Professional Documents
Culture Documents
Information Update
March 25, 2022
Engineering Department
Police Department
Stabbing Case
At 9:36 am on Tuesday, March 22nd, patrols were dispatched to a complaint of a male having been
stabbed by a female at 309 Mill Street. Responding patrols found the male, 56-year-old Jamie Doyle,
had been stabbed in the chest. The investigation led to the arrest of the defendant, 51-year-old
Michelle Matthews, on charges of Assault in the Second Degree (a class “D” felony) and Criminal
Possession of a Weapon in the Fourth Degree (a class “A” misdemeanor). The defendant was
arraigned in City of Watertown Court and was released on her own recognizance (without bail).
K-9 Demonstration
Officer Wayne McConnell giving
a K-9 demonstration in a local
classroom.
Planning Department
The plans have been finalized and the parking issue on Court Street that was raised during the
preliminary design phase has been addressed. Originally, the plans called to convert the on-street
angled parking to parallel parking to allow for a two-way cycle track (bike lane). This would have
resulted in the loss of 23 parking spaces. After feedback from the Council and the public, the final
plans will retain angled parking for most of the street.
However, one safety improvement that the project will implement will be restriping these spaces to
convert them to reverse-angled parking. This style of parking space eliminates the limited visibility
movement that occurs when backing out of a traditional angled parking space. Leaving a reverse-
angled space by contrast is a simple movement akin to merging with traffic. Due to road geometry
considerations, a small segment of Court Street will convert to parallel parking to allow safer left-
turning movements from Arcade Street.
City Manager’s
Information Update
March 25, 2022
The project will also replace the existing water feature at Lachenauer Plaza with a circular concrete
fountain faced with a stone veneer and simple spray pattern. The new 16’ diameter, 16” tall fountain
will occupy approximately the same footprint as the existing fountain.
This project is currently out to bid with a due date of April 6, 2022. Copies of the final plan set and
bid book are both available in the Planning office if any Council Members wish to arrange a time to
examine them and/or ask questions of Staff related to the project.
Lachenauer
Plaza
Conceptual
Rendering
Water Department
Water Treatment
The water treatment staff installed equipment to pilot test sodium permanganate to oxidize organic
material. The goal of the test is to reduce disinfection by-products and was approved by the
NYSDOH.
Water Distribution
Crews have been pro-actively engaged in leak detection beginning near Thompson Park and
expanding city wide.
City Manager’s
Information Update
March 25, 2022
A sink hole was discovered & investigated by Distribution Staff on 3/4/22 at 135 North Rutland
Street. The crew found a leak within the 4” water main, which was quickly repaired.
The meter service crew answered 61 service calls for City residents.
Wastewater Treatment
WWTP staff are completing repairs to Final "B" settling tank. Wear strips on the rails need to be
replaced along with the drive unit on top of the tank. The new drive unit need parts which will be
fabricated on site by the WWTP staff.
WWTP staff has completed the city’s annual respirator training and annual fit testing prior to
disinfection starting April 1st.