Earth Work Bill of Quantity for Samera Boarding School

Item
No Description Unit Qty Unit price Total price
1 Earth work
1.1 Administration room
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 928.00 180.00 167,040.00
1.2 Library
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 443.52 180.00 79,833.60
1.3 Laboratory
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 549.05 180.00 98,829.00
1.4 Class Room
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 876.40 180.00 157,752.00
1.5 Work Shop
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 216.75 180.00 39,015.00
1.6 Toilet
Trench Excavation for foundation and footing pad to the levels and
axis ( depth not exceeding 1.5 m) and Cart away surplus excavated
material to a distance 0.5km m3 552.00 180.00 99,360.00

Total 641,829.60
Vat 96,274.44

Grand Total 738,104.04


Project Name:-Semera High School
TYPE OF EQUIPMENT:- Loader OPERATOR NAME:-Keder
DAILY TIME SHEET FORMAT :- FROM
Working period
Effective Intersite Total
Morning After noon Type of working Mobilizati Down Force contact Payable Operator
Rf. Date Start Finsh Start Finsh work hour Idle Time on Time majoures hour Time signature Remark
1 29/05/2014 7:00 12:00 15:00 18:00 Clearing 8:00 8:00 8:00
2 30/05/2014 7:00 12:00 15:00 18:00 8:00 8:00 8:00
3 1/6/2014 7:00 12:00 15:00 18:00 8:00 8:00 8:00
4 2/6/2014 7:00 12:00 15:00 18:00 8:00 8:00 8:00
5 3/6/2014 7:00 12:00 15:00 18:00 8:00 8:00 8:00
6 4/6/2014 7:00 12:00 15:00 18:00 8:00 8:00 8:00

Total hour (hr) = 48:00:00 0:00:00 0:00:00 0:00:00 0:00:00 48:00:00 48:00:00

PREPARED BY:- ________________________ CHECKED BY:- ________________________ APPROVED BY:-________________________

SIGNITURE:- ___________________________ SIGNITURE:- ___________________________ SIGNITURE:- ___________________________


Lessor:- Ali Mirahe Aloo Construction Material Supply and Machinery Rent
Lessee:- OBM Construction S.C
Project Location: Afar
SUMMERY UTILITY TIME SHEET 29 /05/2014 - 07 /06/2014

Maintenanc
Effective Intersite Total Payable Hourly Rental
Machenery Type/ Operator Down Force Payable Payable e & Oil Net Amount
No Description Model
Plate No.
Name
working Idle Time Mobilizat
Time majoures
contact
Time
Time
Time (hr)
Cost [Birr/hr]
Consumed [Birr]
hour ion hour (day) + Fuel
Price (Birr)

1 Loader Keder 48:00:00 0:00:00 0:00:00 0:00:00 0:00:00 48:00:00 48:00:00 2.00 48.00 1,650.00 79,200.00

TOTAL RENTAL COST WITH OUT VAT(Birr) 79,200.00


TOTAL RENTAL COST + 15 % VAT(Birr) 91,080.00

PREPARED BY:-________________________ CHECKED BY:-________________________ APPROVED BY:-________________________

SIGNITURE:- ___________________________ SIGNITURE:- ___________________________ SIGNITURE:- ___________________________