You are on page 1of 46

IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

CHAPTER-19 : BRIDGE WORKS - SUBSTRUCTURE


RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
191010 Exploratory drilling of Boreholes down to required depth, drilling of 150mm
diameter boreholes in all type of soils except hard rock and large boulders
(boulder core more than 30 cm), including refilling and reinstating surface,
and disposing off surplus material including use of mechanical rigs with
power operated winches as well as percussion / chieselling tool for
advancing through occasional seams of hard strata to be employed, where
necessary in Dry area
191011 0m to 10m metre 9000 950.00 1.00 950.00
950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
Total 959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

191012 10m to 20m metre 9001 950.00 1.00 950.00


950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
Total 959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

191013 Exploratory drilling of Boreholes of 150mm diameter in all type of soils metre 9002 950.00 1.00 950.00
except hard rock/large boulders (core more than 30 cm), including refilling
and reinstating surface, and disposing off surplus material including use of
mechanical rigs with power op
950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
COST PER METER metre 1103.43

191014 30m to 40m metre 9003 950.00 1.00 950.00


950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

Page 1
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
191015 40m to 50m metre 9004 950.00 1.00 950.00
950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

191016 50m to 60m metre 9005 950.00 1.00 950.00


950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

191017 60 m to 70 m metre 9006 950.00 1.00 950.00


950.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 9.50
959.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 143.93
Cost per meter metre 1103.43

191020 Exploratory drilling of Boreholes down to required depth, drilling of 150mm


diameter boreholes in all type of soils except hard rock and large boulders
(boulder core more than 30 cm), including refilling and reinstating surface,
and disposing off surplus material including use of mechanical rigs with
power operated winches as well as percussion / chieselling tool for
advancing through occasional seams of hard strata to be employed where
necessary in River bed area including standing/flowing water up to 2 M
depth with all necessary arrangements

191021 0m to 10m metre 9008 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191022 10m to 20m metre 9009 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00

Page 2
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191023 20m to 30m metre 9010 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191024 30m to 40m metre 9011 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191025 40m to 50m metre 9012 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191026 50m to 60m metre 9013 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191027 60 to 70 M metre 9014 2600.00 1.00 2600.00


2600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 26.00
2626.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 393.90
Cost per meter metre 3019.90

191030 Extra for 150mm dia bore in hard Rock/ large Boulder at all levels metre 9015 2500.00 1.00 2500.00
2500.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 25.00

Page 3
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
2525.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 378.75
Cost per meter metre 2903.75

191040 Drilling of NX size borehole (75 mm dia) in all types of hard rock (fresh rock)
and collection of rock core samples from boreholes and preserving in boxes

191041 0m to 10m metre 9017 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65

191042 10m to 20m metre 9018 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65

191043 20m to 30m metre 9019 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65

191044 30m to 40m metre 9020 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65

191045 40m to 50m metre 9021 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65

Page 4
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Cost per meter metre 3600.65

191046 50m to 60m metre 9022 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65

191047 60 m to 70 m metre 9023 3100.00 1.00 3100.00


3100.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 31.00
3131.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 469.65
Cost per meter metre 3600.65
191050 Conducting in situ full size Plate load test (PLT) at selected location as per
IS: 1888 including making loading arrangements & casting of RCC/cast in
situ concrete footing as per codal provisions including excavation and
refilling of trial pit
191051 a. Plate size 30 cm x 30 cm
Conducting in situ full size Plate load test (PLT) at selected location as per Each 9025 16500.00 1.00 16500.00
IS: 10042-1984 including making loading arrangements & casting of
RCC/cast in situ concrete footing as per codal provisions including
excavation of trial pit : Plate size 30 cm
16500.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 165.00
Total 16665.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2499.75
Cost of each Each 19164.75
191052 b. Plate size 45 cm x 45 cm
Conducting in situ full size Plate load test (PLT) at selected location as per Each 9026 18600.00 1.00 18600.00
IS: 10042-1984 including making loading arrangements & casting of
RCC/cast in situ concrete footing as per codal provisions including
excavation of trial pit : Plate size 45 cm
18600.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 186.00
Total 18786.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2817.90

Cost of each each 21603.90


191053 c. Plate size 60 cm x 60 cm Each 9027 25600.00 1.00 25600.00

Page 5
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 256.00
Total 25856.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3878.40

Cost of each Each 29734.40

191060 Conducting in situ Vane shear test for soil as per IS 4434 Each 9028 1605.00 1.00 1605.00

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 16.05
Total 1621.05
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 243.16

Cost of each Each 1864.21

191070 Conducting SCPT for soil as per IS - 4968 Each 9029 28000.00 1.00 28000.00

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 280.00
Total 28280.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 4242.00

Cost of each Each 32522.00

191080 Conducting DCPT for soil as per IS - 4968 Each 9030 25000.00 1.00 25000.00

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 250.00
Total 25250.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3787.50

Cost of each Each 29037.50

191090 Conducting determination of California Bearing Ratio as per IS 2720 Each 9031 3050.00 1.00 3050.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 30.50
Total 3080.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 462.08

Cost of each Each 3542.58

Page 6
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
191100 Taking out 100mm dia & 450mm long undisturbed samples of soil from bore Each 9032 110.00 1.00 110.00
holes, including provision of air tight containers for packing and, labelling
incl. transporting the samples to laboratory. Piston sampler shall be used for
extracting undisturbed samples where necessary. Samples shall be
collected as per IS 2720
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.10
Total 111.10
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 16.67
Cost of each Each 127.77
191110 Taking out 100mm dia & 450mm long disturbed samples of soil from bore Each 9033 110.00 1.00 110.00
holes, including provision of air tight containers for packing, labelling and
transporting the samples to laboratory. Samples shall be collected as per IS
2720
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.10
Total 111.10
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 16.67

Cost of each Each 127.77

191120 Conducting standard penetration test as per IS 2131 at approximate1.5 m Each 9034 116.00 1.00 116.00
intervals in bore holes, as directed by the Engineer in charge
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.16
Total 117.16
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 17.57

Cost of each Each 134.73

191130 Collection of water samples at required intervals Each 9035 13.00 1.00 13.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.13
Total 13.13
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1.97
Cost of each Each 15.10

191140 Conducting laboratory Tests on collected soil samples as per relevant IS


code
191141 Moisture contents/ Dry density Each 9036 38.00 1.00 38.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.38
Total 38.38
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5.76
Cost of each Each 44.14

Page 7
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
191142 Atterberg Limit Each 9037 45.00 1.00 45.00

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.45
Total 45.45
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 6.82
Cost of each Each 52.27

191143 Specific Gravity Each 9038 33.00 1.00 33.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.33
Total 33.33
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5.00
Cost of each Each 38.33

191144 Grain size analysis including Hydrometer analysis Each 9039 146.00 1.00 146.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.46
Total 147.46
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 22.12
Cost of each Each 169.58

191145 Direct Shear Test Each 9040 602.00 1.00 602.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 6.02
Total 608.02
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 91.20
Cost of each Each 699.22

191146 Natural density Each 9041 26.00 1.00 26.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.26
Total 26.26
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3.94
Cost of each Each 30.20

191147 Consolidation test Each 9042 73.00 1.00 73.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.73
Total 73.73
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 11.06
Cost of each Each 84.79

191148 Unconfined compression test Each 9043 602.00 1.00 602.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 6.02
Total 608.02
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 91.20

Page 8
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Cost of each Each 699.22

191149 Tri-axial test Each 9044 602.00 1.00 602.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 6.02
Total 608.02
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 91.20
Cost of each Each 699.22

191150 Conducting Laboratory tests on collected ROCK SAMPLES as per relevant


IS code

191151 Density test Each 9045 200.00 1.00 200.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 2.00
Total 202.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 30.30
Cost of each Each 232.30

191152 Water absorption & Porosity Each 9046 200.00 1.00 200.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 2.00
Total 202.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 30.30
Cost of each Each 232.30

191153 Hardness Each 9047 300.00 1.00 300.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 3.00
Total 303.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 45.45
Cost of each Each 348.45

191154 Unconfined compression test Each 9048 602.00 1.00 602.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 6.02
Total 608.02
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 91.20
Cost of each Each 699.22

191155 Point load test Each 9049 1100.00 1 1100.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 11.00
Total 1111.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 166.65
Cost of each Each 1277.65

Page 9
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
191156 Modulus of elasticity Each 9050 5000.00 1.00 5000.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 50.00
Total 5050.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 757.50
Cost of each Each 5807.50

191157 Abrasion testing Each 9051 2000.00 1.00 2000.00


Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 20.00
Total 2020.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 303.00
Cost of each Each 2323.00

191160 Conducting chemical analysis of ground water samples to determine Each 9052 13.00 1.00 13.00
suitability for concreting and aggressiveness in relation to attack on
concrete / reinforcement including determination of pH value
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.13
Total 13.13
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1.97
Cost of each Each 15.10

191170 Conducting chemical analysis of soil samples to determine aggressiveness Each 9053 13.00 1.00 13.00
in relation to attack on concrete / reinforcement including determination of
pH value
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.13
Total 13.13
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1.97
Cost of each Each 15.10

191180 Preparation and submission of Final report giving complete and Each 9054 55000.00 1.00 55000.00
comprehensive record of investigations, laboratory test reports and
calculations in approved format
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 550.00
Total 55550.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 8332.50
Cost of each Each 63882.50
OPEN FOUNDATION

Page 10
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192010 Earth work in excavation for foundations and floors of the bridges, retaining
walls etc., including setting out, dressing of sides, ramming of bottom,
getting out the excavated material, back filling in layers with approved
material and consolidation of the layers by ramming and watering etc. incl.
all lift, disposal of surplus soil upto a lead of 300 M, all types of shoring and
strutting with all labour and material complete as per drawing and technical
specification as directed by Engineer in charge
192011 All kinds of soils cum
Ordinary soil
Unit = cum
Taking output = 10cm
Manual Means
a) Labour
Mate Day 0128 221.67 0.18 39.90
Beldar Day 0114 187.50 4.50 843.75
b) Machinery
Hire and running charges of tipper Day 0017 2225.00 0.25 556.25
Total 1439.90
Sundries (no rates reqd.) Lumpsum 9999 1.00 16.69 16.69
2012.84

d) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 20.13
2032.97
e) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 304.94

cost of 15 cum = a+b+c+d+e 2337.91 2337.91

Rate per cum = (a+b+c+d+e)/10 cum 233.79 233.79

192012 Ordinary rock cum


Ordinary rock (not requiring blasting)
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10cm
a) Labour
Mate Day 0128 221.67 0.20 44.33
Beldar Day 0114 187.50 8.00 1500.00
b) Machinery
Hire and running charges of tipper Day 0017 2225.00 0.25 556.25
Total 2100.58

Page 11
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Sundries (no rates reqd.) Lumpsum 9999 1.00 63.02 63.02
2163.60

d) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 21.64
2185.24
e) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 327.79

cost of 15 cum = a+b+c+d+e 2513.02 2513.02

Rate per cum = (a+b+c+d+e)/10 cum 251.30 251.30

192013 Hard rock ( requiring blasting) cum


Hard rock ( requiring blasting)
Manual Means
Unit = cum
Taking output = 10cm
a) Labour
Mate Day 0128 221.67 0.35 77.58
Rock Hole Driller Day 0134 243.33 0.50 121.67
Rock Excavator Day 0132 243.33 0.25 60.83
Beldar Day 0114 187.50 8.00 1500.00
b) Machinery
Hire and running charges of tipper Day 0017 2225.00 0.25 556.25
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.20 525.00
cutters /hammers
c) Material
Blasting powder Kg 0325 36.75 3.50 128.63
Blasting fuse (fuse wire) Each 0326 15.67 14.00 219.38

Total 2841.33 348.01

Sundries (no rates reqd.) Lumpsum 9999 1.00 61.11 61.11


2902.44 348.01
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 29.02 3.48
2931.47 351.49
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 439.72 52.72

cost of 10 cum = a+b+c+d+e+f 3371.19 404.21 3775.39

Rate per cum =(a+b+c+d+e+f)/10 cum 337.12 40.42 377.54

Page 12
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192014 Hard rock ( blasting prohibited ) cum
Hard rock ( blasting prohibited )
Unit = cum
Taking output = 10cm
Mechanical means
a) Labour
Mate Day 0128 221.67 0.20 44.33
Beldar Day 0114 187.50 5.00 937.50
b) Machinery
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 1.00 2625.00
cutters /hammers
Hire and running charges of tipper Day 0017 2225.00 0.25 556.25
4163.08
Sundries (no rates reqd.) Lumpsum 9999 1.00 124.89 124.89
4287.98
d) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 42.88
4330.86
e) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 649.63

cost of 10cum = a+b+c+d+e 4980.48 4980.48

Rate per cum = (a+b+c+d+e)/10 cum 498.05 498.05

192020 Extra for the quantity of works, executed in or underwater and/ or liquid mud
including pumping out water as required
Extra due to slow progress and dewatering of the rate of the item cum 20% of Basic of basic item
Items
192030 Providing and laying Plain Cement Concrete 1:3:6 with graded stone cum
aggregate of 40 mm nominal size, in foundation and floors, retaining walls
of bridges including mechanical mixing, vibrating, pumping and bailing out
water where ever required with all materials and labour complete but
excluding the cost of cement and shuttering as per drawings and technical
specifications as directed by Engineer

CC 1:3:6
Unit = cum
Taking output = 15 cm
a) Labour
Mate Day 0128 221.67 0.64 141.87
Mason (brick layer) 2nd class Day 0124 250.00 1.00 250.00
Coolie Day 0115 170.00 15.00 2550.00
b) Material

Page 13
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Stone Aggregate (Single size) : 40 mm nominal size cum 0293 500.00 13.50 6750.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Portland Cement free (rate not required) Tonne 0367 0.00 3.45 0.00
c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 0.20 220.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
4561.87 10800.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 491.76 491.76
5053.63 10800.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 50.54 108.00
5104.17 10908.00
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 765.62 1636.20
cost of 15 cm = a+b+c+d+e+f 5869.79 12544.20 18413.99

Rate per cum = (a+b+c+d+e+f)/15 cum 391.32 836.28 1227.60

192040 Providing and laying in position machine mixed, machine vibrated and cum
machine batched Design Mix Cement Concrete M35 grade (Cast - in Situ)
using 20 mm graded crushed stone aggregate and coarse sand of approved
quality in RCC raft foundation & Pile cap including finishing, Using
Admixtures in recommended proportions ( as per IS 9103), if approved in
Mix design to accelerate or retard setting of concrete and/or improve
workability without impairing strength and durability complete as per
specifications and direction of the Engineer in charge. Payment for cement,
reinforcement and shuttering shall be paid extra
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items

RCC Grade M35


Using concrete mixer
Unit = cum
Taking output = 15 cm
a) Material
Portland Cement free (rate not required) Tonne 0367 0.00 6.33 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 8.10 4050.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 5.40 2565.00
b) Labour
Mate Day 0128 221.67 0.86 190.64

Page 14
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50
Coolie Day 0115 170.00 20.00 3400.00
c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
6503.14 10665.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 574.18 574.18
7077.32 10665.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 70.77 106.65
7148.09 10771.65
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1072.21 1615.75
cost of 15 cm = a+b+c+d+e+f 8220.30 12387.40 20607.70

Rate per cum = (a+b+c+d+e+f)/15 cum 548.02 825.83 1373.85

192050 Providing and laying in position machine mixed, machine vibrated and cum
machine batched Design Mix Cement Concrete M20 grade (Cast - in Situ)
using 20 mm graded crushed stone aggregate and coarse sand of approved
quality in Abutment, pier, wing walls and return walls of Mass cement
concrete above RCC raft Including finishing complete as per specifications
and direction of the Engineer in charge. Payment for cement, reinforcement
and shuttering shall be paid extra
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
RCC Grade M20
Using concrete mixer
Unit = cum
Taking output = 15 cm
a) Material
Portland Cement free (rate not required) Tonne 0367 0.00 5.21 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 8.10 4050.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 5.40 2565.00
b) Labour
Mate Day 0128 221.67 0.86 190.64
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50
Coolie Day 0115 170.00 20.00 3400.00
c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50

Page 15
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
6503.14 10665.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 574.18 574.18
7077.32 10665.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 70.77 106.65
7148.09 10771.65
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1072.21 1615.75
cost of 15 cm = a+b+c+d+e+f 8220.30 12387.40 20607.70

Rate per cum = (a+b+c+d+e+f)/15 cum 548.02 825.83 1373.85

192060 Providing and laying in position machine mixed, machine vibrated and 0
machine batched Design Mix Cement Concrete M35 grade (Cast - in Situ)
using 20 mm graded crushed stone aggregate and coarse sand of approved
quality for the following Reinforced cement concrete structural elements up
to height of 10 M from foundation top level, including finishing, Using
Admixtures in recommended proportions ( as per IS 9103), if approved in
Mix design to accelerate or retard setting of concrete and/or improve
workability without impairing strength and durability complete as per
specifications and direction of the Engineer in charge. Payment for cement,
reinforcement and shuttering shall be paid extra

192061 Abutment & Pier cum


Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Rate same as for item 192040 cum 1373.85
Add extra for height 0.05 68.69
Cost per cum cum 1442.54
192062 Wing wall and Return wall cum
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Rate same as for item 192040 1373.85
Add extra for height and thin sections and slanting surfaces cum 0.10 137.38
1511.23
192063 Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, cum
Fender wall, Diaphragm wall, etc.
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Rate same as for item 192040 1373.85

Page 16
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Add extra for height and thin sections and slanting surfaces 0.15 206.08
cost per cum cum 1579.92
192064 Approach slab at formation level, Dirt wall/ ballast wall at formation level cum
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Rate same as for item 192040 1373.85
Add extra for height and thin sections and slanting surfaces 0.20 274.77
cost per cum cum 1648.62
192065 Extra for every increase of 1 M or part thereof in the height above 10 M & 20 cum/m height
M
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Taking output = 15 cm
a) Labour
Mate Day 0128 221.67 0.64 141.87
Mason (brick layer) 2nd class Day 0124 250.00 1.00 250.00
Coolie Day 0115 170.00 15.00 2550.00
Labour cost for 15 Cum at normal level 2941.87
Add for labour cost at 10mts height @ 5%/mt. 0.50 1470.93
4412.80
Labour cost/cum 225.90
Add for additional labour cost/Mt. heightor part thereof 0.05 11.30
Cost/cum/mtheight or part there of cum/m height 11.30 11.30

Page 17
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192070 Providing, Driving and installing Bored cast in situ Reinforced Cement
Concrete piles of specified diameter and length below pile cap in M- 35
grade Design Mix Cement Concrete , using 20 mm graded crushed stone
aggregate and coarse sand of approved quality, to carry a safe working load
not less than specified, excluding the cost of casing pipe but including the
cost of shoe and length of pile to be embedded in pile cap etc complete,
concreting by machine batching, machine mixing, scaffolding, using
Admixture in recommended proportion( as per IS 9103), if approved in
design Mix, placing with tremie pipe, chipping off of pile top to remove
laitance concrete above cut off level etc, pumping and bailing out water, with
all labour material complete including crossing of tracks if required, as per
approved drawing, specification and direction of the Engineer in charge.
Length of the pile for payment shall be measured Up to the bottom of pile
cap excluding the mud mat. Payment for cement, casing pipe &
reinforcement shall be paid extra

Note: The shuttering, scaffolding,centering, Reinforcement, placing of


reinforcement and cost of cement to be paid extra under relevant items
192071 1500mm diameter metre
Pile diameter = 1200mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 9062 3000.00 15.91 47730.00
Rate for concrete may be adopted same as for bottom plug vide item no.
192040
Concrete to be cast with a tremie pipe 200 mm dia.
b) Machinery(for boring and construction)
Hire and running charges of hydraulic piling rig with power unit etc. including per Day 0024 29000.00 1.50 43500.00
complete accessories and shifting at site.
Hire and running charges of light crane per Day 0025 3000.00 0.10 300.00
Hire and running charges of bentonite pump per Day 0026 4000.00 1.50 6000.00
Hire and running charges of loader Day 0018 4500.00 0.20 900.00
Hire and running charges of tipper Day 0017 2225.00 0.20 445.00
Bentonite Tonne 7185 2500.00 0.60 1505.00

c) Labour
Mate Day 0128 221.67 0.28 62.07
Beldar Day 0114 187.50 7.04 1320.00
54032.07 47730.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 2264.06 2264.06

Page 18
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
56296.13 47730.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 562.96 477.30
56859.09 48207.30
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 8528.86 7231.10
cost of 15 cm = a+b+c+d+e+f 65387.95 55438.40 120826.35

Rate per Metre = (a+b+c+d+e+f)/9 metre 7265.33 6159.82 13425.15

192072 1200mm diameter metre


Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Pile diameter = 1200mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 9062 3000.00 10.17 30510.00
Rate for concrete may be adopted same as for bottom plug vide item no.
192040
Concrete to be cast with a tremie pipe 200 mm dia.
b) Machinery(for boring and construction)
Hire and running charges of hydraulic piling rig with power unit etc. including per Day 0024 29000.00 1.00 29000.00
complete accessories and shifting at site.
Hire and running charges of light crane per Day 0025 3000.00 0.10 300.00
Hire and running charges of bentonite pump per Day 0026 4000.00 1.00 4000.00
Hire and running charges of loader Day 0018 4500.00 0.20 900.00
Hire and running charges of tipper Day 0017 2225.00 0.20 445.00
Bentonite Tonne 7185 2500.00 0.39 975.00

c) Labour
Mate Day 0128 221.67 0.18 39.90
Beldar Day 0114 187.50 4.50 843.75
36503.65 30510.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 1492.90 1492.90
37996.55 30510.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 379.97 305.10
38376.52 30815.10
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5756.48 4622.27
cost of 15 cm = a+b+c+d+e+f 44132.99 35437.37 79570.36

Rate per Metre = (a+b+c+d+e+f)/9 metre 4903.67 3937.49 8841.15

Page 19
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192073 1000mm diameter metre
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Pile Diameter = 1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 9062 3000.00 7.85 23550.00
Rate for concrete may be adopted same as for bottom plug vide item no.
192040
Concrete to be cast with a tremie pipe 200 mm dia.
b) Machinery(for boring and construction)
Hire and running charges of hydraulic piling rig with power unit etc. including per Day 0024 29000.00 1.00 29000.00
complete accessories and shifting at site.
Hire and running charges of light crane per Day 0025 3000.00 0.10 300.00
Hire and running charges of bentonite pump per Day 0026 4000.00 1.00 4000.00
Hire and running charges of loader Day 0018 4500.00 0.10 450.00
Hire and running charges of tipper Day 0017 2225.00 0.10 222.50
Bentonite Tonne 7185 2500.00 0.35 875.00

c) Labour
Mate Day 0128 221.67 0.16 35.47
Beldar Day 0114 187.50 4.00 750.00
35632.97 23550.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 1376.22 1376.22
37009.19 23550.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 370.09 235.50
37379.28 23785.50
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5606.89 3567.83
cost of 15 cm = a+b+c+d+e+f 42986.17 27353.33 70339.50

Rate per Metre = (a+b+c+d+e+f)/10 metre 4298.62 2735.33 7033.95

192074 800mm diameter metre


Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Pile Diameter = 750 mm
Unit = meter
Taking Output = 15 m
a) Materials
PCC Grade M35 cum 9062 3000.00 6.62 19860.00

Page 20
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Rate for concrete may be adopted same as for bottom plug vide item no.
192040
Concrete to be cast with a tremie pipe 200 mm dia.
b) Machinery(for boring and construction)
Hire and running charges of hydraulic piling rig with power unit etc. including per Day 0024 29000.00 1.00 29000.00
complete accessories and shifting at site.
Hire and running charges of light crane per Day 0025 3000.00 0.10 300.00
Hire and running charges of bentonite pump per Day 0026 4000.00 1.00 4000.00
Hire and running charges of loader Day 0018 4500.00 0.10 450.00
Hire and running charges of tipper Day 0017 2225.00 0.10 222.50
Bentonite Tonne 7185 2500.00 0.35 875.00

c) Labour
Mate Day 0128 221.67 0.16 35.47
Beldar Day 0114 187.50 4.00 750.00
35632.97 19860.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 1319.89 1319.89
36952.86 19860.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 369.53 198.60
37322.39 20058.60
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5598.36 3008.79
cost of 15 cm = a+b+c+d+e+f 42920.74 23067.39 65988.13

Rate per Metre = (a+b+c+d+e+f)/15 metre 2861.38 1537.83 4399.21

192075 600mm diameter metre


Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Pile Diameter = 750 mm
Unit = meter
Taking Output = 22 m
a) Materials
PCC Grade M35 cum 9062 3000.00 6.22 18660.00
Rate for concrete may be adopted same as for bottom plug vide item no.
192040
Concrete to be cast with a tremie pipe 200 mm dia.
b) Machinery(for boring and construction)
Hire and running charges of hydraulic piling rig with power unit etc. including per Day 0024 29000.00 1.00 29000.00
complete accessories and shifting at site.
Hire and running charges of light crane per Day 0025 3000.00 0.10 300.00
Hire and running charges of bentonite pump per Day 0026 4000.00 1.00 4000.00

Page 21
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Hire and running charges of loader Day 0018 4500.00 0.10 450.00
Hire and running charges of tipper Day 0017 2225.00 0.10 222.50
Bentonite Tonne 7185 2500.00 0.30 750.00

c) Labour
Mate Day 0128 221.67 0.14 31.03
Beldar Day 0114 187.50 3.50 656.25
35409.78 18660.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 1295.41 1295.41
36705.19 18660.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 367.05 186.60
37072.25 18846.60
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 5560.84 2826.99
cost of 15 cm = a+b+c+d+e+f 42633.08 21673.59 64306.67

Rate per Metre = (a+b+c+d+e+f)/22 metre 1937.87 985.16 2923.03

192080 Providing, fabricating and installing of casing pipe for bored piles for all MT
diameters with specified thickness of steel plate including all labour,
materials, pumping and bailing out water where ever required, complete as
per technical specifications as directed by Engineer in charge. This will
include the weight of plate only and no cognizance will be given for the
fittings i.e. rivets and welding etc.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel such as tees, angles channels and R.S. joists quintal 1007 3650.00 10.50 38325.00
b) Labour
Mate Day 0128 221.67 1.24 274.87
Fitter (Grade-1) Day 0116 300.00 6.00 1800.00
Blacksmith 1st class Day 0102 250.00 5.00 1250.00
Assistant Fitter or 2nd class Fitter Day 0117 245.00 5.00 1225.00
Beldar Day 0114 187.50 10.00 1875.00
6424.87 38325.00
c) Electrodes, cutting gas and other consumables @ 5 percent on cost a (a) 0.05 44749.87 2237.49
above
8662.36 38325.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 225.34 225.34
8887.70 38325.00
e) Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 88.88 383.25
8976.58 38708.25

Page 22
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
f) Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1346.49 5806.24

Cost of MT = a+b+c+d+e+f 10323.07 44514.49 54837.56

Rate per MT = (a+b+c+d+e+f) MT 10323.07 44514.49 54837.56

192090 Extra for chieselling in addition to boring of piles if chieselling is resorted to


in hard rock or big stone boulders larger than 30 cm depth by any means i.e.
by chiesel or manual chiesel and hammer method
192091 1200mm Diameter pile metre
Details of cost for 0.5 cum
Beldar Day 0114 187.50 3.00 562.50
Assistant Fitter or 2nd class Fitter Day 0117 245.00 0.05 12.25
574.75
Sundries (no rates reqd.) Lumpsum 9999 1.00 20.00 20.00
20.00 574.75
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.20 5.75
20.20 580.50
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3.03 87.07
Cost for 0.5 cum 23.23 667.57 690.80
Rate per cum 46.46 1335.14 1381.60
Rate per metre (Qty of 1 M =22/7*1.2*1.2/4*1 =1.13 cum) metre 1.13 1563.19

192092 1000mm Diameter


Qty of 1 M =22/7*1.0*1.0/4*1 =0.786 cum metre 1381.60 0.79 1085.55
Add extra for reestricted space in working inside the shaft of pile. 0.10 108.55
Cost per meter metre 1194.10

192093 800mm Diameter


Qty of 1 M =22/7*0.8*0.8/4*1 =0.503 cum metre 1381.60 0.50 694.75
Add extra for reestricted space in working inside the shaft of pile. 0.30 208.42
Cost per meter metre 903.17

192094 600mm Diameter


Qty of 1 M =22/7*0.6*0.6/4*1 =0.283 cum metre 1381.60 0.28 390.80
Add extra for reestricted space in working inside the shaft of pile. 0.50 195.40
Cost per meter metre 586.19

Page 23
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192100 Conducting load testing of a single pile Up to following capacity in
accordance with IS 2911(Part IV) including installation of loading platform
and preparation of pile head or construction of test cap and dismantling of
test cap after test etc with all labour, material, tool & plants, equipment,
machinery, etc complete as per drawing and specification, as directed by the
Engineer

192101 Initial load test Up to 50 ton capacity pile Each 7246 23500.00 1.00 23500.00
23500.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 585.00 585.00
24085.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 240.85
24325.85
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3648.88

Cost of MT = a+b+c+d 27974.73

Rate per TEST = (a+b+c+d) Each 27974.73

192102 Initial load test above 50 ton capacity Up to 100 ton capacity pile Each 7247 27500.00 1.00 27500.00
27500.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 825.00 825.00
28325.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 283.25
28608.25
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 4291.24

Cost of MT = a+b+c+d 32899.49

Rate per TEST = (a+b+c+d) Each 32899.49

192103 Initial load test above 100 ton capacity Up to 250 ton capacity pile
Extra to 'rate code' - 7247 for vertical load above 100 MT upto 250 MT MT 9055 600.00 75.00 45000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 675.00 675.00
45675.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 456.75
46131.75
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 6919.76
Rate per TEST = (a+b+c+d) 53051.51
f) Initial rate upto 100 tonne capacity as above per test 32899.49 1.00 32899.49
TOTAL Each 85951.00

Page 24
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

192104 Extra for every increase of 50 T in pile capacity or part thereof over 250 T Each
Extra to 'rate code' - 7247 for vertical load above 250 MT MT 9056 600.00 25.00 15000.00
15000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 225.00 225.00
15225.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 152.25
15377.25
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2306.59

Rate per TEST = (a+b+c+d) Each 17683.84

192105 Routine Load Test Up to 50 ton capacity pile Each 7249 13500.00 1.00 13500.00 As per
171652
Sundries (no rates reqd.) Lumpsum 9999 1.00 345.00 345.00
13845.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 138.45
13983.45
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2097.52

Rate per TEST = (a+b+c+d) Each 16080.97

192106 Routine Load Test above 50 ton capacity Up to 100 ton capacity pile Each 7250 20000.00 1.00 20000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 540.00 540.00
20540.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 205.40
20745.40
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3111.81

Rate per TEST = (a+b+c+d) Each 23857.21

192107 Routine Load Test above 100 ton capacity Up to 250 ton capacity pile Each
Extra to 'rate code' - 7247 for vertical load above 250 MT MT 9056 600.00 75.00 45000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 675.00 675.00
45675.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 456.75
46131.75
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 6919.76
Rate per TEST = (a+b+c+d) 53051.51
f) Initial rate upto 100 tonne capacity as above per test 23857.21 1.00 23857.21
76908.72

Page 25
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
TOTAL Each 76908.72

192110 Lateral load testing of single pile in accordance with “IS Code of practice IS:
2911 (Part IV) for determining safe allowable lateral load of pile” with all
labour, material, tool & plants, equipment, machinery, etc complete as per
drawing and specification as directed by the Engineer
192111 Piles with lateral load capacity of Up to 10 ton Each 7252 15000.00 15000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 345.00 345.00
15345.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 153.45
15498.45
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2324.77

Rate per TEST = (a+b+c+d) 17823.22

TOTAL Each 17823.22

192112 Piles with lateral load capacity of above 10 ton & Up to 20 ton Each 7253 21000.00 21000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 540.00 540.00
21540.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 215.40
21755.40
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3263.31

Rate per TEST = (a+b+c+d) 25018.71

TOTAL Each 25018.71

192113 Piles with lateral load capacity of above 20 ton


Basic cost for lateral load capacity up to 20 tonne . Each 25018.71 1.00 25018.71
Extra to 'rate code' - 7253 for lateral load above 20 tonne MT 9057 6000.00 2.50 15000.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 375.00 375.00
40393.71
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 403.94
40797.65
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 6119.65

Rate per TEST = (a+b+c+d) 46917.29

TOTAL Each 46917.29

Page 26
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
192120 Pulse Echo Test (PET) for integrity testing of piles with contractor’s men, per test 7246 23500.00 1.00 23500.00
materials and machines. The rate includes cost of Inspection of site,
preparation of pile head and any other unforeseen cost required for the test,
submission of reports in triplicate as per satisfaction of the Engineer in
Charge at site
Sundries (no rates reqd.) Lumpsum 9999 1.00 1500.00 1500.00
25000.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 250.00
25250.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 3787.50
Rate per Test Each 29037.50

WELL FOUNDATION
193010 Earth work in OPEN excavation in foundation of bridges, for placing of well cum
curbs of all shapes and designs in all kinds of soil including taking out the
excavated soil, levelling, ramming of bottom of excavation and trimming of
sides, returning the soil in layers, consolidation, disposal of surplus soil
within a lead of 300 M, incl. all lift, dewatering, shoring and strutting
complete as per technical specification and as directed by Engineer in
charge. (The compaction of surplus soil when led to the bank will be paid as
per relevant item separately)
Depth 3 m to 6 m Average depth) 0-9 mts
Unit = meter
Taking output =120 cum
a) Labour
Mate Day 0128 221.67 0.32 70.93
Beldar Day 0114 187.50 8.00 1500.00
b) Machinery
Hire charges of Hydraulic Excavator Day 0020 6275.00 0.75 4706.25
Hire and running charges of tipper Day 0017 2225.00 1.00 2225.00
Total 8502.18
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 85.02
(a+b+c) 8587.21
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1288.08

Cost for 120 cum = a+b+c+d 9875.29 9875.29

Rate per cum =(a+b+c+d)/120 cum 82.29 82.29

193011 Extra to item for Earth work in excavation over item no. 193010 if the cum
excavation is carried out in Rock not requiring blasting

Page 27
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Taking Output 75 cum
a) Labour
Mate Day 0128 221.67 0.24 53.20
Beldar Day 0114 187.50 6.00 1125.00
b) Machinery
Hire charges of Hydraulic Excavator Day 0020 6275.00 0.75 4706.25
Hire and running charges of tipper Day 0017 2225.00 1.00 2225.00
Total 8109.45
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 81.09
(a+b+c) 8190.55
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1228.58

Cost for 75 cum = a+b+c+d 9419.13 9419.13

Rate per cum =(a+b+c+d)/75 cum 125.59 125.59

193012 Extra for Earth work in excavation over item 193010 if the excavation is cum
carried out requiring controlled blasting or chieselling where required and
permitted by the engineer in charge
Unit cum
Taking Output 15 cum
a) Labour
Mate Day 0128 221.67 0.20 44.33
Beldar Day 0114 187.50 5.00 937.50
b) Machinery
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.75 1968.75
cutters /hammers
Hire and running charges of tipper Day 0017 2225.00 0.20 445.00
Total 3395.58
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 33.96
(a+b+c) 3429.54
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 514.43

Cost for 10 cum = a+b+c+d 3943.97

Rate per cum =(a+b+c+d)/15 cum 262.93 0.00 262.93

Page 28
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
193020 Providing and constructing Temporary Earthen Island / coffer dam for
construction of well foundations, including bailing and pumping out of water,
provision of sand bags, wooden ballies, sheet piling, earth, sand or any
other suitable material, in water depth upto 1.5m, as required with all labour
and material complete job
193021 For well size (longest dimension) upto 10 M 0
Providing and Constructing Temporary Island 16 m diameter for
construction of Well Foundation for 8m dia. Well
Assuming depth of water 1.0 m and height of island to be 1.25 m
Unit = 1 No.
Taking output = 1 No.
a) Material
Earth (compacted) cum 0979 16.50 251.20 4144.80
Filled Sand bags (30 kg weight) Each 9058 5.00 750.00 3750.00
b) Labour
Mate Day 0128 221.67 0.40 88.67
Beldar Day 0114 187.50 15.00 2812.50
c) Machinery
Hire and running charges of light crane per Day 0025 3000.00 1.00 3000.00
5901.17 7894.80
Sundries (no rates reqd.) Lumpsum 9999 1.00 410.29 410.29
6311.46 7894.80
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 946.72 1184.22

Rate for Each UNIT Each 7258.18 9079.02 16337.20

193022 For well size (longest dimension) above 10 M Each


Assuming depth of water 4m and height of island 4.5 mts. Island dia =
16mts average
Assuming depth of water 4.0 m and height of island 4.5 m
Unit =1 No.
Taking output = 1No.
a) Material
Earth (compacted) cum 0979 16.50 904.32 14921.28
Filled Sand bags (30 kg weight) Each 9058 5.00 6000.00 30000.00
Hollock ballies 150 mm diameter metre 2448 64.69 95.00 6145.55
Hollock ballies 80 mm diameter metre 2445 37.19 190.00 7066.10
b) Labour
Mate Day 0128 221.67 5.60 1241.35
Beldar Day 0114 187.50 120.00 22500.00
c) Machinery

Page 29
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Hire and running charges of light crane per Day 0025 3000.00 2.00 6000.00
29741.35 58132.93
Sundries (no rates reqd.) Lumpsum 9999 1.00 2191.07 2191.07
31932.42 58132.93
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 4789.86 8719.94
Rate per No. Each 36722.29 66852.87 103575.15

193030 Supplying, Fabrication, assembly erection & placing in position of cutting metre
edge of well curb with structural steel including M.S sheet/ Plates of
specified thickness for pier/abutment complete as per approved plans and
as per direction of Engineering In charge including all operations like cutting,
bending, straightening, drilling holes, bolting, riveting, welding, threading,
jointing of steel sections including outer and inner places liners and skin
plates, stiffeners, hooks bottle nuts, bond rods etc as per design including all
ascent, descents, leads, lifts, handing, re-handling, all other obstructions
whatsoever, diverting channels, pumping / bailing out of water and wherever
required including cost of steel such as flats, sheets, angles, steel bars etc.
with all labour and material as a complete job

Unit = 1 No.
Taking Output = 1 MT
a) Material
Structural steel such as tees, angles channels and R.S. joists quintal 1007 3650.00 10.50 38325.00
Nut and bolts Kg 9059 60.00 20.00 1200.00
39525.00
Electrodes, cutting gas and other consumables @ 10 per cent of cost of (a) 0.10 3952.50
above

b) Labour
(for cutting, bending, making holes, joining, welding and erecting in position)

Mate Day 0128 221.67 1.32 292.60


Fitter (Grade-1) Day 0116 300.00 5.50 1650.00
Blacksmith 1st class Day 0102 250.00 5.50 1375.00
Assistant Fitter or 2nd class Fitter Day 0117 245.00 5.50 1347.50
Beldar Day 0114 187.50 16.50 3093.75

Total a+b 7758.85 43477.50

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 77.59 434.78

Page 30
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
7836.44 43912.28
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1175.47 6586.84

Rate per metre =(a+b+c+d) metre 9011.91 50499.12 59511.03

193040 Dry/Wet Sinking of Circular Wells (Other than pneumatic method) in all
types of strata except hard rock requiring ballasting, including bailing and
pumping out water, removal of excavated soil, with all labour and material
required for sinking as per drawing and direction of the Engineer in charge,
disposal of surplus soil upto 1 Km lead in the adjoining bank/embankment
(The compaction to be paid separately under the relevant item)

193041 From initial level of cutting edge & Up to 3m depth cum


Dia of well(assumed) 9 metre Area 63.64
Unit = Running meter
Taking output = 1cum
Depth below bed level upto 3.0 M
Rate of sinking 0.085 m/hour
a) Labour
Mate Day 0128 221.67 0.24 53.20
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 2.25 506.25
Beldar Day 0114 187.50 3.75 703.13
b) Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and Day 9060 6500.00 0.75 4875.00
accessories
6137.58
c) Add water charges @ 1% + Dewatering charges @ 5% 0.06 368.25
6505.83
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 975.87

Rate per metre =(a+b+c+d) 7481.70 7481.70

Rate per Cum cum 117.66

193042 From 3m to 10m depth cum


Beyond 3 m upto 10m depth
Rate of sinking 0.15/hour
a) Labour
Mate Day 0128 221.67 0.34 75.37
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 2.50 562.50

Page 31
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Beldar Day 0114 187.50 5.00 937.50
b) Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and Day 9060 6500.00 0.75 4875.00
accessories
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.60 1575.00
cutters /hammers
8025.37
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 481.52
8506.89
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1276.03

Rate per metre =(a+b+c+d) 9782.92 9782.92

Rate per Cum cum 153.86

193043 From 10m to 20m depth cum 67.61 153.86


Add 5% for every extra metre Av15-8.5=6.5Mts@5%=33% 0.33 50.77
Total/cum 204.63
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 12.28

Rate per Cum cum 216.91

193044 From 20m to 30 m depth cum 216.91


Add 7.5% for every extra metre Av 25-15=10Mts@7.5%=75% 0.75 162.68
Total/cum 379.59

c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 22.78

Add 25% for kenteledges including supports, loading arrangement nand 0.25 94.90
Labour etc

Rate per cum cum 497.26

193045 From 30m to 40 m depth cum


Cost per cum from 20-30mts 497.26
Add 10% for every extra metre Av 35-25=10Mts@10%=100% 1.00 497.26

Total/Cum 994.51

c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 59.67

Page 32
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 198.90
Labour etc

Rate per cum cum 1253.09


193046 From 40m to 50 m depth cum
Cost per cum from 30-40mts 1253.09
Add 10% for every extra metre Av 45-35=10Mts@10%=100% 1.00 1253.09

Total/Cum 2506.17

c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 150.37

Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 501.23
Labour etc

Rate per cum cum 3157.78


193047 From 50 m depth onwards cum
Cost per cum from 40-50mts 3157.78
Add 10% for every extra metre Av 45-35=10Mts@10%=100% 0 0 1.00 3157.78

Total/Cum 6315.56

c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 378.93

Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 1263.11
Labour etc
Rate per cum cum 7957.61

193050 Dry/Wet Sinking of Twin D type Wells (Other than pneumatic method) in all
types of strata except hard rock requiring ballasting, including bailing and
pumping out water, removal of excavated soil, with all labour and material
required for sinking as per drawing and direction of the Engineer in charge
including disposal of surplus soil in the adjoining bank or within the zone
including disposal of surplus soil in the adjoining bank or within the zone
including compaction (The compaction to be paid separately under the
relevant item)
193051 From initial level of cutting edge & Up to 3m depth cum
Unit = Running meter
Taking output = 1m
Dimension of well
Overall length = 12 m @43.72 Cum/M

Page 33
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Overall width = 6m
Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate Day 0128 221.67 0.26 57.63
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 2.50 562.50
Beldar Day 0114 187.50 4.00 750.00
b) Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and Day 9060 6500.00 0.80 5200.00
accessories

6570.13
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 394.21
6964.34
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1044.65

Rate per meter =(a+b+c+d) 8008.99 8008.99

Rate per Cum cum 183.19

193052 From 3m to 10m depth cum


Beyond 3 m upto 10 m depth
Rate of sinking 0.15 m/hour
a) Labour
Mate Day 0128 221.67 0.45 99.75
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 3.25 731.25
Beldar Day 0114 187.50 6.00 1125.00
b) Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and Day 9060 6500.00 0.90 5850.00
accessories
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.60 1575.00
cutters /hammers
9381.00
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 562.86
9943.86
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1491.58

Rate per meter =(a+b+c+d) 11435.44 11435.44

Rate per Cum cum 261.56

Page 34
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
193053 From 10m to 20m depth
From 10m to 20m depth cum 0.00 261.56
Add 5% for every extra metre Av15-8.5=6.5Mts@5%=33% 0 0 0.33 86.32
Total/cum 347.88
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 20.87

Rate per Cum cum 368.75

193054 From 20m to 30 m depth cum 368.75


Add 7.5% for every extra metre Av 25-15=10Mts@7.5%=75% 0.75 276.56
Total/cum 645.31
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 38.72
Add 25% for kenteledges including supports, loading arrangement nand 0 0 0.25 161.33
Labour etc

Rate per cum cum 845.36

193055 From 30m to 40 m depth


Cost per cum from 20-30 mts cum 845.36
Add 10% for every extra metre Av 35-25=10Mts@10%=100% 0 0 1.00 845.36

Total/Cum 1690.71
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 101.44
Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 338.14
Labour etc

Rate per cum cum 2130.30

193056 From 40m to 50 m depth cum

Cost per cum from 30-40 mts 2130.30


Add 10% for every extra metre Av 45-35=10Mts@10%=100% 0 0 1.00 2130.30

Total/Cum 4260.59
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 255.64
Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 852.12
Labour etc

Rate per cum cum 5368.35

193057 From 50 m depth onwards cum

Page 35
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

Cost per cum from 40-50 mts 5368.35

Add 10% for every extra metre Av 45-35=10Mts@10%=100% 0 0 1.00 5368.35

Total/Cum 10736.70
c) Add water charges @ 1% + Dewatering charges @ 5% 0 0 0.06 644.20
Add 20% for kenteledges including supports, loading arrangement nand 0 0 0.20 2147.34
Labour etc

Rate per cum cum 13528.24

193060 Extra for sinking of wells in hard rock requiring controlled blasting including cum
cost of explosive, detonators, chieselling including all other ancillary works

Unit = Running Meter For 43.72 Cum


Taking output = 1m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Materials
Blasting powder Kg 0325 36.75 10.00 367.50
Blasting fuse (fuse wire) Each 0326 15.67 40.00 626.80
b) Labour
Mate Day 0128 221.67 1.34 297.04
Rock Hole Driller Day 0134 243.33 2.00 486.66
Rock Breaker Day 0133 243.33 0.25 60.83
Coolie Day 0115 170.00 25.00 4250.00
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 4.25 956.25
c) Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and Day 9060 6500.00 1.25 8125.00
accessories
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.50 1312.50
cutters /hammers
15488.28 994.30 0.00
Dewatering @ 5 percent of cost of (b+c), LS 0.05 774.41 49.72 0.00
16262.69 1044.02 0.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 162.63 10.44 0.00
16425.32 1054.46 0.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 2463.80 158.17 0.00

Rate per meter =(a+b+c+d) 18889.12 1212.62 20101.74

Page 36
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

Rate per Cum cum 459.78

193070 Providing and laying in position machine mixed, machine vibrated and
machine batched Design Mix Cement Concrete M35 grade (Cast - in Situ)
using 20 mm graded crushed stone aggregate and coarse sand of approved
quality in the following elements of well including finishing, using Admixtures
in recommended proportions( as per IS 9103), if approved in Mix design, to
accelerate, retard setting of concrete, improve workability without impairing
strength and durability complete .. Contd. --
193071 In well Kerb cum
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
H RCC Grade M35
Case-I Unit = cum
Taking output = 15cum
a) Materials
Portland Cement free (rate not required) Tonne 0367 0.00 6.33 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 8.10 4050.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 5.40 2565.00

b) Labour
Mate Day 0128 221.67 0.86 190.64
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50
Coolie Day 0115 170.00 20.00 3400.00

c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
6503.14 10665.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 574.18 574.18
7077.32 10665.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 70.77 106.65
7148.09 10771.65
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1072.21 1615.75

Cost of 15cum = (a+b+c+d+e+f) 8220.30 12387.40 20607.70

Page 37
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Rate per cum = (a+b+c+d+e+f)/15 cum 1373.85

193072 In Steining of wells cum

Same as in wellcurb cum 1373.85

193073 In Bottom plug for wells incl. arrangements for placing concrete under water cum
with tremie or bottom opening skips
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
Bottom Plug
Concrete to be placed usin tremie pipe
Note: 10% extra cement to be added where under water concreting is
involved
PCC Grade M20
Using concrete mixer
Unit = cum
Taking output = 15cum
a) Materials
Portland Cement free (rate not required) Tonne 0367 0.00 5.55 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 40 mm nominal size cum 0293 500.00 5.40 2700.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 5.40 2700.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 2.70 1282.50
Water Proofing Admixture Litre 9061 60.00 18.60 1116.00

b) Labour
Mate Day 0128 221.67 0.90 199.50
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50
Coolie Day 0115 170.00 20.00 3400.00

c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire and running charges of light crane per Day 0025 3000.00 1.00 3000.00

8649.50 11848.50
Add 5 per cent of cost of material and labour towards cost of forming sump, 0.05 432.48 592.43
protective bunds, chiselling and making arrangements for under water
concreting with tremie pipe
9081.98 12440.93

Page 38
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Sundries (no rates reqd.) Lumpsum 9999 1.00 625.35 625.35
9707.33 12440.93
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 97.07 124.41
9804.40 12565.33
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1470.66 1884.80

Cost of 15cum = (a+b+c+d+e+f) 11275.06 14450.13 25725.20

Rate per cum = (a+b+c+d+e+f)/15 cum 751.67 963.34 1715.01

193074 In Intermediate/top plug without shuttering cum


Rate same as 193073 as reinforcement, cement & shuttering are being paid 1373.85
separately and in addition to CC rats.
Add extra for thin sections and difficult locations 0.15 206.08

Rate per Cum cum 1579.92

193075 In Intermediate/Top plug with internal shuttering cum


Rate same as above as reinforcement, cement & shuttering are being paid 1579.92
separately and in addition to CC rats.

Rate per Cum cum 1579.92

193076 In Well cap and corbel if provided cum

Rate same as above as reinforcement, cement & shuttering are being paid 1579.92
separately and in addition to CC rats.

Rate per Cum cum 1579.92

193080 Supplying and filling ordinary sand/ excavated river bed material, if approved cum
in between bottom plug and top plug in wells including all lead lift handling,
re handling, as a complete job. The sand should be simultaneously filled
with water for three days to achieve full compaction so that further chances
of shrinkage due to voids are eliminated. Note - If sand is brought from a
source other then bridge site it shall be paid as NS item

Unit = cum
Taking Output = 1 cum
a) Materials

Page 39
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Fine sand (Zone IV) cum 0983 350.00 1.20 420.00
b) Labour
Mate Day 0128 221.67 0.01 2.22
Beldar Day 0114 187.50 0.30 56.25

58.47 420.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.58 4.20
59.05 424.20
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 8.86 63.63

Rate per meter =(a+b+c+d) 67.91 487.83 555.74

Rate per Cum cum 555.74

RCC BOX
194010 Providing and laying in position machine mixed, machine vibrated and cum
machine batched Design Mix Cement Concrete M35 grade (Cast - in Situ)
In Bottom/top slab, side walls, toe wall and sumps haunch filling head walls
or any other component using 20 mm graded crushed stone aggregate and
coarse sand of approved quality of cast-in-situ RCC box of size upto 5 M
(bigger inside dimension) including finishing, Admixtures in recommended
proportions (as per IS 9103), if approved in Mix design, to accelerate, retard
setting of concrete, improve workability without impairing strength and
durability, complete as per drawings and technical specifications as directed
by Engineer in charge. Payment for cement, reinforcement and shuttering
shall be paid extra

Note: The shuttering, scaffolding,centering, Reinforcement, placing of


reinforcement and cost of cement to be paid extra under relevant items
Using concrete mixer
Unit = cum
Taking output = 15cum
a) Materials
Portland Cement free (rate not required) Tonne 0367 0.00 6.10 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 8.10 4050.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 5.40 2565.00

b) Labour
Mate Day 0128 221.67 0.86 190.64
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50

Page 40
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Coolie Day 0115 170.00 20.00 3400.00

c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
6503.14 10665.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 574.18 574.18
7077.32 10665.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 70.77 106.65
7148.09 10771.65
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1072.21 1615.75

Cost of 15cum = (a+b+c+d+e+f) 8220.30 12387.40 20607.70

Rate per cum = (a+b+c+d+e+f)/15 cum 548.02 825.83 1373.85

194020 Providing and laying in position machine mixed, machine vibrated and cum
machine batched Design Mix Mass Cement Concrete M20 grade (Cast - in
Situ) using 20 mm graded crushed stone aggregate and coarse sand of
approved quality in Drop and curtain wall and alike structures below bed
level, Including the cost of centring, shuttering and finishing complete as per
drawings and technical specifications as directed by Engineer. Payment for
cement & reinforcement shall be paid extra
Note: The shuttering, scaffolding,centering, Reinforcement, placing of
reinforcement and cost of cement to be paid extra under relevant items
RCC Grade M20
Using concrete mixer
Unit = cum
Taking output = 15cum
a) Materials
Portland Cement free (rate not required) Tonne 0367 0.00 5.21 0.00
Coarse sand (Zone III) cum 0982 600.00 6.75 4050.00
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 8.10 4050.00
Stone Aggregate (Single size) : 10 mm nominal size cum 0297 475.00 5.40 2565.00

b) Labour
Mate Day 0128 221.67 0.86 190.64
Mason (brick layer) 1st class Day 0123 275.00 1.50 412.50
Coolie Day 0115 170.00 20.00 3400.00

Page 41
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

c) Machinery
Hire charges of Concrete Mixer 0.14 cubic metre Day 0002 537.50 1.00 537.50
Hire charges of Generator 250 KVA per Day 0030 1100.00 1.00 1100.00
Hire charges of Pin vibrator Day 0021 350.00 1.00 350.00
Hire charges of Surface Vibrator Day 0022 512.50 1.00 512.50
6503.14 10665.00
Sundries (no rates reqd.) Lumpsum 9999 1.00 574.18 574.18
7077.32 10665.00
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 70.77 106.65
7148.09 10771.65
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 1072.21 1615.75

Cost of 15cum = (a+b+c+d+e+f) 8220.30 12387.40 20607.70

Rate per cum = (a+b+c+d+e+f)/15 cum 548.02 825.83 1373.85

MISCELLANEOUS

195010 Deduct if 40mm graded stone aggregate is used in place of 20mm graded cum
stone aggregate in any grade of concrete. (Deduction to be made for
quantity of concrete)
Stone Aggregate (Single size) : 20 mm nominal size cum 0295 500.00 1.00 500.00
Stone Aggregate (Single size) : 40 mm nominal size cum 0293 500.00 1.00 500.00

Difference 0.00

Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 0.00
0.00
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 0.00

Cost of 15cum = (a+b+c+d+e+f) 0.00

Rate per cum = (a+b+c+d+e+f)/1 cum 0.00 0.00

195020 Providing and applying two coats of coal tar or bitumen confirming to IS Sqm
3117 - 1965 on the top and sides of RCC box/slabs @ 1.70 Kgs / Sqm after
cleaning the surface with all labour and materials complete job as directed
by the Engineer
Details of cost for 10Sqm

Page 42
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
Blown type of petroleum bitumen of penetration 85/25 of approved quality Tonne 0313 35000.00 0.02 595.00
Kerosene oil litre 0771 26.25 1.00 26.25
Fuel wood quintal 0761 500.00 0.04 17.50

Beldar Day 0114 187.50 0.50 93.75


93.75 638.75
Sundries (no rates reqd.) Lumpsum 9999 1.00 15.63 15.63
109.38 638.75
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.09 6.39
110.47 645.14
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 16.57 96.77

Cost of 10 Sqm 127.04 741.91 868.95

Rate per Sqm Sqm 12.70 74.19 86.90

195030 Centring and shuttering including strutting, propping etc. and removal of 0
form for :

195031 RCC raft foundation & Pile cap Sqm

Rate same as for item no 042011 Sqm 59.80 67.70 127.50

195032 Abutment, pier, wing walls and return walls Sqm

Rate same as for item no 042012 Sqm 166.00 66.60 232.60

195033 Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Sqm
Fender wall, Diaphragm wall, etc.

Rate same as for item no 042013 Sqm 181.32 55.70 237.02

195034 Approach slab at formation level, Dirt wall/ ballast wall at formation level Sqm

Rate same as for item no 042011 Sqm 59.80 67.70 127.50

195035 In well Kerb & Steining Sqm

Rate same as for item no 042021 Sqm 166.00 70.20 236.20

195036 In Intermediate/Top plug Sqm

Page 43
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

Rate same as for item no 042013 Sqm 181.32 55.70 237.02

195037 In Well cap and corbel if provided Sqm

Rate same as for item no 042011 Sqm 59.80 67.70 127.50

195038 In Bottom/top slab, side walls, toe wall and sumps haunch filling head walls Sqm
or any other component

Rate same as for item no 042012 Sqm 166.00 66.60 232.60

195040 Providing and laying in position machine mixed, machine vibrated and Sqm
machine batched Design Mix Cement Concrete M-25 grade (Cast - in Situ)
using 20 mm graded crushed stone aggregate and coarse sand of approved
quality in jacketing of piers and abutments from bottom of foundation upto a
height of 10m including finishing for average 30cm thickness of jacketing.
Payment for reinforcement, cement, wire mesh, shuttering, drilling of holes
and insertion of rods will be made extra.

Taking out 10 Sqm. Preparation of surface


Mate Day 0128 221.67 0.02 4.43
Coolie Day 0115 170.00 1.00 170.00
174.43
Sundries (no rates reqd.) Lumpsum 9999 1.00 4.14 4.14
178.57
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 1.79
180.36
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 27.05

Cost of 10 cum =a+b+c+d+e+f 207.41

Assuming 30 cm thickness of Jacketing. Qty of Concrete = 3 Cum. Rate as 1373.85 3.00 4121.54
per item 192040
4328.95
Add extra for thinner section 0.25 1082.24

5411.19
cost per sqm Sqm 1803.73 0.00 1803.73

195041 Drilling 32 mm dia holes for jacketing metre

Page 44
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)

Taking Out put 50 Mts


a) Labour
Mate Day 0128 221.67 1.00 221.67
Rock Hole Driller Day 0134 243.33 2.00 486.66
Coolie Day 0115 170.00 2.00 340.00
Skilled Beldar (for floor rubbing etc.) Day 0139 225.00 2.00 450.00
b) Machinery
Hire charges of Air compressor 250 cfm with two leads for pneumatic per Day 0040 2625.00 0.50 1312.50
cutters /hammers
Sundries (no rates reqd.) Lumpsum 9999 1.00 52.69 52.69
2863.52
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 28.64
2892.16
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 433.82

Total = (a+b+c+d+e) 3325.98

Rate per Rmt = (a+b+c+d+e)/50 metre 66.52 66.52

195042 Inserting of dowel bars of specified dia. (cost of rods to be paid extra) metre
Taking output 200 kgs
a) Labour
Mate Day 0128 221.67 1.00 221.67
Mason (for plain stone work) 2nd class) Day 0125 266.25 1.00 266.25
Coolie Day 0115 170.00 2.00 340.00

Sundries (no rates reqd.) Lumpsum 9999 1.00 16.52 16.52


844.44
Add for Water Charges @ 1% (no rates reqd.) Lumpsum 9997 0.01 8.44
852.88
Add for Contractor’s Profit and Overheads @ 15% (no rates reqd.) Lumpsum 9998 0.15 127.93

Total = (a+b+c+d+e) 980.82 980.82

Rate per Rmt = (a+b+c+d+e)/200 metre 4.90 4.90

New Items To Be Added By Zonal Railways


196010
196020
196030

Page 45
IR's Unified Standard Analysis Of Rates 2010 Chapter-19 : Bridge Works Substructure

RItem no. Description Unit Rate Rate Quantity Labour Material Labour & Remarks
e Code (Rs.) Cost (Rs.) Cost (Rs.) Material
f Cost (Rs.)
196040
196050
196060
196070
196080
196090
196100

Page 46

You might also like