Earth Work Bill of Quantity for Samera Boarding School(Current Unit Price)

Item
No Description Unit Qty Unit price Total price
1 Site work
1.1 Surveying Work (Top layout) ls 1.00 54,000.00 54,000.00
1.2 Siting Out Profile ls 1.00 161,000.00 161,000.00
1.3 Bush Clearing and stripping the area and its disposal 1.5km m2 12,000.00 67.84 814,050.00
1.4 Site Clearing remove top soil to average depth of 20cm m2 35,051.95 43.20 1,514,244.17
Sub Total 2,543,294.17
2 Administration room
Earth work
Trench Excavation for foundation and footing pad to the levels and axis
2.1 ( depth not exceeding 1.5 m m3 928.00 255.65 237,243.20
Trench Excavation for foundation and footing pad to the levels and axis
2.2 ( depth not exceeding 2 m m3 Rate only 275.57
2.5 Cart away surplus excavated material to a distance 1km m3 928.00 164.35 152,516.80
Sub Total 389,760.00
3 Library
Trench Excavation for foundation and footing pad to the levels and axis
3.1 ( depth not exceeding 1.5 m m3 926.00 255.65 236,731.90
Trench Excavation for foundation and footing pad to the levels and axis
3.2 ( depth not exceeding 2 m m3 Rate only 275.57
3.3 Cart away surplus excavated material to a distance 1km m3 926.00 164.35 152,188.10
Sub Total 388,920.00
4 Laboratory
Trench Excavation for foundation and footing pad to the levels and axis
4.1 ( depth not exceeding 1.5 m m3 1,100.00 255.65 281,215.00
Trench Excavation for foundation and footing pad to the levels and axis
4.2 ( depth not exceeding 2 m m3 Rate only 275.57
4.3 Cart away surplus excavated material to a distance 1km m3 1,100.00 164.35 180,785.00
Sub Total 462,000.00
5 Class Room
Trench Excavation for foundation and footing pad to the levels and axis
5.1 ( depth not exceeding 1.5 m m3 832.00 255.65 212,700.80
Trench Excavation for foundation and footing pad to the levels and axis
5.2 ( depth not exceeding 2 m m3 Rate only 275.57
5.3 Cart away surplus excavated material to a distance 1km m3 832.00 164.35 136,739.20
Sub Total 349,440.00
6 Work Shop
Trench Excavation for foundation and footing pad to the levels and axis
6.1 ( depth not exceeding 1.5 m m3 364.00 255.65 93,056.60
Trench Excavation for foundation and footing pad to the levels and axis
6.2 ( depth not exceeding 2 m m3 Rate only 275.57
6.3 Cart away surplus excavated material to a distance 1km m3 364.00 164.35 59,823.40
Sub Total 152,880.00

Total 4,286,294.17
Material Supply Unit Rate
Item Loading Unit price (Including
No Material Unit Capacity Qty transport and loading )/m3 Price/Trip

1 Sand for Logaya River m3 16 1.00 268.75 4,300.00


m3
2 Sand for Haresise River 16 1.00 531.25 8,500.00
m3
3 Stone for Semera 14 1.00 542.86 7,600.00
m3
4 Gravel for Logaya 16 1.00 1031.25 16,500.00
m3
5 Gravel for Asayita 16 1.00 1156.25 18,500.00