1. Choose Logistics --> Production - process -->Process order and then Process order -->Create
--> With material.(Or write COR1in the command box)
1. Material
Number
2. Plant
3. Order
Type
Then Enter: Header - General Data screen appears.
Then Enter
1. Total
Quantity
Here, you
specify the
quantity you
want to
produce
2. Finish Date
3. Start Date
Again enter
Select the menu option Confirmation → Enter for phase → Time ticket. (Or Write COR6)
Enter the completion confirmation number, or the order number, and phase number. This
identifies the phase to be confirmed.
If you enter only the order number, the system lists the operations and phases contained in
the order. Select the phase you want to confirm.
Choose between final confirmation and partial confirmation. If you want to confirm data for a phase
that is only partially processed, select the indicator Partial confirmation.If you want to confirm
data for a phase that is finished, and you wish to simultaneously clear any open
reservations for the phase, mark the indicator
Enter the data
1. Yield
2. Reason
if any
3. Running
Hours
4. Down Time
5. Power
Starting in the initial screen, select the menu options Logistics --> Materials management--
>Inventory management and then Goods movement --> Goods receipt--> For order. (Or write
MB31)
Write
1. Movement type
2. Order No.
3. Plant
How to Cancel a Completion Confirmation
Select the menu options Confirmation → Cancel. (Or write CORS in the command box)
Write the
Order number
To be
cancelled
Write Transaction
MB21
Enter
1. Movement
Type
2. Plant
Then Enter
Enter
All the
Required
Field.
1. Cost Center
2. Material code
3. Quantity
Then Enter
Save It And Note the Order Number.
How to Print The Order
Write Transaction
ZRSLIP
In command field.
Enter
1. Plant
2. Slip No.
And Then
Execute it
.
Click on
Print Preview
And Click On
Print TAB
Create Stock Transport Purchase Order
Select the
Material Code
Enter P.O Quantity & Plant
Select Condition
Type i.e. FRC1
Save It.
Write
P.O. no. and
Press Enter.
Click on
Expand Header
Click on Release option for Code: R1
Click on Release option for Code: R2
Execute
Here Quantity of Material in Stock is displayed.
Enter
Movement Type
Purchase Order
Enter the Quantity against which Goods Receipt is to be done & Storage Location.
Save it.
Document
Posted will
be
displayed.
Notification
Write the
1. Notification
Header
2. Functional Location
4. Reported By
Click on Structure List Button to search for the Equipment Tag no.
Select the Equipment from the structure
1. Malfunction Start
Date & Time.
2. Malfunction End
Date & Time.
3. Tick if it is a Breakdown.
Press Enter.
Breakdown Duration will
appear
2. In System Availability
Enter Availability
i) Before Malfunction
ii) After Malfunction
iii) After Task
Enter Condition
i) Before Malfunction
ii) After Malfunction
iii) After Task
Go to Activities Tab
Select the Code Group from
Press Enter
Fill in following data corresponding to the activity entered.
Start Date Start Time End Date End Time
1.
CLICK
ON
ON
3 (B) ENTER NAME OF THE VENDOR
NAME EMBEDED WITH *
PRESS ENTER
PRESS ENTER
4. PRESS ENTER
CLICK ON
5 (B)THE PURCHASE
ORDER IS DISPLAYED
5 (C)CLICK ON
BACK BUTTON TO
COME BACK TO
SERVICE SHEET
5 (D) TO CHOOSE ANOTHER LINE ITEM CLICK ON
5. CLICK ON
6. CLICK ON
7. PRESS ENTER
8. SELECT
SERVICE
9. CLICK ON
12. CLCIK ON
13. CHECK COST CENTER,
CHANGE IF REQUIRED
14. CLICK ON
17. CLICK ON TO
ACCEPT THE SERVICE
ENTRY SHEET
Execute
Write the
Inspectors
Name
And GR status
Whether it is
1. Accepted
2. Rejected
3. Partial
Accepted
4. Accept with
Penalty
1.Plant
2.Material
3.Date
This will give us the Complete Detail Related to that Material.
1.Daily Production.
2.Monthly production.
3.Yearly Production.
Date
Material
Plant
Enter
Material No.
IW39: Display of Orders.
Put Order Type and Period for which you want to display the report.
Than Execute.
It will give you the following details about cost.
TCODE : MB25
Put Plant and execute.
The report will be like this.
Report from ZPPMENU : Cost center Actual Varience.