Professional Documents
Culture Documents
TECHNIQUES.
If resources are not identified soon enough, they might not be available when
required and so delay the overall completion of the project. This will damage
the reputation of the organisation and may result in penalty charges.
The core material for the lesson is to be found in Chapters 13 of the module
text by Burke. You should read the module text as directed and complete all
the in text exercises and Self Assessed Questions. Also make use of the
supporting PowerPoint presentation.
*You should now read Chapter 13 of the module text, taking care to
follow the tables and in particular to understand the construction and
use of the resource histogram.
10.4 RESOURCE ESTIMATING, FORECASTING & AVAILABILITY.
SAQ 1: How does Burke define (i) Resource and (ii) Resource Planning
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
Ensure that you can freely convert between (i) Resource tables, (ii) Gantt
charts showing resource requirements and (ii) Resource histograms (e.g. see
Burke, Section 2).
Employees
Float Early Start Duration Required
Activity (Days) Date (Day) (Days) (per Day)
A1 0 1 2 2
A2 2 3 2 2
A3 0 3 2 6
A4 2 5 2 3
A5 0 5 4 1
A6 0 9 1 2
(a) Construct the associated Gantt chart, showing (i) any activity float and
(ii) resource requirements superimposed on each activity
(b) Construct a resource histogram based on (i) early starts, and (ii) late
starts.
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
10.6 RESOURCE SCHEDULING CONSTRAINTS
When a project is running late and the planned end date cannot be
exceeded, it is necessary to accelerate the project (see also Lesson 10:
Project Acceleration). For the purposes of this lesson, all we need to
understand is that we can accelerate the project by allocating additional
resources to it.
Resources
Planned
Resources Apply
Time-
Additional Limited
Resources
Time
Planned
End-Date
In the above example, because the end date is inflexible, the resource
availability must be flexible to accommodate the constraint.
Planned
Resources
Extend
End
Date
Time
Planned
End-Date
If insufficient resources are available to complete the project on time AND the
project end date cannot be moved then, as Burke says, something must give.
This type of situation is not supportable.
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
10.7 ANSWERS TO SELF-ASSESSMENT QUESTIONS.
SAQ 1:
(i) A resource is the machine or person who will perform the scope of work.
SAQ 2:
The resource constraint should be considered after having constructed the
network diagram, schedule Gantt chart and procurement schedule, but before
the cash-flow statement.
SAQ 3:
(a) The completed Gantt Chart should appear as shown:
Activity Day
Number 1 2 3 4 5 6 7 8 9
A1 2 2
A2 2 2
A3 6 6
A4 3 3
A5 1 1 1 1
A6 2
Total Resources 2 2 8 8 4 4 1 1 2
In this Gantt chart, float is shown for Activities A2 (2 days) and A4 (2 days).
Resource loadings are shown directly on activities.
(c) The discussion should centre on the “resource smoothing” effect which
can be achieved by moving activities within their float. If this mechanism is
not sufficient, other remedies must be sought to balance available and
required resources.
SAQ 4:
Working Overtime
Working Shifts
Increase Productivity
Job and Knock
Learning Curve
Sub-Contractors
Scope of Work.
SAQ 5:
Train your workforce during slack periods to gain new skills, which will
make them more productive and flexible in the future.
Burke reminds us that the profit of a company in the long term is likely to
depend directly on the efficient utilisation of its resources.
SAQ 7:
The least flexible resource - this could be the resource that comes
from overseas, is difficult to get hold of or is least available.