Product Costing flow for Engineer-to-order Production

SAP’s Engineer-to-Order Production process, using the Project System module and valuing the cost of
sales for the finished product with actual production Costs.

1).Create Material With (Z5 Specific Configured) Strategy Group Z5 :


Bill of Material Creation

Standard Template: Standard WBS


Basic Data Tab
Control Data Tab

Save
CJ92- Standard WBS Change
Assignment Tab

Control Data Tab


Standard Network-CN01
Save again go to Change

Then select 0010 row and click on Activity Components


Then SAVE

Network Parameters from Sales Order: CN08


Sale Order Creation: VA01

Network header data automatically will generate while doing sale order

I did not do Sales Order Costing or Standard Costing but will come automatically based network link

Now WBS Element is blank after Sale Order save then will WBS create automatically
Now Sale Order Display: 51
WBS Element automatically generated

CJ20N-Project Builder—Open WBS element


Now release Project
Network Confirmation: CN25

Give network
KKA2: Result Analysis
CJ88’ Settlement
CKM3-Material Price Analysis