditions (AIA A201, Article 10 or EJCDC C-700, Paragraph 6.13)
Study General Conditions (AIA A201, Article 14 or EJCDC C-700, Article 15)
Study General Conditions (AIA A201, Article 15 or EJCDC C-700, Article 16)
Claims are initial requests for ____________________ in contract sum or time. Disputes
are claims that cannot be resolved by the parties to the construction contract without the
intervention of an ____________________ third party.
13.11.1 Claims
Two sources of claims include claims by the contractor (often on behalf of their
subcontractors and suppliers) against the owner, and claims by the owner against
the contractor of the A/E. The third source is a claim initiated by someone other
than a party to the construction contract.
When the owner believes the value of the work received is not
____________________ with the contract price, or the owner’s costs
are increased because of actions or inactions by the contractor, the
owner may initiate a claim.
13.11.2 Entitlement
Upon receipt of a claim, the A/E or initial decision maker may request additional
information to support the claim. Once the claim is clearly documented and
understood, it may be appropriate to generate a written preliminary response
summarizing the ____________________ of the claim, identifying any concerns
requiring ____________________, and establishing a proposed schedule for
resolving the claim.
13.11.4 Disputes
Disputes often occur when the A/E’s or the initial decision maker’s decision on
a claim is not ____________________ by one or both parties and the claim
cannot be resolved through ____________________.
2. The responsibility of inspecting work already performed for proper condition to receive
subsequent work lies with the:
A. Owner
B. A/E
C. Contractor
D. Subcontractor
4. True or False: By executing the contract, the Contractor confirms that the contract time is
reasonable.
A. Owner
B. A/E
C. Contractor
D. Authorities having jurisdiction
6. Under AIA A201, who has the responsibility to pay sales, consumer, use and similar taxes for
the work provided?
A. A/E
B. Owner
C. Contractor
D. Installing subcontractor
E. None of the above
7. If the contractor is delayed in the progress of the work by the Owner, the Contractor should:
A. Alternates
B. Shop drawing submittals
C. Substitution requests
D. Change order request
9. All of the following may be accomplished through issuing of a change order except which
one?
10. All of the following are defined as a contract modification except which one?
A. Change order
B. Construction change directive/ work change directive
C. Architect's supplemental instruction/field order
D. Addendum
11. Under AIA A201, who has the authority to stop the work, if nonconforming work fails to be
corrected?
A. A/E
B. Owner
C. Contractor
D. Varies - As stated in Division 01 General Requirements
E. None of the above
12. Drawings prepared by the contractor, subcontractor, or material supplier that show how a
particular aspect of the work is to be fabricated and installed, are called:
A. Record drawings
B. Construction documents
C. Shop drawings
D. Details
13. The contract clauses that establish payment responsibilities are found in:
A. General conditions
B. Division 01 General Requirements
C. Payment bond
D. Addenda
14. True or False: The A/E may withhold certification for payment in whole or in part if in the
A/E’s opinion representations to Owner cannot be made concerning the progress of the work.
16. True or False: Acceptance of final payment constitutes a waiver of claims by the contractor,
subcontractor, and material supplier.
17. True or False: If a portion of the work is covered contrary to requirements specifically
expressed in the Contract Documents, it must if requested by the A/E, be uncovered for
examination and at the Contractors expense without change in the contract time.
Reading List
Knowledge Item No. 10-1: Role and responsibilities of facility manager during project closeout.
PDPG 14.1.2 and 14.2.3
Key Terms
Knowledge Item No. 10-1: Role and responsibilities of facility manager during project closeout.
Role and Responsibilities of Facility Manager during Project Closeout. The facility
manager is involved in project closeout to assist in the successful transfer of the completed
facility for the owner’s use. During project closeout, it is important for facility managers to:
Understand their roles and the construction contract requirements affecting
commissioning, equipment and systems start-up, and project closeout
Identify maintenance-staffing requirements, assign and train staff
Take delivery of extra stock and maintenance equipment and supplies in the
construction contract
Coordinate installation of owner provided furniture, furnishings, and equipment
Participate in systems start-up and testing
Participate in systems demonstration
Participate in systems operations and maintenance training
Understand the project correction period and warranties
Accept and manage the record documents
Accept and manage building informational models
The contract documents used for construction might require the contractor to provide several
types of documents and materials to assist the facility manager in facility operations and
maintenance. These documents are called record documents and include:
Operations and maintenance data
Materials and finishes data
Record submittals and shop drawings
Record drawings
Record specifications
(PDPG 14.1.2)
Demonstration and Training. Equipment and systems operation and training sessions
provide an opportunity for the facility manager to review and ask the trainers questions about
the data, equipment, and systems. (PDPG 14.1.2.2)
Substantial Completion. The point at which the project is sufficiently complete for the
owner to occupy or utilize the facility for its intended use. The date of substantial completion
is established by the A/E and documented by the issuance of a certificate of substantial
completion. At substantial completion, the owner typically assumes responsibility for the
following for the facility and its adjacent grounds:
Routine maintenance
Utilities
Security
Property insurance
Liability
(PDPG 14.1.2.5)
Total Building Commissioning. Begins during project conception and continues through the
facility management and facility use; documents the owner’s facility criteria and verifies that
the criteria are achieved and that the facility is placed into proper operations. (PDPG 14.1.2.6)
Project Record Documents. During project closeout, the facility manager receives and
reviews project record documents. The requirements for these record documents are
described in the contract documents to ensure they will be submitted during project closeout.
(PDPG 14.1.2.7)
Correction Period and Warranties. Contractors are typically required to provide a one-year
correction period for the facility. Separate warranties and guarantees for specific products,
equipment, and systems might be required by the contract documents. (PDPG 14.1.2.8)
Warranty and Correction Period Inspection. The contractor’s correction period and some
manufacturer warranties might expire one year after substantial completion. Prior to
expiration, the facility manager should review:
Status of the facility with users
Status of warranty notices
Correction issues with the A/E
Facility’s condition
(PDPG 14.1.2.9)
Warranty and Correction period Inspections. Refer to Knowledge Item 10-1 above.
Operations and Maintenance. Operation activities include the management of the day to
day functions of a facility and its systems. (PDPG 14.2.4)
Maintenance Issues. Maintenance issues must be considered and addressed by the project
team in the design of facilities, facility improvements, and selection of materials and finishes.
(PDPG 14.2.4.1)
Types of Maintenance. Project team members should understand these common terms used
by facility management staff as they discuss issues in meetings during design and
construction:
Maintenance
Emergency maintenance
General maintenance
Preventive maintenance
Routine maintenance
Renovation/modification
Deferred maintenance
(PDPG 14.2.4.2)
Financial Issues. Developing a budget for the operation and maintenance of a facility
requires that the facility manager do the following based on facility records and operation and
maintenance data:
Anticipate maintenance needs
document the operations
forecast future spending
(PDPG 14.2.4.6)
Budgeting and Cost Control. Cost control and budgeting rely on accurate accounting. The
goal of operations and maintenance budgeting is to ensure the most effective and efficient use
of resources toward meeting the company’s stated facility objectives. (PDPG 14.2.4.6)
Cost Accounting . Cost accounting assigns cost to every activity, thereby creating data that
can be used as part of a productivity measurement. (PDPG 14.2.4.6)
Life Cycle Costing. Life cycle costing analysis exams the relationship between present and
future value of facilities and equipment. (PDPG 14.2.4.6)
Planning, Design, and Construction. Space planning, changes in use, and tenant
improvements should include consideration of the project’s effect on the entire facility.
(PDPG 14.2.4.6)
Project Record Documents. Record documents are construction documents that are
substantially modified to show the actual construction. (PDPG 14.2.5.1)
Record Submittals. Record submittals can include a complete set of the information on
materials, equipment, and systems incorporated into the project including the following: a
complete set of shop drawings, product data, test reports, and other information on materials,
equipment, and systems incorporated into the project. (PDPG 14.2.5.1)
Start-up Logs. Start-up logs record system information at the time of system and equipment
start-up. (PDPG 14.2.5.1)
Operations and Maintenance Data. Operations and maintenance data should be specific to
the facility for which it is provided rather than generic product or system information. (PDPG
14.2.5.2)
Spare Parts and Extra Stock Materials. Spare parts and maintenance materials are
provided by product, equipment, and system manufacturers and installers. (PDPG 14.2.5.3)
Protecting Resource Documents. For fire and security reasons, copies of the most critical
information should be maintained at a location away from the subject facility. (PDPG
14.2.5.3)
Facility Evaluations. The facility manager develops and maintains an ongoing evaluation
program. This process begins at occupancy with a postoccupancy evaluation and continues
through the life of the facility. Facility evaluations address the following: facility use,
effectiveness, efficiency, operational cost, maintenance, and environment. Facility evaluations
assemble information that will assist in planning and scheduling the following:
Routine and preventive maintenance
Capital improvements
Facility upgrades
System and equipment replacement
(PDPG 14.2.6)
Knowledge Synopsis
Knowledge Item No. 10-1: Role and responsibilities of facility manager during project closeout.
The contract documents used for construction might require the contractor to
provide several types of documents and materials to assist the facility manager
in facility operations and maintenance. These documents are called record
documents and include:
14.1.2.6 Commissioning
For fire and security reasons, copies of the most critical information
should be maintained at a location away from the subject facility.
2.8 Commissioning
14.1.2.6 Commissioning
2. It is important for the long-term success of the facility’s operations and maintenance that
project closeout activities include all of the following except which one?
3. True or False: Equipment and system review and training should occur immediately after
substantial completion.
4. True or False: A punch list is generated by the A/E just prior to Substantial Completion.
6. Facility managers should perform a postoccupancy evaluation how long after initial
occupancy?
A. Three months
B. Three to six months
C. Six to nine months
D. Just before the one-year correction period completion
7. Objectives of a good maintenance program include all of the following except which one?
8. True or False: Record drawings and project manual provide adequate record documentation.
Answers | Page 1
Activities and Exercises
6.2 Due diligence investigations | Site selection | Facility programming | Facility performance
criteria | Anticipating the cost of the work | Setting the project schedule
6.3 preparatory | evaluate | summarize | programming
6.3.1 present | operational and maintenance | constructing | modifications | size and
characteristics | Bank loans | Philanthropic donations | Government grants | Private
investment | Venture capital | Tax and bond issues
6.3.2 Public Facilities and Utilities Impact | Relocation | Operations | Economic Impact |
Environmental Impact
6.3.3 coordinated investigations | suitability |topography | easements | site utilities | property
lines
6.3.3.1 contaminated or environmentally sensitive | brownfields | airborne dust | Density |
automobiles | natural resources | biodiversity
6.3.3.3 Hidden, subsurface conditions | Soil types and its stability | Underground streams |
Water-level problems
6.3.4 Functional evaluation | Facility service evaluation | Structural evaluation | Environmental
evaluation
6.4 conducive, suitable, and fitting | search, evaluation, selection, and acquisition
6.4.1 location, location, location
6.4.2 enable | authority
6.4.4 Marketability
6.5 Schematic programming | Program development | C, B, D, A | 4, 5, 1, 3, 2 | programming
| design
6.5.1 Functional considerations | Existing conditions | Aesthetics | Economics | Regulations |
Social considerations | Environmental concerns | Time | Other
6.5.2 clearly and objectively | impartial | Preconceptions | defined goals
6.5.3 Prioritizing
6.5.4 initial economic feasibility test | wish list
6.6 Amenity, Comfort | Health, Safety | Structure | Durability | Operational, Maintenance
6.7.2 project | construction | Due diligence studies, programming, and master planning | Project
design fees | Commissioning | Jurisdictional fees | Relocation | Terminating leases of
rental agreements on existing facilities | Site-related costs | Construction | Furniture,
furnishings, and equipment
6.7.3 Systems | Cost per Measured Units | Component cost
6.8 succession | smaller | script | milestone
8.7 Environmental Protection Agency
Answers | Page 2
8.7.1 environmental performance | life cycle | Site optimization | Use of energy | Water use |
Building materials and products | Indoor environmental quality | Optimizing operational
and maintenance practices
8.7.2 product | facility
10.5.4.4 Sustainable sites | Water efficiency | Energy and atmosphere | Materials and resources |
Indoor environmental quality | Innovations in design
1. E [PDPG 6.7.2]
2. False [PDPG 6.8]
3. C [PDPG 6.2]
4. True [PDPG 6.4.2]
5. True [PDPG Figure 6.2]
6. B [PDPG 6.7.3]
7. False [www.epa.gov/greenbuilding/pubs/about.htm | operations maintenance, renovation,
and deconstruction]
8. D [www.epa.gov/greenbuilding/pubs/about.htm]
9. G [PDPG 6.5.4]
10. G [PDPG 6.3.1]
11. I [PDPG 6.3.3]
Answers | Page 3
confidentially | owner | compared and evaluated | irregularities | responsible | lowest |
initial | total | changes
7.2.3 tripartite | contractual | third-party
7.2.3.1 bidding documents | competitive
7.2.3.2 full
7.2.3.3 project management | contract documents
7.2.3.4 subcontracts | purchase orders
7.2.3.5 providing accurate technical information about the products they represent | can identify
installers that are certified, approved, authorized , or otherwise acceptable | can assist
specialty subcontractors and material suppliers by ensuring their bids are properly based
on their products that are specified
7.2.4 design professions and construction industries | roles and responsibilities | conditions of
the contract | expect | contract sum | sufficient
7.2.5 bid-day surprise | exceed | adversarial | contingency fund | perfect | errors, discrepancies,
omissions, and/or contradictory information | change orders, claims, and disputes |
gamble | unknowns | subcontractors and suppliers
7.2.6 represents | services | best interests | time of completion
7.3.1 construction documents | adversarial | subcontractors and suppliers
7.3.2 mutual benefits | risks | specialty subcontractors and material suppliers
7.3.3 face-to-face | consensus
7.3.3.2 full
7.3.3.3 design process | time schedules, cost estimates, and details | influence | determine
7.3.4 experience, expertise | reputation | cost | scope of work | funds available | constructability
| emerging construction techniques | special materials and products | scheduling |
definition of bid/subcontract packages | ambiguities
7.3.5 lowest | absence | inflated prices | change orders | scope creep | partially | unanticipated,
unexpected | financially | final
7.3.6 shortest | lowest | Finding the compromises needed to achieve balanced results | Forging a
cohesive relationship between the owner, the contractor, and the A/E
7.4.1 represented
7.4.2 extent, cost, and time | with complex schedules or budgets | that require extensive
coordination between disciplines | where the owner has limited expertise with regard to
design and construction
7.4.3 To advise the owner on the management of the design and construction of the project |
May or may not have the authority to represent and act on behalf of the owner | The
owner maintains direct contractual relationships with the A/E and either a single-prime
contractor or multiple-prime contractors | Does not bear financial risk for the design and
construction | May be used for any type project
7.4.5.1 contract | prime
7.4.5.2 diminish | construction | Prequalification of bidders | Evaluating change orders |
Providing full-time on-site representation | Processing applications for payment |
Providing interpretations of scope issues for each contract | Preparing change
documentation | Resolving claims and avoiding disputes | Communicating directly with
the owner | Processing submittals | additional
7.4.5.3 quality assurance and quality control | site observations and payment requests
7.4.5.4 single-prime | multiple-prime
7.4.5.5 design-bid-build or design-negotiate-build
7.4.6 multiple contracts | fast-tracking | complex nature | Coordination of construction |
Information management | Cost management | Time management | Quality assurance |
Job-site safety | Assistance | tailored
7.4.7 small and simple | stipulated sum | time constraints | greater | professional fees | restrict |
conflicts of interest
Answers | Page 4
7.4.8 leadership | Management | bid or negotiated
7.5.1 contract | single
7.5.2 design | directly | developing the design | providing the contract documents | constructing
the project | control | bridging documents | competitive
7.5.3.1 day-to-day | less
7.5.3.2 completed
7.5.3.3 representative | interest | final
7.5.3.4 preconstruction activities | Construction experience | Cost estimating | Logisitics | Other
project management expertise
7.5.3.5 prime contractors
7.5.4 timing and costs | cost, availability, and performance
7.5.5 professional services | conventionally |documentation | risk | services | administrative
professional | errors, discrepancies, omissions
7.5.6 accountability | negotiated
7.6.2 specialty subcontractors
7.6.3 direct | construction documents | means, methods, and techniques | greatest | risk
7.6.3.1 experience, qualifications, and expertise | architects, engineers, and drafters/technicians |
General Requirements
7.6.3.2 procurement and construction | responsibilities
7.6.3.3 subcontractors | prime contractors
7.6.4 cost savings | control
7.6.5 risk | design | errors, discrepancies, or omissions
7.6.6 Large corporate entities | Contractor-developers who do large-scale development or
housing project | Owners with large numbers of built facilities and an ongoing capital
construction program
7.7.1 decide, design, and determine | supply, construct, and install | integration
7.7.2 collaboratively | talents and insights | optimize | increase | reduce | maximize | Building
Information Modeling | digital | physical and functional | repository
7.7.3 Collaboration | one | common | outcomes | individual
2.6 agreements | relationships
2.6.1 education, practical experience, and skills | harmoniously |
2.6.2 expertise
2.6.2.1 A recommendation from a friend or associate | Retaining an A/E that provided services
on a previous project | Based on seeing an existing facility in the area or in a periodical |
research, interviews | markets | presentations | capabilities
2.6.2.2 experience, qualifications, and recommendations | qualifications-based selections
2.6.2.3 aesthetic and technical | design criteria | open | closed
2.6.3.1 competitive bidding | negotiating
2.6.3.2 capability | physical | financial
2.6.3.3 subdivided | competitive bidding | price
2.6.4 negotiations | directly | qualifications
2.6.5.1 performance | description | separate | bridging
2.6.5.2 stipulated | greater | greater
2.8 validation | confirmation | authority | agent | project requirements | contract documents
Answers | Page 5
6. [PDPG 7.2.5]
Linear sequence extends project schedule
Bids may exceed budget
Adversarial relationships
Low bids may encourage change orders
Little margin for errors
7. [PDPG 7.5]
Architect lead
Contractor lead
Joint venture – single company
8. True [PDPG 7.5.3.1]
Answers | Page 6
8.13 alternative | enhancing | Timing | earlier | disruptive
8.13.1.1 relevant
8.13.1.2 alternatives
8.13.2 Identification | Substituting | Constructability | Changes | Modifications | Elimination |
Reduction | Identification | reducing
8.3 Regulatory requirements | Owner requirements
8.4 sensory | visual | values | influence | vision | context
8.6 means, methods, and products | difficult or impractical | practical
8.7 Environmental preservation | healthier | resources
8.7.1 Site optimization | Use of energy | Water use | Building materials and products | Indoor
environmental quality | Optimizing operational and maintenance practices
8.7.2 building products | Energy Star | energy consumption | Leadership in Energy and
Environmental Design | product | facility
8.7.3 Raw materials acquisition | Product manufacture | Transportation | Installation | Operation
and maintenance | Recycling and waste management | Global warming potential |
Acidification | Nitrification potential | Natural resource depletion | Solid waste produced |
Indoor air quality
8.7.4 high-performance
8.10 financial | limitations
10.1 performance | Identify | product representatives | history | alternatives | owner | Document
10.2.1 naturally | asset
10.2.2 uniformly and consistently | predetermined
10.2.3 physical properties
10.2.3.1 quantity | shipment
10.2.3.2 nonstandard | Prepayment | Submittals | Minimum purchase orders | Custom colors | Lead
time | Testing and certification | Proprietary products
10.2.3.4 self-contained | operational
10.3 appropriate, suitable, functional, and compatible
10.5 disciplined and thorough
10.5.1 generic
10.5.2.1 performance | Requirements | Criteria | Tests
10.5.2.2 budget | schedule | Regulatory | marketplace
10.5.3 evaluated
10.5.4.1 context | Compatibility | attributes | manufacturer | climatic | history | market | Optimum |
Maintenance | others
10.5.4.2 measured
10.5.4.8 expensive, labor-intensive | Initial | life cycle | replacement
10.5.4.9 Preventive
1. D [PDPG 3.4.3.2]
2. D [PDPG 5.5 and 8.14.3]
Answers | Page 7
11.1.2 written and graphic | communicating | Procurement documents | Contract documents |
Bidding (public and private) | Negotiating | Purchasing | Drawings | Specifications |
Procurement requirements | Contracting requirements | Resource drawings | Precontract
revisions (addenda) | Contracting requirements | Drawings | Specifications | Notice or
award | Agreement | Bonds | Conditions of the contract | Revisions, clarifications, and
modifications | General conditions | Supplementary conditions | Precontract revisions |
clarify | revise | add | delete | Clarifications and proposals | Contract modifications
11.1.3 quantitative
11.1.4 administration and performance
11.4.1 bid or negotiated
11.4.2 Bid | Proposal | contract documents
11.4.3.1 invitation | advertisement | Project identification | Description of work | Type of bid |
Time of completion | Prebid meeting | Bid opening | Document availability | Bidder
qualifications | Bid security | Owner right to reject bids | Laws and regulations |
traditional | request for proposal
11.4.4.1 Documents | Examination of documents, site, and local conditions | Interpretations during
bidding | Substitution of products | Type of bid | Preparation of bid | Bid security
information | Performance bond and payment bond | Subcontractor listing | Identification
and submittal of bid | Modification or withdrawal of bid | Disqualification of bidders |
Special applicable laws | Prebid meeting | Liquidated damages | Opening of bids |
Evaluation and consideration of bids | Execution of contract
11.4.5 contract documents | investigations | Preliminary schedules | Project budget information |
Existing condition information | Survey information | Environmental assessment
information | Existing material information | Existing hazardous material information |
Geophysical data | Geotechnical data | Permit application
11.4.6 basis of payment
11.4.6.1 identification | Entity | time | addenda | Unit | Completion | Liquidated
11.4.6.3 public agencies | additional information
11.4.6.4 owner | qualification or capability
11.5.2.1 owner | awarded
11.5.2.2 preprinted standard
11.5.4 rights, responsibilities, and relationships | design and construction agreements | Division
01 - General Requirements | General and supplementary
11.5.4.2 baseline | exceptions, modifications, and additions
11.5.4.3 modified or expanded | standard
11.2.9 complementary | construction materials | qualitative | coordination | assurance |
communication
11.2.9.1 many | one | generic | describe | specifications | subcontractors or trades
11.2.9.2 physical | chemical | performance | standards
11.2.9.4 dovetail | milestones | issuance | project manual | recommended | intraoffice and interteam
| concurrently | continuous | consistent | duplicate
5.9 communications | Organization | Execution | Quality Assurance | Duplications |
Omissions | Errors or discrepancies | responsibility | Terminology differences
11.3.12 changes
11.3.12.1 words | drawings | Oral | Narrative method | Revised page method
11.3.12.3 procurement | before | bidders or proposers | errors or omissions
11.3.12.3 interpretations | minor | authorizes | sum | time | directing | prior | interpretation
11.3.18.1 Full | Express | Guarantor | Warranty | Title | Implied | Warrantor | Limited | Guaranty
11.3.18.2 Warranty | Guaranty | warrants | guaranty | warranty
11.3.18.3 new | quality | defects | contract documents | To protect against faults, defects, or failures
| To provide a remedy for nonconformance after completion and acceptance | To give
recourse against additional parties | To extend the manufacturer’s responsibility beyond
Answers | Page 8
the end of the correction period | To allow a remedy beyond the normal statute of
limitations | limited | labor | consequential | incidental | manufacturer’s | financial |
merchantability and fitness
11.3.18.4 An affirmation of fact or promise related to goods, such as claim of performance | A
description of the goods | A sample or model that becomes a basis of the agreement |
Implied warranty of merchantability | Implied warranty of fitness
11.3.20 risks | liability | interest
11.3.20.1 Builder’s risk | Claim | Claims-made | Endorsement | Hold-harmless | Indemnify | Limit
of Liability | Loss | Occurrence | Subrogation
11.3.20.2 insured | activities | injuries | obligated | General aggregate limit | Products/completed
operations aggregate | Personal and advertising injury limit | Each occurrence limit | Fire
damage limit | Medical expense limit
11.3.20.3 Builder’s risk | Named peril | All-risk | owner | waive
11.3.19 owner
11.3.19.1 Lien | Surety | Claimant | Surety | Obligee
11.3.19.2 assurance | complete | insurance policy
11.3.19.3 bid | mechanic’s | default | breach | nonperformance
11.3.19.4 commits | fails or refuses | damages
11.3.19.5 complete | funds
11.3.19.6 labor, material, and equipment
1. B [PDPG 11.4.4]
2. D [PDPG 11.4.5]
3. C [PDPG 11.2.9]
4. C [PDPG 11.3.18.1]
5. B [PDPG 11.3.18.3]
6. B [AIA A201 Article 11.3 and EJCDCC-700 Article 5]
7. Clear | Concise | Correct | Complete [PDPG 11.3.5]
8. M [PDPG 11.3.20.1]
9. N [PDPG 11.3.20.1]
10. I [PDPG 11.3.20.1]
11. D [PDPG 11.3.20.1]
12. H [PDPG 11.3.20.1]
13. B [PDPG 11.3.20.1]
14. L [PDPG 11.3.20.1]
15. C [PDPG 11.3.20.1]
16. K [PDPG 11.3.20.1]
17. A [PDPG 11.3.20.1]
18. E [PDPG 11.3.20.1]
19. F [PDPG 11.3.20.1]
20. J [PDPG 11.3.20.1]
21. G [PDPG 11.3.20.1]
22. C [PDPG 11.3.19.4]
Answers | Page 9
Study Module No. 6
Knowledge Synopsis
Answers | Page 10
11.3.14.3 Small projects | Design-Negotiate-Build Project Delivery | Construction Management
Project Delivery | Design-Build Project Delivery | Owner-Build Project Delivery |
Interior design and tenant improvement projects | Single-prime contract | Projects where a
shortform specification is specifically requested
11.3.15 measureable
11.3.15.1 complete | products
11.3.15.2 descriptively
11.3.15.3 research and development
11.3.15.4 definitive
11.3.15.5 design-build | alternative | traditional | different | review
11.3.15.6 elements | extent
11.3.15.7 which
11.3.15.9 diagrammatic | definitive
11.3.16 acquisition | goods
11.3.16.1 plant | designated | additional
11.3.16.2 limited
11.3.16.3 contracts | commerce | effective | enforceable | ambiguities | expressed and implied |
transfer | An affirmation or promise | A description of the goods | A sample or model |
Merchantability | Fitness for a particular purpose | good faith | insolvent or breaches
11.3.16.4 purchasing | Procurement requirements | Contracting forms | Conditions of the contract |
Specifications | Retention by owner for own used and installation | Furnished by owner
for installation by others | Assignment of purchasing contract to construction contractor
11.3.17 different | MasterFormat
11.3.17.1 solicitation | agency | General Provisions | General Standards | Special Provisions |
Contract Clauses | contracting | owner | jurisdiction | self-insured | disputes
11.3.17.2 Wage rates | Environmental regulations | Preference for American shipping | Affirmative
action | Utilization of small businesses | Utilization of businesses owned by women and
minorities | Labor standards | Environmental issues | Accessibility standards
11.3.17.3 prohibit | unlimited | maximize
11.3.17.4 Private-sector standards | Commercial item descriptions | Federal specifications |
Military specifications
11.3.17.5 Specifications | Technical manuals | Standards | Electronic details | Other documents
11.3.4.1 Procurement requirements | Contracting forms | Conditions of the contract
11.3.7.4 uniform | organizing | material | product | installation | administrative or procedural |
administrative | procedural | Division 01 | materials | fabrications | installation |
application
11.3.6 Descriptive | Performance | Reference standard | Proprietary
11.3.6.1 properties | workmanship | Proprietary | performance
11.3.6.2 results | compliance | methods
11.3.6.3 consensus | entirety
11.3.6.4 manufacturer’s | substitutions | bidder/proposer | named | little or no | wide | competition |
quality | several
11.3.5.1 accuracy, brevity, and clarity
11.3.5.2 verb | first | shall
11.3.5.3 effective
11.3.5.4 substitutes
11.3.5.5 quantity
11.3.5.6 consistent
11.3.5.7 legal | rules
11.3.5.8 agree | predicate
11.3.5.10 Personal
11.3.5.12 modifiers
Answers | Page 11
11.3.5.13 verbiage
11.3.5.14 commensurate | without
11.3.10 Administrative and Procedural Requirements | Temporary Facilities and Controls |
Performance Requirements | Life Cycle Activities | execution
11.3.10.1 parallel
11.3.10.2 expands | broadly | bidding | responsibilities | broadly | general | specification | specific
11.3.10.4 Procurement requirements | Conditions of the contract | Division 01 - General
Requirements | Individual specification sections
1. A [GreenFormatTM]
2. C [PDPG Figure 11.13 and SectionFormatTM]
3. A [PDPG 9.3.2]
4. D [PDPG 11.3.7.3 and MasterFormat® Introduction and Applications Guide]
5. C [PDPG 11.3.10]
6. A [PDPG 11.3.4.3]
7. B [PDPG 11.3.4.3]
8. B [PDPG 11.3.7]
9. D [PDPG 11.3.5]
10. C [PDPG 11.3.5]
11. C [PDPG 11.3.10.4]
12. A and B [PDPG 11.3.5.2]
13. D [PDPG 11.3.7.3]
14. B [PDPG 11.3.7.3 and MasterFormat®]
15. C [PDPG Figure 11.13 and SectionFormatTM]
16. True [PDPG 11.3.7.1]
TM
17. False [GreenFormat is organized by MasterFormat® ]
18. A Substructure
B Shell
C Interiors
D Services
E Equipment and Furnishings
F Special Construction & Demolition
G Building Sitework
Z General
[PDPG 11.3.7.2]
11.2.1 variety
11.2.2 design intent | Location | Identification | Dimension and size | Details and diagrams of
connections | Shape and form
11.2.3.1 traditional | Financial advisors | Lenders | Cost estimators | Authorities having jurisdiction
11.2.3.2 general | Preliminary project descriptions | detailed | Outline specifications | aesthetic |
qualities
11.2.3.3 Contract drawings | Resource drawings | enforceable | Alteration | Drawings during
construction | Record drawings
11.2.3.4 illustrate | shop | not | clarifications | supplement
11.2.3.5 contract | Field changes | Modifications | Supplemental drawings | actual | maintenance
Answers | Page 12
11.2.4 Plans | Elevations | Sections | Details | Schedules | Perspectives | Isometrics
11.2.4.1 Scaled | Nonscaled
11.2.4.2 plans | elevations | Sections | detail
11.2.4.3 Diagrams | Key plans | Schedules | Perspectives | Isometrics | Title sheet drawings |
Diagrams | key | Schedule | perspective | isometric
11.2.5.1 Symbols and abbreviations | Dimensions | Drawing identification | Notes or keynotes |
Various types of graphic representations
11.2.5.2 locating
11.2.5.3 Name of the project | Name of the owner | Name of the A/E and consultants | General
project data such as location map | Code information | List of included sheets
11.2.6 disciplines | parts | contracts | phase | sequence | delivery
11.2.7 exchange | standards, guidelines, and tools
11.2.7.2 hierarchical | Discipline Designator | Major Group | Minor Groups | Status
11.2.7.3 format
11.2.8 thinking | database | visualization, analysis, and record keeping
1. C [PDPG 11.2.3.5]
2. B [PDPG 11.2.2]
3. True [PDPG 11.2.3.4]
Answers | Page 13
12.7.1.11 submission | finalize | rejection | withdraw | instructions | irregularities
12.7.1.12 reliability | unethical | fairness and impartiality
12.7.1.13 opened or considered | instructions | signatures | instructions | responsive | responsible |
errors | problematic | default | acceptability | significant | variance | evaluated | Private |
public
12.8.1 Owner | A/E | Prospective contractor or contractors
12.8.2 offer
12.8.3 contractor | Exchange | value analysis | Acceptance or rejection
12.8.4 design | extent
12.9.1 owner | owner | contractor | owner | owner | facility | competitive | negotiating
12.9.1.1 direct
12.9.1.2 lowest | solicit
12.9.2 buyer | seller
12.9.3 procurement
12.9.4 request for proposal | Visiting | bid | Evaluation | Delivery schedule | Terms of pricing |
Contract requirements | Modifications | Executing | Modifications | destination
12.9.5.1 origin | stocking or nonstocking
12.9.5.2 purchase order
12.9.5.4 distribution | Trade | assurance | measurement and payment
12.9.5.5 down | approved
12.9.5.6 selection | phasing | storage | delays | submittals | submittals
12.2 design | competitively | cost of the work | overhead and profit | stipulated | percentage |
exceed | negotiated | percentages | labor and material | extent | square foot | per item |
Labor | Material | Equipment | Overhead | Profit | Applicable taxes | Other pricing
considerations | prices
12.3 materials and equipment | services
12.4 evaluation | analysis | procurement |
12.4.1 Costs | Contingency | Overhead | Profit | estimated | profit
12.4.1.2 Incomplete | unverified | Errors | contractor | scheduling | Default
12.4.1.3 maintaining | Licensing | General | equipment
12.6 exchanging | contract
12.6.1 contractors | subcontractors | trade | plan | reporting | subscription | reproduction | printed |
reproducible media | electronic
12.6.2 fair | misuse or loss
5.3 bound | obligations or promises | service or product | Offer and Acceptance | Mutual
Consent | Capacity | Scope of Work | Consideration | Good Faith | Legality | Breach of
Contract | Written | Signatures
5.4 preparation | assurance | understood | interpreted and adjudicated
1. C [PDPG 12.7.1.7]
2. D [PDPG 5.4]
3. B [PDPG 11.21]
Answers | Page 14
13.3.1 Furnishing information to the contractor | Payment of fees and charges associated with
the work | Making payment to the contractor | Right to stop the work | Right to carry out
the work | Right to perform construction | Right to award separate contracts | Right to
clean | Right to partial occupancy | Termination for convenience | Termination for cause
13.3.2 Represent | payments | Interpret | disputes | Modify | Review | Observe | inspections
13.3.3 Review | substitution | supervision | construction | deliveries | payment and performance |
safety | testing | Implement and monitor | pay | submittals | inspections | record
13.3.4 bound
13.3.4.1 materials
13.3.4.2 labor
13.3.6 contractual | regulatory
13.3.8 measurement and verification
13.3.9 functional and performance | submittal | substitutions
13.9.3 many | 01 | RFI | shop | submittals | contractor | Acceptance | comparison
13.9.3.1 alternatives
13.9.3.2 Owner-Initiated Substitutions | Contractor-Initiated Substitutions | Integrated Project
Delivery Substitutions | Unavailability of Product
13.9.3.3 contract | research and document | A/E
13.9.2 time or cost | Change orders | Minor changes | contractor | order | directive
13.9.2.1 owner | contractor | A/E | Written requests for change | Minor changes | Change directives
| Change orders
13.9.2.2 instructions or clarifications
13.9.2.3 change order | value
13.9.2.4 addition, deletion, or revision
13.5 information | ideas | decisions | Purpose | Agenda | Time Limit
13.5.1 01
13.5.2.1 Introducing the project team | Establishing the ground rules for communication |
Explaining the administrative process
13.5.2.2 progress | forum | timely
13.5.2.3 Address the progress and scheduling of the work | Coordination between contractor and
subcontractors | Coordination between two or more subcontractors
13.5.2.4 installation | coordination
13.5.2.5 completion | submittal
13.5.2.6 as-needed
13.7 quality control | observe | inspect | administration | quality | Inform | defects and
deficiencies | inspections | correlate | observations | continual
13.7.2 representative | intervals | familiar | communicator | reject | inspections | Substantial |
Final | The contractor has completed the contract requirements | The A/E has inspected to
determine completion | The owner has made final payment to the contractor | The
Contractor has accepted final payment
13.7.3 supervise and direct | responsibility | control | contract
13.7.4 physical | legal | utility | separate
13.7.5 safety and welfare | codes and ordinances | approve
13.7.6 quality
13.7.8 contractor
13.7.9 reject | owner
13.7.9.1 A/E | contractor
13.7.11 A/E
13.7.12 communication | historical
13.7.14 actual | 01
13.7.15 feedback
Answers | Page 15
13.6 Product data | Shop drawings | Samples | Information submittals | Closeout submittals |
Maintenance material submittals | modify | assurance
13.6.1 conditions of the contract | A/E
13.6.2 no
13.6.3 perform | approved
13.6.3.1 responsive | Product Data | Shop Drawings | Samples
13.6.3.2 responsive | verification and certification | Coordination drawings | Certificates | Design
and delegated design data | Test and evaluation reports | Manufacturer’s instructions |
Manufacturer’s reports | Sustainable design reports | Qualification statements |
Construction photographs
13.6.3.3 O&M data | Bonds | Special warranties | Record documents | Spare parts and maintenance
materials | Keying
13.6.4 contractor | A/E | procedures
13.6.5 reviewed and approved | consistent | intent | accuracy and completeness
13.6.7 timely
13.6.8 complete and accurate | consistent | specified | submittal
13.8 quality | Quality Assurance | Quality Control
13.8.1 conditions of the contract | inform | defects and deficiencies | interpreter | intent | visit |
submittals | supervise and direct | means, methods
13.8.2 understanding | site | field | coordination | solutions | Scheduling | unclear or conflicting |
certifications
13.8.3 standard | tolerance | Monitoring | Testing
13.8.4 control | assurance
13.8.5 quality | criteria and workmanship
13.8.6 success
13.12 quantifying | disbursement
13.12.1 contracts | schedule of values |
13.12.2 contract documents | Periodic Progress | Provisional | Single
13.12.3 Stipulated Sum | Unit Price | Cost-Plus Fee
13.12.4 certify | observations | knowledge, information, and belief
13.12.5 schedule of values | measurable | materials | payroll
13.12.6 itemization | proportionate
13.12.7 representations
13.2.7.1 certifies | obligations
13.12.8 certification | acceptance
13.12.9 percentage | force | release
13.12.10 certification
13.12.11 breach | stop
13.12.12 control | property
13.12.13 substantial completion
13.12.14 A/E | intended purpose | acceptance
13.12.15 change order | Unit price item quantities | Stipulated allowances | Liquidated damages or
penalty/bonus clauses | Testing reimbursement | Reimbursement of utilities |
Reimbursement of owner’s expense for additional A/E services
13.10.11 contractor’s
13.10.13 contractor | direct | Personal protective equipment | Safety meetings | Safety committees |
New employee orientation | Accident/incident reporting
13.11 time | budget | claims | manage | adjustment | independent
13.11.1.1 foreseeable | inferred | documentation | damages
13.11.1.2 commensurate
13.11.2 right
13.11.2.1 contract documents | timing
Answers | Page 16
13.11.2.2 inferred
13.11.3 essence | reconciliation
13.11.3.1 management | understanding
13.11.4 accepted | negotiation | obligated
Answers | Page 17
14.2.4.6 Anticipate maintenance needs | Document the operations | Forecast future spending based
on facility records and operations and maintenance data | accounting | resources | present
and future
14.2.5 Permanent record set | Regular use set(s) | Equipment and systems information | Cleaning
and regular maintenance information
14.2.5.1 construction | actual | Modifications | Revisions | locations | underground | Modifications |
Identification | Shop drawings | Product data | Test reports | Other information
14.2.5.2 specific
14.2.6 occupancy | Facility use | Effectiveness | Efficiency | Operational cost | Maintenance |
Environment | Routing and preventive maintenance | Capital improvements | Facility
upgrades | System and equipment replacement
14.2.6.1 baseline
Answers | Page 18