You are on page 1of 1748

1/1748

Technical Documentation

MV Switchgear
English

Project: 5304532 Phnom Penh

ABB s.r.o., EPDS BRNO


Videnska 117
CZ-619 00 BRNO

MAN-material numbers:
11.98032-0545
11.98032-0552
11.98032-0553
11.98032-0554
11.98032-0555
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 2/1748

A
ABB s.r.o., EPDS BRNO A

Videnska 117
CZ-619 00 BRNO

17.5 kV SWITCHGEAR TYPE UNIGEAR ZS1


B B

CUSTOMER: MAN Energy Solutions SE


CUSTOMER REF. No.: MAN 5304532
ABB REF. No.: 1000047172
C C
SWITCHGEAR BASIC DATA ABB PROJECT REALIZATION TEAM
STANDARD IEC 62271-200 PROJECT MANAGER: KORISTA Jan
RATED VOLTAGE 17.5 kV
PROJECT ENGINEER: BERCES Erik
SERVICE VOLTAGE 15 kV
RATED FREQUENCY 50 Hz DESIGN ENGINEER: SKACEL Antonin
POWER FREQUENCY WITHSTAND VOLTAGE / BIL 38 kV / 95 kV
RATED BUSBAR CURRENT 4000 A
D RATED SHORT-TIME WITHSTAND CURRENT / MAKE CURRENT 50 kA / 125 kA D
RATED DURATION OF SHORT CIRCUIT 1s
RATED SHORT-TIME WITHSTAND CURRENT FOR EARTHING CIRCUITS 50 kA
RATED DURATION OF SHORT CIRCUIT FOR EARTHING CIRCUIT 1s
INTERNAL ARC CLASSIFICATION (IAC) TYPE AFLR
INTERNAL ARC CLASSIFICATION (IAC) CURRENT 50 kA
INTERNAL ARC CLASSIFICATION (IAC) TIME 1s
DEGREE OF PROTECTION IP4X
E DEGREE OF PROTECTION - INTERNAL IP20 E
MV PHASE DESIGNATION L1, L2, L3
AMBIENT TEMPERATURE -5 °C ... 40 °C
ALTITUDE ≤1000 m

DURING THE INSTALLATION, COMMISSIONING PERIOD AND THE TIME OF OPERATION, CLIENT IS OBLIGED TO FOLLOW ALL INSTRUCTIONS AND RECOMMENDATION GIVEN BY MANUFACTURERS OF INDIVIDUAL INSTRUMENTS INSTALLED INSIDE SUPPLIED EQUIPMENT

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812202 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
PROJECT TITLE PAGE &EAA A01 4
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 3/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=K00/A01 PROJECT TITLE PAGE AM
=K00/A02 SHEET INDEX AM
=K00/C01 GEN. SPECIFICATION OF SWGR. AM
=K00/C02 GEN. SPECIFICATION OF SWGR. AM

B B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812202 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 4
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 4/1748

GENERAL INFORMATION
SWITCHGEAR TYPE UniGear Single busbar system
PACKING Wooden pallet
A A
SECONDARY WIRES PARAMETERS
STANDARD ABB EPDS Brno Standard 1VLD110036
AC CIRCUIT PHASE BK (Black) / 1.5 mm²
NEUTRAL LB (Light blue) / 1.5 mm²
DC CIRCUIT POSITIVE BK (Black) / 1.5 mm²
NEGATIVE BK (Black) / 1.5 mm²
CT SECONDARY CIRCUIT PHASE 1 BK (Black) / 4 mm²
B PHASE 2 BK (Black) / 4 mm² B
PHASE 3 BK (Black) / 4 mm²
COMMON BK (Black) / 4 mm²
VT SECONDARY CIRCUIT PHASE 1 BK (Black) / 2.5 mm²
PHASE 2 BK (Black) / 2.5 mm²
PHASE 3 BK (Black) / 2.5 mm²
NEUTRAL LB (Light blue) / 2.5 mm²
EARTHING CIRCUIT GNYE (Green-yellow) / 4 mm²
C SUPPLY INTERCONNECTION 2.5 mm² C
LOGIC INTERCONNECTION 2.5 mm²
SECONDARY WIRES TERMINATION Non insulated crimping or welding
MARKING OF WIRE ENDS (MATERIAL) Terminal (Ring ferrules) *)
SEC. WIRES TYPE AND NOMINAL VOLTAGE Halogen free flame retardant, 0.45/0.75 kV

AUXILIARY VOLTAGES
CONTROL/SIGNALIZATION/PROTECTION CIRCUITS 2 DC 110 V, 6 kA
D CIRCUIT BREAKER SPRING CHARGER MOTOR 2 DC 110 V, 6 kA D
CIRCUIT BREAKER TRUCK MOTOR -
EARTHING SWITCH MOTOR DRIVE -
2nd TRIPPING COIL 2 DC 110 V, 6 kA
INTERNAL LIGHTING AND HEATING 1/N AC 230 V, 50 Hz, 6 kA
AUXILIARY VOLTAGES CONNECTION POSITION Step-Up Transformer 1, 2, 3

OTHER ELECTRICAL PARAMETERS


E TERMINALS TYPE / PRODUCER Screw type / Phoenix E
FAULT LIMITING DEVICE 1x Ith Limiter for every comp. (3 pcs)
ANTICONDENS. HEATER IN COMP. LV/CB/CABLE No/No/No
INTERNAL LIGHTING LV compartment light with IR sensor
REMOTE COMMUNICATION PROTOCOL None
IED COMMUNICATION PROTOCOL 1st / 2nd None / None/N/A
COMMUNICATION MEDIA None

F *)
BECAUSE OF TECHNICAL REASONS, MARKING FOR THE INTERCONNECTION WIRES (I.E. FOR THE BUNDLES OF WIRES BETWEEN PANELS) WILL BE OF THE TERMINAL TYPE ON WHITE RING FERRULES. F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812202 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
GEN. SPECIFICATION OF SWGR. &EEC C01 4
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 5/1748

SWITCHGEAR MECHANICAL DESIGN


COATING COLOR RAL 7035
Cu BARS DESIGN
A MAIN CIRCUIT Cu BARS COATING No **) A
BUSBAR PARTITIONING Yes - each panel (N/A for 500R,MCC,ZVC)
INSULATED T-OFFS AND BUSBARS Yes ***)
LOW VOLTAGE COMPARTMENT
LV COMPARTMENT DOORS DESIGN Standard
MIMIC DIAGRAM On LV comp. doors - self-adhesive
MIMIC DIAGRAM COLOR Black
LV ASSEMBLY PANEL MECH. DESIGN Comb profiles
B LOCKS B
LV COMPARTMENT DOORS CLOSING VERSION T-Handle Double Bit 3.2 mm
BREAKER COMPARTMENT DOORS CLOSING VERS. Handle Double Bit 5.2 mm
CABLE COMPARTMENT DOORS CLOSING VERSION Handle Double Bit 5.2 mm
LABELS
UNIT NAMEPLATES LANGUAGE English
UNIT NAMEPLATES DESIGN Engraved – fixed by plastic rivet
UNIT NAMEPLATES COLOR Black letters/white background
C DEVICES ON LV DOORS LABELS LANGUAGE English C
DEVICES ON LV DOORS LABELS DESIGN Engraved – fixed by plastic rivet
DEVICES ON LV DOORS LABELS COLOR Black letters/white background
DEVICES INSIDE LV COMP. LABELS LANGUAGE English
DEVICES INSIDE LV COMP. LABELS DESIGN Self-adhesive Brother tape
DEVICES INSIDE LV COMP. LABELS COLOR Black letters/white background
WARNING LABELS LANGUAGE English
WARNING LABELS DESIGN Glue
D OTHER PARAMETERS D
SHUTTERS PAINTING Standard RAL7035

FINAL DOCUMENTATION
NUMBER OF HARDCOPIES/CD DISC/FTP 0/0/Yes
STRUCTURE For every panel
FORMAT Pdf + Dwg + Eplan
CTs, VTs ROUTINE TEST REPORTS LANGUAGE Not required
E CTs, VTs MAGNETIZATION CURVES REQUIRED Yes E
CTs, VTs CALIBRATION FOR TARIFF METERING REQ. No
CTs, VTs CORRECTION CURVES REQUIRED Yes
MEASUREMENT OF PARTIAL DISCHARGE No

**)
BECAUSE OF TECHNICAL REASONS, SOME BARS CAN BE SILVERED ALSO IN CASE WHEN “NO“ IS SELECTED.
F ***)
BECAUSE OF TECHNICAL REASONS, SOME BARS CANNOT BE INSULATED ALSO IN CASE WHEN “YES“ IS SELECTED. F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812202 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
GEN. SPECIFICATION OF SWGR. &EEC C02 4
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 6/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=K00+SLD/A02 SHEET INDEX AM
=K00+SLD/D01 SINGLE LINE DIAGRAM AM
=K00+SLD/D02 SINGLE LINE DIAGRAM AM
=K00+SLD/D03 SINGLE LINE DIAGRAM AM
=K00+SLD/D04 SINGLE LINE DIAGRAM AM
=K00+SLD/D05 SINGLE LINE DIAGRAM AM
=K00+SLD/D06 SINGLE LINE DIAGRAM AM
B =K00+SLD/Z15 LEGEND AND SYMBOLS AM B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 7/1748

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D02/1A
MV Busbar 1 0.2, 15 VA
3P, 50 VA 00BBA
A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBA

BB EARTHING TRUCK
WITHOUT MAKING
CAPACITY

-QAB1 -QAB1 -QAB1 -QBT1 -QAB2


VD4G-50/25 p210 VD4G-50/25 p210 VD4G-50/25 p210 E-U/P 17.32.50 P275 VD4G-50/37 p275
17.5 kV 17.5 kV 17.5 kV 17,5 kV 15kV
M 2000 A M 2000 A M 2000 A 3200 A M 4000A
50 kA 50 kA 50 kA 50 kA 50kA

B -BCT1,-BCT2,-BCT3 -BCT4,-BCT5,-BCT6 -BCT4,-BCT5,-BCT6 -BCT7,-BCT8,-BCT9 B


TPU 54.43 TPU 54.13 TPU 54.13 KOKS 17.5A31
P1 150/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P1 4000/1/1/1 A at 40 °C
-PFV1 -PFV1 -PFV1
Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 3: 5P20, 10 VA
CPI PLUS/R CPI PLUS/R CPI PLUS/R
Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 2: 5P20, 10 VA

3 P2 3 P1 3 P1
Core 1: 0,2Fs5, 10 VA

3 P2

C -PFV1 C
-BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3
TJC5 TJC5 CPI PLUS/R TJC5
15/√3//0.11/√3//0.11/3 kV 15/√3//0.11/√3//0.11/3 kV IN INSULATOR 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA 0.2, 15 VA 0.2, 15 VA
3P, 50 VA 3P, 50 VA 3P, 50 VA

-FA11, -FA11, -FA11, -FA11,


-FA21, -FA21, -FA21, -FA21,
-FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE2
MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG

D D

-BCN1
RKU 2918
Under cubicle (accessory)
60/1 A; 1FS10, 1,25VA G1 G2
inner diameter d=180mm

E E

PANEL 1 00BBA01GS103 2 01BAC01GS003 3 02BAC01GS003 4 00BCT01GS203


PANEL NAME Station Transformer 1 Alternator G1 Alternator G2 Step-Up Transformer 1
DRAWING Nr. 1VL3812208 1VL3812209 1VL3812210 1VL3812211
-PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1
A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1
A-Meter A-Meter A-Meter A-Meter
METERING, TEST AND -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D01 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 8/1748

MV Busbar 1
A D01/8A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBA 00BBA

-QAB1 -QAB1
VD4G-50/25 p210 VD4G-50/25 p210
17.5 kV 17.5 kV
M 2000 A M 2000 A
50 kA 50 kA

B -BCT4,-BCT5,-BCT6 -BCT4,-BCT5,-BCT6 B
TPU 54.13 TPU 54.13
P2 1000/1/1 A at 40 °C P2 1000/1/1 A at 40 °C
-PFV1 -PFV1
Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA
CPI PLUS/R CPI PLUS/R
Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA

3 P1 3 P1

C C
-BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3
TJC5 TJC5
15/√3//0.11/√3//0.11/3 kV 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA 0.2, 15 VA
3P, 50 VA 3P, 50 VA

-FA11, -FA11,
-FA21, -FA21,
-FA31 -QCE1 -FA31 -QCE1
MWD 16 ST-UG MWD 16 ST-UG

D D

G3 G4

E E

PANEL 5 03BAC01GS003 6 04BAC01GS003


PANEL NAME Alternator G3 Alternator G4
DRAWING Nr. 1VL3812212 1VL3812213
-PF1 -SFO1 -PF1 -SFO1
A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1
A-Meter A-Meter
METERING, TEST AND -SFC1 Local/Remote -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter -PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D02 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 9/1748

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D04/1A
MV Busbar 2 0.2, 15 VA
3P, 50 VA 00BBB
A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBB

BB EARTHING TRUCK
WITHOUT MAKING
CAPACITY

-QAB1 -QAB1 -QAB1 -QBT1 -QAB2


VD4G-50/25 p210 VD4G-50/25 p210 VD4G-50/25 p210 E-U/P 17.32.50 P275 VD4G-50/37 p275
17.5 kV 17.5 kV 17.5 kV 17,5 kV 15kV
M 2000 A M 2000 A M 2000 A 3200 A M 4000A
50 kA 50 kA 50 kA 50 kA 50kA

B -BCT1,-BCT2,-BCT3 -BCT4,-BCT5,-BCT6 -BCT4,-BCT5,-BCT6 -BCT7,-BCT8,-BCT9 B


TPU 54.43 TPU 54.13 TPU 54.13 KOKS 17.5A31
P1 150/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P1 4000/1/1/1 A at 40 °C
-PFV1 -PFV1 -PFV1
Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 3: 5P20, 10 VA
CPI PLUS/R CPI PLUS/R CPI PLUS/R
Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 2: 5P20, 10 VA

3 P2 3 P1 3 P1
Core 1: 0,2Fs5, 10 VA

3 P2

C -PFV1 C
-BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3
TJC5 TJC5 CPI PLUS/R TJC5
15/√3//0.11/√3//0.11/3 kV 15/√3//0.11/√3//0.11/3 kV IN INSULATOR 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA 0.2, 15 VA 0.2, 15 VA
3P, 50 VA 3P, 50 VA 3P, 50 VA

-FA11, -FA11, -FA11, -FA11,


-FA21, -FA21, -FA21, -FA21,
-FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE2
MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG

D D

-BCN1
RKU 2918
Under cubicle (accessory)
60/1 A; 1FS10, 1,25VA G5 G6
inner diameter d=180mm

E E

PANEL 7 00BBB02GS103 8 05BAC01GS003 9 06BAC01GS003 10 00BCT02GS203


PANEL NAME Station Transformer 2 Alternator G5 Alternator G6 Step-Up Transformer 2
DRAWING Nr. 1VL3812214 1VL3812215 1VL3812216 1VL3812217
-PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1
A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1
A-Meter A-Meter A-Meter A-Meter
METERING, TEST AND -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D03 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 10/1748

MV Busbar 2
A D03/8A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBB 00BBB

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

B -BCT4,-BCT5,-BCT6 B
TPU 54.13
P2 1000/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
CPI PLUS/R
Core 1: 0.2Fs5, 10 VA

3 P1

C C
-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

D D

G7

E E

PANEL 11 07BAC01GS003
PANEL NAME Alternator G7
DRAWING Nr. 1VL3812218
-PF1 -SFO1
A -PGA1,2,3 CB open -SFS1
A-Meter
METERING, TEST AND -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D04 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 11/1748

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D06/1A
MV Busbar 3 0.2, 15 VA
3P, 50 VA 00BBC
A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBC

BB EARTHING TRUCK
WITHOUT MAKING
CAPACITY

-QAB1 -QAB1 -QAB1 -QBT1 -QAB2


VD4G-50/25 p210 VD4G-50/25 p210 VD4G-50/25 p210 E-U/P 17.32.50 P275 VD4G-50/37 p275
17.5 kV 17.5 kV 17.5 kV 17,5 kV 15kV
M 2000 A M 2000 A M 2000 A 3200 A M 4000A
50 kA 50 kA 50 kA 50 kA 50kA

B -BCT1,-BCT2,-BCT3 -BCT4,-BCT5,-BCT6 -BCT4,-BCT5,-BCT6 -BCT7,-BCT8,-BCT9 B


TPU 54.43 TPU 54.13 TPU 54.13 KOKS 17.5A31
P1 150/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P2 1000/1/1 A at 40 °C P1 4000/1/1/1 A at 40 °C
-PFV1 -PFV1 -PFV1
Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA Core 3: 5P20, 10 VA
CPI PLUS/R CPI PLUS/R CPI PLUS/R
Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA Core 2: 5P20, 10 VA

3 P2 3 P1 3 P1
Core 1: 0,2Fs5, 10 VA

3 P2

C -PFV1 C
-BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3
TJC5 TJC5 CPI PLUS/R TJC5
15/√3//0.11/√3//0.11/3 kV 15/√3//0.11/√3//0.11/3 kV IN INSULATOR 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA 0.2, 15 VA 0.2, 15 VA
3P, 50 VA 3P, 50 VA 3P, 50 VA

-FA11, -FA11, -FA11, -FA11,


-FA21, -FA21, -FA21, -FA21,
-FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE1 -FA31 -QCE2
MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG MWD 16 ST-UG

D D

-BCN1
RKU 2918
Under cubicle (accessory)
60/1 A; 1FS10, 1,25VA G8 G9
inner diameter d=180mm

E E

PANEL 12 00BBC03GS103 13 08BAC01GS003 14 09BAC01GS003 15 00BCT03GS203


PANEL NAME Station Transformer 3 Alternator G8 Alternator G9 Step-Up Transformer 3
DRAWING Nr. 1VL3812219 1VL3812220 1VL3812221 1VL3812222
-PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1 -PF1 -SFO1
A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1
A-Meter A-Meter A-Meter A-Meter
METERING, TEST AND -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter -PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D05 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 12/1748

MV Busbar 3
A D05/8A 3 AC, 17.5 kV, 50 Hz, 4000 A, 50 kA/1 s A
00BBC 00BBC

-QAB1 -QAB1
VD4G-50/25 p210 VD4G-50/25 p210
17.5 kV 17.5 kV
M 2000 A M 2000 A
50 kA 50 kA

B -BCT4,-BCT5,-BCT6 -BCT4,-BCT5,-BCT6 B
TPU 54.13 TPU 54.13
P2 1000/1/1 A at 40 °C P2 1000/1/1 A at 40 °C
-PFV1 -PFV1
Core 2: 5P20, 10 VA Core 2: 5P20, 10 VA
CPI PLUS/R CPI PLUS/R
Core 1: 0.2Fs5, 10 VA Core 1: 0.2Fs5, 10 VA

3 P1 3 P1

C C
-BAT1,-BAT2,-BAT3 -BAT1,-BAT2,-BAT3
TJC5 TJC5
15/√3//0.11/√3//0.11/3 kV 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA 0.2, 15 VA
3P, 50 VA 3P, 50 VA

-FA11, -FA11,
-FA21, -FA21,
-FA31 -QCE1 -FA31 -QCE1
MWD 16 ST-UG MWD 16 ST-UG

D D

G10 G11

E E

PANEL 16 10BAC01GS003 17 11BAC01GS003


PANEL NAME Alternator G10 Alternator G11
DRAWING Nr. 1VL3812223 1VL3812224
-PF1 -SFO1 -PF1 -SFO1
A -PGA1,2,3 CB open -SFS1 A -PGA1,2,3 CB open -SFS1
A-Meter A-Meter
METERING, TEST AND -SFC1 Local/Remote -SFC1 Local/Remote
CONTROL EQUIPMENT
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
Kuvag CPI PLUS/R
V -PGV1 CB close -SFV1
-PFX1,2,3 V-Meter -PFX1,2,3 V-Meter
-SFT1 0/L1/L2/L3 -SFT1 0/L1/L2/L3
F Pos. Indicators Lamp Test Pos. Indicators Lamp Test F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SINGLE LINE DIAGRAM &EFA D06 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 13/1748

LEGEND AND SYMBOLS

A A

-QAB
VD4/P 12.25.32 P275
12 kV CIRCUIT BREAKER -QBT1
M 2500 A, 2280 A at 50°C E-U/P 17.32.50 P275 BUSBAR EARTHING TRUCK
31.5 kA 17,5 kV
3200 A
50 kA

P2
-BCT7,-BCT8,-BCT9
B B
TPU 60.13 3 CORE CURRENT TRANSFORMER
600/1/1 A at 40°C -FA11,
Core 3: 5P10, 10 VA
Core 2: 0.2Fs5, 10 VA -FA21,
Core 1: 0.2Fs5, 10 VA -FA31 SURGE ARRESTER
MWD 16
3 P1

P1
-PFV1 -BCT1,-BCT2,-BCT3 2 CORE CT WITH VOLTAGE PRESENCE INDICATOR
TPU 54.43
C CPI PLUS/R 150/1/1 A at 40 °C C
Core 2: 5P20, 10 VA
Core 1: 0.5Fs5, 10 VA
3 P2
-PF1
VOLTAGE PRESENCE INDICATOR
Kuvag CPI PLUS/R

-BAT1,-BAT2,-BAT3
TJC5
2 CORES VOLTAGE TRANSFORMER (STAR AND OPEN DELTA WINDING)
15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA A A - METER
3P, 50 VA
D D

V V - METER

-QCE
EK6
LINE EARTHING SWITCH EK6 WITH BLOCKING MAGNET
W WATT - METER

POSITION INDICATOR
E BUSHING E

3x1Cx120mm²
PUSH BUTTON

-BCN1
SELECTOR SWITCH
KOLMA 06 D2 RING CORE CT KOLMA
100/1 A
10P10, VA

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812204 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description SLD
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
LEGEND AND SYMBOLS &EFS Z15 8
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 14/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=K00+GA/A02 SHEET INDEX AM
=K00+GA/F01 FRONT VIEW AM
=K00+GA/F02 FRONT VIEW AM
=K00+GA/F03 FRONT VIEW AM
=K00+GA/F04 FRONT VIEW AM
=K00+GA/F05 FRONT VIEW AM
=K00+GA/H01 SWGR. FOOTPRINT AM
B =K00+GA/H02 SWGR. FOOTPRINT AM B
=K00+GA/H03 SWGR. FOOTPRINT AM
=K00+GA/H04 SWGR. FOOTPRINT AM
=K00+GA/H05 SWGR. FOOTPRINT AM
=K00+GA/J01 SWGR. FOOTPRINT DETAILS AM
=K00+GA/K01 FIXING DETAILS CPROF AM
=K00+GA/L01 SECTION VIEW DRAWINGS AM
=K00+GA/L02 SECTION VIEW DRAWINGS AM
C =K00+GA/L03 SECTION VIEW DRAWINGS AM C
=K00+GA/L04 SECTION VIEW DRAWINGS AM
=K00+GA/L05 SECTION VIEW DRAWINGS AM
=K00+GA/L06 SECTION VIEW DRAWINGS AM

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 15/1748
Minimum switchgear room height - H: 3100 mm

800
A A
400

B B

00BBA01GS103 01BAC01GS003 02BAC01GS003 00BCT01GS203 03BAC01GS003


Station Transformer 1 Alternator G1 Alternator G2 Step-Up Transformer Alternator G3

C C
2427

HOLES FOR ON BUTTON


WITH BLIND COVER
ON EACH PANEL

D D
263

263
E E

540 740
30 800 800 800 1000 800
Total Length: 5060

PANEL 1 00BBA01GS103 2 01BAC01GS003 3 02BAC01GS003 4 00BCT01GS203 5 03BAC01GS003


PANEL NAME Station Transformer 1 Alternator G1 Alternator G2 Step-Up Transformer 1 Alternator G3
F CB MECHANICAL CONTROL Off Off Off Off Off F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FRONT VIEW &ELH F01 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 16/1748
Minimum switchgear room height - H: 3100 mm
Gas duct outlets rear number / placement: 2 /

A A

B B

04BAC01GS003
Alternator G4

C C

D D
263

E E

540
800 30
Total Length: 5060

PANEL 6 04BAC01GS003
PANEL NAME Alternator G4
F CB MECHANICAL CONTROL Off F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FRONT VIEW &ELH F02 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 17/1748
Minimum switchgear room height - H: 3100 mm Rear exhaust of gas duct

A A

B B
2898

00BBB02GS103 05BAC01GS003 06BAC01GS003 00BCT02GS203 07BAC01GS003


Station Transformer 2 Alternator G5 Alternator G6 Step-Up Transformer Alternator G7

C C
2200

HOLES FOR ON BUTTON


WITH BLIND COVER
ON EACH PANEL

D D
263

263
E E

540 740
30 800 800 800 1000 800 30
Total Length: 4260

PANEL 7 00BBB02GS103 8 05BAC01GS003 9 06BAC01GS003 10 00BCT02GS203 11 07BAC01GS003


PANEL NAME Station Transformer 2 Alternator G5 Alternator G6 Step-Up Transformer 2 Alternator G7
F CB MECHANICAL CONTROL Off Off Off Off Off F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FRONT VIEW &ELH F03 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 18/1748
Minimum switchgear room height - H: 3100 mm

A A

B B
2898

00BBC03GS103 08BAC01GS003 09BAC01GS003 00BCT03GS203 10BAC01GS003


Station Transformer 3 Alternator G8 Alternator G9 Step-Up Transformer Alternator G10

C C
2200

HOLES FOR ON BUTTON


WITH BLIND COVER
ON EACH PANEL

D D
263

263
E E

540 740
30 800 800 800 1000 800
Total Length: 5060

PANEL 12 00BBC03GS103 13 08BAC01GS003 14 09BAC01GS003 15 00BCT03GS203 16 10BAC01GS003


PANEL NAME Station Transformer 3 Alternator G8 Alternator G9 Step-Up Transformer 3 Alternator G10
F CB MECHANICAL CONTROL Off Off Off Off Off F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FRONT VIEW &ELH F04 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 19/1748
Minimum switchgear room height - H: 3100 mm

800
A A

400
B B

11BAC01GS003
Alternator G11

C C

2427
D D
263

E E

540
800 30
Total Length: 5060

PANEL 17 11BAC01GS003
PANEL NAME Alternator G11
F CB MECHANICAL CONTROL Off F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FRONT VIEW &ELH F05 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 20/1748

Minimal distance between a wall and a panel must be for wall installation 100 mm (recommended 500 mm) lateral and on back side.

A A

C-PROFILES ARE NOT


IN SCOPE OF DELIVERY OF ABB

B B

C C

800 800 800 1000 800

D D
Total Length: 5000

PANEL 1 00BBA01GS103 2 01BAC01GS003 3 02BAC01GS003 4 00BCT01GS203 5 03BAC01GS003


PANEL NAME Station Transformer 1 Alternator G1 Alternator G2 Step-Up Transformer 1 Alternator G3

MV CABLE N2XSY 1x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 6x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²)

E MV CABLEHOLDER SIZE 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm E
ESTIMATED PANEL WEIGHT 1460 kg 1340 kg 1340 kg 1730 kg 1340 kg
INTERLOCKING BETWEEN CABLE
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
COMP. DOOR AND ES
INTERLOCKING BETWEEN CB DOOR
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
AND WITHDRAW. PART
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
CB-RACK.-CRANK-INSERT. HOLE
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
F ES-OPER.-LEVER-INSERT. HOLE F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT &ELH H01 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 21/1748

Minimal distance between a wall and a panel must be for wall installation 100 mm (recommended 500 mm) lateral and on back side.

A A

B B

C C

800

D D
Total Length: 5000

PANEL 6 04BAC01GS003
PANEL NAME Alternator G4

MV CABLE N2XSY 2x3x(1Cx400mm²)

E MV CABLEHOLDER SIZE 35 - 54 mm E
ESTIMATED PANEL WEIGHT 1340 kg
INTERLOCKING BETWEEN CABLE
Mechanical interlocking
COMP. DOOR AND ES
INTERLOCKING BETWEEN CB DOOR
Mechanical interlocking
AND WITHDRAW. PART
LOCK ON COVER FOR THE
Padlock
CB-RACK.-CRANK-INSERT. HOLE
LOCK ON COVER FOR THE
Padlock
F ES-OPER.-LEVER-INSERT. HOLE F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT &ELH H02 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 22/1748

Minimal distance between a wall and a panel must be for wall installation 100 mm (recommended 500 mm) lateral and on back side.

A A

C-PROFILES ARE NOT


IN SCOPE OF DELIVERY OF ABB

B B

C C

800 800 800 1000 800

D D
Total Length: 4200

PANEL 7 00BBB02GS103 8 05BAC01GS003 9 06BAC01GS003 10 00BCT02GS203 11 07BAC01GS003


PANEL NAME Station Transformer 2 Alternator G5 Alternator G6 Step-Up Transformer 2 Alternator G7

MV CABLE N2XSY 1x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 4x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²)

E MV CABLEHOLDER SIZE 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm E
ESTIMATED PANEL WEIGHT 1460 kg 1340 kg 1340 kg 1730 kg 1340 kg
INTERLOCKING BETWEEN CABLE
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
COMP. DOOR AND ES
INTERLOCKING BETWEEN CB DOOR
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
AND WITHDRAW. PART
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
CB-RACK.-CRANK-INSERT. HOLE
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
F ES-OPER.-LEVER-INSERT. HOLE F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT &ELH H03 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 23/1748

Minimal distance between a wall and a panel must be for wall installation 100 mm (recommended 500 mm) lateral and on back side.

A A

C-PROFILES ARE NOT


IN SCOPE OF DELIVERY OF ABB

B B

C C

800 800 800 1000 800

D D
Total Length: 5000

PANEL 12 00BBC03GS103 13 08BAC01GS003 14 09BAC01GS003 15 00BCT03GS203 16 10BAC01GS003


PANEL NAME Station Transformer 3 Alternator G8 Alternator G9 Step-Up Transformer 3 Alternator G10

MV CABLE N2XSY 1x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²) N2XSY 6x3x(1Cx400mm²) N2XSY 2x3x(1Cx400mm²)

E MV CABLEHOLDER SIZE 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm 35 - 54 mm E
ESTIMATED PANEL WEIGHT 1460 kg 1340 kg 1340 kg 1730 kg 1340 kg
INTERLOCKING BETWEEN CABLE
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
COMP. DOOR AND ES
INTERLOCKING BETWEEN CB DOOR
Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking Mechanical interlocking
AND WITHDRAW. PART
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
CB-RACK.-CRANK-INSERT. HOLE
LOCK ON COVER FOR THE
Padlock Padlock Padlock Padlock Padlock
F ES-OPER.-LEVER-INSERT. HOLE F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT &ELH H04 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 24/1748

Minimal distance between a wall and a panel must be for wall installation 100 mm (recommended 500 mm) lateral and on back side.

A A

B B

C C

800

D D

Total Length: 5000


PANEL 17 11BAC01GS003
PANEL NAME Alternator G11

MV CABLE N2XSY 2x3x(1Cx400mm²)

E MV CABLEHOLDER SIZE 35 - 54 mm E
ESTIMATED PANEL WEIGHT 1340 kg
INTERLOCKING BETWEEN CABLE
Mechanical interlocking
COMP. DOOR AND ES
INTERLOCKING BETWEEN CB DOOR
Mechanical interlocking
AND WITHDRAW. PART
LOCK ON COVER FOR THE
Padlock
CB-RACK.-CRANK-INSERT. HOLE
LOCK ON COVER FOR THE
Padlock
F ES-OPER.-LEVER-INSERT. HOLE F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT &ELH H05 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 25/1748

Tolerances for laying the floor frame are:


Evenness tolerance: ± 1 mm within a measuring length of 1 m
Straightness tolerance: 1 mm per 1 m, but not more than 3 mm over entire length of frame.
For more details refer to Installation, service and maintenance manual.
A A

B B

105 790 105


105 590 105
35

100
255

255
131

131
C C
843

843
670

670
1455
1285

1285
1390

100 600 100 100 800 100


D D
65 65
225

225
360

360
311

311
80

80
70

70
E 800 1000 E

VALID FOR: VALID FOR:


A01, A02, A03, A05, A06, A07, A08, A04, A10, A15
A09, A11, A12, A13, A14, A16, A17
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SWGR. FOOTPRINT DETAILS &ELH J01 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 26/1748

A
ADDITIONAL DETAILS FOR PREPARATION OF FOOTPRINT A

"C" PROFILE FOR CONCRETE FLOOR


25 1

0<H<5
3
2

3
B B

50
4

LEGEND:
C C
1 - BOLT M12 x 30
2 - SPECIAL NUT
3 - SPECIAL WASHER
4 - ANCHORING BOLT M10 x 90

95
D D

SZ M10

E E

d 16
80
Tolerances for laying the floor frame are:
Evenness tolerance: ± 1 mm within a measuring length of 1 m
Straightness tolerance: 1 mm per 1 m, but not more than 3 mm over entire length of frame.
For more details refer to Installation, service and maintenance manual No.1VLM000363_revH, section-5.2.1
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
FIXING DETAILS CPROF &ELH K01 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 27/1748

696

FRONT VIEW 650

A 800 No. Description A


3
Incoming feeder with CB - SU,
1
17.5 kV, 2000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm

464
400
3 Gas Duct with Right Side Exhaust

4 Circuit Breaker VD4

B B

705
C C

310
2227

1 4

2200
2100

1495
D D
990
10
383,5
546,5

E E
263

70
330
405 180 180 520
285 610 390
35 1285
VALID FOR:
A01
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L01 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 28/1748

A No. Description A
3
Incoming feeder with CB - SU,
1
17.5 kV, 2000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm

3 Gas Duct

4 Circuit Breaker VD4

B B

705
C C

310
1 4

2200
2100

1495
D D
990
10
383,5
546,5

E E
263

70
330
405 180 180 520
285 610 390
35 1285
VALID FOR:
A07, A12
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L02 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 29/1748

A No. Description A
3
Incoming feeder with CB - SU,
1
17.5 kV, 2000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm

3 Gas Duct

4 Circuit Breaker VD4

B 5 Fixed VT, 50 kA
B

705
C C

310
1 4

2200
2100

1495
D D
990
10

5
383,5
546,5

E E
263

70
330
405 180 180 520
285 610 390
35 1285
VALID FOR:
A02, A03, A05, A06, A08, A09, A13, A14, A16
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L03 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 30/1748

REAR VIEW
646
A 340 - 990 No. Description A
600 3
Incoming feeder with CB - SU,
1
17.5 kV, 2000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm
414
350

3 Gas Duct with Rear Exhaust

4 Circuit Breaker VD4

B 5 Fixed VT, 50 kA
B
= =
800 2

705
C C

310
1 4

2200
2198

2100

1495
D D
990
10

5
383,5
546,5

E E
263

70
330
405 180 180 520
285 610 390
35 1285
VALID FOR:
A11
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L04 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 31/1748

696

FRONT VIEW 650

A 800 No. Description A


3
Incoming feeder with CB - SU,
1
17.5 kV, 2000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm

464
400
3 Gas Duct with Left Side Exhaust

4 Circuit Breaker VD4

B 5 Fixed VT, 50 kA
B

705
C C

310
2227

1 4

2200
2100

1495
D D
990
10

5
383,5
546,5

E E
263

70
330
405 180 180 520
285 610 390
35 1285
VALID FOR:
A17
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L05 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 32/1748

A No. Description A
3
Incoming feeder with CB - SU,
1
17.5 kV, 4000 A, 50 kA

Low Voltage Compartment Standard, Standard Door,

798
2
Height 705 mm

502
3 Gas Duct

90
4 Circuit Breaker VD4

B B

2 6 Top Box with Voltage Transformers, Up to 17.5 kV

705
C C

310
1 4

2200
2100

1495
D D
990
388,5
551,5

E E
263

70
330
375 90 90 90 90 90 460
285 610 390
100 1285
VALID FOR:
A04, A10, A15
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812205 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description GA
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SECTION VIEW DRAWINGS &ELH L06 19
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 33/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=K00+ICL/A02 SHEET INDEX AM
=K00+ICL/Q01 XDI1 - SUPPLY INTERCONNECTION AM
=K00+ICL/Q02 XDI1 - SUPPLY INTERCONNECTION AM
=K00+ICL/Q03 XDI1 - SUPPLY INTERCONNECTION AM
=K00+ICL/Q04 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q05 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q06 XDI2 - SIGNAL INTERCONNECTION AM
B =K00+ICL/Q07 XDI2 - SIGNAL INTERCONNECTION AM B
=K00+ICL/Q08 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q09 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q10 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q11 XDI2 - SIGNAL INTERCONNECTION AM
=K00+ICL/Q12 XDI2 - SIGNAL INTERCONNECTION AM

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 34/1748

PANEL 1 00BBA01GS103
Station
2 01BAC01GS003
Alternator G1
3 02BAC01GS003
Alternator G2
4 00BCT01GS203
Step-Up
5 03BAC01GS003
Alternator G3
6 04BAC01GS003
Alternator G4
-XDI1:
PANEL NAME
Transformer 1 Transformer 1 Wires: 2,5mm² Black (+, -, L), Light Blue (N)
A Terminals: UT 4-QUATTRO 3044571 A

CONTROL CIRCUIT
-XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1
-XDCS 1

-XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2


-XDCS 2

SPRING CHARGING CIRCUIT


B B
-XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3
2 DC 110V
1. DC POWER SUPPLY

-XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5

SIGNAL CIRCUIT
C -XDCS 3 C

-XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6


-XDCS 4

LIGHTING CIRCUIT
-XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7
2 DC 110V
-XDCS 5
2. DC POWER SUPPLY
D D
-XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8
-XDCS 6

L N
-XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9
1/N AC 230V
-XDCS 7

SPARE
-XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10
E -XDCS 8 E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI1 - SUPPLY INTERCONNECTION &EFF Q01 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 35/1748

PANEL 7 00BBB02GS103
Station
8 05BAC01GS003
Alternator G5
9 06BAC01GS003
Alternator G6
10 00BCT02GS203
Step-Up
11 07BAC01GS003
Alternator G7
-XDI1:
PANEL NAME
Transformer 2 Transformer 2 Wires: 2,5mm² Black (+, -, L), Light Blue (N)
A Terminals: UT 4-QUATTRO 3044571 A

CONTROL CIRCUIT
-XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1
-XDCS 1

-XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2


-XDCS 2

SPRING CHARGING CIRCUIT


B B
-XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3
2 DC 110V
1. DC POWER SUPPLY

-XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5

SIGNAL CIRCUIT
C -XDCS 3 C

-XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6


-XDCS 4

LIGHTING CIRCUIT
-XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7
2 DC 110V
-XDCS 5
2. DC POWER SUPPLY
D D
-XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8
-XDCS 6

L N
-XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9
1/N AC 230V
-XDCS 7

SPARE
-XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10
E -XDCS 8 E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI1 - SUPPLY INTERCONNECTION &EFF Q02 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 36/1748

PANEL 12 00BBC03GS103
Station
13 08BAC01GS003
Alternator G8
14 09BAC01GS003
Alternator G9
15 00BCT03GS203
Step-Up
16 10BAC01GS003
Alternator G10
17 11BAC01GS003
Alternator G11
-XDI1:
PANEL NAME
Transformer 3 Transformer 3 Wires: 2,5mm² Black (+, -, L), Light Blue (N)
A Terminals: UT 4-QUATTRO 3044571 A

CONTROL CIRCUIT
-XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1 -XDI1 1
-XDCS 1

-XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2 -XDI1 2


-XDCS 2

SPRING CHARGING CIRCUIT


B B
-XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3 -XDI1 3
2 DC 110V
1. DC POWER SUPPLY

-XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5 -XDI1 5

SIGNAL CIRCUIT
C -XDCS 3 C

-XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6 -XDI1 6


-XDCS 4

LIGHTING CIRCUIT
-XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7 -XDI1 7
2 DC 110V
-XDCS 5
2. DC POWER SUPPLY
D D
-XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8 -XDI1 8
-XDCS 6

L N
-XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9 -XDI1 9
1/N AC 230V
-XDCS 7

SPARE
-XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10 -XDI1 10
E -XDCS 8 E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI1 - SUPPLY INTERCONNECTION &EFF Q03 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 37/1748

PANEL 1 00BBA01GS103
Station
2 01BAC01GS003
Alternator G1
3 02BAC01GS003
Alternator G2
4 00BCT01GS203
Step-Up
5 03BAC01GS003
Alternator G3
6 04BAC01GS003
Alternator G4
-XDI2:
PANEL NAME
Transformer 1 Transformer 1 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A
-BGB1
-BGT2
-BGC2

-XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1

-KFA1 -KFA1 -KFA1 -KFA1

-XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2

B B
-BGB1
-BGT2
-BGC2

-XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3

-KFA2 -KFA2 -KFA2 -KFA2

-XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4

C C
-BGB1
-BGT2
-BGC2

CB CLOSING BLOCKING
-XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5

-KFA3 -KFA3 -KFA3 -KFA3

-XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6

D -BGB1
D
-BGT2
-BGC2

-XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7

-KFA4 -KFA4 -KFA4 -KFA4

-XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8

E -BGB1 E
-BGT2
-BGC2

-XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9

-KFA5 -KFA5 -KFA5 -KFA5

-XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10


Legend:

-BGB1, -BGT2, -BGC2 = CB open or in Test position or Plug out


F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q04 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 38/1748

PANEL 7 00BBB02GS103
Station
8 05BAC01GS003
Alternator G5
9 06BAC01GS003
Alternator G6
10 00BCT02GS203
Step-Up
11 07BAC01GS003
Alternator G7
-XDI2:
PANEL NAME
Transformer 2 Transformer 2 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A
-BGB1
-BGT2
-BGC2

-XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1

-KFA1 -KFA1 -KFA1

-XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2

B B
-BGB1
-BGT2
-BGC2

-XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3

-KFA2 -KFA2 -KFA2

-XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4

CB CLOSING BLOCKING
C C
-BGB1
-BGT2
-BGC2

-XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5

-KFA3 -KFA3 -KFA3

-XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6

D -BGB1
D
-BGT2
-BGC2

-XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7

-KFA4 -KFA4 -KFA4

-XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8

E E

-XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9


SPARE

-XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10


Legend:

-BGB1, -BGT2, -BGC2 = CB open or in Test position or Plug out


F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q05 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 39/1748

PANEL 12 00BBC03GS103
Station
13 08BAC01GS003
Alternator G8
14 09BAC01GS003
Alternator G9
15 00BCT03GS203
Step-Up
16 10BAC01GS003
Alternator G10
17 11BAC01GS003
Alternator G11
-XDI2:
PANEL NAME
Transformer 3 Transformer 3 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A
-BGB1
-BGT2
-BGC2

-XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1 -XDI2 1

-KFA1 -KFA1 -KFA1 -KFA1

-XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2 -XDI2 2

B B
-BGB1
-BGT2
-BGC2

-XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3 -XDI2 3

-KFA2 -KFA2 -KFA2 -KFA2

-XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4 -XDI2 4

C C
-BGB1
-BGT2
-BGC2

CB CLOSING BLOCKING
-XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5 -XDI2 5

-KFA3 -KFA3 -KFA3 -KFA3

-XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6 -XDI2 6

D -BGB1
D
-BGT2
-BGC2

-XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7 -XDI2 7

-KFA4 -KFA4 -KFA4 -KFA4

-XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8 -XDI2 8

E -BGB1 E
-BGT2
-BGC2

-XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9 -XDI2 9

-KFA5 -KFA5 -KFA5 -KFA5

-XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10 -XDI2 10


Legend:

-BGB1, -BGT2, -BGC2 = CB open or in Test position or Plug out


F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q06 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 40/1748

PANEL 1 00BBA01GS103
Station
2 01BAC01GS003
Alternator G1
3 02BAC01GS003
Alternator G2
4 00BCT01GS203
Step-Up
5 03BAC01GS003
Alternator G3
6 04BAC01GS003
Alternator G4
-XDI2:
PANEL NAME
Transformer 1 Transformer 1 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A

-BT1 (-QAB)

-BT2 (-QAB)

-BGC2
-BT2 (-QBT)

CB TRUCK INTERLOCKING
-XDI2 11 11 11 11 11 11

-KFA9 -KFA9 -KFA9 -KFA9 -KFA9


B B
-XDI2 12 12 12 12 12 12

EARTHING TRUCK INTERLOCKING


-XDI2
13 14 13 14 13 14 13 14 13 14 13 14

C -BGT2 -BGT2 -BGT2 -BGT2 -BGT2 C


-BGC2 -BGC2 -BGC2 -BGC2 -BGC2

-XDI2 15 15 15 15 15 15

-RLE2

-XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16


D D

ITH LIMITOR TRIPPING LOGIC


ITH_BB ITH_BB ITH_BB ITH_BB ITH_BB ITH_BB
ITH_CB ITH_CB ITH_CB ITH_CB ITH_CB ITH_CB
ITH_CAB ITH_CAB ITH_CAB ITH_CAB ITH_CAB ITH_CAB

-XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17

-KFA10 -KFA10 -KFA10 -KFA10 -KFA10 -KFA10

-XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18

E E

-XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19

SPARE
-XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q07 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 41/1748

PANEL 7 00BBB02GS103
Station
8 05BAC01GS003
Alternator G5
9 06BAC01GS003
Alternator G6
10 00BCT02GS203
Step-Up
11 07BAC01GS003
Alternator G7
-XDI2:
PANEL NAME
Transformer 2 Transformer 2 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A

-BT1 (-QAB)

-BT2 (-QAB)

-BGC2
-BT2 (-QBT)

CB TRUCK MOVEMENT BLOCKING


-XDI2 11 11 11 11 11

-KFA6 -KFA6 -KFA6 -KFA6


B B
-XDI2 12 12 12 12 12

BUSBAR EARTHING SWITCH BLOCKING


-XDI2
13 14 13 14 13 14 13 14 13 14

C -BGT2 -BGT2 -BGT2 -BGT2 C


-BGC2 -BGC2 -BGC2 -BGC2

-XDI2 15 15 15 15 15

-RLE2

-XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16


D D

ITH LIMITOR TRIPPING LOGIC


ITH_BB ITH_BB ITH_BB ITH_BB ITH_BB
ITH_CB ITH_CB ITH_CB ITH_CB ITH_CB
ITH_CAB ITH_CAB ITH_CAB ITH_CAB ITH_CAB

-XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17

-KFA10 -KFA10 -KFA10 -KFA10 -KFA10

-XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18

E E

-XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19


SPARE

-XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q08 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 42/1748

PANEL 12 00BBC03GS103
Station
13 08BAC01GS003
Alternator G8
14 09BAC01GS003
Alternator G9
15 00BCT03GS203
Step-Up
16 10BAC01GS003
Alternator G10
17 11BAC01GS003
Alternator G11
-XDI2:
PANEL NAME
Transformer 3 Transformer 3 Wires: 2,5mm² Black
A Terminals: UT 4-QUATTRO 3044571 A

-BGT1 (-QAB)

-BGT2 (-QAB)

-BGC2
-BGT2 (-QBT)

CB TRUCK MOVEMENT BLOCKING


-XDI2 11 11 11 11 11 11

-KFA6 -KFA6 -KFA6 -KFA6 -KFA6


B B
-XDI2 12 12 12 12 12 12

BUSBAR EARTHING SWITCH BLOCKING


-XDI2
13 14 13 14 13 14 13 14 13 14 13 14

C -BGT2 -BGT2 -BGT2 -BGT2 -BGT2 C


-BGC2 -BGC2 -BGC2 -BGC2 -BGC2

-XDI2 15 15 15 15 15 15

-RLE2

-XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16 -XDI2 16


D D

ITH LIMITOR TRIPPING LOGIC


ITH_BB ITH_BB ITH_BB ITH_BB ITH_BB ITH_BB
ITH_CB ITH_CB ITH_CB ITH_CB ITH_CB ITH_CB
ITH_CAB ITH_CAB ITH_CAB ITH_CAB ITH_CAB ITH_CAB

-XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17 -XDI2 17

-KFA10 -KFA10 -KFA10 -KFA10 -KFA10 -KFA10

-XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18 -XDI2 18

E E

-XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19 -XDI2 19

SPARE
-XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 -XDI2 20 Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q09 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 43/1748

PANEL 1 00BBA01GS103
Station
2 01BAC01GS003
Alternator G1
3 02BAC01GS003
Alternator G2
4 00BCT01GS203
Step-Up
5 03BAC01GS003
Alternator G3
6 04BAC01GS003
Alternator G4
-XDV:
PANEL NAME
Transformer 1 Transformer 1 Wires: 2,5mm² Black
A Wires: 2,5mm² Light Blue A

TERMINAL URTK/S 0311087 E6345611700

-XDV 1 2,5mm² BK -XDV 6


L1

B B
-XDV 2 2,5mm² BK -XDV 7
L2

-XDV 3 2,5mm² BK -XDV 8


L3

-XDV 54 2,5mm² LB -XDV 9


N

-XDV 41 2,5mm² BK -XDV 11


da
C C
-XDV 49 2,5mm² BK -XDV 12
dn

D D

E E

Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q10 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 44/1748

PANEL 7 00BBB02GS103
Station
8 05BAC01GS003
Alternator G5
9 06BAC01GS003
Alternator G6
10 00BCT02GS203
Step-Up
11 07BAC01GS003
Alternator G7
-XDV:
PANEL NAME
Transformer 2 Transformer 2 Wires: 2,5mm² Black
A Wires: 2,5mm² Light Blue A

TERMINAL URTK/S 0311087 E6345611700

-XDV 1 2,5mm² BK -XDV 6


L1

B B
-XDV 2 2,5mm² BK -XDV 7
L2

-XDV 3 2,5mm² BK -XDV 8


L3

-XDV 54 2,5mm² LB -XDV 9


N

-XDV 41 2,5mm² BK -XDV 11


da
C C
-XDV 49 2,5mm² BK -XDV 12
dn

D D

E E

Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q11 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 45/1748

PANEL 12 00BBC03GS103
Station
13 08BAC01GS003
Alternator G8
14 09BAC01GS003
Alternator G9
15 00BCT03GS203
Step-Up
16 10BAC01GS003
Alternator G10
17 11BAC01GS003
Alternator G11
-XDV:
PANEL NAME
Transformer 3 Transformer 3 Wires: 2,5mm² Black
A Wires: 2,5mm² Light Blue A

TERMINAL URTK/S 0311087 E6345611700

-XDV 1 2,5mm² BK -XDV 6


L1

B B
-XDV 2 2,5mm² BK -XDV 7
L2

-XDV 3 2,5mm² BK -XDV 8


L3

-XDV 54 2,5mm² LB -XDV 9


N

-XDV 41 2,5mm² BK -XDV 11


da
C C
-XDV 49 2,5mm² BK -XDV 12
dn

D D

E E

Legend:

-BGT2 (QBT) = Earthing Truck in Test position


-BGT1, -BGT2, -BGC2 = CB open or in Test position or Plug out
F -KFAx = Aux. Relay for CB closing blocking F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812206 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description ICL
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
XDI2 - SIGNAL INTERCONNECTION &EFF Q12 13
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 46/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=K00+INF/A02 SHEET INDEX AM
=K00+INF/Z01 ZONES IN EPLAN - MV AM
=K00+INF/Z02 ZONES IN EPLAN - LV AM
=K00+INF/Z03 REFERENCE DESIG. OF OBJECTS AM
=K00+INF/Z04 REFERENCE DESIG. OF OBJECTS AM
=K00+INF/Z05 REFERENCE DESIG. OF OBJECTS AM
=K00+INF/Z06 REFERENCE DESIG. OF OBJECTS AM
B =K00+INF/Z07 REFERENCE DESIG. OF OBJECTS AM B
=K00+INF/Z08 REFERENCE DESIG. OF OBJECTS AM
=K00+INF/Z10 ANSI CODES AM
=K00+INF/Z11 ANSI CODES AM

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 47/1748

A
TVT A
Top mounted busbar Voltage Transformers
(TOP MOUNTED VOLTAGE TRANSFORMER, CAPACITIVE DIVIDERS, C.D. CABLES)

TOP TES
Top mounted busbar Earthing Switch
TOP of switchgear (TOP MOUNTED EARTHING SWITCH, CAPACITIVE DIVIDERS, C.D. CABLES)
(ANTIFERRORESONANCE RESISTOR)

B B

LVD BB
Low Voltage compartment Door BusBar compartment
(DEVICES ON DOOR OF LV COMPARTMENT) (ARC DETECTOR ON BUSBAR, ITH LIMITOR IN BB COMPARTMENT)

C C

CB
Circuit Breaker compartment
(HEATER AND/OR ARC SENSOR IN BREAKER COMPARTMENT,
WITHDRAWABLE VT METERING, ITH LIMITOR IN CB COMPARTMENT)

MV
D Medium Voltage compartment
(LOAD BREAK SWITCH - NALFE)
CT D
Current Transformer
(CURRENT TRANSFORMERS, CAPACITIVE DIVIDERS, C.D. CABLES)

CAB
CABle compartment
(SURGE ARRESTERS, GFCT*,ARC SENSOR, ITH LIMITOR IN CABLE COMPARTMENT)
VT
Voltage Transformer
(FIX MOUNTED VOLTAGE TRANSFORMERS)

E CRT/CWT E
Cable Removable/Withdrawable voltage Transformers
(REMOVABLE/WITHDRAWABLE VT IN CABLE COMPARTMENT)

ES
Earthing Switch
(LIMIT SWITCHES AND COIL OF EARTHING SWITCH)

F * - GFCT (Ground Fault Current Transformer) also in case if are mounted under cubicle. For place of mounting see SLD diagram of switchgear F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
ZONES IN EPLAN - MV &EFS Z01 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 48/1748

LCT REF
Low voltage Compartment – Top low voltage compartment, place for the basic unit of the divided protection device
(LV COMPARTMENT LIGHT, LIMIT SWITCH OF LV COMPARTMENT (BASIC UNIT OF PROTECTION RELAY WITH DIVIDED DISPLAY)
A LIGHT) A

LVL
Low Voltage compartment – Left panel
B (CABLE TREES TERMINALS, OTHER TERMINALS B
OR RELAYS)

LV
wiring panel of Low Voltage compartment
(DEVICES AND TERMINALS INSIDE LV COMPARTMENT)

C C

D D
LVR + LCR
Low Voltage compartment – Right panel
(CABLE TREES TERMINALS, LV HEATER
+ LOW VOLTAGE COMPARTMENT LIGHT)

E E

PLG LCB
medium voltage compartment – truck multiPLuG Low voltage Compartment – Bottom
(TRUCK MULTIPLUG) (LIMIT SWITCH OF TRUCK MULTIPLUG)
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
ZONES IN EPLAN - LV &EFS Z02 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 49/1748

DESCRIPTION OF ZONES ASSIGNED IN EPLAN


A A
ZONE DESCRIPTION

ACS ACCESSORIES

BB BUSBAR COMPARTMENT

CAB CABLE COMPARTMENT

B CB CIRCUIT BREAKER COMPARTMENT B


CRT CABLE REMOVABLE VOLTAGE TRANSFORMERS

CT CURRENT TRANSFORMERS

ES EARTHING SWITCH

LCB LOW VOLTAGE COMPARTMENT-BOTTOM

LCR LOW VOLTAGE COMPARTMENT-RIGHT PANEL

C LCT LOW VOLTAGE COMPARTMENT-TOP C


LV WIRING PANEL OF LOW VOLTAGE COMPARTMENT

LVD LOW VOLTAGE COMPARTMENT DOOR

LVR WIRING PANEL OF LOW VOLTAGE COMPARTMENT-RIGHT PANEL

MV MEDIUM VOLTAGE COMPARTMENT

PLG MEDIUM VOLTAGE COMPARTMENT-TRUCK MULTIPLUG

D REF LOW VOLTAGE COMPARTMENT- BASIC UNIT OF DIVIDED REF PROTECTION D


SPA PROJECT SPARE PARTS

TES TOP MOUNTED BUSBAR EARTHING SWITCH

TOP TOP OF SWITCHGEAR (FOR DUMPING RESISTOR)

TRA TRANSFORMER ACCESSORIES

TVT TOP MOUNTED BUSBAR VOLTAGE TRANSFORMERS

E VT VOLTAGE TRANSFORMERS E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z03 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 50/1748

DEVICE NAME DESCRIPTION


A A
DEVICE NAME DESCRIPTION DEVICE NAME DESCRIPTION

-AA MULTIFUNCTION UNIT (CENTRAL UNITS) -BGF POSITION SWITCHES OF MEDIUM VOLTAGE FUSES

-BAD CAPACITIVE VOLTAGE DIVIDERS -BGI POSITION SWITCHES OF DISCONNECTORS

-BAR VOLTAGE PROTECTION RELAYS -BGK POSITION SWITCHES OF KEY LOCKS

B -BAS VOLTAGE SENSORS -BGL POSITION SWITCHES OF ELECTROMECHANICAL LOCKS B


-BAT VOLTAGE TRANSFORMERS -BGS POSITION SWITCHES (PROXIMITY SENSORS) OF CIRCUIT-BREAKER SPRINGS

-BCD DIFFERENTIAL PROTECTION RELAYS -BGT POSITION SWITCHES (PROXIMITY SENSORS) OF CIRCUIT-BREAKER TRUCK

-BCF FEEDER PROTECTION RELAYS -BGV POSITION SWITCHES OF VENTILATORS

-BCG GENERATOR PROTECTION RELAYS -BGZ OTHER POSITION SWITCHES

-BCM MOTOR PROTECTION RELAYS -BM HYGROSTAT

C -BCN NEUTRAL CURRENT TRANSFORMERS -BPA ARC PRESSURE DETECTORS C


-BCP TRANSFORMER PROTECTION RELAYS -BPS PRESSURE SWITCHES

-BCR CURRENT PROTECTION RELAYS -BQ INSULATION MONITORING DEVICE

-BCS CURRENT SENSORS -BR FLAME DETECROS, SMOKE DETECTORS, OPTOCOUPLER

-BCT CURRENT TRANSFORMERS -BT THERMOSTATS

-BCZ DISTANCE PROTECTION RELAYS -BU BUCHHOLZ RELAY

D -BD DENSITY SWITCHES -BX ARC PROTECTION RELAYS D


-BEF FREQUENCY SCHUTZ RELAYS -BZ MULTIFUNCTION SENSORS, COMBINED CURRENT AND VOLTAGE SENSORS

-BER SUPERVISONS RELAYS -BZR RADIO FREQUENCY IDENTIFICATION DEVICES

-BES SYNCHRONIZING RELAYS -CA CAPACITORS

-BET THERMAL PROTECTION RELAYS -CN GAS CYLINDER

-BGA ARC SCHOCK DETECTORS (POSITION SWITCHES) -CQ SPRING

E -BGB POSITION SWITCHES (PROXIMITY SENSORS) OF CIRCUIT-BREAKER -EA LIGHTING LAMPS E


-BGC POSITION SWITCHES OF CIRCUIT-BREAKER CONNECTOR -EB HEATERS

-BGD POSITION SWITCHES (PROXIMITY SENSORS) OF THE DOOR -FA SURGE ARRESTER

-BGE POSITION SWITCHES (PROXIMITY SENSORS) OF EARTHING SWITCH -FB RESIDUAL CURRENT DEVICE

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z04 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 51/1748

DEVICE NAME DESCRIPTION


A A
DEVICE NAME DESCRIPTION DEVICE NAME DESCRIPTION

-FCD FUSE-DISCONNECTORS FOR PROTECTION OF AUXILIARY CIRCUITS -MBC CLOSING RELEASES

-FCF MEDIUM VOLTAGE FUSES -MBO OPENING RELEASE

-FCM MINIATURE CIRCUIT-BREAKERS -MBU UNDERVOLTAGE RELEASES

B -FCT THERMAL OVERLOAD RELEASES -ML OPERATING MECHANISM B


-FN MECHANICAL OR INSULATING PROTECTION -PFB BLUE SIGNAL LAMPS

-GA GENERATORS -PFF FLAG RELAYS

-GQ VENTILATORS -PFG GREEN SIGNAL LAMPS

-KFA AUXILIARY RELAYS OR CONTACTORS -PFR RED SIGNAL LAMPS

-KFC AUXILIARY RELAYS OR CONTACTORS FOR CLOSING -PFS SHORT CIRCUIT INDICATORS

C -KFE INPUT/OUTPUT MODULE, INPUT/OUTPUT EXPANSION MODULE -PFV VOLTAGE INDICATORS C


-KFI INTEGRATED CIRCUITS -PFW WHITE SIGNAL LAMPS

-KFL LOCK-OUT RELAYS -PFX CROSS INDICATORS, ELECTROMECHANICAL INDICATORS

-KFM MICROPROCESSORS -PFY YELLOW SIGNAL LAMPS

-KFN ANTIPUMPING RELAYS -PGA AMMETERS

-KFO AUXILIARY RELAYS OR CONTACTORS FOR OPENING -PGC COUNTERS

D -KFP PROGRAMMABLE LOGIC CONTROLLER (PLC) -PGF FREQUENCY METERS D


-KFR RECLOSING RELAYS -PGH HOUR METERS

-KFS SYNCHRONIZING DEVICES -PGI HUMAN MACHINE INTERFACES

-KFT AUXILIARY TIME RELAYS, DELAY ELEMENTS -PGJ ACTIVE ENERGY METERS

-KFU CONTROL UNITS -PGK REACTIVE ENERGY METERS

-KFZ FEEDBACK CONTROLLER, POTENTIOMETER, REGULATOR -PGM MULTIFUNCTION INDICATORS

E -MAD MOTORS FOR ELECTRICAL OPERATION OF DISCONNECTORS -PGP POWER-FACTOR METERS E


-MAE MOTORS FOR ELECTRICAL OPERATION OF EARTHING SWITCH -PGQ VARMETERS

-MAS MOTORS FOR SPRINGS CHARGING OF CIRCUIT-BREAKER OR DISCONNECTOR -PGS SYNCHRONOSCOPES

-MAT MOTORS FOR ELECTRICAL OPERATION OF TRUCK -PGV VOLTMETERS

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z05 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 52/1748

DEVICE NAME DESCRIPTION


A A
DEVICE NAME DESCRIPTION DEVICE NAME DESCRIPTION

-PGW WATTMETERS -SFA AMMETRIC SWITCHES

-PH NAMEPLATES -SFC CLOSING PUSH-BUTTONS, CONTROL SWITCHES

-PJ ACOUSTICAL SIGNAL DEVICES (BELLS, SIRENS) -SFL LOCKING CONTACTS

B -QAB CIRCUIT-BREAKERS -SFM MOTOR CONTROL PUSH-BUTTON B


-QAC CONTACTORS (FOR POWER) -SFO OPENING PUSH-BUTTONS

-QBD DISCONNECTORS -SFR RESET PUSH-BUTTONS

-QBH MANUAL CIRCUIT-BREAKERS -SFS SELECTOR SWITCHES

-QBL LINKS -SFT TEST PUSH-BUTTONS

-QBM MINIATURE SWITCH-DISCONNECTORS -SFU UNLOCKING PUSH-BUTTONS

C -QBP POLES OR VACUUM INTERRUPTER -SFV VOLTMETRIC SWITCHES C


-QBS SWITCH-DISCONNECTORS -TA POWER TRANSFORMERS

-QBT TRUCKS -TB RECTIFIERS, CONVERTERS (FEEDERS)

-QCA EARTHING SWITCHES FOR ELIMINATION OF INTERNAL ARC -TFA ACTIVE POWER TRANSDUCERS

-QCE EARTHING SWITCHES -TFC CURRENT TRANSDUCERS

-QQ CLUTCHES -TFF FREQUENCY TRANSDUCERS

D -QZD THREE-POSITION DISCONNECTORS (COMBINED DISCONNECTOR AND EARTHING -TFJ ACTIVE ENERGY TRANSDUCERS D
SWITCHES)
-QZS THREE-POSITION SWITCH-DISCONNECTORS (COMBINED SWITCH-DISCONNECTORS AND -TFK REACTIVE ENERGY TRANSDUCERS
EARTHING SWITCHES)
-RAA ANTIFERRORESONANCE RESISTORS -TFM MULTIFUNCTION TRANSDUCERS

-RAD DIODES -TFP POWER-FACTOR TRANSDUCERS

-RAI INDUCTORS -TFQ REACTIVE POWER TRANSDUCERS

-RAR RESISTORS -TFS SIGNAL CONVERTERS

E -RF FILTERS -TFT TEMPERTAURE TRANSDUCERS E


-RLE ELECTROMECHANICAL LOCKS -TFV VOLTAGE TRANSDUCERS

-RLM MECHANICAL INTERLOCKS -UA SUPPORTS

-RR SHOCK-ABSORBERS -UZ FITTINGS

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z06 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 53/1748

DEVICE NAME DESCRIPTION


A A
DEVICE NAME DESCRIPTION DEVICE NAME DESCRIPTION

-WA BUSBARS -XDZ CONNECTORS OR TERMINAL BLOCKS FOR THREE-POSITION DISCONNECTORS OR


SWITCH-DISCONNECTORS
-WBB BUSHINGS
-XE EARTHING TERMINALS
-WBC POWER CABLES

B -WE EARTHING CONNECTIONS B


-WGC CONTROL CABLES

-WGS COMMUNICATION CABLES (SHIELDED TWISTED PAIRS)

-WH OPTICAL FIBRES

-WQ MECHANICAL TRANSMISSIONS

-XB POWER CONNECTORS

C -XD CONNECTORS OR TERMINAL BLOCKS FOR MEDIUM VOLTAGE SWITCHES (ADMITTED) C


-XDA TERMINAL BLOCKS FOR AMMETRIC CIRCUITS

-XDB CONNECTORS OR TERMINAL BLOCKS FOR CIRCUIT-BREAKER

-XDC TERMINAL BLOCKS FOR CUSTOMER

-XDE CONNECTORS OR TERMINAL BLOCKS FOR EARTHING SWITCH

-XDF CONNECTORS OR TERMINAL BLOCKS FOR FORCED COOLING VENTILATORS

D -XDH CONNECTORS OR TERMINAL BLOCKS FOR HEATERS AND FOR POSITION SWITCHES DETECTING INTERNAL ARC D
-XDI CONNECTORS OR TERMINAL BLOCKS FOR INTERCONNECTIONS

-XDJ CONNECTORS OR TERMINAL BLOCKS FOR DISCONNECTORS

-XDM TERMINAL BLOCKS FOR MEASURING TEST

-XDP MULTILEVEL TERMINAL BLOCKS WITH ADVANCED BRIDGING OPTIONS

-XDS SOCKET OUTLETS

E -XDT CONNECTORS OR TERMINAL BLOCKS FOR TRUCK POSITION CONTACTS E


-XDU CONNECTORS OR TERMINAL BLOCKS FOR VOLTAGE TRANSFORMER TRUCKS

-XDV CONNECTORS OR TERMINAL BLOCKS FOR VOLTMETRIC CIRCUITS

-XDX SUPPORT TERMINAL BLOCKS OR SUPPORT CONNECTORS

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z07 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 54/1748

TERMINAL STRIP DESCRIPTION


A A
TERMINAL STRIP DESCRIPTION

-XDI1 INTERCONNECTIONS

-XDI2 INTERCONNECTIONS

-XDI3 INTERCONNECTIONS

B -XDI4 INTERCONNECTIONS B
-XDIV INTERCONNECTIONS

-XDIA INTERCONNECTIONS

-XDA CURRENT TRANSFORMERS

-XDV VOLTAGE TRANSFORMER

-XDCA CURRENTS TO CUSTOMER SIDE

C -XDCV VOLTAGES TO CUSTOMER SIDE C


-XDB1 TERMINAL BLOCKS FOR CB AUXILIARY CIRCUITS

-XDB2 END SWITCH OF CB 58-PIN PLUG

-XDJ TERMINAL BLOCK FOR DISCONNECTOR AUXILIARY CIRCUIT

-XDX CONTROL AND PROTECTION CIRCUITS

-XDX1 PROTECTION RELAY CARDS

D -XDH AC 230 V CIRCUITS D


-XE GROUND

-XDE EARTHING SWITCH

-XDF TERMINALS BLOCK FOR AUXILIARY CIRCUIT OF FORCED COOLING VENTILATORS

-XDH ITH LIMITORS

-XDC CUSTOMER TERMINALS

E -XDCS AUXILIARY SUPPLY TERMINALS E


-WE EARTHING POINTS

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
REFERENCE DESIG. OF OBJECTS &EFS Z08 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 55/1748

PROTECTION FUNCTIONS - ANSI CODES


A A
FUNCTION DESCRIPTION FUNCTION DESCRIPTION

21, 21P, 21N DISTANCE PROTECTION 47O- NEGATIVE-SEQUENCE OVERVOLTAGE PROTECTION

21FL FAULT LOCATOR 47U+ POSITIVE-SEQUENCE UNDERVOLTAGE PROTECTION

B 21GT THREE-PHASE UNDERIMPEDANCE PROTECTION 49F THREE-PHASE THERMAL PROTECTION FOR FEEDERS, CABLES AND DISTRIBUTION B
TRANSFORMERS
21YN ADMITTANCE BASED EARTH-FAULT PROTECTION 49T, 49G THREE-PHASE THERMAL OVERLOAD PROTECTION (POWER TRANSFORMERS, GENERATORS)

24 OVEREXCITATION PROTECTION 49M THERMAL OVERLOAD PROTECTION FOR MOTORS

27 THREE-PHASE UNDERVOLTAGE PROTECTION 50L/50NL ARC PROTECTION

C 27/59THD THIRD HARMONIC BASED STATOR EARTH-FAULT PROTECTION 50N NON-DIRECTIONAL EARTH-FAULT INSTANTANEOUS PROTECTION C

32N WATTMETRIC BYSED EARTH-FAULT PROTECTION 50P THREE-PHASE NON-DIRECTIONAL INSTANTANEOUS OVERCURRENT PROTECTION

32R/32O REVERSE POWER/DIRECTIONAL OVERPOWER PROTECTION 51BF/51NBF CIRCUIT BREAKER FAILURE PROTECTION

32U UNDERPOWERPROTECTION 51LR MOTOR LOAD JAM PROTECTION

D 37F LOSS OF PHASE (UNDERCURRENT) 51N NON-DIRECTIONAL EARTH-FAULT PROTECTION D

37, 37M LOSS OF LOAD SUPERVISION 51NHA HARMONIC BASED EARTH-FAULT PROTECTION

40 THREE-PHASE UNDEREXCITATION PROTECTION 51P THREE-PHASE NON-DIRECTIONAL OVERCURRENT PROTECTION

46 NEGATIVE-SEQUENCE OVERCURRENT PROTECTION 51V VOLTAGE DEPENDENT OVERCURRENT PROTECTION

E 46G, 46M NEGATIVE-SEQUENCE OVERCURRENT PROTECTION (FOR MOTORS, GENERATORS) 59 THREE-PHASE OVERVOLTAGE PROTECTION E

46PD PHASE DISCONTINUITY PROTECTION 59G RESIDUAL OVERVOLTAGE PROTECTION

46R PHASE REVERSAL PROTECTION 64 ROTOR EARTH-FAULT PROTECTION

47O+ POSITIVE-SEQUENCE OVERVOLTAGE PROTECTION 67 THREE-PHASE DIRECTIONAL OVERCURRENT PROTECTION

NOTE: All protection functions mentioned on this page can be used in ABB Relion protection relays. Not all of protection functions are usable in every ABB Relion protection type.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
ANSI CODES &EFS Z10 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 56/1748

PROTECTION FUNCTIONS - ANSI CODES


A A
FUNCTION DESCRIPTION

67N DIRECTIONAL EARTH-FAULT PROTECTION

67NIEF TRANSIENT / INTERMITTENT EARTH-FAULT PROTECTION

B 68 THREE-PHASE INRUSH DETECTOR B

81 FREQUENCY PROTECTION

81LSH LOAD SHEDDING

81O OVERFREQUENCY PROTECTION

C 81R FREQUENCY GRADIENT PROTECTION C

81U UNDERFREQUENCY PROTECTION

87 HIGH-IMPEDANCE DIFFERENTIAL PROTECTION

87G/87M STABILIZED DIFFERENTIAL PROTECTION FOR MACHINES

D 87GH/87MH HIGH-IMPEDANCE OR FLUX-BALANCE BASED DIFFERENTIALPROTECTION FOR MACHINES D

87M MOTOR DIFFERENTIAL PROTECTION

87NH HIGH IMPEDANCE BASED RESTRICTED EARTH-FAULT PROTECTION

87NL NUMERICAL STABILIZED LOW IMPEDANCE RESTRICTED EARTH-FAULT PROTECTION

E 87L LINE DIFFERENTIAL PROTECTION WITH IN ZONE POWER TRANSFORMER E

87T STABILIZED AND INSTANTANEOUS DIFFERENTIAL PROTECTION FOR 2-WINDING


TRANSFORMERS
94/86 MASTER TRIP

94 TRIPPING LOGIC

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 K00
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812207 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description INF
COMMON DRAWINGS DCC & Page Pages
ABB s.r.o.
ANSI CODES &EFS Z11 11
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 57/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT1,-BCT2,-BCT3
TPU 54.43
P1 150/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P2
POS. DESIGN. NAME
1 00BBA01GS103 Station Transformer 1

D D

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

-BCN1
E RKU 2918 E
Under cubicle (accessory)
60/1 A; 1FS10, 1,25VA
inner diameter d=180mm

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 58/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=A01+LV/A01 SINGLE LINE SCHEME AM
=A01+LV/A02 SHEET INDEX AM
=A01+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A01+LV/G02 AC SUPPLY CIRCUITS AM
=A01+LV/M01 VD4 INTERNAL WIRING AM
=A01+LV/M02 EARTHING SWITCH AM
=A01+LV/M03 CONTROL CIRCUITS AM
B =A01+LV/M04 TRIPPING CIRCUITS AM B
=A01+LV/M05 SIGNAL CIRCUITS AM
=A01+LV/P01 XDI2 SIGNALS AM
=A01+LV/P02 XDI2 SIGNALS AM
=A01+LV/Q01 MAN CONTROL SYSTEM AM
=A01+LV/Q02 MAN CONTROL SYSTEM AM
=A01+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A01+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A01+LV/S03 GFCT AM C
=A01+LV/S05 VOLTAGE METERING AM
=A01+LV/V01 PANEL LAYOUT AM
=A01+LV/W01 LV COMP. DOOR LAYOUT AM
=A01+LV/X01 SPARE TERMINALS AM
=A01+LV/X02 ES SPARE CONTACTS AM
=A01+LV/X03 CB SPARE CONTACTS AM
=A01+LV/X04 MCB SPARE CONTACTS AM
D =A01+LV/X05 TERMINALS =A01+LV-XDA AM D
=A01+LV/X06 TERMINALS =A01+LV-XDC AM
=A01+LV/X07 TERMINALS =A01+LV-XDC AM
=A01+LV/X08 TERMINALS =A01+LV-XDC AM
=A01+LV/X09 TERMINALS =A01+LV-XDI1 AM
=A01+LV/X10 TERMINALS =A01+LV-XDI2 AM
=A01+LV/X11 TERMINALS =A01+LV-XDV AM
=A01+LV/X12 TERMINALS =A01+LV-XDX AM
E =A01+LV/X13 TERMINALS =A01+LV-XDX AM E
=A01+LV/X14 TERMINALS =A01+LV-XE AM
=A01+LV/X15 TERMINALS =A01+LVR-XDE1 AM
=A01+LV/X16 TERMINALS =A01+LVR-XDH AM
=A01+LV/X17 TERMINALS =A01+LVR-XDH1 AM
=A01+LV/X18 PART LIST AM
=A01+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 59/1748

SPRING
=A02
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1

A A
-XDI1 2

-XDI1 3

-XDI1 4

-XDI1 5

-XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 60/1748

=A02
LIGHTING
CIRCUIT SPARE
-XDI1 7

A A
-XDI1 8

-XDI1 9

-XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 61/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

1011

1012
M04/1D

M04/3D

M04/3D

M04/4D

M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/4C

Q02/2C
X03/6C

X03/6C

X03/3C

X03/2C

X03/5C

X03/3C

X03/8C

X03/4C

X03/5C

X03/4C

X03/7C

X03/7C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

X03/3D

Q02/4D

Q02/2D

X03/2D

M04/1E

M04/3E

M04/4E

X03/5D

X03/8D

M05/3C

M05/3C

X03/4D

X03/5D

X03/4D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

X03/7D

X03/7D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

X03/1C

X03/1C

X03/2C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 62/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 63/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/7C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

00BHT01GS103-YB01

00BHT01GS108-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
9 - 10
11 - 12

-XDC 2 -XDC 4 -XDC 6 -XDC 10


C C

13
-KFA9
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 64/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
00BHT01GS103-YB32

00BHT01GS103-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:16
13 P02/6E 11 24 24 GY BN GY BN
+LVD P02/5C
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P02/7D
M01/5D XDI2:18
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/5C 13 14 Q02/6C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 65/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 66/1748

ALTERNATOR G1 ALTERNATOR G2 STEP-UP ALTERNATOR G3 ALTERNATOR G4 =A02


OFF OFF TRANSFORMER 1 OFF OFF
OFF
-XDI2 1

A A
-XDI2 2

-XDI2 3

-XDI2 4

-XDI2 5

-XDI2 6

-XDI2 7

B B
-XDI2 8

-XDI2 9

-XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 67/1748

CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A02


TRIPPING

-XDI2 11

A A
-XDI2 12

-XDI2 13

-XDI2 14

-XDI2 15

-XDI2 16

-XDI2 17

B B
-XDI2 18

-XDI2 19

-XDI2 20

XDI2:16
M04/8B
C C

-XDI2 11 12 13 14 15 16 17 18 19 20

XDI2:18
M04/8E

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 68/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 00BHT01GS108-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 00BHT01GS108-XB02 00BHT01GW101-XM84 00BBA01CE011-XM85 00BBA01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 69/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE STATION


00BHT01GS103-XB01 00BHT01GS103-XB02 POSITION POSITION TRANSFORMER CB
00BHT01GS103-XB41 00BHT01GS103-XB40 REMOTE
A COMMAND MODE A
00BHT01GS103-XB43

B B

M01/3B M01/3B
C +PLG -XDB 7 +PLG -XDB 28 C
-QAB -QAB
11 9
-BGB1 -BGB1 13 13 11

12 10 -KFA11 -KFA12 +LVD-SFS1


M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38
M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 70/1748

L1 L2 L3
A = A
+ PROTECTION CT
00BHT01CE001A/B/C
1 -XDA 17
+CT -XE
P1 P1 P1

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 11

2S1
B TPU 54.43 -BCT1 B
150/1A 2S2
Core 2: 5P20, 10VA
-XDA 12

-XDA 13

2S1
-BCT2
C 2S2 C
-XDA 14
MAN
CONTROL
SYSTEM
(CCP)
-XDA 15

2S1
-BCT3
2S2
D D
-XDA 16

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 71/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
00BHT01CE003A/B/C
2 -XDA 7
+CT -XE DO NOT REMOVE THESE JUMPERS
UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

+LVD
-PGA1
-XDA 1 17 18 -XDA 18
A
1S1 FB96-1
B TPU 53.43 -BCT1 150/1A B
150/1A 1S2 0-150/300A
Core 1: 0.5Fs5, 10VA RED LINE AT 121 A
-XDA 2 -XDA 19

+LVD
-PGA2
-XDA 3 17 18 -XDA 20
A
1S1 FB96-1
-BCT2 150/1A
C TPU 53.43 1S2 0-150/300A C
-XDA 4
RED LINE AT 121 A
-XDA 21
MAN
CONTROL
+LVD
SYSTEM
-PGA3 (CCP)
-XDA 5 17 18 -XDA 22
A
1S1 FB96-1
-BCT3 150/1A
TPU 53.43 1S2 0-150/300A
RED LINE AT 121 A
D D
-XDA 6 -XDA 23

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
Ck
-WE

E E
+LVD GND L3 GND L2 GND L1 GND
1
-PFV1 2 M03/7B
CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
P2 P2 P2 6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 72/1748

A = A
+ GROUND FAULT
CURRENT
00BHT01CE021

L1 L2 L3

B B
+CAB

C C
MAN
CONTROL
SYSTEM
(CCP)

P1 S1
+ACS
D -BCN1 P2 S2 D
RKU 2918
Under cubicle (accessory)
60/1 A
1FS10, 1,25VA, VA

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
GFCT &EFS S03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 73/1748

=A04 =A04

A A

=A04S07/2D =L1-A04
=A04S07/3D =L2-A04 =A04S07/5E =dn-A04
=A04S07/3E =L3-A04 =A04S07/5D =da-A04

-XDV 1 2 3

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
VT - Y WINDING VT - Y WINDING
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22
VT - OPEN DELTA

Q01/7C

X04/4C
=A04

C =A04S07/3E C
=N-A04 -XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 00BB101CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (CCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
00BBA01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(CCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 74/1748

=A01+LV =A01
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 91
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 13
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 55
+LV +LVR -XE TERMINAL USLKG 5 0441504 7
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-RAD1 DIODES
=A02+LCT
DEVICE TAG TEXT
-XDI1 -XDI2 -XDV
-EA1 LV LIGHTING

-XDX -XDA

-XDC
D D

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 75/1748

=A01+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX1 E/S OPEN / CLOSED

B -PFX2 B

A01 Station -PFX3


Transformer 1
-SFS1 LOCAL - REMOTE SWITCH

-SFT1 LAMP TEST

705 mm
-PGA1 -PGA2 -PGA3

-SFO1 CB OPEN

-SFC1 CB CLOSE

-PGV1
-SFV1 VOLTMETER SELECTOR SWITCH
C -PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 76/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 77/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED

A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 78/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED CB CLOSED AND CB CLOSED CB CLOSED CB OPEN CB OPEN CB SPRING CB SPRING CB IN TEST CB IN SERVICE CB OPEN OR IN
IN SERVICE CHARGED DISCHARGED POSITION POSITION TEST POSITION
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439 441 443 445 447 449

B B

C M01/3B M01/3B M01/5B M01/6B M01/6B M01/5B M01/6B M01/1B M01/1B M01/8B M01/8B M01/5B
C
+PLG -XDB 3+PLG -XDB 5 +PLG -XDB 6 +PLG -XDB 9 +PLG -XDB 32 +PLG -XDB 8 +PLG -XDB 27 +PLG -XDB +PLG
24 -XDB 26 +PLG -XDB 57 +PLG -XDB 55 +PLG -XDB 29
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 28 7 19 -BGB1 23 31 1 25 4 2 53 53 13 33
+LCB +LCB +LCB
-BGB1 -BGB1 16 -BGB1 -BGB1 -BGB1 -BGB1 -BGS2 -BGS2 -BGT2 -BGT1 -BGB1 -BGT2
-BGC2 -BGC2 -BGC2 33
23 27 29 8 20 24 32 2 26 3 1 54 54 14 34
M01/1F M01/2F M01/2F
-BGT1
34
-XDB 13 -XDB 15 -XDB 19 -XDB 42 -XDB 18 -XDB 37 -XDB 34 -XDB 36 -XDB 58 -XDB 56 -XDB 39
M01/3D M01/3D -XDB 16 M01/6D M01/6D M01/5D M01/6D M01/1D M01/1D M01/8D M01/8D M01/5D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440 442 444 446 448 450

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 79/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT1 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
19 -XDA BK
+CT-BCT1 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT2 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
21 -XDA +CT-BCT2 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT3 1S1 S02/4D
BK

6
23 -XDA +CT-BCT3 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4A
GNYE

Project number

Document number
11
+CT-BCT1 2S1 S01/4B
BK
12
+CT-BCT1 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
13

+CT-BCT2 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT2 2S2 S01/4C


BK

Customer
15

+CT-BCT3 2S1 S01/4D


BK
16

+CT-BCT3 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4A


GNYE
4

18

+LVD-PGA1 18 S02/5B
BK
19

-XDA 2 S02/5B
BK
20

+LVD-PGA2 18 S02/5C
BK
21

-XDA 4 S02/5C
BK
22

+LVD-PGA3 18 S02/5D
BK
5

23

-XDA 6 S02/5D
BK

Project name

Page description
6

Station Transformer 1
TERMINALS =A01+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A01
8 80/1748

Pages
38
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

91 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/2D
371

BK

+PLG-QAB-XDB 7 Q02/3D
372

BK
Station Transformer 1
TERMINALS =A01+LV-XDC

+PLG-QAB-XDB 38 Q02/4D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/4D
374

BK

-KFA11 14 Q02/5D
375

BK
7

-KFA12 14 Q02/6D
376

BK
DCC &

-KFA11 13 Q02/6D
377

BK
Installation =

+LVD-SFS1 12 Q02/7D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/7D
379

BK
Page

X01/3B
391

LV

X06
A01

X01/3B
392

X01/4B
8 81/1748

393

Pages
38

X01/4B
394

F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/4B

395

HAVELKA Libor
Remark
X01/4B

396
+LVR-XDE1 11 X02/2B

401
BK

Released by
BRAUN Jiri
+LVR-XDE1 12 X02/2E

402
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVR-XDE1 13 X02/3B

403
BK

+LVR-XDE1 14 X02/3E

Date
404
BK

91 PCS
+LVR-XDE1 15 X02/4B

405
BK

Project number

Document number
+LVR-XDE1 16 X02/4E
406
BK

+LVR-XDE1 21 X02/5B

ABB s.r.o.
407
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
+LVR-XDE1 22 X02/5E

TERMINAL UT 4 3044102
408

BK

+LVR-XDE1 23 X02/6B
409

BK

Customer
+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

Customer project number


Customer document number
+LVR-XDE1 26 X02/7E
412

BK
4

+LCB-BGC2 22 X03/1B
421

BK

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E
424

BK

+LCB-BGC2 28 X03/2B
425

BK
5

+LCB-BGC2 29 X03/2E
426

BK

+PLG-QAB-XDB 3 X03/2B
427

BK

+PLG-QAB-XDB 13 X03/2E

Project name
428

BK

Page description
+PLG-QAB-XDB 5 X03/3B
429

BK

+PLG-QAB-XDB 15 X03/3E
430

BK
6

+PLG-QAB-XDB 6 X03/3B
431

BK

+PLG-QAB-XDB 16 X03/3E
432

BK
Station Transformer 1
TERMINALS =A01+LV-XDC

+PLG-QAB-XDB 9 X03/4B
MAN PHNOM PENH 5304532
433

BK

+PLG-QAB-XDB 19 X03/4E
434

BK

+PLG-QAB-XDB 32 X03/4B
435

BK
7

+PLG-QAB-XDB 42 X03/4E
436

BK
DCC &

+PLG-QAB-XDB 8 X03/5B
437

BK
Installation =

+PLG-QAB-XDB 18 X03/5E
438

BK
Place of installation +

+PLG-QAB-XDB 27 X03/5B
439

BK
Page

+PLG-QAB-XDB 37 X03/5E
440

BK
LV

X07
A01

+PLG-QAB-XDB 24 X03/6B
441

BK

+PLG-QAB-XDB 34 X03/6E
8 82/1748

442

BK
Pages
38

+PLG-QAB-XDB 26 X03/6B
443

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 83/1748

PAGE
A A

X03/7B

X03/7B

X03/8B

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/6E

X03/7E

X03/7E

X03/8E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

36

57

58

55

56

29

39

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
444 445 446 447 448 449 450 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 91 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LV-XDC X08 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 84/1748

PAGE
A A

G01/2C

G01/3C

G01/4C

G01/5C

G01/6C

G01/6C

G02/2C

G02/3C

G02/6C

G02/6C
DEVICE
PIN

3N
3

1
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK

BK

BK

BK

LB

BK

BK
COLOR

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1
DESIGNATION
DEVICE

E E
DEVICE

10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LV-XDI1 X09 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1 =A02-XDI2 BK
P01/2C

HAVELKA Libor
2

Remark
2 =A02-XDI2 BK
P01/3C

3
3 =A02-XDI2 BK
P01/4C

Released by
4

BRAUN Jiri
4 =A02-XDI2 P01/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5 =A02-XDI2 BK
P01/5C

6
6 =A02-XDI2 P01/5C

Date
BK

20 PCS
7
7 =A02-XDI2 BK
P01/6C

Project number

Document number
8
8 =A02-XDI2 BK
P01/6C
9
9 =A02-XDI2 P01/7C

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
10

10 =A02-XDI2 BK
P01/7C
11

11 =A02-XDI2 BK
-KFA9 A1 P02/2C
BK

Customer
12

12 =A02-XDI2 BK
-KFA9 A2 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13 =A02-XDI2 BK
P02/3C

Customer project number


Customer document number
14

14 =A02-XDI2 BK
-XDX 327 P02/3C
BK
4

15

15 =A02-XDI2 BK
-XDX 326 P02/4C
BK
16

16;210 =A02-XDI2 BK;BK


-XDX 329;3 P02/5C
BK;BK
17

17 =A02-XDI2 BK
-XDX 331 P02/6C
BK
18

18 =A02-XDI2 BK
-KFA10 A2;238 P02/6C
BK;BK
19

19 =A02-XDI2 BK
P02/7C
5

20

20 =A02-XDI2 BK
P02/7C

Project name

Page description
6

Station Transformer 1
TERMINALS =A01+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X10
A01
8 85/1748

Pages
38
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 86/1748

PAGE
A A

S05/7C

S05/7C

S05/7C

S05/8C

S05/8C

S05/2C

S05/2C

S05/2C

S05/2C
S05/7B

S05/3B

S05/4B

S05/4B
DEVICE
PIN

5:1
11

12
2

9
DESIGNATION
DEVICE

B B
+TOP-RAA1
=A04-XDV

=A04-XDV

=A04-XDV

=A04-XDV

=A04-XDV

=A04-XDV
-FCM14.1

-FCM12.1

-FCM12.1

-FCM12.1
-XE
POTENTIAL/
COLOR

GNYE
BK

BK

BK

BK

BK

BK

BK

BK

BK
LB

LB
C C
41 42 43 48 49 50 1 51 2 52 3 53 54
TERMINALS
+LV-XDV

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

-FCM14.1

-FCM11.1

-FCM11.1

-FCM11.1
DESIGNATION
DEVICE

E E
DEVICE

5
PIN

TOTAL TERMINALS COUNT: 13 PCS


TERMINAL TYPE: TERMINAL URTK/S 0311087
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LV-XDV X11 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M03/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M03/4A

202
BK BK

-XDC 5 M03/5A

203
BK

Released by
BRAUN Jiri
M03/6A

204
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M03/7A

205
BK

-XDC 11 M04/1A

Date
206
BK

55 PCS
+LVD-SFS1 5 M04/3A

207
BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M04/4A
208
BK BK

+PLG-QAB-XDB 52 M04/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
16 -XDI2 +LVR-XDH1 1 M04/7A

TERMINAL UT 4 3044102
210

BK BK

2 +LVD-SFS1 M03/2B
211

BK

Customer
M03/3B
212

+LVD-SFC1 13 M03/2D
213

BK

Customer project number


Customer document number
M03/3D
214
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M03/2E


215

BK BK

2 -XDC M03/3E
216

BK

14 -KFA9 +PLG-QAB-XDB 45 M03/5E


217

BK BK

-RAD1 1 M03/6E
218

BK

10 -XDC +LCB-BGC2 20 M03/7D


219

BK BK
5

-KFA11 43 M03/8D
220

BK

21 +LCB-BGC2 +LVR-XDE1 31 M03/7E


221

BK BK

44 -KFA11 -RAD1 5 M03/8E

Project name
222

BK BK

Page description
12 -XDC +PLG-QAB-XDB 43 M04/1C
223

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M04/3C


224

BK BK
6

M04/3C
225

14 -XDC M04/4C
226

BK
Station Transformer 1
TERMINALS =A01+LV-XDX

11 -KFA10 -RAR1 B M04/5C


MAN PHNOM PENH 5304532
227

BK BK

+PLG-QAB-XDB 41 M04/3D
228

BK

+PLG-QAB-XDB 23 M04/4D
229

BK
7

14 +PLG-QAB-XDB -FCM2.1 2 M03/2F


230

BK BK
DCC &

20 +PLG-QAB-XDB M03/4F
231

BK
Installation =

46 +PLG-QAB-XDB -RAD1 2 M03/5F


232

BK BK
Place of installation +

M03/6F
233

Page

32 +LVR-XDE1 -RAD1 6 M03/7F


234

BK BK
LV

X12
A01

44 +PLG-QAB-XDB M04/1F
235

BK

30 +PLG-QAB-XDB M04/3F
8 87/1748

236

BK
Pages
38

A2 -KFA11 -KFA12 A2 M04/6F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
A2 -KFA13 -XDI2 18 M04/7F

238
BK BK

HAVELKA Libor
Remark
4 -FCM4.1 +LVR-XDE1 27 M05/2A

301
BK BK

17 +LVR-XDE1 +PLG-QAB-XDB 11 M05/3A

302
BK BK

Released by
BRAUN Jiri
M05/6A

303
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
7 +LVD-PFV1 +LVD-SFT1 13 M05/8A

304
BK BK

22 +PLG-QAB-XDB +LVD-PFX2 R M05/3D

Date
305
BK BK

55 PCS
21 +PLG-QAB-XDB +LVD-PFX2 G M05/3D

306
BK BK

Project number

Document number
50 +PLG-QAB-XDB +LVD-PFX3 R M05/4D
307
BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M05/4D

ABB s.r.o.
308
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
- +LVD-PFX1 -FCM4.1 2 M05/2F

TERMINAL UT 4 3044102
309

BK BK

+LVD-PFV1 8 M05/6F
310

BK

Customer
-KFA11 23 P02/3D
325

BK

15 -XDI2 +LCB-BGC2 24 P02/4D


326

BK BK

Customer project number


Customer document number
14 -XDI2 -KFA11 24 P02/3E
327

BK BK
4

+LCB-BGC2 25 P02/4E
328

BK

16 -XDI2 -KFA13 14 P02/5D


329

BK BK

6 +LVR-XDH1 -KFA13 11 P02/5E


330

BK BK

A1 -KFA10 -XDI2 17 P02/6E


331

BK BK
5

Project name

Page description
6

Station Transformer 1
TERMINALS =A01+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X13
A01
8 88/1748

Pages
38
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 89/1748

PAGE
A A

M01/7A

M01/7A
X01/3A

X01/4A
X01/3B

S05/8C
S01/3A

S02/3A
DEVICE
PIN

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDV
POTENTIAL/
COLOR

1011

1012
GNYE

GNYE

GNYE

GNYE

GNYE

C GNYE C
1 2 3 4 5 6 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 7 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LV-XE X14 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM05/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM05/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812208
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM05/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM05/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 221 +LVM03/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 234 +LVM03/7E

Project name
BK BK

Page description
6

Station Transformer 1
MAN PHNOM PENH 5304532

TERMINALS =A01+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X15
A01
8 90/1748

Pages
38
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 91/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LVR-XDH X16 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 92/1748

PAGE

+LVM04/7C

+LVM04/7C

+LVM04/7C

+LVM04/7C
+LVM04/7B

+LVM04/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A01+LVR-XDH1 X17 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 93/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 Protection devices - Circuit breaker - Miniature breakers G01/2C
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/13717
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G02/2C B
-FCM11.1 MCB S203-Z1 ABB VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - =K000+PLDV01/54217;=K000+PLDV01/57317;S
Miniature breakers
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 =K000+PLDV01/54317;=K000+PLDV01/57417;S
Protection devices - General - Accessories
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - =K000+PLDV01/54417;=K000+PLDV01/57517;S
Miniature breakers
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 =K000+PLDV01/54517;=K000+PLDV01/57617;S
Protection devices - General - Accessories
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - =K000+PLDV01/54517;=K000+PLDV01/57617;S
Miniature breakers
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 =K000+PLDV01/54517;=K000+PLDV01/57617;S
Protection devices - General - Accessories
-KFA9 AUXILIARY RELAY KC6-40E 110-125VDC ABB BB ES OPEN GJH1213001R0404 Relays, contactors - General - Aux. relays P02/2E
-KFA9 SUPPRESSOR DIODE RD-RD7/250 ABB BB ES OPEN GHV2501910R0001 Relays, contactors - Contactors - Accessories P02/2E
C C
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays P02/6E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories P02/6E
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M04/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M04/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M04/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M04/6E
D -KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays M04/7E D
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories M04/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories M04/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories M04/7E
-PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage =K000+DLDW01;S02/5E
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position =K000+DLDW01;M05/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 =K000+DLDW01;=K000+DLDW01/9C;M05/3
Signal devices - Signal device, acoustic - Position
E indicators E
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 =K000+DLDW01;=K000+DLDW01/9C;M05/4
Signal devices - Signal device, acoustic - Position
indicators
-PGA1 AMMETER FB96-1 150/1A METRA L1 1000028251 Measuring instruments, test devices - General - =K000+DLDW01;S02/5B
Ammeters
-PGA2 AMMETER FB96-1 150/1A METRA L2 1000028251 Measuring instruments, test devices - General - =K000+DLDW01;S02/5C
Ammeters
-PGA3 AMMETER FB96-1 150/1A METRA L3 1000028251 Measuring instruments, test devices - General - =K000+DLDW01;S02/5D
Ammeters

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
PART LIST X18 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 94/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-PGA.1 SCALE FB96-1 150/1A METRA 1000313641 Measuring instruments, test devices - General - S02/6D
Accessories
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - =K000+DLDW01;S05/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES;DIODES 1VL7621116R0101 General - Undefined =K000+PLDV01/54914;=K000+PLDV01/58014;M
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes M03/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined M04/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M03/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories M03/2D
B B
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton=K000+DLDW01;M03/2D
-
Pushbuttons
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories M04/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories M04/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton=K000+DLDW01;M04/3B
-
Pushbuttons
-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton=K000+DLDW01;M03/2B
-
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M05/8D
C C
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton=K000+DLDW01;M05/8D
-
Pushbuttons
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton=K000+DLDW01;S05/4C
-
Voltage switches
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors X01/7D
D -XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors X01/7D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A01
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 1 DCC & Page Pages
ABB s.r.o.
PART LIST X19 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 95/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT4,-BCT5,-BCT6
TPU 54.13
P2 1000/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P1
POS. DESIGN. NAME
2 01BAC01GS003 Alternator G1

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D 0.2, 15 VA D
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

E E
G

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 96/1748

SHEET INDEX
A PAGE PAGE NAME REVISION PAGE PAGE NAME REVISION A
=A02+LV/A01 SINGLE LINE SCHEME AM =A02+LV/X20 PART LIST AM
=A02+LV/A02 SHEET INDEX AM
=A02+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A02+LV/G02 AC SUPPLY CIRCUITS AM
=A02+LV/M01 VD4 INTERNAL WIRING AM
=A02+LV/M02 EARTHING SWITCH AM
=A02+LV/M03 CONTROL CIRCUITS AM
B =A02+LV/M04 TRIPPING CIRCUITS AM B
=A02+LV/M05 SIGNAL CIRCUITS AM
=A02+LV/P01 XDI2 SIGNALS AM
=A02+LV/P02 XDI2 SIGNALS AM
=A02+LV/Q01 MAN CONTROL SYSTEM AM
=A02+LV/Q02 MAN CONTROL SYSTEM AM
=A02+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A02+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A02+LV/S04 VOLTAGE METERING Y/yd AM C
=A02+LV/S05 VOLTAGE METERING AM
=A02+LV/V01 PANEL LAYOUT AM
=A02+LV/W01 LV COMP. DOOR LAYOUT AM
=A02+LV/X01 SPARE TERMINALS AM
=A02+LV/X02 ES SPARE CONTACTS AM
=A02+LV/X03 CB SPARE CONTACTS AM
=A02+LV/X04 MCB SPARE CONTACTS AM
D =A02+LV/X05 TERMINALS =A02+LV-XDA AM D
=A02+LV/X06 TERMINALS =A02+LV-XDC AM
=A02+LV/X07 TERMINALS =A02+LV-XDC AM
=A02+LV/X08 TERMINALS =A02+LV-XDC AM
=A02+LV/X09 TERMINALS =A02+LV-XDI1 AM
=A02+LV/X10 TERMINALS =A02+LV-XDI2 AM
=A02+LV/X11 TERMINALS =A02+LV-XDV AM
=A02+LV/X12 TERMINALS =A02+LV-XDX AM
E =A02+LV/X13 TERMINALS =A02+LV-XDX AM E
=A02+LV/X14 TERMINALS =A02+LV-XE AM
=A02+LV/X15 TERMINALS =A02+LVR-XDE1 AM
=A02+LV/X16 TERMINALS =A02+LVR-XDH AM
=A02+LV/X17 TERMINALS =A02+LVR-XDH1 AM
=A02+LV/X18 PART LIST AM
=A02+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 97/1748

SPRING
=A01 =A03
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1 -XDI1 1

A A
-XDI1 2 -XDI1 2

-XDI1 3 -XDI1 3

-XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5

-XDI1 6 -XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 98/1748

=A01 =A03
LIGHTING
CIRCUIT SPARE
-XDI1 7 -XDI1 7

A A
-XDI1 8 -XDI1 8

-XDI1 9 -XDI1 9

-XDI1 10 -XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8 99/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

M04/1D

M04/3D

M04/3D

M04/4D

M03/3C
M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/7C

Q02/2C

Q02/1C

Q02/6C

P01/2D
X03/6C

X03/6C

X03/3C

X03/4C

X03/2C

X03/4C

X03/3C

X03/5C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

Q02/7D

Q02/2D

Q02/1D

Q02/6D

M04/1E

M04/3E

M04/4E

P01/2E

X03/4D

M05/3C

M05/3C

X03/2D

X03/4D

X03/3D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

M03/3C

X03/5D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

P01/3D
X03/1C

X03/1C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8100/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8101/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/5C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

01BAC01GS003-YB01

01BAC01GS008-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
9 - 10
11 - 12
12 14
-KFA2 M01/8B
P01/4D 11 +PLG -XDB 57
-QAB
12 14
-KFA3 53
-XDC 2 -XDC 4 -XDC 6 -XDC 10
C P01/5D 11 -BGT2 C
54
12 14
-KFA4
P01/6D -XDB 58
11
M01/8D

12 14
13
-KFA5
P01/7D
-KFA9
11
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8102/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
01BAC01GS003-YB32

01BAC01GS003-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:1
13 P02/6E 11 24 24 GY BN GY BN
+LVD P01/2E
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P01/2C
M01/5D XDI2:2
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/3C 13 14 Q02/4C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 P01/2D 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8103/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8104/1748

=A01 CB OPEN/IN TEST/PLUG OUT ALTERNATOR G2 STEP-UP ALTERNATOR G3 ALTERNATOR G4 =A03


INCOMERS INTERLOCKING OFF TRANSFORMER 1 OFF OFF
OFF
-XDI2 1 -XDI2 1

A A
-XDI2 2 -XDI2 2

-XDI2 3 -XDI2 3

-XDI2 4 -XDI2 4

-XDI2 5 -XDI2 5

-XDI2 6 -XDI2 6

-XDI2 7 -XDI2 7

B B
-XDI2 8 -XDI2 8

-XDI2 9 -XDI2 9

-XDI2 10 -XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

M04/8E
XDI2:2

-KFA2 -KFA3 -KFA4 -KFA5


-XDX 321 322 CR-U110DC3L A1 CR-U110DC3L A1 CR-U110DC3L A1 CR-U110DC3L A1

D M01/5B A2 A2 A2 A2 D
+PLG -XDB 8
-QAB
1 28
33
-BGB1 +LCB
-KFA11
2 M04/6E -BGC2
34 29
M01/2F

-XDB 18
14 14 14 14
M01/5D 11 11 11 11
12 12 12 12
24 24 24 24
E -XDX 323 324 21 21 21 21 E
22 22 22 22
34 34 34 34
31 31 31 31
32 32 32 32
14 14 14 14
M04/8B 11 M03/2C 11 M03/2C 11 M03/2C 11 M03/2D
12 12 12 12
XDI2:1

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8105/1748

=A01 CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A03
TRIPPING

-XDI2 11 -XDI2 11

A A
-XDI2 12 -XDI2 12

-XDI2 13 -XDI2 13

-XDI2 14 -XDI2 14

-XDI2 15 -XDI2 15

-XDI2 16 -XDI2 16

-XDI2 17 -XDI2 17

B B
-XDI2 18 -XDI2 18

-XDI2 19 -XDI2 19

-XDI2 20 -XDI2 20

C C

-XDI2 11 12 13 14 15 16 17 18 19 20

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8106/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 01BAC01GS008-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 01BAC01GS008-XB02 01BAC01GW001-XM84 01BAC01CE011-XM85 01BAC01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8107/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE ALTERNATOR CB CB CLOSED CB CLOSED


01BAC01GS003-XB01 01BAC01GS003-XB02 POSITION POSITION REMOTE 01BAC01GS003-XB01 01BAC01GS003-XB01
01BAC01GS003-XB41 01BAC01GS003-XB40 COMMAND MODE
A 01BAC01GS003-XB43 A

B B

M01/3B M01/3B M01/3B M01/3B


C +PLG -XDB 7 +PLG -XDB 28 +PLG -XDB 3 +PLG -XDB 5 C
-QAB -QAB -QAB -QAB
11 9 7 19
-BGB1 -BGB1 13 13 11 -BGB1 -BGB1
12 10 -KFA11 -KFA12 +LVD-SFS1 8 20
M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38 -XDB 13 -XDB 15


M01/3D M01/3D M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379 380 381 382 383

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8108/1748

L1 L2 L3
A = A
+ PROTECTION CT
01BAC01CE001A/B/C

+CT
P2 P2 P2

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 12

2S2
B TPU 54.13 -BCT4 B
1000/1A 2S1
Core 2: 5P20, 10VA
-XDA 11

-XDA 14

2S2
-BCT5
C 2S1 C
-XDA 13
MAN
CONTROL
SYSTEM
(GCP)
-XDA 16

2S2
-BCT6
2S1
D D
-XDA 15

1 -XDA 17

-XE

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8109/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
01BAC01CE003A/B/C

+CT DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 2 -XDA 18

1S2
B TPU 54.13 -BCT4 B
1000/1A 1S1 +LVD
Core 1: 0.5Fs5, 10VA -PGA1
-XDA 1 17 18 -XDA 19
A
FB96-1
1000/1A
0-1000/2000A
-XDA 4 RED LINE AT 891 A -XDA 20

1S2
-BCT5
C 1S1 +LVD C
-XDA 3
-PGA2
17 18 -XDA 21
MAN
A CONTROL
FB96-1 SYSTEM
1000/1A
0-1000/2000A (GCP)
-XDA 6 RED LINE AT 891 A -XDA 22

1S2
-BCT6
1S1 +LVD
D -PGA3 D
-XDA 5 17 18 -XDA 23
A
2 FB96-1
-XDA 7
1000/1A
-XE 0-1000/2000A
RED LINE AT 891 A

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
E Ck E
-WE

+LVD GND L3 GND L2 GND L1 GND


1
-PFV1 2 M03/7B
P1 P1 P1 CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8110/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 1 2 3 4 5

-XE 4
D D

L1 da
S05/3A L2 S05/6A dn
S05/3A L3 S05/6A
S05/3A N
S05/2C

E E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8111/1748

A A

S04/2D L1
S04/3D L2 S04/5D dn
S04/3D L3 S04/5D da

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22

Q01/7C

X04/4C
S04/3D
C N C
-XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 01BAC01CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (GCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
01BAC01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(GCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8112/1748

=A02+LV =A02
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 85
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 15
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 59
+LV +LVR -XE TERMINAL USLKG 5 0441504 8
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13
-KFA2
-KFA3
-KFA4
-KFA5

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-KFA2 PANEL A03 OFF

-KFA3 PANEL A04 OFF

-KFA4 PANEL A05 OFF


-XDI1 -XDI2 -XDV

-KFA5 PANEL A06 OFF


-XDX -XDA -RAD1 DIODES
=A02+LCT
-XDC
D DEVICE TAG TEXT D
-EA1 LV LIGHTING

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8113/1748

=A02+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX2 CB OPEN / CLOSED

B -PFX1 E/S OPEN / CLOSED B

A02 Alternator G1 -PFX3 CB IN TEST / SERVICE

-SFO1 CB OPEN

-SFC1 CB CLOSE

705 mm
-PGA1 -PGA2 -PGA3

-SFT1 LAMP TEST

-SFS1 LOCAL - REMOTE SWITCH

-PGV1
-SFV1 VOLTMETER SELECTOR SWITCH
C -PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8114/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8115/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED
A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8116/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED AND CB CLOSED CB OPEN CB OPEN OR IN CB IN SERVICE CB SPRING CB SPRING
IN SERVICE TEST POSITION POSITION CHARGED DISCHARGED
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439

B B

C M01/6B M01/5B M01/6B M01/6B M01/5B M01/8B M01/1B M01/1B


C
+PLG -XDB 9 +PLG -XDB 6 +PLG -XDB 32 +PLG -XDB 27 +PLG -XDB 29 +PLG -XDB 55 +PLG -XDB 24 +PLG -XDB 26
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 23 -BGB1 31 25 13 33 53 4 2
+LCB +LCB
-BGB1 16 -BGB1 -BGB1 -BGB1 -BGT2 -BGT1 -BGS2 -BGS2
-BGC2 -BGC2 33
23 27 24 32 26 14 34 54 3 1
M01/1F M01/2F
-BGT1
34
-XDB 19 -XDB 42 -XDB 37 -XDB 39 -XDB 56 -XDB 34 -XDB 36
M01/6D -XDB 16 M01/6D M01/6D M01/5D M01/8D M01/1D M01/1D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8117/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT4 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
18 -XDA BK
+CT-BCT4 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT5 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
20 -XDA +CT-BCT5 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT6 1S1 S02/4D
BK

6
22 -XDA +CT-BCT6 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4D
GNYE

Project number

Document number
11
+CT-BCT4 2S1 S01/4B
BK
12
+CT-BCT4 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
13

+CT-BCT5 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT5 2S2 S01/4C


BK

Customer
15

+CT-BCT6 2S1 S01/4D


BK
16

+CT-BCT6 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4D


GNYE
4

18

-XDA 2 S02/6B
BK
19

+LVD-PGA1 18 S02/6B
BK
20

-XDA 4 S02/6C
BK
21

+LVD-PGA2 18 S02/6C
BK
22

-XDA 6 S02/6D
BK
5

23

+LVD-PGA3 18 S02/6D
BK

Project name

Page description
6

Alternator G1
TERMINALS =A02+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A02
8118/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

85 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/1D
371

BK

+PLG-QAB-XDB 7 Q02/2D
Alternator G1
372

BK
TERMINALS =A02+LV-XDC

+PLG-QAB-XDB 38 Q02/2D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/3D
374

BK

-KFA11 14 Q02/3D
375

BK
7

-KFA12 14 Q02/4D
376

BK
DCC &

-KFA11 13 Q02/4D
377

BK
Installation =

+LVD-SFS1 12 Q02/5D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/5D
379

BK
Page

+PLG-QAB-XDB 13 Q02/6D
380

BK
LV

X06
A02

+PLG-QAB-XDB 3 Q02/7D
381

BK

+PLG-QAB-XDB 15 Q02/7D
8119/1748

382

BK
Pages
39

+PLG-QAB-XDB 5 Q02/8D
383

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/3B

391

HAVELKA Libor
Remark
X01/3B

392
X01/4B

393

Released by
BRAUN Jiri
X01/4B

394
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
X01/4B

395
X01/4B

Date
396

85 PCS
+LVR-XDE1 11 X02/2B

401
BK

Project number

Document number
+LVR-XDE1 12 X02/2E
402
BK

+LVR-XDE1 13 X02/3B

ABB s.r.o.
403
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
+LVR-XDE1 14 X02/3E

TERMINAL UT 4 3044102
404

BK

+LVR-XDE1 15 X02/4B
405

BK

Customer
+LVR-XDE1 16 X02/4E
406

BK

+LVR-XDE1 21 X02/5B
407

BK

Customer project number


Customer document number
+LVR-XDE1 22 X02/5E
408

BK
4

+LVR-XDE1 23 X02/6B
409

BK

+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

+LVR-XDE1 26 X02/7E
412

BK

+LCB-BGC2 22 X03/1B
421

BK
5

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E

Project name
424

BK

Page description
+PLG-QAB-XDB 9 X03/2B
425

BK

+PLG-QAB-XDB 19 X03/2E
426

BK
6

+PLG-QAB-XDB 6 X03/3B
427

BK

+PLG-QAB-XDB 16 X03/3E
Alternator G1
428

BK
TERMINALS =A02+LV-XDC

+PLG-QAB-XDB 32 X03/3B
MAN PHNOM PENH 5304532
429

BK

+PLG-QAB-XDB 42 X03/3E
430

BK

+PLG-QAB-XDB 27 X03/4B
431

BK
7

+PLG-QAB-XDB 37 X03/4E
432

BK
DCC &

+PLG-QAB-XDB 29 X03/4B
433

BK
Installation =

+PLG-QAB-XDB 39 X03/4E
434

BK
Place of installation +

+PLG-QAB-XDB 55 X03/5B
435

BK
Page

+PLG-QAB-XDB 56 X03/5E
436

BK
LV

X07
A02

+PLG-QAB-XDB 24 X03/6B
437

BK

+PLG-QAB-XDB 34 X03/6E
8120/1748

438

BK
Pages
39

+PLG-QAB-XDB 26 X03/6B
439

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8121/1748

PAGE
A A

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/6E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

36

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB
DEVICE

B B
-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
440 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 85 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LV-XDC X08 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8122/1748

PAGE
A A

G01/2C

G01/3C

G01/4C

G01/5C

G01/6C

G01/6C

G02/2C

G02/3C

G02/6C

G02/6C
DEVICE
PIN

3N
3

1
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

LB;LB

BK;BK

BK;BK
COLOR

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1

=A01-XDI1
DESIGNATION
DEVICE

E E
DEVICE

1;1

2;2

3;3

4;4

5;5

6;6

7;7

8;8

9;9

10;10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LV-XDI1 X09 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1;1 =A01-XDI2 BK;BK
-XDX 321 P01/2C
BK

HAVELKA Libor
2

Remark
2;2 =A01-XDI2 BK;BK
-XDX 238 P01/2C
BK

3
3;3 =A01-XDI2 BK;BK
-KFA2 A1 P01/4C
BK

Released by
4

BRAUN Jiri
4;4 =A01-XDI2 -KFA2 A2 P01/4C
2

BK;BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5;5 =A01-XDI2 BK;BK
-KFA3 A1 P01/5C
BK

6
6;6 =A01-XDI2 -KFA3 A2 P01/5C

Date
BK;BK BK

20 PCS
7
7;7 =A01-XDI2 BK;BK
-KFA4 A1 P01/6C
BK

Project number

Document number
8
8;8 =A01-XDI2 BK;BK
-KFA4 A2 P01/6C
BK
9
9;9 =A01-XDI2 -KFA5 A1 P01/7C

ABB s.r.o.
BK;BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
10

10;10 =A01-XDI2 BK;BK


-KFA5 A2 P01/7C
BK
11

11;11 =A01-XDI2 BK;BK


-KFA9 A1 P02/2C
BK

Customer
12

12;12 =A01-XDI2 BK;BK


-KFA9 A2 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13;13 =A01-XDI2 BK;BK


-XDX 327 P02/3C
BK

Customer project number


Customer document number
14

14;14 =A01-XDI2 BK;BK


-XDX 326 P02/3C
BK
4

15

15;15 =A01-XDI2 BK;BK


P02/4C
16

16;16 =A01-XDI2 BK;BK


-XDX 329;3 P02/5C
BK;BK
17

17;17 =A01-XDI2 BK;BK


-XDX 331 P02/6C
BK
18

18;18 =A01-XDI2 BK;BK


-KFA10 A2 P02/6C
BK
19

19;19 =A01-XDI2 BK;BK


P02/7C
5

20

20;20 =A01-XDI2 BK;BK


P02/7C

Project name

Page description
6

Alternator G1
TERMINALS =A02+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X10
A02
8123/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8124/1748

PAGE
A A

S04/2D

S04/3D

S04/3D

S04/3D

S04/3D

S05/7C

S05/7C

S05/7C

S05/8C

S05/8C

S05/2C

S05/2C

S05/2C

S05/2C
S05/7B
DEVICE
PIN

4:1

5:1
dn
da
n

4
a

a
DESIGNATION
DEVICE

B B

+TOP-RAA1
+TVT-BAT1

+TVT-BAT2

+TVT-BAT3

+TVT-BAT3

+TVT-BAT1

+TVT-BAT3
-FCM14.1

-FCM12.1

-FCM12.1

-FCM12.1

-XDV
-XE

-XE
POTENTIAL/
COLOR

GNYE

GNYE
BK

BK

BK

BK

BK

BK

BK

BK
LB

LB

LB

LB
C C
1 2 3 4 5 41 42 43 48 49 50 51 52 53 54
TERMINALS
+LV-XDV

D D
POTENTIAL/

BK

BK

BK

LB

BK
COLOR

-FCM11.1

-FCM11.1

-FCM11.1

-XDV

-FCM14.1
DESIGNATION
DEVICE

E E
DEVICE

54

1
PIN

TOTAL TERMINALS COUNT: 15 PCS


TERMINAL TYPE: TERMINAL URTK/S 0311087
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LV-XDV X11 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M03/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M03/4A

202
BK BK

-XDC 5 M03/5A

203
BK

Released by
BRAUN Jiri
M03/6A

204
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M03/7A

205
BK

-XDC 11 M04/1A

Date
206
BK

59 PCS
+LVD-SFS1 5 M04/3A

207
BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M04/4A
208
BK BK

+PLG-QAB-XDB 52 M04/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
+LVR-XDH1 1 M04/7A

TERMINAL UT 4 3044102
210

BK

2 +LVD-SFS1 -KFA2 14 M03/2B


211

BK BK

Customer
+PLG-QAB-XDB 57 M03/3B
212

BK

11 -KFA5 +LVD-SFC1 13 M03/2D


213

BK BK

Customer project number


Customer document number
58 +PLG-QAB-XDB M03/3D
214

BK
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M03/2E


215

BK BK

2 -XDC M03/3E
216

BK

14 -KFA9 +PLG-QAB-XDB 45 M03/5E


217

BK BK

-RAD1 1 M03/6E
218

BK

10 -XDC +LCB-BGC2 20 M03/7D


219

BK BK
5

-KFA11 43 M03/8D
220

BK

21 +LCB-BGC2 +LVR-XDE1 31 M03/7E


221

BK BK

44 -KFA11 -RAD1 5 M03/8E

Project name
222

BK BK

Page description
12 -XDC +PLG-QAB-XDB 43 M04/1C
223

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M04/3C


224

BK BK
6

M04/3C
225

14 -XDC M04/4C
Alternator G1
226

BK
TERMINALS =A02+LV-XDX

11 -KFA10 -RAR1 B M04/5C


MAN PHNOM PENH 5304532
227

BK BK

+PLG-QAB-XDB 41 M04/3D
228

BK

+PLG-QAB-XDB 23 M04/4D
229

BK
7

14 +PLG-QAB-XDB -FCM2.1 2 M03/2F


230

BK BK
DCC &

20 +PLG-QAB-XDB M03/4F
231

BK
Installation =

46 +PLG-QAB-XDB -RAD1 2 M03/5F


232

BK BK
Place of installation +

M03/6F
233

Page

32 +LVR-XDE1 -RAD1 6 M03/7F


234

BK BK
LV

X12
A02

44 +PLG-QAB-XDB M04/1F
235

BK

30 +PLG-QAB-XDB M04/3F
8125/1748

236

BK
Pages
39

A2 -KFA11 -KFA12 A2 M04/6F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
A2 -KFA13 -XDI2 2 M04/7F

238
BK BK

HAVELKA Libor
Remark
4 -FCM4.1 +LVR-XDE1 27 M05/2A

301
BK BK

17 +LVR-XDE1 +PLG-QAB-XDB 11 M05/3A

302
BK BK

Released by
BRAUN Jiri
M05/6A

303
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
7 +LVD-PFV1 +LVD-SFT1 13 M05/8A

304
BK BK

22 +PLG-QAB-XDB +LVD-PFX2 R M05/3D

Date
305
BK BK

59 PCS
21 +PLG-QAB-XDB +LVD-PFX2 G M05/3D

306
BK BK

Project number

Document number
50 +PLG-QAB-XDB +LVD-PFX3 R M05/4D
307
BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M05/4D

ABB s.r.o.
308
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
- +LVD-PFX1 -FCM4.1 2 M05/2F

TERMINAL UT 4 3044102
309

BK BK

+LVD-PFV1 8 M05/6F
310

BK

Customer
1 -XDI2 +PLG-QAB-XDB 8 P01/2D
321

BK BK

28 +LCB-BGC2 -KFA11 33 P01/2D


322

BK BK

Customer project number


Customer document number
18 +PLG-QAB-XDB P01/2E
323

BK
4

34 -KFA11 +LCB-BGC2 29 P01/2E


324

BK BK

-KFA11 23 P02/3D
325

BK

14 -XDI2 +LCB-BGC2 24 P02/4D


326

BK BK

13 -XDI2 -KFA11 24 P02/3E


327

BK BK

+LCB-BGC2 25 P02/4E
328

BK
5

16 -XDI2 -KFA13 14 P02/5D


329

BK BK

6 +LVR-XDH1 -KFA13 11 P02/5E


330

BK BK

A1 -KFA10 -XDI2 17 P02/6E

Project name
331

BK BK

Page description
6

Alternator G1
TERMINALS =A02+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X13
A02
8126/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8127/1748

PAGE
A A

M01/7A

M01/7A
S01/3D

S02/3D

S04/3D
X01/3A

X01/4A
S05/8C
DEVICE
PIN

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDV

-XDV
POTENTIAL/
COLOR

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

C GNYE C
1 2 3 4 5 6 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 8 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LV-XE X14 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM05/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM05/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812209
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM05/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM05/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 221 +LVM03/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 234 +LVM03/7E

Project name
BK BK

Page description
6

Alternator G1
MAN PHNOM PENH 5304532

TERMINALS =A02+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X15
A02
8128/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8129/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LVR-XDH X16 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8130/1748

PAGE

+LVM04/7C

+LVM04/7C

+LVM04/7C

+LVM04/7C
+LVM04/7B

+LVM04/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A02+LVR-XDH1 X17 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8131/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 G01/2C
Protection devices - Circuit breaker - Miniature breakers
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/10617
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G02/2C B
-FCM11.1 MCB S203-Z1 ABB =K000+PLDV01/23217;=K000+PLDV01/26317;=K000+PLDV01/29417;=K000+PLDV01/32517;=K000+PLDV01/35617;=K000+PLDV01/38717;=
VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - Miniature breakers
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB =K000+PLDV01/23317;=K000+PLDV01/26417;=K000+PLDV01/29517;=K000+PLDV01/32617;=K000+PLDV01/35717;=K000+PLDV01/38817;=
VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - Miniature breakers S05/2B
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories S05/2B
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - Miniature breakers S05/7C
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 Protection devices - General - Accessories S05/7C
-KFA2 RELAY CR-U110DC3L ABB PANEL A03 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/4D
-KFA2 HOLDER CR-UH ABB PANEL A03 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/4D
C C
-KFA2 SUPPRESSOR DIODE CR-U 21 ABB PANEL A03 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/4D
-KFA2 SOCKET CR-U3S ABB PANEL A03 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/4D
-KFA3 RELAY CR-U110DC3L ABB PANEL A04 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/5D
-KFA3 HOLDER CR-UH ABB PANEL A04 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/5D
-KFA3 SUPPRESSOR DIODE CR-U 21 ABB PANEL A04 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/5D
-KFA3 SOCKET CR-U3S ABB PANEL A04 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/5D
-KFA4 RELAY CR-U110DC3L ABB PANEL A05 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/6D
-KFA4 HOLDER CR-UH ABB PANEL A05 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/6D
D -KFA4 SUPPRESSOR DIODE CR-U 21 ABB PANEL A05 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/6D D
-KFA4 SOCKET CR-U3S ABB PANEL A05 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/6D
-KFA5 RELAY CR-U110DC3L ABB PANEL A06 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/7D
-KFA5 HOLDER CR-UH ABB PANEL A06 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/7D
-KFA5 SUPPRESSOR DIODE CR-U 21 ABB PANEL A06 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/7D
-KFA5 SOCKET CR-U3S ABB PANEL A06 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/7D
-KFA9 AUXILIARY RELAY KC6-40E 110-125VDC ABB BB ES OPEN GJH1213001R0404 Relays, contactors - General - Aux. relays P02/2E
-KFA9 SUPPRESSOR DIODE RD-RD7/250 ABB BB ES OPEN GHV2501910R0001 Relays, contactors - Contactors - Accessories P02/2E
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays P02/6E
E E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories P02/6E
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M04/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M04/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M04/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M04/6E
-KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays M04/7E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
PART LIST X18 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8132/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories M04/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories M04/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories M04/7E
-PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage S02/5E
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position M05/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 Signal devices - Signal device, acoustic - Position M05/3D
indicators
B B
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 Signal devices - Signal device, acoustic - Position M05/4D
indicators
-PGA1 AMMETER FB96-1 1000/1A METRA L1 E6911085180 Measuring instruments, test devices - General - S02/5B
Ammeters
-PGA2 AMMETER FB96-1 1000/1A METRA L2 E6911085180 Measuring instruments, test devices - General - S02/5C
Ammeters
-PGA3 AMMETER FB96-1 1000/1A METRA L3 E6911085180 Measuring instruments, test devices - General - S02/5D
Ammeters
-PGA.1 SCALE FB96-1 1000/1A METRA 1000353264 Measuring instruments, test devices - General - S02/6D
C Accessories C
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - S05/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES 1VL7621116R0101 General - Undefined M03/6E
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes M03/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined M04/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M03/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories M03/2D
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - M03/2D
D Pushbuttons D
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories M04/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories M04/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - M04/3B
Pushbuttons
-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton - M03/2B
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M05/8D
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton - M05/8D
E Pushbuttons E
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton - S05/4C
Voltage switches
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors X01/7D
-XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
PART LIST X19 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8133/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors X01/7D

B B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A02
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G1 DCC & Page Pages
ABB s.r.o.
PART LIST X20 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8134/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT4,-BCT5,-BCT6
TPU 54.13
P2 1000/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P1
POS. DESIGN. NAME
3 02BAC01GS003 Alternator G2

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D 0.2, 15 VA D
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

E E
G

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8135/1748

SHEET INDEX
A PAGE PAGE NAME REVISION PAGE PAGE NAME REVISION A
=A03+LV/A01 SINGLE LINE SCHEME AM =A03+LV/X20 PART LIST AM
=A03+LV/A02 SHEET INDEX AM
=A03+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A03+LV/G02 AC SUPPLY CIRCUITS AM
=A03+LV/M01 VD4 INTERNAL WIRING AM
=A03+LV/M02 EARTHING SWITCH AM
=A03+LV/M03 CONTROL CIRCUITS AM
B =A03+LV/M04 TRIPPING CIRCUITS AM B
=A03+LV/M05 SIGNAL CIRCUITS AM
=A03+LV/P01 XDI2 SIGNALS AM
=A03+LV/P02 XDI2 SIGNALS AM
=A03+LV/Q01 MAN CONTROL SYSTEM AM
=A03+LV/Q02 MAN CONTROL SYSTEM AM
=A03+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A03+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A03+LV/S04 VOLTAGE METERING Y/yd AM C
=A03+LV/S05 VOLTAGE METERING AM
=A03+LV/V01 PANEL LAYOUT AM
=A03+LV/W01 LV COMP. DOOR LAYOUT AM
=A03+LV/X01 SPARE TERMINALS AM
=A03+LV/X02 ES SPARE CONTACTS AM
=A03+LV/X03 CB SPARE CONTACTS AM
=A03+LV/X04 MCB SPARE CONTACTS AM
D =A03+LV/X05 TERMINALS =A03+LV-XDA AM D
=A03+LV/X06 TERMINALS =A03+LV-XDC AM
=A03+LV/X07 TERMINALS =A03+LV-XDC AM
=A03+LV/X08 TERMINALS =A03+LV-XDC AM
=A03+LV/X09 TERMINALS =A03+LV-XDI1 AM
=A03+LV/X10 TERMINALS =A03+LV-XDI2 AM
=A03+LV/X11 TERMINALS =A03+LV-XDV AM
=A03+LV/X12 TERMINALS =A03+LV-XDX AM
E =A03+LV/X13 TERMINALS =A03+LV-XDX AM E
=A03+LV/X14 TERMINALS =A03+LV-XE AM
=A03+LV/X15 TERMINALS =A03+LVR-XDE1 AM
=A03+LV/X16 TERMINALS =A03+LVR-XDH AM
=A03+LV/X17 TERMINALS =A03+LVR-XDH1 AM
=A03+LV/X18 PART LIST AM
=A03+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8136/1748

SPRING
=A02 =A04
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1 -XDI1 1

A A
-XDI1 2 -XDI1 2

-XDI1 3 -XDI1 3

-XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5

-XDI1 6 -XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8137/1748

=A02 =A04
LIGHTING
CIRCUIT SPARE
-XDI1 7 -XDI1 7

A A
-XDI1 8 -XDI1 8

-XDI1 9 -XDI1 9

-XDI1 10 -XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8138/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

M04/1D

M04/3D

M04/3D

M04/4D

M03/3C
M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/7C

Q02/2C

Q02/1C

Q02/6C

P01/3D
X03/6C

X03/6C

X03/3C

X03/4C

X03/2C

X03/4C

X03/3C

X03/5C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

Q02/7D

Q02/2D

Q02/1D

Q02/6D

M04/1E

M04/3E

M04/4E

P01/3E

X03/4D

M05/3C

M05/3C

X03/2D

X03/4D

X03/3D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

M03/3C

X03/5D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

P01/4D
X03/1C

X03/1C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8139/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8140/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/5C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

01BAC01GS003-YB01

01BAC01GS008-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
9 - 10
11 - 12
12 14
-KFA2 M01/8B
11 +PLG -XDB 57
-QAB
12 14
-KFA3 53
-XDC 2 -XDC 4 -XDC 6 -XDC 10
C P01/5D 11 -BGT2 C
54
12 14
-KFA4
P01/6D -XDB 58
11
M01/8D

12 14
13
-KFA5
P01/7D
-KFA9
11
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8141/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
01BAC01GS003-YB32

01BAC01GS003-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:1
13 P02/6E 11 24 24 GY BN GY BN
+LVD P01/3E
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P01/3C
M01/5D XDI2:2
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/3C 13 14 Q02/4C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 P01/4D 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8142/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8143/1748

=A02 ALTERNATOR G1 CB OPEN/IN TEST/PLUG OUT STEP-UP ALTERNATOR G3 ALTERNATOR G4 =A04


OFF INCOMERS INTERLOCKING TRANSFORMER 1 OFF OFF
OFF
-XDI2 1 -XDI2 1

A A
-XDI2 2 -XDI2 2

-XDI2 3 -XDI2 3

-XDI2 4 -XDI2 4

-XDI2 5 -XDI2 5

-XDI2 6 -XDI2 6

-XDI2 7 -XDI2 7

B B
-XDI2 8 -XDI2 8

-XDI2 9 -XDI2 9

-XDI2 10 -XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

M04/8E
XDI2:2

-KFA1 -KFA3 -KFA4 -KFA5


CR-U110DC3L A1 -XDX 321 322 CR-U110DC3L A1 CR-U110DC3L A1 CR-U110DC3L A1

D A2 M01/5B A2 A2 A2 D
+PLG -XDB 8
-QAB
1 28
33
-BGB1 +LCB
-KFA11
2 M04/6E -BGC2
34 29
M01/2F

-XDB 18
14 14 14 14
11 M01/5D 11 11 11
12 12 12 12
24 24 24 24
E 21
-XDX 323 324 21 21 21 E
22 22 22 22
34 34 34 34
31 31 31 31
32 32 32 32
14 14 14
M04/8B 11 M03/2C 11 M03/2C 11 M03/2D
12 12 12
XDI2:1

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8144/1748

=A02 CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A04
TRIPPING

-XDI2 11 -XDI2 11

A A
-XDI2 12 -XDI2 12

-XDI2 13 -XDI2 13

-XDI2 14 -XDI2 14

-XDI2 15 -XDI2 15

-XDI2 16 -XDI2 16

-XDI2 17 -XDI2 17

B B
-XDI2 18 -XDI2 18

-XDI2 19 -XDI2 19

-XDI2 20 -XDI2 20

C C

-XDI2 11 12 13 14 15 16 17 18 19 20

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8145/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 02BAC01GS008-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 02BAC01GS008-XB02 02BAC01GW001-XM84 02BAC01CE011-XM85 02BAC01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8146/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE ALTERNATOR CB CB CLOSED CB CLOSED


02BAC01GS003-XB01 02BAC01GS003-XB02 POSITION POSITION REMOTE 02BAC01GS003-XB01 02BAC01GS003-XB01
02BAC01GS003-XB41 02BAC01GS003-XB40 COMMAND MODE
A 02BAC01GS003-XB43 A

B B

M01/3B M01/3B M01/3B M01/3B


C +PLG -XDB 7 +PLG -XDB 28 +PLG -XDB 3 +PLG -XDB 5 C
-QAB -QAB -QAB -QAB
11 9 7 19
-BGB1 -BGB1 13 13 11 -BGB1 -BGB1
12 10 -KFA11 -KFA12 +LVD-SFS1 8 20
M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38 -XDB 13 -XDB 15


M01/3D M01/3D M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379 380 381 382 383

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8147/1748

L1 L2 L3
A = A
+ PROTECTION CT
01BAC01CE001A/B/C

+CT
P2 P2 P2

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 12

2S2
B TPU 54.13 -BCT4 B
1000/1A 2S1
Core 2: 5P20, 10VA
-XDA 11

-XDA 14

2S2
-BCT5
C 2S1 C
-XDA 13
MAN
CONTROL
SYSTEM
(GCP)
-XDA 16

2S2
-BCT6
2S1
D D
-XDA 15

1 -XDA 17

-XE

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8148/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
01BAC01CE003A/B/C

+CT DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 2 -XDA 18

1S2
B TPU 54.13 -BCT4 B
1000/1A 1S1 +LVD
Core 1: 0.5Fs5, 10VA -PGA1
-XDA 1 17 18 -XDA 19
A
FB96-1
1000/1A
0-1000/2000A
-XDA 4 RED LINE AT 891 A -XDA 20

1S2
-BCT5
C 1S1 +LVD C
-XDA 3
-PGA2
17 18 -XDA 21
MAN
A CONTROL
FB96-1 SYSTEM
1000/1A
0-1000/2000A (GCP)
-XDA 6 RED LINE AT 891 A -XDA 22

1S2
-BCT6
1S1 +LVD
D -PGA3 D
-XDA 5 17 18 -XDA 23
A
2 FB96-1
-XDA 7
1000/1A
-XE 0-1000/2000A
RED LINE AT 891 A

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
E Ck E
-WE

+LVD GND L3 GND L2 GND L1 GND


1
-PFV1 2 M03/7B
P1 P1 P1 CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8149/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 1 2 3 4 5

-XE 4
D D

L1 da
S05/3A L2 S05/6A dn
S05/3A L3 S05/6A
S05/3A N
S05/2C

E E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8150/1748

A A

S04/2D L1
S04/3D L2 S04/5D dn
S04/3D L3 S04/5D da

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22

Q01/7C

X04/4C
S04/3D
C N C
-XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 01BAC01CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (GCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
01BAC01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(GCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8151/1748

=A02+LV =A02
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 85
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 15
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 59
+LV +LVR -XE TERMINAL USLKG 5 0441504 8
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13
-KFA2
-KFA3
-KFA4
-KFA5

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-KFA2 PANEL A03 OFF

-KFA3 PANEL A04 OFF

-KFA4 PANEL A05 OFF


-XDI1 -XDI2 -XDV

-KFA5 PANEL A06 OFF


-XDX -XDA -RAD1 DIODES
=A02+LCT
-XDC
D DEVICE TAG TEXT D
-EA1 LV LIGHTING

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8152/1748

=A02+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX2 CB OPEN / CLOSED

B -PFX1 E/S OPEN / CLOSED B

A03 Alternator G2 -PFX3 CB IN TEST / SERVICE

-SFO1 CB OPEN

-SFC1 CB CLOSE

705 mm
-PGA1 -PGA2 -PGA3

-SFT1 LAMP TEST

-SFS1 LOCAL - REMOTE SWITCH

-SFV1 VOLTMETER SELECTOR SWITCH


C -PGV1
-PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8153/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8154/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED
A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8155/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED AND CB CLOSED CB OPEN CB OPEN OR IN CB IN SERVICE CB SPRING CB SPRING
IN SERVICE TEST POSITION POSITION CHARGED DISCHARGED
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439

B B

C M01/6B M01/5B M01/6B M01/6B M01/5B M01/8B M01/1B M01/1B


C
+PLG -XDB 9 +PLG -XDB 6 +PLG -XDB 32 +PLG -XDB 27 +PLG -XDB 29 +PLG -XDB 55 +PLG -XDB 24 +PLG -XDB 26
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 23 -BGB1 31 25 13 33 53 4 2
+LCB +LCB
-BGB1 16 -BGB1 -BGB1 -BGB1 -BGT2 -BGT1 -BGS2 -BGS2
-BGC2 -BGC2 33
23 27 24 32 26 14 34 54 3 1
M01/1F M01/2F
-BGT1
34
-XDB 19 -XDB 42 -XDB 37 -XDB 39 -XDB 56 -XDB 34 -XDB 36
M01/6D -XDB 16 M01/6D M01/6D M01/5D M01/8D M01/1D M01/1D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8156/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT4 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
18 -XDA BK
+CT-BCT4 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT5 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
20 -XDA +CT-BCT5 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT6 1S1 S02/4D
BK

6
22 -XDA +CT-BCT6 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4D
GNYE

Project number

Document number
11
+CT-BCT4 2S1 S01/4B
BK
12
+CT-BCT4 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
13

+CT-BCT5 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT5 2S2 S01/4C


BK

Customer
15

+CT-BCT6 2S1 S01/4D


BK
16

+CT-BCT6 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4D


GNYE
4

18

-XDA 2 S02/6B
BK
19

+LVD-PGA1 18 S02/6B
BK
20

-XDA 4 S02/6C
BK
21

+LVD-PGA2 18 S02/6C
BK
22

-XDA 6 S02/6D
BK
5

23

+LVD-PGA3 18 S02/6D
BK

Project name

Page description
6

Alternator G2
TERMINALS =A03+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A03
8157/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

85 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/1D
371

BK

+PLG-QAB-XDB 7 Q02/2D
Alternator G2
372

BK
TERMINALS =A03+LV-XDC

+PLG-QAB-XDB 38 Q02/2D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/3D
374

BK

-KFA11 14 Q02/3D
375

BK
7

-KFA12 14 Q02/4D
376

BK
DCC &

-KFA11 13 Q02/4D
377

BK
Installation =

+LVD-SFS1 12 Q02/5D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/5D
379

BK
Page

+PLG-QAB-XDB 13 Q02/6D
380

BK
LV

X06
A03

+PLG-QAB-XDB 3 Q02/7D
381

BK

+PLG-QAB-XDB 15 Q02/7D
8158/1748

382

BK
Pages
39

+PLG-QAB-XDB 5 Q02/8D
383

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/3B

391

HAVELKA Libor
Remark
X01/3B

392
X01/4B

393

Released by
BRAUN Jiri
X01/4B

394
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
X01/4B

395
X01/4B

Date
396

85 PCS
+LVR-XDE1 11 X02/2B

401
BK

Project number

Document number
+LVR-XDE1 12 X02/2E
402
BK

+LVR-XDE1 13 X02/3B

ABB s.r.o.
403
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
+LVR-XDE1 14 X02/3E

TERMINAL UT 4 3044102
404

BK

+LVR-XDE1 15 X02/4B
405

BK

Customer
+LVR-XDE1 16 X02/4E
406

BK

+LVR-XDE1 21 X02/5B
407

BK

Customer project number


Customer document number
+LVR-XDE1 22 X02/5E
408

BK
4

+LVR-XDE1 23 X02/6B
409

BK

+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

+LVR-XDE1 26 X02/7E
412

BK

+LCB-BGC2 22 X03/1B
421

BK
5

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E

Project name
424

BK

Page description
+PLG-QAB-XDB 9 X03/2B
425

BK

+PLG-QAB-XDB 19 X03/2E
426

BK
6

+PLG-QAB-XDB 6 X03/3B
427

BK

+PLG-QAB-XDB 16 X03/3E
Alternator G2
428

BK
TERMINALS =A03+LV-XDC

+PLG-QAB-XDB 32 X03/3B
MAN PHNOM PENH 5304532
429

BK

+PLG-QAB-XDB 42 X03/3E
430

BK

+PLG-QAB-XDB 27 X03/4B
431

BK
7

+PLG-QAB-XDB 37 X03/4E
432

BK
DCC &

+PLG-QAB-XDB 29 X03/4B
433

BK
Installation =

+PLG-QAB-XDB 39 X03/4E
434

BK
Place of installation +

+PLG-QAB-XDB 55 X03/5B
435

BK
Page

+PLG-QAB-XDB 56 X03/5E
436

BK
LV

X07
A03

+PLG-QAB-XDB 24 X03/6B
437

BK

+PLG-QAB-XDB 34 X03/6E
8159/1748

438

BK
Pages
39

+PLG-QAB-XDB 26 X03/6B
439

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8160/1748

PAGE
A A

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/6E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

36

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB
DEVICE

B B
-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
440 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 85 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LV-XDC X08 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8161/1748

PAGE
A A

G01/2C

G01/3C

G01/4C

G01/5C

G01/6C

G01/6C

G02/2C

G02/3C

G02/6C

G02/6C
DEVICE
PIN

3N
3

1
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

LB;LB

BK;BK

BK;BK
COLOR

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1

=A02-XDI1
DESIGNATION
DEVICE

E E
DEVICE

1;1

2;2

3;3

4;4

5;5

6;6

7;7

8;8

9;9

10;10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LV-XDI1 X09 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1;1 =A02-XDI2 BK;BK
-KFA1 A1 P01/2C
BK

HAVELKA Libor
2

Remark
2;2 =A02-XDI2 BK;BK
-KFA1 A2 P01/2C
BK

3
3;3 =A02-XDI2 BK;BK
-XDX 321 P01/3C
BK

Released by
4

BRAUN Jiri
4;4 =A02-XDI2 -XDX 238 P01/3C
2

BK;BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5;5 =A02-XDI2 BK;BK
-KFA3 A1 P01/5C
BK

6
6;6 =A02-XDI2 -KFA3 A2 P01/5C

Date
BK;BK BK

20 PCS
7
7;7 =A02-XDI2 BK;BK
-KFA4 A1 P01/6C
BK

Project number

Document number
8
8;8 =A02-XDI2 BK;BK
-KFA4 A2 P01/6C
BK
9
9;9 =A02-XDI2 -KFA5 A1 P01/7C

ABB s.r.o.
BK;BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
10

10;10 =A02-XDI2 BK;BK


-KFA5 A2 P01/7C
BK
11

11;11 =A02-XDI2 BK;BK


-KFA9 A1 P02/2C
BK

Customer
12

12;12 =A02-XDI2 BK;BK


-KFA9 A2 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13;13 =A02-XDI2 BK;BK


-XDX 327 P02/3C
BK

Customer project number


Customer document number
14

14;14 =A02-XDI2 BK;BK


-XDX 326 P02/3C
BK
4

15

15;15 =A02-XDI2 BK;BK


P02/4C
16

16;16 =A02-XDI2 BK;BK


-XDX 329;3 P02/5C
BK;BK
17

17;17 =A02-XDI2 BK;BK


-XDX 331 P02/6C
BK
18

18;18 =A02-XDI2 BK;BK


-KFA10 A2 P02/6C
BK
19

19;19 =A02-XDI2 BK;BK


P02/7C
5

20

20;20 =A02-XDI2 BK;BK


P02/7C

Project name

Page description
6

Alternator G2
TERMINALS =A03+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X10
A03
8162/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8163/1748

PAGE
A A

S04/2D

S04/3D

S04/3D

S04/3D

S04/3D

S05/7C

S05/7C

S05/7C

S05/8C

S05/8C

S05/2C

S05/2C

S05/2C

S05/2C
S05/7B
DEVICE
PIN

4:1

5:1
dn
da
n

4
a

a
DESIGNATION
DEVICE

B B

+TOP-RAA1
+TVT-BAT1

+TVT-BAT2

+TVT-BAT3

+TVT-BAT3

+TVT-BAT1

+TVT-BAT3
-FCM14.1

-FCM12.1

-FCM12.1

-FCM12.1

-XDV
-XE

-XE
POTENTIAL/
COLOR

GNYE

GNYE
BK

BK

BK

BK

BK

BK

BK

BK
LB

LB

LB

LB
C C
1 2 3 4 5 41 42 43 48 49 50 51 52 53 54
TERMINALS
+LV-XDV

D D
POTENTIAL/

BK

BK

BK

LB

BK
COLOR

-FCM11.1

-FCM11.1

-FCM11.1

-XDV

-FCM14.1
DESIGNATION
DEVICE

E E
DEVICE

54

1
PIN

TOTAL TERMINALS COUNT: 15 PCS


TERMINAL TYPE: TERMINAL URTK/S 0311087
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LV-XDV X11 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M03/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M03/4A

202
BK BK

-XDC 5 M03/5A

203
BK

Released by
BRAUN Jiri
M03/6A

204
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M03/7A

205
BK

-XDC 11 M04/1A

Date
206
BK

59 PCS
+LVD-SFS1 5 M04/3A

207
BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M04/4A
208
BK BK

+PLG-QAB-XDB 52 M04/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
+LVR-XDH1 1 M04/7A

TERMINAL UT 4 3044102
210

BK

2 +LVD-SFS1 -KFA2 14 M03/2B


211

BK BK

Customer
+PLG-QAB-XDB 57 M03/3B
212

BK

11 -KFA5 +LVD-SFC1 13 M03/2D


213

BK BK

Customer project number


Customer document number
58 +PLG-QAB-XDB M03/3D
214

BK
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M03/2E


215

BK BK

2 -XDC M03/3E
216

BK

14 -KFA9 +PLG-QAB-XDB 45 M03/5E


217

BK BK

-RAD1 1 M03/6E
218

BK

10 -XDC +LCB-BGC2 20 M03/7D


219

BK BK
5

-KFA11 43 M03/8D
220

BK

21 +LCB-BGC2 +LVR-XDE1 31 M03/7E


221

BK BK

44 -KFA11 -RAD1 5 M03/8E

Project name
222

BK BK

Page description
12 -XDC +PLG-QAB-XDB 43 M04/1C
223

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M04/3C


224

BK BK
6

M04/3C
225

14 -XDC M04/4C
Alternator G2
226

BK
TERMINALS =A03+LV-XDX

11 -KFA10 -RAR1 B M04/5C


MAN PHNOM PENH 5304532
227

BK BK

+PLG-QAB-XDB 41 M04/3D
228

BK

+PLG-QAB-XDB 23 M04/4D
229

BK
7

14 +PLG-QAB-XDB -FCM2.1 2 M03/2F


230

BK BK
DCC &

20 +PLG-QAB-XDB M03/4F
231

BK
Installation =

46 +PLG-QAB-XDB -RAD1 2 M03/5F


232

BK BK
Place of installation +

M03/6F
233

Page

32 +LVR-XDE1 -RAD1 6 M03/7F


234

BK BK
LV

X12
A03

44 +PLG-QAB-XDB M04/1F
235

BK

30 +PLG-QAB-XDB M04/3F
8164/1748

236

BK
Pages
39

A2 -KFA11 -KFA12 A2 M04/6F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
A2 -KFA13 -XDI2 4 M04/7F

238
BK BK

HAVELKA Libor
Remark
4 -FCM4.1 +LVR-XDE1 27 M05/2A

301
BK BK

17 +LVR-XDE1 +PLG-QAB-XDB 11 M05/3A

302
BK BK

Released by
BRAUN Jiri
M05/6A

303
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
7 +LVD-PFV1 +LVD-SFT1 13 M05/8A

304
BK BK

22 +PLG-QAB-XDB +LVD-PFX2 R M05/3D

Date
305
BK BK

59 PCS
21 +PLG-QAB-XDB +LVD-PFX2 G M05/3D

306
BK BK

Project number

Document number
50 +PLG-QAB-XDB +LVD-PFX3 R M05/4D
307
BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M05/4D

ABB s.r.o.
308
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
- +LVD-PFX1 -FCM4.1 2 M05/2F

TERMINAL UT 4 3044102
309

BK BK

+LVD-PFV1 8 M05/6F
310

BK

Customer
3 -XDI2 +PLG-QAB-XDB 8 P01/3D
321

BK BK

28 +LCB-BGC2 -KFA11 33 P01/4D


322

BK BK

Customer project number


Customer document number
18 +PLG-QAB-XDB P01/3E
323

BK
4

34 -KFA11 +LCB-BGC2 29 P01/4E


324

BK BK

-KFA11 23 P02/3D
325

BK

14 -XDI2 +LCB-BGC2 24 P02/4D


326

BK BK

13 -XDI2 -KFA11 24 P02/3E


327

BK BK

+LCB-BGC2 25 P02/4E
328

BK
5

16 -XDI2 -KFA13 14 P02/5D


329

BK BK

6 +LVR-XDH1 -KFA13 11 P02/5E


330

BK BK

A1 -KFA10 -XDI2 17 P02/6E

Project name
331

BK BK

Page description
6

Alternator G2
TERMINALS =A03+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X13
A03
8165/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8166/1748

PAGE
A A

M01/7A

M01/7A
S01/3D

S02/3D

S04/3D
X01/3A

X01/4A
S05/8C
DEVICE
PIN

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDV

-XDV
POTENTIAL/
COLOR

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

C GNYE C
1 2 3 4 5 6 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 8 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LV-XE X14 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM05/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM05/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812210
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM05/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM05/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 221 +LVM03/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 234 +LVM03/7E

Project name
BK BK

Page description
6

Alternator G2
MAN PHNOM PENH 5304532

TERMINALS =A03+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X15
A03
8167/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8168/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LVR-XDH X16 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8169/1748

PAGE

+LVM04/7C

+LVM04/7C

+LVM04/7C

+LVM04/7C
+LVM04/7B

+LVM04/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
TERMINALS =A03+LVR-XDH1 X17 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8170/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 =A02G01/2C
Protection devices - Circuit breaker - Miniature breakers
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers =A02G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/10617
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers =A02G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers =A02G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G02/2C B
-FCM11.1 MCB S203-Z1 ABB =A02S05/3B;=K000+PLDV01/23217;=K000+PLDV01/26317;=K000+PLDV01/29417;=K000+PLDV01/32517;=K000+PLDV01/35617;=K000+PLDV0
VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - Miniature breakers
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB =A02S05/3B;=K000+PLDV01/23317;=K000+PLDV01/26417;=K000+PLDV01/29517;=K000+PLDV01/32617;=K000+PLDV01/35717;=K000+PLDV0
VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - Miniature breakers =A02S05/2B
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories =A02S05/2B
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - Miniature breakers =A02S05/7C
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 Protection devices - General - Accessories =A02S05/7C
-KFA2 RELAY CR-U110DC3L ABB PANEL A03 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/4D
-KFA2 HOLDER CR-UH ABB PANEL A03 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/4D
C C
-KFA2 SUPPRESSOR DIODE CR-U 21 ABB PANEL A03 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA2 SOCKET CR-U3S ABB PANEL A03 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA3 RELAY CR-U110DC3L ABB PANEL A04 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/5D
-KFA3 HOLDER CR-UH ABB PANEL A04 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SUPPRESSOR DIODE CR-U 21 ABB PANEL A04 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SOCKET CR-U3S ABB PANEL A04 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA4 RELAY CR-U110DC3L ABB PANEL A05 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/6D
-KFA4 HOLDER CR-UH ABB PANEL A05 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/6D
D -KFA4 SUPPRESSOR DIODE CR-U 21 ABB PANEL A05 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/6D D
-KFA4 SOCKET CR-U3S ABB PANEL A05 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/6D
-KFA5 RELAY CR-U110DC3L ABB PANEL A06 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/7D
-KFA5 HOLDER CR-UH ABB PANEL A06 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SUPPRESSOR DIODE CR-U 21 ABB PANEL A06 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SOCKET CR-U3S ABB PANEL A06 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA9 AUXILIARY RELAY KC6-40E 110-125VDC ABB BB ES OPEN GJH1213001R0404 Relays, contactors - General - Aux. relays =A02P02/2E
-KFA9 SUPPRESSOR DIODE RD-RD7/250 ABB BB ES OPEN GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02P02/2E
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P02/6E
E E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02M04/7E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
PART LIST X18 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8171/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories =A02M04/7E
-PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage =A02S02/5E
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 Signal devices - Signal device, acoustic - Position =A02M05/3D
indicators
B B
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/4D
indicators
-PGA1 AMMETER FB96-1 1000/1A METRA L1 E6911085180 Measuring instruments, test devices - General - =A02S02/5B
Ammeters
-PGA2 AMMETER FB96-1 1000/1A METRA L2 E6911085180 Measuring instruments, test devices - General - =A02S02/5C
Ammeters
-PGA3 AMMETER FB96-1 1000/1A METRA L3 E6911085180 Measuring instruments, test devices - General - =A02S02/5D
Ammeters
-PGA.1 SCALE FB96-1 1000/1A METRA 1000353264 Measuring instruments, test devices - General - =A02S02/6D
C Accessories C
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - =A02S05/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES 1VL7621116R0101 General - Undefined =A02M03/6E
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes =A02M03/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined =A02M04/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2D
D Pushbuttons D
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M04/3B
Pushbuttons
-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2B
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M05/8D
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M05/8D
E Pushbuttons E
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton - =A02S05/4C
Voltage switches
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
PART LIST X19 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8172/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors =A02X01/7D

B B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A03
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812210 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G2 DCC & Page Pages
ABB s.r.o.
PART LIST X20 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8173/1748

A A

-BAT1,-BAT2,-BAT3
TJC5
B 15/√3//0.11/√3//0.11/3 kV B
0.2, 15 VA
3P, 50 VA

BB EARTHING TRUCK
WITHOUT MAKING
CAPACITY

-QBT1 -QAB2
E-U/P 17.32.50 P275 VD4G-50/37 p275
17,5 kV 15kV
3200 A M 4000A
C 50 kA 50kA C

-BCT7,-BCT8,-BCT9
VALID FOR PANELS:
KOKS 17.5A31
P1 4000/1/1/1 A at 40 °C POS. DESIGN. NAME
Core 3: 5P20, 10 VA
4 00BCT01GS203 Step-Up Transformer 1

Core 2: 5P20, 10 VA

Core 1: 0,2Fs5, 10 VA

3 P2
D D

-PFV1
-BAT1,-BAT2,-BAT3
CPI PLUS/R TJC5
IN INSULATOR 15/√3//0.11/√3//0.11/3 kV
0.2, 15 VA
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE2
MWD 16 ST-UG
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8174/1748

SHEET INDEX
A PAGE PAGE NAME REVISION PAGE PAGE NAME REVISION A
=A04+LV/A01 SINGLE LINE SCHEME AM =A04+LV/X15 TERMINALS =A04+LV-XE AM
=A04+LV/A02 SHEET INDEX AM =A04+LV/X16 TERMINALS =A04+LVR-XDE1 AM
=A04+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM =A04+LV/X17 TERMINALS =A04+LVR-XDF AM
=A04+LV/G02 AC SUPPLY CIRCUITS AM =A04+LV/X18 TERMINALS =A04+LVR-XDH AM
=A04+LV/M01 VD4 INTERNAL WIRING AM =A04+LV/X19 TERMINALS =A04+LVR-XDH1 AM
=A04+LV/M02 EARTHING SWITCH AM =A04+LV/X20 PART LIST AM
=A04+LV/M03 BB EARTH. TRUCK - INT. WIRING AM =A04+LV/X21 PART LIST AM
B =A04+LV/M04 CONTROL CIRCUITS AM =A04+LV/X22 PART LIST AM B
=A04+LV/M05 TRIPPING CIRCUITS AM
=A04+LV/M06 SIGNAL CIRCUITS AM
=A04+LV/M07 COOLING FANS AM
=A04+LV/P01 XDI2 SIGNALS AM
=A04+LV/P02 XDI2 SIGNALS AM
=A04+LV/Q01 MAN CONTROL SYSTEM AM
=A04+LV/Q02 MAN CONTROL SYSTEM AM
C =A04+LV/Q03 MAN CONTROL SYSTEM AM C
=A04+LV/S02 CURRENT TRANSFORMER CORE 3 AM
=A04+LV/S03 CURRENT TRANSFORMER CORE 2 AM
=A04+LV/S04 CURRENT TRANSFORMER CORE 1 AM
=A04+LV/S05 VOLTAGE METERING Y/yd AM
=A04+LV/S06 VOLTAGE METERING AM
=A04+LV/S07 VOLTAGE METERING Y/yd AM
=A04+LV/V01 PANEL LAYOUT AM
D =A04+LV/W01 LV COMP. DOOR LAYOUT AM D
=A04+LV/X01 SPARE TERMINALS AM
=A04+LV/X02 ES SPARE CONTACTS AM
=A04+LV/X03 CB SPARE CONTACTS AM
=A04+LV/X04 MCB SPARE CONTACTS AM
=A04+LV/X05 TERMINALS =A04+LV-XDA AM
=A04+LV/X06 TERMINALS =A04+LV-XDC AM
=A04+LV/X07 TERMINALS =A04+LV-XDC AM
E =A04+LV/X08 TERMINALS =A04+LV-XDC AM E
=A04+LV/X09 TERMINALS =A04+LV-XDCS AM
=A04+LV/X10 TERMINALS =A04+LV-XDI1 AM
=A04+LV/X11 TERMINALS =A04+LV-XDI2 AM
=A04+LV/X12 TERMINALS =A04+LV-XDV AM
=A04+LV/X13 TERMINALS =A04+LV-XDX AM
=A04+LV/X14 TERMINALS =A04+LV-XDX AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8175/1748

SPRING
=A03 =A05
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1 -XDI1 1

A A
-XDI1 2 -XDI1 2

-XDI1 3 -XDI1 3

-XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5

-XDI1 6 -XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
-V01 4 2 -V02 4 2
DSEI 2x 101-12A DSEI 2x 101-12A

M01/1B
3 1 +PLG -XDB 25 3 1
-QAB
D D
-BGS1

-MAS
-XDCS 1 2 -XDCS 3 4
M
CON+ SIG+
M04/1A M06/1A
CON- -XDB 35 SIG-
M04/1F M01/1D M06/1F

2 DC 110V 2 DC 110V
E E
1. POWER SUPPLY 2. POWER SUPPLY

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8176/1748

=A03 =A05
LIGHTING
CIRCUIT SPARE
-XDI1 7 -XDI1 7

A A
-XDI1 8 -XDI1 8

-XDI1 9 -XDI1 9

-XDI1 10 -XDI1 10

B B

-XDI1 7 8 -XDI1 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

-XDCS 5 6 -XDCS 7 8

D SPARE D
+LVR-XDH 1 11 2 12

L N
CAUTION: WIRES OF
1/N AC 230V 1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8177/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

M05/1D

M05/3D

M05/3D

M05/4D

M04/3C
M06/3B

M05/6B
G01/4D

M04/5E

M04/2E

M04/5E

M04/4E
Q02/4C

Q02/2C

P01/4D

P02/3D
X03/6C

X03/7C

X03/3C

X03/2C

X03/4C

X03/3C

X03/5C

X03/4C

X03/6C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/7D

G01/4E

M04/5E

M04/4E

M04/2E

X03/3D

Q02/4D

Q02/2D

X03/2D

M05/1E

M05/3E

M05/4E

P01/4E

P02/3E

M06/3C

M06/3C

X03/3D

X03/5D

X03/4D

M06/4C

M06/4C

M05/6C

M05/6C

X03/4D

M04/3C

X03/6D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M04/7D

P01/5D
X03/1C

X03/1C
P02/3E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8178/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M06/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M04/7E
G
-RLE3
C H C

M06/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8179/1748

BUSBAR EARTHING TRUCK


Type
DOC. NO:
EM-U-HD4/P
A A

-XE 11 12

M04/6E

P02/2D
+PLG
-QBT

-XDB 12 1 40 47

B B

-XDB15 1 -XDB7 4

-RLE2 23 23

-BGT2

-BGT1
24 24

-XDB15 2 -XDB7 5 6

C C

-XDB 2 48
M04/6E

P02/2E

-WE

D D

DESIGNAT. FIGURE DESCRIPTION


-RLE2 BLOCKING MAGNET AGAINST TRUCK MOVING
-BGT1 TRUCK IN SERVICE POSITION
-BGT2 TRUCK IN TEST POSITION

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
BB EARTH. TRUCK - INT. WIRING &EFS M03 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8180/1748

CB CLOSING CB CB BLOCKING ES BLOCKING


RELEASE ELECTROMECH. ELECTROMECH. MAGNET COIL
LOCK CLOSING LOCK TRUCK AGAINST BB ES
TRUCK MOVING
LOCAL REMOTE
A A

CON+ CON+
G01/2D -XDX 201 202 203 204 205 M05/1A

SFS1 1
4 3 M04/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M05/3B
+LVD-PFV1
-SFS1 7 8 M05/4B
S04/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/7C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 7 -XDC 9 B
3-4
5-6 -XDX 211 212

00BCT01GS203-YB01

00BCT01GS208-YB15
7-8

INTERLOCKING

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
9 - 10
11 - 12
12 14
-KFA1 M01/8B
P01/2D 11 +PLG -XDB 57
-QAB
12 14
-KFA2 53
-XDC 2 -XDC 4 -XDC 6 -XDC 8 -XDC 10
C P01/3D 11 -BGT2 C
54
12 14
-KFA4
P01/6D -XDB 58 XDI2:14
11
M01/8D P02/3D

12 14
-KFA5
P01/7D 11
-XDX 221 222

P02/4D
-XDX 213 214
D XDI2:15 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M05/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 219 220 223 224

-QAB
43 43
M01/3B M01/2B M03/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB +PLG -XDB 31
4 45 12 -XDE1
-QAB 44 44 -QAB 1 -QBT 3 5
-RAD1 -RAD1 -RAD1
M04/7E M04/6E +ES M04/6E
E -MBC -RLE1 -RLE2 -RLE2 G E

-RLE3
M04/8E
-QCE1
M02/5C
H

-XDB 20 2 4 6
-XDB 14 M01/2D -XDB 46 -XDB 2 +LVR
32
M01/3D M01/2D M03/2D -XDE1

-XDX 232 233 234 235 236


CON- CON-
G01/3E M05/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M04 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8181/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A CON+' M07/7B A

CON+
M04/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M04/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
00BCT01GS203-YB32

00BCT01GS203-YB02
M04/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:5
13 P02/6E 11 24 24 GY BN GY BN
+LVD P01/4E
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 225 226 227 228 229

XDI2:11
P02/2E

-XDX 230 231

P02/2D M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D XDI2:12 D
-QAB -QAB
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P01/5C
M01/5D XDI2:6
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/5C 13 14 Q02/6C
14
23 24 23 24 11 P02/5E
33 34 P01/5D 33 34 12
43 44 M04/8D 43 44 24
21 X01/1C
22

-XDX 237 238 239 240


CON-
M04/8F
CON-' M07/7D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M05 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8182/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6D -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14

-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D KUVAG+
+LVR +LVR S04/6F
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD S04/6F D


-PFX1 -PFX2 -PFX3 KUVAG-
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

- - - - - -

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M06 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8183/1748

EXTERNAL
A SUPPLY A
230V AC 60Hz

CON+'
-XDC 415 416 M05/3A

-XDC 413

B B

COOLING FAN
START COMMAND
1 3N 13 21 1 3N 13 21
-FCM5.3 -FCM5.4 MAN CONTROL SYSTEM
S201-K1,6 NA 2 4N 14 22 S201-K1,6 NA 2 4N 14 22 (CCP)

1L1 3L2 -XDC 414


C -KC1 -KC1 C
M07/7D 2T1 M07/7D 4T2

1L1 2T1 M07/2C


3L2 4T2 M07/4C
A1
5L3 6T3
-KC1 7L4 8T4
BC7-40-00 A2 13 14
+LVR-XDF 11 12 +LVR-XDF 13 14 110-125VDC
21 22

CON-'
D M05/3F D
1051 1052
Q03/4C

Q03/5C
-XG -XG
GND
1 2 3 4
-XH2 -XH3 1 2 3 4
+CB U +CAB U
-MAV1 -MAV2
Q03/3C L CAP N PE Q03/5C L CAP N PE
AIR FLOW SENSOR

AIR FLOW SENSOR


CAP CAP
GREEN/YELLOW

GREEN/YELLOW
BROWN

BROWN

-MAV 1 1 -MAV 1 1
4 4
-BGV2 -BGV3
E M 3 2
M 3 2 E
1~ 1~
AIR BLOWER

AIR BLOWER

2 3 2 3
-PE -PE
WHITE

WHITE
BLUE

BLUE

-XH2 6 5 -XH3 6 5
Q03/3D

Q03/4D

Q03/5D

Q03/5D

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
COOLING FANS &EFS M07 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8184/1748

=A03 ALTERNATOR G1 ALTERNATOR G2 CB OPEN/IN TEST/PLUG OUT ALTERNATOR G3 ALTERNATOR G4 =A05


OFF OFF INCOMERS INTERLOCKING OFF OFF

-XDI2 1 -XDI2 1

A A
-XDI2 2 -XDI2 2

-XDI2 3 -XDI2 3

-XDI2 4 -XDI2 4

-XDI2 5 -XDI2 5

-XDI2 6 -XDI2 6

-XDI2 7 -XDI2 7

B B
-XDI2 8 -XDI2 8

-XDI2 9 -XDI2 9

-XDI2 10 -XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

M05/8E
XDI2:6

-KFA1 -KFA2 -KFA4 -KFA5


CR-U110DC3L A1 CR-U110DC3L A1 -XDX 321 322 CR-U110DC3L A1 CR-U110DC3L A1

D A2 A2 M01/5B A2 A2 D
+PLG -XDB 8
-QAB
1 28
33
-BGB1 +LCB
-KFA11
2 M05/6E -BGC2
34 29
M01/2F

-XDB 18
14 14 14 14
11 11 M01/5D 11 11
12 12 12 12
24 24 24 24
E 21 21
-XDX 323 324 21 21 E
22 22 22 22
34 34 34 34
31 31 31 31
32 32 32 32
14 14 14 14
11 M04/2C 11 M04/2C M05/8B 11 M04/2C 11 M04/2D
12 12 12 12
XDI2:5

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8185/1748

=A03 CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A05
TRIPPING

-XDI2 11 -XDI2 11

A A
-XDI2 12 -XDI2 12

-XDI2 13 -XDI2 13

-XDI2 14 -XDI2 14

-XDI2 15 -XDI2 15

-XDI2 16 -XDI2 16

-XDI2 17 -XDI2 17

B B
-XDI2 18 -XDI2 18

-XDI2 19 -XDI2 19

-XDI2 20 -XDI2 20

C C

-XDI2 11 12 13 14 15 16 17 18 19 20

XDI2:12 XDI2:14 XDI2:15


M05/2D M04/6C M04/6D

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D
M03/3B M01/5B
+PLG -XDB +PLG -XDB

ITH_3
47 29
-QBT -QAB 14
-KFA10 11
23 23 13 33 24 12

-BGA2
-BGT2 -BGT1 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
-BGB1 -BGT2 -KFA13 21
-BGC2 M05/7E
24 24 14 34 25 GY BN 11 A1 22
M01/1F 34
31
ITH_11

ITH_7
-XDB 48 -XDB 39 32
14
M03/3D M01/5D 11 M05/5B
+LVR 12
E -XDX 327 328 9 6 -XDX 330 331 E
-XDH1

XDI2:11
M05/2C

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8186/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 00BCT01GS208-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 00BCT01GS208-XB02 00BCT01GW201-XM84 00BCT01CE061-XM85 00BCT01CE061D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S06/2B S06/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8187/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE STEP-UP


00BCT01GS203-XB01 00BCT01GS203-XB02 POSITION POSITION TRANSFORMER CB
00BCT01GS203-XB41 00BCT01GS203-XB40 REMOTE
A COMMAND MODE A
00BCT01GS203-XB43

B B

M01/3B M01/3B
C +PLG -XDB 7 +PLG -XDB 28 C
-QAB -QAB
11 9
-BGB1 -BGB1 13 13 11

12 10 -KFA11 -KFA12 +LVD-SFS1


M05/6E 14 M05/6E 14 M04/2B 12

-XDB 17 -XDB 38
M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8188/1748

COOLING FAN 1 COOLING FAN 2


RUNNING RUNNING

A A

B B

4
-XH2 -XH3 4
C C

AIR FLOW SENSOR

AIR FLOW SENSOR


+CB +CAB
-MAV1 -MAV2
M07/2D M07/4D
1 1
-BGV2 -BGV3
3 2 3 2

-XH2 6 5 -XH3 6 5

D D

-XDC 380 381 382 383

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q03 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8189/1748

L1 L2 L3 =
+ PROTECTION CT
00BCT01CE051A/B/C
A 2 A
-XDA 27
+CT -XE
DO NOT REMOVE THESE JUMPERS
UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 21

3S1
KOKS 17.5A31, Ip=4000A -BCT7
4000/1A 3S2
Core 3: 5P20, 10VA
B B
-XDA 22

-XDA 23

3S1
-BCT8
3S2

-XDA 24
MAN
C C
CONTROL
SYSTEM
(CCP)
-XDA 25

3S1
-BCT9
3S2

-XDA 26

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 3 &EFS S02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8190/1748

L1 L2 L3 =
+ PROTECTION CT
00BCT01CE052A/B/C
A 3 A
-XDA 17
+CT -XE
DO NOT REMOVE THESE JUMPERS
UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 11

2S1
KOKS 17.5A31, Ip=4000A -BCT7
4000/1A 2S2
Core 2: 5P20, 10VA
B B
-XDA 12

-XDA 13

2S1
-BCT8
2S2

-XDA 14
MAN
C C
CONTROL
SYSTEM
(CCP)
-XDA 15

2S1
-BCT9
2S2

-XDA 16

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S03 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8191/1748

SEALABLE COVER
L1 L2 L3 =
+ CURRENT MEASURING
00BCT01CE053A/B/C
A 4 A
-XDA 7
DO NOT REMOVE THESE JUMPERS
+CT -XE UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM
ARE SECURELY CONNECTED
+LVD
-PGA1
-XDA 1 17 18 -XDA 28
A
1S1 FB96-1
KOKS 17.5A31 -BCT7 4000/1A
4000/1A 1S2 0-4000/8000A
Core 1: 0,2Fs5, 10VA RED LINE AT 3849 A
B B
-XDA 2 -XDA 29

+LVD
-PGA2
-XDA 3 17 18 -XDA 30
A
1S1 FB96-1
-BCT8 4000/1A
KOKS 17.5A31, Ip=4000A 1S2 0-4000/8000A

-XDA 4
RED LINE AT 3849 A
-XDA 31
MAN
C C
CONTROL
+LVD
SYSTEM
-PGA3 (CCP)
-XDA 5 17 18 -XDA 32
A
1S1 FB96-1
-BCT9 4000/1A
KOKS 17.5A31, Ip=4000A 1S2 0-4000/8000A
RED LINE AT 3849 A
-XDA 6 -XDA 33

D D
P2 P2 P2

+CAB
-BAD1
SGB 12N Ck
KAP – 20PF
-BAD2
Ck
21
-BAD3 +LVD
CAPACITY Ck
INSULATOR
-WE
E E
CAPACITY
INSULATOR +LVD GND L3 GND L2 GND L1 GND
1
-PFV1 2 M04/7B
CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
6
7 8

KUVAG+ KUVAG-
M06/8B M06/8D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S04 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8192/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 1 2 3 4 5

-XE 5
D D

L1 da
S06/3A L2 S06/6A dn
S06/3A L3 S06/6A
S06/3A N
S06/2C

E E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S05 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8193/1748

A A

S05/2D L1
S05/3D L2 S05/5D dn
S05/3D L3 S05/5D da

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22

Q01/7C

X04/4C
S05/3D
C N C
-XDV 42 43 48 49 50
-XE 6
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 00BCT01CE061D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (CCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
00BCT01CE061A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(CCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S06 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8194/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 6 7 8 9 10 -XDV 11 12

D -XE 1 D

=A01
=L1-A04
=A01S05/3A
=da-A04
=L2-A04 =A01S05/6A
=A01S05/3A
=dn-A04
=L3-A04 =A01S05/6A
=A01S05/3A

=N-A04
E =A01S05/2C E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S07 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8195/1748

=A04+LV =A04
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 34 A
-XDC TERMINAL UT 4 3044102 91
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDCS TERMINAL UK 6 N 3004524 8
-FCM4.1 SIGNAL CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-RAR1 TCS MODUL -XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-KFA11 CB IN TEST POSITION -XDV TERMINAL URTK/S 0311087 22
+LV +LVR -XDX TERMINAL UT 4 3044102 61
-KFA12 CB IN SERVICE POSITION
-XE TERMINAL USLKG 5 0441504 9

-RAR1
B -FCM11.1 VT - Y WINDING B
-XDE1 TERMINAL UTTB 2,5 3044636 22
-RAD1
-FCM12.1 VT - Y WINDING -XDF TERMINAL UT 4-MT 3046139 4
-KFA10
-KFA13
-KFA1
-KFA2
-KFA4
-KFA5

-KC1

11

12
-V01

FA

FA
-FCM14.1 VT - OPEN DELTA -XDH TERMINAL UTTB 2,5 3044636 4

-K

-K
-XDF
-XDH
-XDH1 TERMINAL UT 4-MT 3046139 9
-KC1 COOLING FAN START COMMAND
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1
-FCM5.3
-FCM5.4

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-V02
-FCM

-FCM

-FCM5.3 COOLING FAN CB

1
DH
-X
-FCM5.4 COOLING FAN CAB.

-FCM5.1 LIGHTING CIRCUIT


C C
-V01 DIODE MODUL

-KFA13 ITH LIMITER IN CAB./CB COMP.

-KFA1 PANEL A02 OFF


-XDI1 -XDI2 -XDCS

-KFA2 PANEL A03 OFF


-XDX -XDA -XDV -KFA4 PANEL A05 OFF

-KFA5 PANEL A06 OFF


-XDC
D -KFA10 ITH LIMITER TRIP D

-V02 DIODE MODUL

-RAD1 DIODES
=A04+LCT
DEVICE TAG TEXT
-EA1 LV LIGHTING

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8196/1748

=A04+LVD
A A
DEVICE TAG TEXT
-PFV1 VOLTAGE INDICATOR

-PFX1 E/S OPEN / CLOSED

-PGA1 L1

-PGA2 L2

-PFX2

B -PGA3 L3 B

A04 Step-Up -PFX3


Transformer 1
-PGV1 VOLTMETER

-PGA1 -PGA2 -PGA3


-SFC1 CB CLOSE

705 mm
-SFO1 CB OPEN

-SFT1 LAMP TEST

-PGV1
-PFX3 -SFS1 LOCAL - REMOTE SWITCH
C C
-PFV1
-SFV1 VOLTMETER SELECTOR SWITCH
-SFO1 -PFX2 -SFC1

-PFX1

-SFV1 -SFS1 -SFT1

D D

1000 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8197/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S04/6E PE1 PE2 PE3 PE4 PE5
-XE 7 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 7 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 391 392 393 394 395 396


+LVR
201 202 203 204 205
-XDA 41 42 43 44 45 46 47
-WE1
GND

C C
22 24
-KFA13
M05/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8198/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED

A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8199/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED CB CLOSED SPARE CB CLOSED AND SPARE CB IN SERVICE CB SPRING CB SPRING
IN SERVICE POSITION CHARGED DISCHARGED
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439 441

B B

C M01/3B M01/3B M01/6B M01/6B M01/5B M01/6B M01/8B M01/1B M01/1B


C
+PLG -XDB 3 +PLG -XDB 5 +PLG -XDB 9 +PLG -XDB 32 +PLG -XDB 6 +PLG -XDB 27 +PLG -XDB 55 +PLG -XDB 24 +PLG -XDB 26
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 7 19 23 31 -BGB1 25 53 4 2
+LCB +LCB
-BGB1 -BGB1 -BGB1 -BGB1 16 -BGB1 -BGT1 -BGS2 -BGS2
-BGC2 -BGC2 33
23 27 8 20 24 32 26 54 3 1
M01/1F M01/2F
-BGT1
34
-XDB 13 -XDB 15 -XDB 19 -XDB 42 -XDB 37 -XDB 56 -XDB 34 -XDB 36
M01/3D M01/3D M01/6D M01/6D -XDB 16 M01/6D M01/8D M01/1D M01/1D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440 442

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8200/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S06/3B 22 S06/2B 22 S06/7C 22 S06/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT7 1S1 S04/4B
BK

HAVELKA Libor
2

Remark
29 -XDA BK
+CT-BCT7 1S2 S04/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT8 1S1 S04/4C
BK

Released by
4

BRAUN Jiri
31 -XDA +CT-BCT8 1S2 S04/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT9 1S1 S04/4C
BK

6
33 -XDA +CT-BCT9 1S2 S04/4D

Date
BK BK

34 PCS
7
-XE 4:1 S04/4A
GNYE

Project number

Document number
11
+CT-BCT7 2S1 S03/4B
BK
12
+CT-BCT7 2S2 S03/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
13

+CT-BCT8 2S1 S03/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT8 2S2 S03/4C


BK

Customer
15

+CT-BCT9 2S1 S03/4C


BK
16

+CT-BCT9 2S2 S03/4D


BK

Customer project number


Customer document number
17

-XE 3:1 S03/4A


GNYE
4

21

+CT-BCT7 3S1 S02/4B


BK
22

+CT-BCT7 3S2 S02/4B


BK
23

+CT-BCT8 3S1 S02/4C


BK
24

+CT-BCT8 3S2 S02/4C


BK
25

+CT-BCT9 3S1 S02/4C


BK
5

26

+CT-BCT9 3S2 S02/4D


BK
27

-XE 2:1 S02/4A


GNYE
28

+LVD-PGA1 18 S04/5B

Project name
BK

Page description
29

-XDA 2 S04/5B
BK
30

+LVD-PGA2 18 S04/5C
BK
6

31

-XDA 4 S04/5C
BK
32

+LVD-PGA3 18 S04/5C
BK
Step-Up Transformer 1
TERMINALS =A04+LV-XDA
33

-XDA 6 S04/5D
MAN PHNOM PENH 5304532

BK
41

X01/3B
42

X01/3B
7

43

X01/3B
DCC &
44

X01/4B
Installation =
45

X01/4B
Place of installation +
46

X01/4B
Page
47

X01/4B
LV

X05
A04
8201/1748

Pages
46
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M04/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M04/3C
BK

3
-XDX 202 M04/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M04/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M04/5B
BK

6
-XDX 217 M04/5C

Date
BK

91 PCS
7
-XDX 204 M04/6B
BK

Project number

Document number
8
-XDI2 14 M04/6C
BK
9
+LVD-PFV1 2 M04/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
10

-XDX 221 M04/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M05/1B


BK

Customer
12

-XDX 225 M05/1C


BK
13

+LVD-SFS1 8 M05/4B
BK

Customer project number


Customer document number
14

-XDX 228 M05/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/2D
371

BK

+PLG-QAB-XDB 7 Q02/3D
372

BK
Step-Up Transformer 1
TERMINALS =A04+LV-XDC

+PLG-QAB-XDB 38 Q02/4D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/4D
374

BK

-KFA11 14 Q02/5D
375

BK
7

-KFA12 14 Q02/6D
376

BK
DCC &

-KFA11 13 Q02/6D
377

BK
Installation =

+LVD-SFS1 12 Q02/7D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/7D
379

BK
Page

+CB-MAV1-XH2 6 Q03/3D
380

BK
LV

X06
A04

+CB-MAV1-XH2 4 Q03/4D
381

BK

+CAB-MAV2-XH3 6 Q03/5D
8202/1748

382

BK
Pages
46

+CAB-MAV2-XH3 4 Q03/6D
383

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/3B

391

HAVELKA Libor
Remark
X01/3B

392
X01/4B

393

Released by
BRAUN Jiri
X01/4B

394
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
X01/4B

395
X01/4B

Date
396

91 PCS
+LVR-XDE1 11 X02/2B

401
BK

Project number

Document number
+LVR-XDE1 12 X02/2E
402
BK

+LVR-XDE1 13 X02/3B

ABB s.r.o.
403
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
+LVR-XDE1 14 X02/3E

TERMINAL UT 4 3044102
404

BK

+LVR-XDE1 15 X02/4B
405

BK

Customer
+LVR-XDE1 16 X02/4E
406

BK

+LVR-XDE1 21 X02/5B
407

BK

Customer project number


Customer document number
+LVR-XDE1 22 X02/5E
408

BK
4

+LVR-XDE1 23 X02/6B
409

BK

+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

+LVR-XDE1 26 X02/7E
412

BK

-XDX 207 M07/7B


413

BK
5

-KC1 A1 M07/7C
414

BK

-FCM5.3 1 M07/2B
415

BK

-FCM5.3 3N M07/2B

Project name
416

LB

Page description
+LCB-BGC2 22 X03/1B
421

BK

+LCB-BGC2 23 X03/1E
422

BK
6

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E
424

BK
Step-Up Transformer 1
TERMINALS =A04+LV-XDC

+PLG-QAB-XDB 3 X03/2B
MAN PHNOM PENH 5304532
425

BK

+PLG-QAB-XDB 13 X03/2E
426

BK

+PLG-QAB-XDB 5 X03/3B
427

BK
7

+PLG-QAB-XDB 15 X03/3E
428

BK
DCC &

+PLG-QAB-XDB 9 X03/3B
429

BK
Installation =

+PLG-QAB-XDB 19 X03/3E
430

BK
Place of installation +

+PLG-QAB-XDB 32 X03/4B
431

BK
Page

+PLG-QAB-XDB 42 X03/4E
432

BK
LV

X07
A04

+PLG-QAB-XDB 6 X03/4B
433

BK

+PLG-QAB-XDB 16 X03/4E
8203/1748

434

BK
Pages
46

+PLG-QAB-XDB 27 X03/5B
435

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8204/1748

PAGE
A A

X03/6B

X03/6B

X03/7B

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/5E

X03/6E

X03/6E

X03/7E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

37

55

56

24

34

26

36

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
436 437 438 439 440 441 442 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 91 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LV-XDC X08 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8205/1748

PAGE
A A

G01/2D

G01/2D

G01/8D

G01/8D

G02/2D

G02/2D

G02/7D

G02/7D
DEVICE
PIN

3N

10
3

9
DESIGNATION
DEVICE

B B

-FCM5.1

-FCM5.1

-XDI1

-XDI1
-V01

-V01

-V02

-V02
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK
LB

C C
1 2 3 4 5 6 7 8
+LV-XDCS
TERMINALS

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 8 PCS


TERMINAL TYPE: TERMINAL UK 6 N 3004524
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LV-XDCS X09 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8206/1748

PAGE
A A

G01/2B

G01/3B

G01/4B

G01/5B

G01/6B

G01/6B

G02/2B

G02/3B

G02/6B

G02/6B
DEVICE
PIN

3;3

1;1

3N
3

8
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1

-XDCS

-XDCS
POTENTIAL/
COLOR

BK;BK

BK;BK

BK

BK

BK

BK

BK

BK

BK
C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

LB;LB

BK;BK

BK;BK
COLOR

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1

=A03-XDI1
DESIGNATION
DEVICE

E E
DEVICE

1;1

2;2

3;3

4;4

5;5

6;6

7;7

8;8

9;9

10;10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LV-XDI1 X10 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1;1 =A03-XDI2 BK;BK
-KFA1 A1 P01/2C
BK

HAVELKA Libor
2

Remark
2;2 =A03-XDI2 BK;BK
-KFA1 A2 P01/2C
BK

3
3;3 =A03-XDI2 BK;BK
-KFA2 A1 P01/3C
BK

Released by
4

BRAUN Jiri
4;4 =A03-XDI2 -KFA2 A2 P01/3C
2

BK;BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5;5 =A03-XDI2 BK;BK
-XDX 321 P01/4C
BK

6
6;6 =A03-XDI2 -XDX 240 P01/5C

Date
BK;BK BK

20 PCS
7
7;7 =A03-XDI2 BK;BK
-KFA4 A1 P01/6C
BK

Project number

Document number
8
8;8 =A03-XDI2 BK;BK
-KFA4 A2 P01/6C
BK
9
9;9 =A03-XDI2 -KFA5 A1 P01/7C

ABB s.r.o.
BK;BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
10

10;10 =A03-XDI2 BK;BK


-KFA5 A2 P01/7C
BK
11

11;11 =A03-XDI2 BK;BK


-XDX 325 P02/2C
BK

Customer
12

12;12 =A03-XDI2 BK;BK


-XDX 237 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13;13 =A03-XDI2 BK;BK


P02/3C

Customer project number


Customer document number
14

14;14 =A03-XDI2 BK;BK


-XDC 8 P02/3C
BK
4

15

15;15 =A03-XDI2 BK;BK


-XDX 219 P02/4C
BK
16

16;16 =A03-XDI2 BK;BK


-XDX 329;3 P02/5C
BK;BK
17

17;17 =A03-XDI2 BK;BK


-XDX 331 P02/6C
BK
18

18;18 =A03-XDI2 BK;BK


-KFA10 A2 P02/6C
BK
19

19;19 =A03-XDI2 BK;BK


P02/7C
5

20

20;20 =A03-XDI2 BK;BK


P02/7C

Project name

Page description
6

Step-Up Transformer 1
TERMINALS =A04+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X11
A04
8207/1748

Pages
46
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDV
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1 -FCM11.1 BK
+TVT-BAT1 a S05/2D
BK

HAVELKA Libor
6

Remark
1 =A01-XDV BK
+TVT-BAT1 a S07/2D
BK

2
3 -FCM11.1 BK
+TVT-BAT2 a S05/3D
BK

Released by
7

BRAUN Jiri
2 =A01-XDV +TVT-BAT2 a S07/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
11
41 =A01-XDV BK
+TVT-BAT1 da S07/5D
BK

3
5 -FCM11.1 +TVT-BAT3 a S05/3D

Date
BK BK

22 PCS
8
3 =A01-XDV BK
+TVT-BAT3 a S07/3D
BK

Project number

Document number
12
49 =A01-XDV BK
+TVT-BAT3 dn S07/5D
BK
4
54 -XDV +TVT-BAT3 n S05/3D

ABB s.r.o.
LB LB

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
9

54 =A01-XDV LB
+TVT-BAT3 n S07/3D
LB

TERMINAL URTK/S 0311087


5

-XE 5:1 S05/3D


GNYE

Customer
10

-XE 1:1 S07/3D


GNYE
41

1 -FCM14.1 BK
+TVT-BAT1 da S06/7B
BK

Customer project number


Customer document number
42

-FCM14.1 2 S06/7C
BK
4

43

S06/7C
48

+TOP-RAA1 2 S06/7C
LB
49

+TVT-BAT3 dn S06/8C
LB
50

-XE 6:1 S06/8C


GNYE
51

-FCM12.1 2 S06/2C
BK
5

52

-FCM12.1 4 S06/2C
BK
53

-FCM12.1 6 S06/2C
BK
54

-XDV 4 S06/2C

Project name
LB

Page description
6

Step-Up Transformer 1
TERMINALS =A04+LV-XDV
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X12
A04
8208/1748

Pages
46
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M04/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M04/4A

202
BK BK

-XDC 5 M04/5A

203
BK

Released by
BRAUN Jiri
-XDC 7 M04/6A

204
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M04/7A

205
BK

-XDC 11 M05/1A

Date
206
BK

61 PCS
413 -XDC +LVD-SFS1 5 M05/3A

207
BK BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M05/4A
208
BK BK

+PLG-QAB-XDB 52 M05/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
+LVR-XDH1 1 M05/7A

TERMINAL UT 4 3044102
210

BK

2 +LVD-SFS1 -KFA1 14 M04/2B


211

BK BK

Customer
+PLG-QAB-XDB 57 M04/3B
212

BK

11 -KFA5 +LVD-SFC1 13 M04/2D


213

BK BK

Customer project number


Customer document number
58 +PLG-QAB-XDB M04/3D
214

BK
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M04/2E


215

BK BK

2 -XDC M04/3E
216

BK

6 -XDC +PLG-QAB-XDB 45 M04/5E


217

BK BK

-RAD1 1 M04/6E
218

BK

15 -XDI2 +PLG-QBT-XDB 12 M04/6E


219

BK BK
5

-RAD1 3 M04/7E
220

BK

10 -XDC +LCB-BGC2 20 M04/7D


221

BK BK

-KFA11 43 M04/8D

Project name
222

BK

Page description
21 +LCB-BGC2 +LVR-XDE1 31 M04/7E
223

BK BK

44 -KFA11 -RAD1 5 M04/8E


224

BK BK
6

12 -XDC +PLG-QAB-XDB 43 M05/1C


225

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M05/3C


226

BK BK
Step-Up Transformer 1
TERMINALS =A04+LV-XDX

M05/3C
MAN PHNOM PENH 5304532
227

14 -XDC M05/4C
228

BK

11 -KFA10 -RAR1 B M05/5C


229

BK BK
7

+PLG-QAB-XDB 41 M05/3D
230

BK
DCC &

+PLG-QAB-XDB 23 M05/4D
231

BK
Installation =

14 +PLG-QAB-XDB -FCM2.1 2 M04/2F


232

BK BK
Place of installation +

20 +PLG-QAB-XDB M04/4F
233

BK
Page

46 +PLG-QAB-XDB -RAD1 2 M04/5F


234

BK BK
LV

X13
A04

2 +PLG-QBT-XDB -RAD1 4 M04/6F


235

BK BK

32 +LVR-XDE1 -RAD1 6 M04/7F


8209/1748

236

BK BK
Pages
46

44 +PLG-QAB-XDB -XDI2 12 M05/1F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
30 +PLG-QAB-XDB -KC1 A2 M05/3F

238
BK BK

HAVELKA Libor
Remark
A2 -KFA11 -KFA12 A2 M05/6F

239
BK BK

A2 -KFA13 -XDI2 6 M05/7F

240
BK BK

Released by
BRAUN Jiri
4 -FCM4.1 +LVR-XDE1 27 M06/2A

301
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
17 +LVR-XDE1 +PLG-QAB-XDB 11 M06/3A

302
BK BK

M06/6A

Date
303

61 PCS
7 +LVD-PFV1 +LVD-SFT1 13 M06/8A

304
BK BK

Project number

Document number
22 +PLG-QAB-XDB +LVD-PFX2 R M06/3D
305
BK BK

21 +PLG-QAB-XDB +LVD-PFX2 G M06/3D

ABB s.r.o.
306
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
50 +PLG-QAB-XDB +LVD-PFX3 R M06/4D

TERMINAL UT 4 3044102
307

BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M06/4D


308

BK BK

Customer
- +LVD-PFX1 -FCM4.1 2 M06/2F
309

BK BK

+LVD-PFV1 8 M06/6F
310

BK

Customer project number


Customer document number
5 -XDI2 +PLG-QAB-XDB 8 P01/4D
321

BK BK
4

28 +LCB-BGC2 -KFA11 33 P01/5D


322

BK BK

18 +PLG-QAB-XDB P01/4E
323

BK

34 -KFA11 +LCB-BGC2 29 P01/5E


324

BK BK

11 -XDI2 +PLG-QBT-XDB 47 P02/2D


325

BK BK

24 +LCB-BGC2 +PLG-QAB-XDB 29 P02/3D


326

BK BK
5

+PLG-QBT-XDB 48 P02/2E
327

BK

25 +LCB-BGC2 +PLG-QAB-XDB 39 P02/3E


328

BK BK

16 -XDI2 -KFA13 14 P02/5D

Project name
329

BK BK

Page description
6 +LVR-XDH1 -KFA13 11 P02/5E
330

BK BK

A1 -KFA10 -XDI2 17 P02/6E


331

BK BK
6

Step-Up Transformer 1
TERMINALS =A04+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X14
A04
8210/1748

Pages
46
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8211/1748

PAGE
A A

M01/7A

M01/7A
S07/3D

S05/3D

X01/4A
S06/8C
S02/3A

S03/3A

S04/3A
DEVICE
PIN

10

27

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDA
-XDV

-XDV

-XDV
POTENTIAL/
COLOR

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE
C C
1 2 3 4 5 6 7 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LV-XE X15 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM06/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM06/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812211
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM06/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM06/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 223 +LVM04/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 236 +LVM04/7E

Project name
BK BK

Page description
6

Step-Up Transformer 1
MAN PHNOM PENH 5304532

TERMINALS =A04+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X16
A04
8212/1748

Pages
46
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8213/1748

PAGE

+LVM07/2D

+LVM07/2D

+LVM07/4D

+LVM07/4D
A A

DEVICE
PIN

2
DESIGNATION

+CAB-MAV2-XH3

+CAB-MAV2-XH3
+CB-MAV1-XH2

+CB-MAV1-XH2
DEVICE

B B
POTENTIAL/
COLOR

BK

BK
LB

LB

C C
11 12 13 14
+LVR-XDF
TERMINALS

D D
POTENTIAL/

BK

LB

BK

LB
COLOR

+LV-KC1

+LV-FCM5.3

+LV-KC1

+LV-FCM5.4
DESIGNATION
DEVICE

E E
DEVICE

2T1

4N

4T2

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LVR-XDF X17 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8214/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LVR-XDH X18 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8215/1748

PAGE

+LVM05/7C

+LVM05/7C

+LVM05/7C

+LVM05/7C
+LVM05/7B

+LVM05/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
TERMINALS =A04+LVR-XDH1 X19 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8216/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 Protection devices - Circuit breaker - Miniature breakers G01/2C
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/16517
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories G02/2C B
-FCM5.3 MCB S201-K1,6 NA ABB COOLING FAN CB 2CDS251103R0257 Protection devices - Circuit breaker - Miniature breakers M07/2B
-FCM5.3 AUXILIARY CONTACT S2C-H11L ABB COOLING FAN CB 2CDS200936R0001 Protection devices - General - Accessories M07/2B
-FCM5.4 MCB S201-K1,6 NA ABB COOLING FAN CAB. 2CDS251103R0257 Protection devices - Circuit breaker - Miniature breakers M07/4B
-FCM5.4 AUXILIARY CONTACT S2C-H11L ABB COOLING FAN CAB. 2CDS200936R0001 Protection devices - General - Accessories M07/4B
-FCM11.1 MCB S203-Z1 ABB VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - Miniature breakers S06/3B
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories S06/3B
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - Miniature breakers S06/2B
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories S06/2B
C C
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - Miniature breakers S06/7C
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 Protection devices - General - Accessories S06/7C
-KC1 MINICONTACTOR BC7-40-00 110-125VDC ABB COOLING FAN START COMMAND GJL1313201R0004 Relays, contactors - Contactors - Contactors M07/7D
-KC1 AUXILIARY CONTACT CAF6-11E ABB COOLING FAN START COMMAND GJL1201330R0002 Relays, contactors - Auxiliary block M07/7D
-KC1 SUPPRESSOR DIODE RD-RD7/250 ABB COOLING FAN START COMMAND GHV2501910R0001 Relays, contactors - Contactors - Accessories M07/7D
-KFA1 RELAY CR-U110DC3L ABB PANEL A02 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/2D
-KFA1 HOLDER CR-UH ABB PANEL A02 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/2D
-KFA1 SUPPRESSOR DIODE CR-U 21 ABB PANEL A02 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/2D
D -KFA1 SOCKET CR-U3S ABB PANEL A02 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/2D D
-KFA2 RELAY CR-U110DC3L ABB PANEL A03 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/3D
-KFA2 HOLDER CR-UH ABB PANEL A03 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/3D
-KFA2 SUPPRESSOR DIODE CR-U 21 ABB PANEL A03 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/3D
-KFA2 SOCKET CR-U3S ABB PANEL A03 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/3D
-KFA4 RELAY CR-U110DC3L ABB PANEL A05 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/6D
-KFA4 HOLDER CR-UH ABB PANEL A05 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/6D
-KFA4 SUPPRESSOR DIODE CR-U 21 ABB PANEL A05 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/6D
-KFA4 SOCKET CR-U3S ABB PANEL A05 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/6D
E E
-KFA5 RELAY CR-U110DC3L ABB PANEL A06 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays P01/7D
-KFA5 HOLDER CR-UH ABB PANEL A06 OFF 1SVR405669R0000 Relays, contactors - General - Accessories P01/7D
-KFA5 SUPPRESSOR DIODE CR-U 21 ABB PANEL A06 OFF 1SVR405661R0000 Relays, contactors - General - Accessories P01/7D
-KFA5 SOCKET CR-U3S ABB PANEL A06 OFF 1SVR405660R0000 Relays, contactors - General - Accessories P01/7D
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays P02/6E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories P02/6E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
PART LIST X20 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8217/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M05/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M05/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays M05/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories M05/6E
-KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays M05/7E
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories M05/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories M05/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories M05/7E
B -PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage S04/5E B
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position M06/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 Signal devices - Signal device, acoustic - Position M06/3D
indicators
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 Signal devices - Signal device, acoustic - Position M06/4D
indicators
-PGA1 AMMETER FB96-1 4000/1A METRA L1 1000047167 Measuring instruments, test devices - General - S04/5B
Ammeters
C C
-PGA2 AMMETER FB96-1 4000/1A METRA L2 1000047167 Measuring instruments, test devices - General - S04/5C
Ammeters
-PGA3 AMMETER FB96-1 4000/1A METRA L3 1000047167 Measuring instruments, test devices - General - S04/5C
Ammeters
-PGA.1 SCALE FB96-1 4000/1A METRA 1000353266 Measuring instruments, test devices - General - S04/5D
Accessories
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - S06/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES 1VL7621116R0101 General - Undefined M04/6E
D D
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes M04/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined M05/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M04/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories M04/2D
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - M04/2D
Pushbuttons
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories M05/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories M05/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - M05/3B
E Pushbuttons
E

-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton - M04/2B
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories M06/8D
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton - M06/8D
Pushbuttons
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton - S06/4C
Voltage switches
-V01 MODULE DIODE DSEI 2x 101-12A IXYS DIODE MODUL 1000099144 Semiconductors - General - Diodes G01/1C
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
PART LIST X21 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8218/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-V01 HOLDER R80 TYPE 132 ABB DIODE MODUL 1VL7637796R0101 Semiconductors - Undefined G01/1C
-V01 COOLER FOR DIODE MODULE R80 TYPE 132 ČKD DIODE MODUL 1000050213 Semiconductors - Undefined G01/1C
-V02 MODULE DIODE DSEI 2x 101-12A IXYS DIODE MODUL 1000099144 Semiconductors - General - Diodes G01/7C
-V02 HOLDER R80 TYPE 132 ABB DIODE MODUL 1VL7637796R0101 Semiconductors - Undefined G01/7C
-V02 COOLER FOR DIODE MODULE R80 TYPE 132 ČKD DIODE MODUL 1000050213 Semiconductors - Undefined G01/7C
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
-XDA.1 TERMINALS COVER AP 3 METER 5022643 PHOENIX E6345711808 Terminals - Cover - Covers X01/7D
B -XDA.1 COVER PROFILE BEAM AP 3-TNS 35 5022672 PHOENIX E6345711809 Terminals - Cover - Covers X01/7D B
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors X01/7D
-XDCS.1 COVER D-UK 4/10 3003020 PHOENIX E6345711140 Terminals - Cover - Covers X01/7D
-XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers X01/7D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions X01/7D
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors X01/7D

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A04
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812211 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Step-Up Transformer 1 DCC & Page Pages
ABB s.r.o.
PART LIST X22 46
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8219/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT4,-BCT5,-BCT6
TPU 54.13
P2 1000/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P1
POS. DESIGN. NAME
5 03BAC01GS003 Alternator G3

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D 0.2, 15 VA D
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

E E
G

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8220/1748

SHEET INDEX
A PAGE PAGE NAME REVISION PAGE PAGE NAME REVISION A
=A05+LV/A01 SINGLE LINE SCHEME AM =A05+LV/X20 PART LIST AM
=A05+LV/A02 SHEET INDEX AM
=A05+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A05+LV/G02 AC SUPPLY CIRCUITS AM
=A05+LV/M01 VD4 INTERNAL WIRING AM
=A05+LV/M02 EARTHING SWITCH AM
=A05+LV/M03 CONTROL CIRCUITS AM
B =A05+LV/M04 TRIPPING CIRCUITS AM B
=A05+LV/M05 SIGNAL CIRCUITS AM
=A05+LV/P01 XDI2 SIGNALS AM
=A05+LV/P02 XDI2 SIGNALS AM
=A05+LV/Q01 MAN CONTROL SYSTEM AM
=A05+LV/Q02 MAN CONTROL SYSTEM AM
=A05+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A05+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A05+LV/S04 VOLTAGE METERING Y/yd AM C
=A05+LV/S05 VOLTAGE METERING AM
=A05+LV/V01 PANEL LAYOUT AM
=A05+LV/W01 LV COMP. DOOR LAYOUT AM
=A05+LV/X01 SPARE TERMINALS AM
=A05+LV/X02 ES SPARE CONTACTS AM
=A05+LV/X03 CB SPARE CONTACTS AM
=A05+LV/X04 MCB SPARE CONTACTS AM
D =A05+LV/X05 TERMINALS =A05+LV-XDA AM D
=A05+LV/X06 TERMINALS =A05+LV-XDC AM
=A05+LV/X07 TERMINALS =A05+LV-XDC AM
=A05+LV/X08 TERMINALS =A05+LV-XDC AM
=A05+LV/X09 TERMINALS =A05+LV-XDI1 AM
=A05+LV/X10 TERMINALS =A05+LV-XDI2 AM
=A05+LV/X11 TERMINALS =A05+LV-XDV AM
=A05+LV/X12 TERMINALS =A05+LV-XDX AM
E =A05+LV/X13 TERMINALS =A05+LV-XDX AM E
=A05+LV/X14 TERMINALS =A05+LV-XE AM
=A05+LV/X15 TERMINALS =A05+LVR-XDE1 AM
=A05+LV/X16 TERMINALS =A05+LVR-XDH AM
=A05+LV/X17 TERMINALS =A05+LVR-XDH1 AM
=A05+LV/X18 PART LIST AM
=A05+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8221/1748

SPRING
=A04 =A06
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1 -XDI1 1

A A
-XDI1 2 -XDI1 2

-XDI1 3 -XDI1 3

-XDI1 4 -XDI1 4

-XDI1 5 -XDI1 5

-XDI1 6 -XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8222/1748

=A04 =A06
LIGHTING
CIRCUIT SPARE
-XDI1 7 -XDI1 7

A A
-XDI1 8 -XDI1 8

-XDI1 9 -XDI1 9

-XDI1 10 -XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8223/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

M04/1D

M04/3D

M04/3D

M04/4D

M03/3C
M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/7C

Q02/2C

Q02/1C

Q02/6C

P01/5D
X03/6C

X03/6C

X03/3C

X03/4C

X03/2C

X03/4C

X03/3C

X03/5C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

Q02/7D

Q02/2D

Q02/1D

Q02/6D

M04/1E

M04/3E

M04/4E

P01/5E

X03/4D

M05/3C

M05/3C

X03/2D

X03/4D

X03/3D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

M03/3C

X03/5D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

P01/6D
X03/1C

X03/1C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8224/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8225/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/5C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

01BAC01GS003-YB01

01BAC01GS008-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
9 - 10
11 - 12
12 14
-KFA2 M01/8B
P01/3D 11 +PLG -XDB 57
-QAB
12 14
-KFA3 53
-XDC 2 -XDC 4 -XDC 6 -XDC 10
C P01/4D 11 -BGT2 C
54
12 14
-KFA4
-XDB 58
11
M01/8D

12 14
13
-KFA5
P01/7D
-KFA9
11
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8226/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
01BAC01GS003-YB32

01BAC01GS003-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:1
13 P02/6E 11 24 24 GY BN GY BN
+LVD P01/5E
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P01/5C
M01/5D XDI2:2
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/3C 13 14 Q02/4C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 P01/6D 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8227/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8228/1748

=A04 STEP-UP ALTERNATOR G4 =A06


ALTERNATOR G1 ALTERNATOR G2 CB OPEN/IN TEST/PLUG OUT
TRANSFORMER 1 OFF
OFF OFF INCOMERS INTERLOCKING
OFF
-XDI2 1 -XDI2 1

A A
-XDI2 2 -XDI2 2

-XDI2 3 -XDI2 3

-XDI2 4 -XDI2 4

-XDI2 5 -XDI2 5

-XDI2 6 -XDI2 6

-XDI2 7 -XDI2 7

B B
-XDI2 8 -XDI2 8

-XDI2 9 -XDI2 9

-XDI2 10 -XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

M04/8E
-KFA1 -KFA2 -KFA3 XDI2:2
CR-U110DC3L A1 A1 A1
CR-U110DC3L CR-U110DC3L
-KFA5
A2 A2 A2 -XDX 321 322 CR-U110DC3L A1

D M01/5B A2 D
+PLG -XDB 8
-QAB
1 28
33
-BGB1 +LCB
-KFA11
2 M04/6E -BGC2
34 29
14 M01/2F
14 14
11 11 11
12 12 12 -XDB 18
24 14
24 24 M01/5D 11
21 21 21
22 12
22 22
34 24
34 34
E 31 31 31 -XDX 323 324 21 E
32 22
32 32
34
14 14 31
11 M03/2C 11 M03/2C 32
12 12
14
M04/8B 11 M03/2D
12
XDI2:1

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8229/1748

=A04 CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A06
TRIPPING

-XDI2 11 -XDI2 11

A A
-XDI2 12 -XDI2 12

-XDI2 13 -XDI2 13

-XDI2 14 -XDI2 14

-XDI2 15 -XDI2 15

-XDI2 16 -XDI2 16

-XDI2 17 -XDI2 17

B B
-XDI2 18 -XDI2 18

-XDI2 19 -XDI2 19

-XDI2 20 -XDI2 20

C C

-XDI2 11 12 13 14 15 16 17 18 19 20

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8230/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 01BAC01GS008-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 01BAC01GS008-XB02 01BAC01GW001-XM84 01BAC01CE011-XM85 01BAC01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8231/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE ALTERNATOR CB CB CLOSED CB CLOSED


01BAC01GS003-XB01 01BAC01GS003-XB02 POSITION POSITION REMOTE 01BAC01GS003-XB01 01BAC01GS003-XB01
01BAC01GS003-XB41 01BAC01GS003-XB40 COMMAND MODE
A 01BAC01GS003-XB43 A

B B

M01/3B M01/3B M01/3B M01/3B


C +PLG -XDB 7 +PLG -XDB 28 +PLG -XDB 3 +PLG -XDB 5 C
-QAB -QAB -QAB -QAB
11 9 7 19
-BGB1 -BGB1 13 13 11 -BGB1 -BGB1
12 10 -KFA11 -KFA12 +LVD-SFS1 8 20
M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38 -XDB 13 -XDB 15


M01/3D M01/3D M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379 380 381 382 383

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8232/1748

L1 L2 L3
A = A
+ PROTECTION CT
01BAC01CE001A/B/C

+CT
P2 P2 P2

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 12

2S2
B TPU 54.13 -BCT4 B
1000/1A 2S1
Core 2: 5P20, 10VA
-XDA 11

-XDA 14

2S2
-BCT5
C 2S1 C
-XDA 13
MAN
CONTROL
SYSTEM
(GCP)
-XDA 16

2S2
-BCT6
2S1
D D
-XDA 15

1 -XDA 17

-XE

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8233/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
01BAC01CE003A/B/C

+CT DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 2 -XDA 18

1S2
B TPU 54.13 -BCT4 B
1000/1A 1S1 +LVD
Core 1: 0.5Fs5, 10VA -PGA1
-XDA 1 17 18 -XDA 19
A
FB96-1
1000/1A
0-1000/2000A
-XDA 4 RED LINE AT 891 A -XDA 20

1S2
-BCT5
C 1S1 +LVD C
-XDA 3
-PGA2
17 18 -XDA 21
MAN
A CONTROL
FB96-1 SYSTEM
1000/1A
0-1000/2000A (GCP)
-XDA 6 RED LINE AT 891 A -XDA 22

1S2
-BCT6
1S1 +LVD
D -PGA3 D
-XDA 5 17 18 -XDA 23
A
2 FB96-1
-XDA 7
1000/1A
-XE 0-1000/2000A
RED LINE AT 891 A

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
E Ck E
-WE

+LVD GND L3 GND L2 GND L1 GND


1
-PFV1 2 M03/7B
P1 P1 P1 CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8234/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 1 2 3 4 5

-XE 4
D D

L1 da
S05/3A L2 S05/6A dn
S05/3A L3 S05/6A
S05/3A N
S05/2C

E E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8235/1748

A A

S04/2D L1
S04/3D L2 S04/5D dn
S04/3D L3 S04/5D da

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22

Q01/7C

X04/4C
S04/3D
C N C
-XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 01BAC01CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (GCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
01BAC01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(GCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8236/1748

=A02+LV =A02
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 85
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 15
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 59
+LV +LVR -XE TERMINAL USLKG 5 0441504 8
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13
-KFA2
-KFA3
-KFA4
-KFA5

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-KFA2 PANEL A03 OFF

-KFA3 PANEL A04 OFF

-KFA4 PANEL A05 OFF


-XDI1 -XDI2 -XDV

-KFA5 PANEL A06 OFF


-XDX -XDA -RAD1 DIODES
=A02+LCT
-XDC
D DEVICE TAG TEXT D
-EA1 LV LIGHTING

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8237/1748

=A02+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX2 CB OPEN / CLOSED

B -PFX1 E/S OPEN / CLOSED B

A05 Alternator G3 -PFX3 CB IN TEST / SERVICE

-SFO1 CB OPEN

-SFC1 CB CLOSE

705 mm
-PGA1 -PGA2 -PGA3

-SFT1 LAMP TEST

-SFS1 LOCAL - REMOTE SWITCH

-SFV1 VOLTMETER SELECTOR SWITCH


C -PGV1
-PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8238/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8239/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED
A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8240/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED AND CB CLOSED CB OPEN CB OPEN OR IN CB IN SERVICE CB SPRING CB SPRING
IN SERVICE TEST POSITION POSITION CHARGED DISCHARGED
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439

B B

C M01/6B M01/5B M01/6B M01/6B M01/5B M01/8B M01/1B M01/1B


C
+PLG -XDB 9 +PLG -XDB 6 +PLG -XDB 32 +PLG -XDB 27 +PLG -XDB 29 +PLG -XDB 55 +PLG -XDB 24 +PLG -XDB 26
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 23 -BGB1 31 25 13 33 53 4 2
+LCB +LCB
-BGB1 16 -BGB1 -BGB1 -BGB1 -BGT2 -BGT1 -BGS2 -BGS2
-BGC2 -BGC2 33
23 27 24 32 26 14 34 54 3 1
M01/1F M01/2F
-BGT1
34
-XDB 19 -XDB 42 -XDB 37 -XDB 39 -XDB 56 -XDB 34 -XDB 36
M01/6D -XDB 16 M01/6D M01/6D M01/5D M01/8D M01/1D M01/1D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8241/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT4 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
18 -XDA BK
+CT-BCT4 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT5 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
20 -XDA +CT-BCT5 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT6 1S1 S02/4D
BK

6
22 -XDA +CT-BCT6 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4D
GNYE

Project number

Document number
11
+CT-BCT4 2S1 S01/4B
BK
12
+CT-BCT4 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
13

+CT-BCT5 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT5 2S2 S01/4C


BK

Customer
15

+CT-BCT6 2S1 S01/4D


BK
16

+CT-BCT6 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4D


GNYE
4

18

-XDA 2 S02/6B
BK
19

+LVD-PGA1 18 S02/6B
BK
20

-XDA 4 S02/6C
BK
21

+LVD-PGA2 18 S02/6C
BK
22

-XDA 6 S02/6D
BK
5

23

+LVD-PGA3 18 S02/6D
BK

Project name

Page description
6

Alternator G3
TERMINALS =A05+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A05
8242/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

85 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/1D
371

BK

+PLG-QAB-XDB 7 Q02/2D
Alternator G3
372

BK
TERMINALS =A05+LV-XDC

+PLG-QAB-XDB 38 Q02/2D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/3D
374

BK

-KFA11 14 Q02/3D
375

BK
7

-KFA12 14 Q02/4D
376

BK
DCC &

-KFA11 13 Q02/4D
377

BK
Installation =

+LVD-SFS1 12 Q02/5D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/5D
379

BK
Page

+PLG-QAB-XDB 13 Q02/6D
380

BK
LV

X06
A05

+PLG-QAB-XDB 3 Q02/7D
381

BK

+PLG-QAB-XDB 15 Q02/7D
8243/1748

382

BK
Pages
39

+PLG-QAB-XDB 5 Q02/8D
383

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/3B

391

HAVELKA Libor
Remark
X01/3B

392
X01/4B

393

Released by
BRAUN Jiri
X01/4B

394
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
X01/4B

395
X01/4B

Date
396

85 PCS
+LVR-XDE1 11 X02/2B

401
BK

Project number

Document number
+LVR-XDE1 12 X02/2E
402
BK

+LVR-XDE1 13 X02/3B

ABB s.r.o.
403
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
+LVR-XDE1 14 X02/3E

TERMINAL UT 4 3044102
404

BK

+LVR-XDE1 15 X02/4B
405

BK

Customer
+LVR-XDE1 16 X02/4E
406

BK

+LVR-XDE1 21 X02/5B
407

BK

Customer project number


Customer document number
+LVR-XDE1 22 X02/5E
408

BK
4

+LVR-XDE1 23 X02/6B
409

BK

+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

+LVR-XDE1 26 X02/7E
412

BK

+LCB-BGC2 22 X03/1B
421

BK
5

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E

Project name
424

BK

Page description
+PLG-QAB-XDB 9 X03/2B
425

BK

+PLG-QAB-XDB 19 X03/2E
426

BK
6

+PLG-QAB-XDB 6 X03/3B
427

BK

+PLG-QAB-XDB 16 X03/3E
Alternator G3
428

BK
TERMINALS =A05+LV-XDC

+PLG-QAB-XDB 32 X03/3B
MAN PHNOM PENH 5304532
429

BK

+PLG-QAB-XDB 42 X03/3E
430

BK

+PLG-QAB-XDB 27 X03/4B
431

BK
7

+PLG-QAB-XDB 37 X03/4E
432

BK
DCC &

+PLG-QAB-XDB 29 X03/4B
433

BK
Installation =

+PLG-QAB-XDB 39 X03/4E
434

BK
Place of installation +

+PLG-QAB-XDB 55 X03/5B
435

BK
Page

+PLG-QAB-XDB 56 X03/5E
436

BK
LV

X07
A05

+PLG-QAB-XDB 24 X03/6B
437

BK

+PLG-QAB-XDB 34 X03/6E
8244/1748

438

BK
Pages
39

+PLG-QAB-XDB 26 X03/6B
439

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8245/1748

PAGE
A A

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/6E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

36

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB
DEVICE

B B
-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
440 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 85 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LV-XDC X08 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8246/1748

PAGE
A A

G01/2C

G01/3C

G01/4C

G01/5C

G01/6C

G01/6C

G02/2C

G02/3C

G02/6C

G02/6C
DEVICE
PIN

3N
3

1
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

BK;BK

LB;LB

BK;BK

BK;BK
COLOR

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1

=A04-XDI1
DESIGNATION
DEVICE

E E
DEVICE

1;1

2;2

3;3

4;4

5;5

6;6

7;7

8;8

9;9

10;10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LV-XDI1 X09 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1;1 =A04-XDI2 BK;BK
-KFA1 A1 P01/2C
BK

HAVELKA Libor
2

Remark
2;2 =A04-XDI2 BK;BK
-KFA1 A2 P01/2C
BK

3
3;3 =A04-XDI2 BK;BK
-KFA2 A1 P01/3C
BK

Released by
4

BRAUN Jiri
4;4 =A04-XDI2 -KFA2 A2 P01/3C
2

BK;BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5;5 =A04-XDI2 BK;BK
-KFA3 A1 P01/4C
BK

6
6;6 =A04-XDI2 -KFA3 A2 P01/4C

Date
BK;BK BK

20 PCS
7
7;7 =A04-XDI2 BK;BK
-XDX 321 P01/5C
BK

Project number

Document number
8
8;8 =A04-XDI2 BK;BK
-XDX 238 P01/5C
BK
9
9;9 =A04-XDI2 -KFA5 A1 P01/7C

ABB s.r.o.
BK;BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
10

10;10 =A04-XDI2 BK;BK


-KFA5 A2 P01/7C
BK
11

11;11 =A04-XDI2 BK;BK


-KFA9 A1 P02/2C
BK

Customer
12

12;12 =A04-XDI2 BK;BK


-KFA9 A2 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13;13 =A04-XDI2 BK;BK


-XDX 327 P02/3C
BK

Customer project number


Customer document number
14

14;14 =A04-XDI2 BK;BK


-XDX 326 P02/3C
BK
4

15

15;15 =A04-XDI2 BK;BK


P02/4C
16

16;16 =A04-XDI2 BK;BK


-XDX 329;3 P02/5C
BK;BK
17

17;17 =A04-XDI2 BK;BK


-XDX 331 P02/6C
BK
18

18;18 =A04-XDI2 BK;BK


-KFA10 A2 P02/6C
BK
19

19;19 =A04-XDI2 BK;BK


P02/7C
5

20

20;20 =A04-XDI2 BK;BK


P02/7C

Project name

Page description
6

Alternator G3
TERMINALS =A05+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X10
A05
8247/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8248/1748

PAGE
A A

S04/2D

S04/3D

S04/3D

S04/3D

S04/3D

S05/7C

S05/7C

S05/7C

S05/8C

S05/8C

S05/2C

S05/2C

S05/2C

S05/2C
S05/7B
DEVICE
PIN

4:1

5:1
dn
da
n

4
a

a
DESIGNATION
DEVICE

B B

+TOP-RAA1
+TVT-BAT1

+TVT-BAT2

+TVT-BAT3

+TVT-BAT3

+TVT-BAT1

+TVT-BAT3
-FCM14.1

-FCM12.1

-FCM12.1

-FCM12.1

-XDV
-XE

-XE
POTENTIAL/
COLOR

GNYE

GNYE
BK

BK

BK

BK

BK

BK

BK

BK
LB

LB

LB

LB
C C
1 2 3 4 5 41 42 43 48 49 50 51 52 53 54
TERMINALS
+LV-XDV

D D
POTENTIAL/

BK

BK

BK

LB

BK
COLOR

-FCM11.1

-FCM11.1

-FCM11.1

-XDV

-FCM14.1
DESIGNATION
DEVICE

E E
DEVICE

54

1
PIN

TOTAL TERMINALS COUNT: 15 PCS


TERMINAL TYPE: TERMINAL URTK/S 0311087
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LV-XDV X11 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M03/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M03/4A

202
BK BK

-XDC 5 M03/5A

203
BK

Released by
BRAUN Jiri
M03/6A

204
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M03/7A

205
BK

-XDC 11 M04/1A

Date
206
BK

59 PCS
+LVD-SFS1 5 M04/3A

207
BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M04/4A
208
BK BK

+PLG-QAB-XDB 52 M04/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
+LVR-XDH1 1 M04/7A

TERMINAL UT 4 3044102
210

BK

2 +LVD-SFS1 -KFA2 14 M03/2B


211

BK BK

Customer
+PLG-QAB-XDB 57 M03/3B
212

BK

11 -KFA5 +LVD-SFC1 13 M03/2D


213

BK BK

Customer project number


Customer document number
58 +PLG-QAB-XDB M03/3D
214

BK
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M03/2E


215

BK BK

2 -XDC M03/3E
216

BK

14 -KFA9 +PLG-QAB-XDB 45 M03/5E


217

BK BK

-RAD1 1 M03/6E
218

BK

10 -XDC +LCB-BGC2 20 M03/7D


219

BK BK
5

-KFA11 43 M03/8D
220

BK

21 +LCB-BGC2 +LVR-XDE1 31 M03/7E


221

BK BK

44 -KFA11 -RAD1 5 M03/8E

Project name
222

BK BK

Page description
12 -XDC +PLG-QAB-XDB 43 M04/1C
223

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M04/3C


224

BK BK
6

M04/3C
225

14 -XDC M04/4C
Alternator G3
226

BK
TERMINALS =A05+LV-XDX

11 -KFA10 -RAR1 B M04/5C


MAN PHNOM PENH 5304532
227

BK BK

+PLG-QAB-XDB 41 M04/3D
228

BK

+PLG-QAB-XDB 23 M04/4D
229

BK
7

14 +PLG-QAB-XDB -FCM2.1 2 M03/2F


230

BK BK
DCC &

20 +PLG-QAB-XDB M03/4F
231

BK
Installation =

46 +PLG-QAB-XDB -RAD1 2 M03/5F


232

BK BK
Place of installation +

M03/6F
233

Page

32 +LVR-XDE1 -RAD1 6 M03/7F


234

BK BK
LV

X12
A05

44 +PLG-QAB-XDB M04/1F
235

BK

30 +PLG-QAB-XDB M04/3F
8249/1748

236

BK
Pages
39

A2 -KFA11 -KFA12 A2 M04/6F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
A2 -KFA13 -XDI2 8 M04/7F

238
BK BK

HAVELKA Libor
Remark
4 -FCM4.1 +LVR-XDE1 27 M05/2A

301
BK BK

17 +LVR-XDE1 +PLG-QAB-XDB 11 M05/3A

302
BK BK

Released by
BRAUN Jiri
M05/6A

303
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
7 +LVD-PFV1 +LVD-SFT1 13 M05/8A

304
BK BK

22 +PLG-QAB-XDB +LVD-PFX2 R M05/3D

Date
305
BK BK

59 PCS
21 +PLG-QAB-XDB +LVD-PFX2 G M05/3D

306
BK BK

Project number

Document number
50 +PLG-QAB-XDB +LVD-PFX3 R M05/4D
307
BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M05/4D

ABB s.r.o.
308
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
- +LVD-PFX1 -FCM4.1 2 M05/2F

TERMINAL UT 4 3044102
309

BK BK

+LVD-PFV1 8 M05/6F
310

BK

Customer
7 -XDI2 +PLG-QAB-XDB 8 P01/5D
321

BK BK

28 +LCB-BGC2 -KFA11 33 P01/6D


322

BK BK

Customer project number


Customer document number
18 +PLG-QAB-XDB P01/5E
323

BK
4

34 -KFA11 +LCB-BGC2 29 P01/6E


324

BK BK

-KFA11 23 P02/3D
325

BK

14 -XDI2 +LCB-BGC2 24 P02/4D


326

BK BK

13 -XDI2 -KFA11 24 P02/3E


327

BK BK

+LCB-BGC2 25 P02/4E
328

BK
5

16 -XDI2 -KFA13 14 P02/5D


329

BK BK

6 +LVR-XDH1 -KFA13 11 P02/5E


330

BK BK

A1 -KFA10 -XDI2 17 P02/6E

Project name
331

BK BK

Page description
6

Alternator G3
TERMINALS =A05+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X13
A05
8250/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8251/1748

PAGE
A A

M01/7A

M01/7A
S01/3D

S02/3D

S04/3D
X01/3A

X01/4A
S05/8C
DEVICE
PIN

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDV

-XDV
POTENTIAL/
COLOR

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

C GNYE C
1 2 3 4 5 6 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 8 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LV-XE X14 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM05/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM05/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812212
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM05/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM05/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 221 +LVM03/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 234 +LVM03/7E

Project name
BK BK

Page description
6

Alternator G3
MAN PHNOM PENH 5304532

TERMINALS =A05+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X15
A05
8252/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8253/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LVR-XDH X16 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8254/1748

PAGE

+LVM04/7C

+LVM04/7C

+LVM04/7C

+LVM04/7C
+LVM04/7B

+LVM04/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
TERMINALS =A05+LVR-XDH1 X17 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8255/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 =A02G01/2C
Protection devices - Circuit breaker - Miniature breakers
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers =A02G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/10617
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers =A02G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers =A02G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G02/2C B
-FCM11.1 MCB S203-Z1 ABB =A02S05/3B;=K000+PLDV01/23217;=K000+PLDV01/26317;=K000+PLDV01/29417;=K000+PLDV01/32517;=K000+PLDV01/35617;=K000+PLDV0
VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - Miniature breakers
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB =A02S05/3B;=K000+PLDV01/23317;=K000+PLDV01/26417;=K000+PLDV01/29517;=K000+PLDV01/32617;=K000+PLDV01/35717;=K000+PLDV0
VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - Miniature breakers =A02S05/2B
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories =A02S05/2B
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - Miniature breakers =A02S05/7C
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 Protection devices - General - Accessories =A02S05/7C
-KFA2 RELAY CR-U110DC3L ABB PANEL A03 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/4D
-KFA2 HOLDER CR-UH ABB PANEL A03 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/4D
C C
-KFA2 SUPPRESSOR DIODE CR-U 21 ABB PANEL A03 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA2 SOCKET CR-U3S ABB PANEL A03 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA3 RELAY CR-U110DC3L ABB PANEL A04 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/5D
-KFA3 HOLDER CR-UH ABB PANEL A04 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SUPPRESSOR DIODE CR-U 21 ABB PANEL A04 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SOCKET CR-U3S ABB PANEL A04 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA4 RELAY CR-U110DC3L ABB PANEL A05 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/6D
-KFA4 HOLDER CR-UH ABB PANEL A05 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/6D
D -KFA4 SUPPRESSOR DIODE CR-U 21 ABB PANEL A05 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/6D D
-KFA4 SOCKET CR-U3S ABB PANEL A05 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/6D
-KFA5 RELAY CR-U110DC3L ABB PANEL A06 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/7D
-KFA5 HOLDER CR-UH ABB PANEL A06 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SUPPRESSOR DIODE CR-U 21 ABB PANEL A06 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SOCKET CR-U3S ABB PANEL A06 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA9 AUXILIARY RELAY KC6-40E 110-125VDC ABB BB ES OPEN GJH1213001R0404 Relays, contactors - General - Aux. relays =A02P02/2E
-KFA9 SUPPRESSOR DIODE RD-RD7/250 ABB BB ES OPEN GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02P02/2E
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P02/6E
E E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02M04/7E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
PART LIST X18 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8256/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories =A02M04/7E
-PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage =A02S02/5E
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 Signal devices - Signal device, acoustic - Position =A02M05/3D
indicators
B B
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/4D
indicators
-PGA1 AMMETER FB96-1 1000/1A METRA L1 E6911085180 Measuring instruments, test devices - General - =A02S02/5B
Ammeters
-PGA2 AMMETER FB96-1 1000/1A METRA L2 E6911085180 Measuring instruments, test devices - General - =A02S02/5C
Ammeters
-PGA3 AMMETER FB96-1 1000/1A METRA L3 E6911085180 Measuring instruments, test devices - General - =A02S02/5D
Ammeters
-PGA.1 SCALE FB96-1 1000/1A METRA 1000353264 Measuring instruments, test devices - General - =A02S02/6D
C Accessories C
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - =A02S05/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES 1VL7621116R0101 General - Undefined =A02M03/6E
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes =A02M03/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined =A02M04/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2D
D Pushbuttons D
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M04/3B
Pushbuttons
-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2B
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M05/8D
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M05/8D
E Pushbuttons E
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton - =A02S05/4C
Voltage switches
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
PART LIST X19 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8257/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors =A02X01/7D

B B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A05
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812212 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G3 DCC & Page Pages
ABB s.r.o.
PART LIST X20 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8258/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT4,-BCT5,-BCT6
TPU 54.13
P2 1000/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P1
POS. DESIGN. NAME
6 04BAC01GS003 Alternator G4

-BAT1,-BAT2,-BAT3
TJC5
15/√3//0.11/√3//0.11/3 kV
D 0.2, 15 VA D
3P, 50 VA

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

E E
G

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8259/1748

SHEET INDEX
A PAGE PAGE NAME REVISION PAGE PAGE NAME REVISION A
=A06+LV/A01 SINGLE LINE SCHEME AM =A06+LV/X20 PART LIST AM
=A06+LV/A02 SHEET INDEX AM
=A06+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A06+LV/G02 AC SUPPLY CIRCUITS AM
=A06+LV/M01 VD4 INTERNAL WIRING AM
=A06+LV/M02 EARTHING SWITCH AM
=A06+LV/M03 CONTROL CIRCUITS AM
B =A06+LV/M04 TRIPPING CIRCUITS AM B
=A06+LV/M05 SIGNAL CIRCUITS AM
=A06+LV/P01 XDI2 SIGNALS AM
=A06+LV/P02 XDI2 SIGNALS AM
=A06+LV/Q01 MAN CONTROL SYSTEM AM
=A06+LV/Q02 MAN CONTROL SYSTEM AM
=A06+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A06+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A06+LV/S04 VOLTAGE METERING Y/yd AM C
=A06+LV/S05 VOLTAGE METERING AM
=A06+LV/V01 PANEL LAYOUT AM
=A06+LV/W01 LV COMP. DOOR LAYOUT AM
=A06+LV/X01 SPARE TERMINALS AM
=A06+LV/X02 ES SPARE CONTACTS AM
=A06+LV/X03 CB SPARE CONTACTS AM
=A06+LV/X04 MCB SPARE CONTACTS AM
D =A06+LV/X05 TERMINALS =A06+LV-XDA AM D
=A06+LV/X06 TERMINALS =A06+LV-XDC AM
=A06+LV/X07 TERMINALS =A06+LV-XDC AM
=A06+LV/X08 TERMINALS =A06+LV-XDC AM
=A06+LV/X09 TERMINALS =A06+LV-XDI1 AM
=A06+LV/X10 TERMINALS =A06+LV-XDI2 AM
=A06+LV/X11 TERMINALS =A06+LV-XDV AM
=A06+LV/X12 TERMINALS =A06+LV-XDX AM
E =A06+LV/X13 TERMINALS =A06+LV-XDX AM E
=A06+LV/X14 TERMINALS =A06+LV-XE AM
=A06+LV/X15 TERMINALS =A06+LVR-XDE1 AM
=A06+LV/X16 TERMINALS =A06+LVR-XDH AM
=A06+LV/X17 TERMINALS =A06+LVR-XDH1 AM
=A06+LV/X18 PART LIST AM
=A06+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8260/1748

SPRING
=A05
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1

A A
-XDI1 2

-XDI1 3

-XDI1 4

-XDI1 5

-XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8261/1748

=A05
LIGHTING
CIRCUIT SPARE
-XDI1 7

A A
-XDI1 8

-XDI1 9

-XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8262/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

M04/1D

M04/3D

M04/3D

M04/4D

M03/3C
M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/7C

Q02/2C

Q02/1C

Q02/6C

P01/7D
X03/6C

X03/6C

X03/3C

X03/4C

X03/2C

X03/4C

X03/3C

X03/5C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

Q02/7D

Q02/2D

Q02/1D

Q02/6D

M04/1E

M04/3E

M04/4E

P01/7E

X03/4D

M05/3C

M05/3C

X03/2D

X03/4D

X03/3D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

M03/3C

X03/5D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

P01/8D
X03/1C

X03/1C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8263/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8264/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/5C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

01BAC01GS003-YB01

01BAC01GS008-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
9 - 10
11 - 12
12 14
-KFA2 M01/8B
P01/3D 11 +PLG -XDB 57
-QAB
12 14
-KFA3 53
-XDC 2 -XDC 4 -XDC 6 -XDC 10
C P01/4D 11 -BGT2 C
54
12 14
-KFA4
P01/6D -XDB 58
11
M01/8D

12 14
13
-KFA5
-KFA9
11
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8265/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
01BAC01GS003-YB32

01BAC01GS003-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (GCP)

SYSTEM (GCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:1
13 P02/6E 11 24 24 GY BN GY BN
+LVD P01/7E
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P01/7C
M01/5D XDI2:2
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/3C 13 14 Q02/4C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 P01/7D 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8266/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8267/1748

=A05 STEP-UP ALTERNATOR G3


CB OPEN/IN TEST/PLUG OUT
ALTERNATOR G1 ALTERNATOR G2 TRANSFORMER 1 OFF
INCOMERS INTERLOCKING
OFF OFF OFF
-XDI2 1

A A
-XDI2 2

-XDI2 3

-XDI2 4

-XDI2 5

-XDI2 6

-XDI2 7

B B
-XDI2 8

-XDI2 9

-XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

M04/8E
XDI2:2

-KFA1 -KFA2 -KFA3 -KFA4 -XDX 321 322


CR-U110DC3L A1 CR-U110DC3L A1 CR-U110DC3L A1 CR-U110DC3L A1

D A2 A2 A2 A2 M01/5B D
+PLG -XDB 8
-QAB
1 28
33
-BGB1 +LCB
-KFA11
2 M04/6E -BGC2
34 29
M01/2F

-XDB 18
14 14 14 14 M01/5D
11 11 11 11
12 12 12 12
24 24 24 24
E 21 21 21 21 -XDX 323 324
E
22 22 22 22
34 34 34 34
31 31 31 31
32 32 32 32
14 14 14 M04/8B
11 M03/2C 11 M03/2C 11 M03/2C
12 12 12 XDI2:1

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8268/1748

=A05 CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE


TRIPPING

-XDI2 11

A A
-XDI2 12

-XDI2 13

-XDI2 14

-XDI2 15

-XDI2 16

-XDI2 17

B B
-XDI2 18

-XDI2 19

-XDI2 20

C C

-XDI2 11 12 13 14 15 16 17 18 19 20

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8269/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 01BAC01GS008-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 01BAC01GS008-XB02 01BAC01GW001-XM84 01BAC01CE011-XM85 01BAC01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8270/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE ALTERNATOR CB CB CLOSED CB CLOSED


01BAC01GS003-XB01 01BAC01GS003-XB02 POSITION POSITION REMOTE 01BAC01GS003-XB01 01BAC01GS003-XB01
01BAC01GS003-XB41 01BAC01GS003-XB40 COMMAND MODE
A 01BAC01GS003-XB43 A

B B

M01/3B M01/3B M01/3B M01/3B


C +PLG -XDB 7 +PLG -XDB 28 +PLG -XDB 3 +PLG -XDB 5 C
-QAB -QAB -QAB -QAB
11 9 7 19
-BGB1 -BGB1 13 13 11 -BGB1 -BGB1
12 10 -KFA11 -KFA12 +LVD-SFS1 8 20
M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38 -XDB 13 -XDB 15


M01/3D M01/3D M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379 380 381 382 383

=
E + E

MAN
CONTROL
SYSTEM
(GCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8271/1748

L1 L2 L3
A = A
+ PROTECTION CT
01BAC01CE001A/B/C

+CT
P2 P2 P2

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 12

2S2
B TPU 54.13 -BCT4 B
1000/1A 2S1
Core 2: 5P20, 10VA
-XDA 11

-XDA 14

2S2
-BCT5
C 2S1 C
-XDA 13
MAN
CONTROL
SYSTEM
(GCP)
-XDA 16

2S2
-BCT6
2S1
D D
-XDA 15

1 -XDA 17

-XE

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8272/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
01BAC01CE003A/B/C

+CT DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

-XDA 2 -XDA 18

1S2
B TPU 54.13 -BCT4 B
1000/1A 1S1 +LVD
Core 1: 0.5Fs5, 10VA -PGA1
-XDA 1 17 18 -XDA 19
A
FB96-1
1000/1A
0-1000/2000A
-XDA 4 RED LINE AT 891 A -XDA 20

1S2
-BCT5
C 1S1 +LVD C
-XDA 3
-PGA2
17 18 -XDA 21
MAN
A CONTROL
FB96-1 SYSTEM
1000/1A
0-1000/2000A (GCP)
-XDA 6 RED LINE AT 891 A -XDA 22

1S2
-BCT6
1S1 +LVD
D -PGA3 D
-XDA 5 17 18 -XDA 23
A
2 FB96-1
-XDA 7
1000/1A
-XE 0-1000/2000A
RED LINE AT 891 A

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
E Ck E
-WE

+LVD GND L3 GND L2 GND L1 GND


1
-PFV1 2 M03/7B
P1 P1 P1 CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8273/1748

L3

A L2 A

L1

+TVT

B A N PE A N PE A N PE B

-BAT1 -BAT2 -BAT3

a +t° n da dn a +t° n da dn a +t° n da dn

C C

-XDV 1 2 3 4 5

-XE 4
D D

L1 da
S05/3A L2 S05/6A dn
S05/3A L3 S05/6A
S05/3A N
S05/2C

E E

DESIGNATION DESCRIPTION

-BAT1,2,3 MV TRANSFORMERS
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING Y/yd &EFS S04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8274/1748

A A

S04/2D L1
S04/3D L2 S04/5D dn
S04/3D L3 S04/5D da

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22

Q01/7C

X04/4C
S04/3D
C N C
-XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 01BAC01CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (GCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
01BAC01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(GCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8275/1748

=A02+LV =A02
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 85
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 15
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 59
+LV +LVR -XE TERMINAL USLKG 5 0441504 8
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13
-KFA2
-KFA3
-KFA4
-KFA5

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-KFA2 PANEL A03 OFF

-KFA3 PANEL A04 OFF

-KFA4 PANEL A05 OFF


-XDI1 -XDI2 -XDV

-KFA5 PANEL A06 OFF


-XDX -XDA -RAD1 DIODES
=A02+LCT
-XDC
D DEVICE TAG TEXT D
-EA1 LV LIGHTING

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8276/1748

=A02+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX2 CB OPEN / CLOSED

B -PFX1 E/S OPEN / CLOSED B

A06 Alternator G4 -PFX3 CB IN TEST / SERVICE

-SFO1 CB OPEN

-SFC1 CB CLOSE

705 mm
-PGA1 -PGA2 -PGA3

-SFT1 LAMP TEST

-SFS1 LOCAL - REMOTE SWITCH

-SFV1 VOLTMETER SELECTOR SWITCH


C -PGV1
-PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8277/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8278/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED
A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8279/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED AND CB CLOSED CB OPEN CB OPEN OR IN CB IN SERVICE CB SPRING CB SPRING
IN SERVICE TEST POSITION POSITION CHARGED DISCHARGED
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439

B B

C M01/6B M01/5B M01/6B M01/6B M01/5B M01/8B M01/1B M01/1B


C
+PLG -XDB 9 +PLG -XDB 6 +PLG -XDB 32 +PLG -XDB 27 +PLG -XDB 29 +PLG -XDB 55 +PLG -XDB 24 +PLG -XDB 26
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 23 -BGB1 31 25 13 33 53 4 2
+LCB +LCB
-BGB1 16 -BGB1 -BGB1 -BGB1 -BGT2 -BGT1 -BGS2 -BGS2
-BGC2 -BGC2 33
23 27 24 32 26 14 34 54 3 1
M01/1F M01/2F
-BGT1
34
-XDB 19 -XDB 42 -XDB 37 -XDB 39 -XDB 56 -XDB 34 -XDB 36
M01/6D -XDB 16 M01/6D M01/6D M01/5D M01/8D M01/1D M01/1D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8280/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT4 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
18 -XDA BK
+CT-BCT4 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT5 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
20 -XDA +CT-BCT5 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT6 1S1 S02/4D
BK

6
22 -XDA +CT-BCT6 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4D
GNYE

Project number

Document number
11
+CT-BCT4 2S1 S01/4B
BK
12
+CT-BCT4 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
13

+CT-BCT5 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT5 2S2 S01/4C


BK

Customer
15

+CT-BCT6 2S1 S01/4D


BK
16

+CT-BCT6 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4D


GNYE
4

18

-XDA 2 S02/6B
BK
19

+LVD-PGA1 18 S02/6B
BK
20

-XDA 4 S02/6C
BK
21

+LVD-PGA2 18 S02/6C
BK
22

-XDA 6 S02/6D
BK
5

23

+LVD-PGA3 18 S02/6D
BK

Project name

Page description
6

Alternator G4
TERMINALS =A06+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A06
8281/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

85 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/1D
371

BK

+PLG-QAB-XDB 7 Q02/2D
Alternator G4
372

BK
TERMINALS =A06+LV-XDC

+PLG-QAB-XDB 38 Q02/2D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/3D
374

BK

-KFA11 14 Q02/3D
375

BK
7

-KFA12 14 Q02/4D
376

BK
DCC &

-KFA11 13 Q02/4D
377

BK
Installation =

+LVD-SFS1 12 Q02/5D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/5D
379

BK
Page

+PLG-QAB-XDB 13 Q02/6D
380

BK
LV

X06
A06

+PLG-QAB-XDB 3 Q02/7D
381

BK

+PLG-QAB-XDB 15 Q02/7D
8282/1748

382

BK
Pages
39

+PLG-QAB-XDB 5 Q02/8D
383

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/3B

391

HAVELKA Libor
Remark
X01/3B

392
X01/4B

393

Released by
BRAUN Jiri
X01/4B

394
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
X01/4B

395
X01/4B

Date
396

85 PCS
+LVR-XDE1 11 X02/2B

401
BK

Project number

Document number
+LVR-XDE1 12 X02/2E
402
BK

+LVR-XDE1 13 X02/3B

ABB s.r.o.
403
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
+LVR-XDE1 14 X02/3E

TERMINAL UT 4 3044102
404

BK

+LVR-XDE1 15 X02/4B
405

BK

Customer
+LVR-XDE1 16 X02/4E
406

BK

+LVR-XDE1 21 X02/5B
407

BK

Customer project number


Customer document number
+LVR-XDE1 22 X02/5E
408

BK
4

+LVR-XDE1 23 X02/6B
409

BK

+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

+LVR-XDE1 26 X02/7E
412

BK

+LCB-BGC2 22 X03/1B
421

BK
5

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E

Project name
424

BK

Page description
+PLG-QAB-XDB 9 X03/2B
425

BK

+PLG-QAB-XDB 19 X03/2E
426

BK
6

+PLG-QAB-XDB 6 X03/3B
427

BK

+PLG-QAB-XDB 16 X03/3E
Alternator G4
428

BK
TERMINALS =A06+LV-XDC

+PLG-QAB-XDB 32 X03/3B
MAN PHNOM PENH 5304532
429

BK

+PLG-QAB-XDB 42 X03/3E
430

BK

+PLG-QAB-XDB 27 X03/4B
431

BK
7

+PLG-QAB-XDB 37 X03/4E
432

BK
DCC &

+PLG-QAB-XDB 29 X03/4B
433

BK
Installation =

+PLG-QAB-XDB 39 X03/4E
434

BK
Place of installation +

+PLG-QAB-XDB 55 X03/5B
435

BK
Page

+PLG-QAB-XDB 56 X03/5E
436

BK
LV

X07
A06

+PLG-QAB-XDB 24 X03/6B
437

BK

+PLG-QAB-XDB 34 X03/6E
8283/1748

438

BK
Pages
39

+PLG-QAB-XDB 26 X03/6B
439

BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8284/1748

PAGE
A A

X04/1B

X04/3B

X04/4B

X04/5B

X01/2B
X03/6E

X04/1E

X04/3E

X04/4E

X04/5E

X01/2E
DEVICE
PIN

36

21

22

21

22

13

14

13

14

24

21
DESIGNATION

+PLG-QAB-XDB
DEVICE

B B
-FCM11.1

-FCM11.1

-FCM11.1

-FCM11.1
-FCM2.1

-FCM2.1

-FCM5.1

-FCM3.1

-KFA13

-KFA13
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK

BK
C C
440 501 502 503 504 505 506 507 508 509 510
TERMINALS
+LV-XDC

D D
POTENTIAL/

BK

BK
COLOR

=EXT-X

=EXT-X
DESIGNATION
DEVICE

E E
DEVICE

_
PIN

TOTAL TERMINALS COUNT: 85 PCS


TERMINAL TYPE: TERMINAL UT 4 3044102
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LV-XDC X08 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8285/1748

PAGE
A A

G01/2C

G01/3C

G01/4C

G01/5C

G01/6C

G01/6C

G02/2C

G02/3C

G02/6C

G02/6C
DEVICE
PIN

3N
3

1
DESIGNATION
DEVICE

B B
-FCM2.1

-FCM2.1

-FCM3.1

-FCM3.1

-FCM4.1

-FCM4.1

-FCM5.1

-FCM5.1
POTENTIAL/
COLOR

BK

BK

BK

BK

BK

BK

BK

C LB C
1 2 3 4 5 6 7 8 9 10
+LV-XDI1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK

BK

BK

BK

LB

BK

BK
COLOR

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1

=A05-XDI1
DESIGNATION
DEVICE

E E
DEVICE

10
PIN

TOTAL TERMINALS COUNT: 10 PCS


TERMINAL TYPE: TERMINAL UT 4-QUATTRO 3044571
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LV-XDI1 X09 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDI2
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
1 =A05-XDI2 BK
-KFA1 A1 P01/2C
BK

HAVELKA Libor
2

Remark
2 =A05-XDI2 BK
-KFA1 A2 P01/2C
BK

3
3 =A05-XDI2 BK
-KFA2 A1 P01/3C
BK

Released by
4

BRAUN Jiri
4 =A05-XDI2 -KFA2 A2 P01/3C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
5 =A05-XDI2 BK
-KFA3 A1 P01/4C
BK

6
6 =A05-XDI2 -KFA3 A2 P01/5C

Date
BK BK

20 PCS
7
7 =A05-XDI2 BK
-KFA4 A1 P01/6C
BK

Project number

Document number
8
8 =A05-XDI2 BK
-KFA4 A2 P01/6C
BK
9
9 =A05-XDI2 -XDX 321 P01/7C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
10

10 =A05-XDI2 BK
-XDX 238 P01/7C
BK
11

11 =A05-XDI2 BK
-KFA9 A1 P02/2C
BK

Customer
12

12 =A05-XDI2 BK
-KFA9 A2 P02/2C
BK

TERMINAL UT 4-QUATTRO 3044571


13

13 =A05-XDI2 BK
-XDX 327 P02/3C
BK

Customer project number


Customer document number
14

14 =A05-XDI2 BK
-XDX 326 P02/3C
BK
4

15

15 =A05-XDI2 BK
P02/4C
16

16 =A05-XDI2 BK
-XDX 329;3 P02/5C
BK;BK
17

17 =A05-XDI2 BK
-XDX 331 P02/6C
BK
18

18 =A05-XDI2 BK
-KFA10 A2 P02/6C
BK
19

19 =A05-XDI2 BK
P02/7C
5

20

20 =A05-XDI2 BK
P02/7C

Project name

Page description
6

Alternator G4
TERMINALS =A06+LV-XDI2
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X10
A06
8286/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8287/1748

PAGE
A A

S04/2D

S04/3D

S04/3D

S04/3D

S04/3D

S05/7C

S05/7C

S05/7C

S05/8C

S05/8C

S05/2C

S05/2C

S05/2C

S05/2C
S05/7B
DEVICE
PIN

4:1

5:1
dn
da
n

4
a

a
DESIGNATION
DEVICE

B B

+TOP-RAA1
+TVT-BAT1

+TVT-BAT2

+TVT-BAT3

+TVT-BAT3

+TVT-BAT1

+TVT-BAT3
-FCM14.1

-FCM12.1

-FCM12.1

-FCM12.1

-XDV
-XE

-XE
POTENTIAL/
COLOR

GNYE

GNYE
BK

BK

BK

BK

BK

BK

BK

BK
LB

LB

LB

LB
C C
1 2 3 4 5 41 42 43 48 49 50 51 52 53 54
TERMINALS
+LV-XDV

D D
POTENTIAL/

BK

BK

BK

LB

BK
COLOR

-FCM11.1

-FCM11.1

-FCM11.1

-XDV

-FCM14.1
DESIGNATION
DEVICE

E E
DEVICE

54

1
PIN

TOTAL TERMINALS COUNT: 15 PCS


TERMINAL TYPE: TERMINAL URTK/S 0311087
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LV-XDV X11 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
4 -FCM2.1 +LVD-SFS1 1 M03/2A

201
BK BK

HAVELKA Libor
Remark
49 +PLG-QAB-XDB -XDC 3 M03/4A

202
BK BK

-XDC 5 M03/5A

203
BK

Released by
BRAUN Jiri
M03/6A

204
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVD-PFV1 1 M03/7A

205
BK

-XDC 11 M04/1A

Date
206
BK

59 PCS
+LVD-SFS1 5 M04/3A

207
BK

Project number

Document number
14 -KFA10 +LVD-SFS1 7 M04/4A
208
BK BK

+PLG-QAB-XDB 52 M04/6A

ABB s.r.o.
209
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
+LVR-XDH1 1 M04/7A

TERMINAL UT 4 3044102
210

BK

2 +LVD-SFS1 -KFA2 14 M03/2B


211

BK BK

Customer
+PLG-QAB-XDB 57 M03/3B
212

BK

11 -KFA5 +LVD-SFC1 13 M03/2D


213

BK BK

Customer project number


Customer document number
58 +PLG-QAB-XDB M03/3D
214

BK
4

14 +LVD-SFC1 +PLG-QAB-XDB 4 M03/2E


215

BK BK

2 -XDC M03/3E
216

BK

14 -KFA9 +PLG-QAB-XDB 45 M03/5E


217

BK BK

-RAD1 1 M03/6E
218

BK

10 -XDC +LCB-BGC2 20 M03/7D


219

BK BK
5

-KFA11 43 M03/8D
220

BK

21 +LCB-BGC2 +LVR-XDE1 31 M03/7E


221

BK BK

44 -KFA11 -RAD1 5 M03/8E

Project name
222

BK BK

Page description
12 -XDC +PLG-QAB-XDB 43 M04/1C
223

BK BK

14 +LVD-SFO1 +PLG-QAB-XDB 31 M04/3C


224

BK BK
6

M04/3C
225

14 -XDC M04/4C
Alternator G4
226

BK
TERMINALS =A06+LV-XDX

11 -KFA10 -RAR1 B M04/5C


MAN PHNOM PENH 5304532
227

BK BK

+PLG-QAB-XDB 41 M04/3D
228

BK

+PLG-QAB-XDB 23 M04/4D
229

BK
7

14 +PLG-QAB-XDB -FCM2.1 2 M03/2F


230

BK BK
DCC &

20 +PLG-QAB-XDB M03/4F
231

BK
Installation =

46 +PLG-QAB-XDB -RAD1 2 M03/5F


232

BK BK
Place of installation +

M03/6F
233

Page

32 +LVR-XDE1 -RAD1 6 M03/7F


234

BK BK
LV

X12
A06

44 +PLG-QAB-XDB M04/1F
235

BK

30 +PLG-QAB-XDB M04/3F
8288/1748

236

BK
Pages
39

A2 -KFA11 -KFA12 A2 M04/6F


237

BK BK
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDX
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
A2 -KFA13 -XDI2 10 M04/7F

238
BK BK

HAVELKA Libor
Remark
4 -FCM4.1 +LVR-XDE1 27 M05/2A

301
BK BK

17 +LVR-XDE1 +PLG-QAB-XDB 11 M05/3A

302
BK BK

Released by
BRAUN Jiri
M05/6A

303
2

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
7 +LVD-PFV1 +LVD-SFT1 13 M05/8A

304
BK BK

22 +PLG-QAB-XDB +LVD-PFX2 R M05/3D

Date
305
BK BK

59 PCS
21 +PLG-QAB-XDB +LVD-PFX2 G M05/3D

306
BK BK

Project number

Document number
50 +PLG-QAB-XDB +LVD-PFX3 R M05/4D
307
BK BK

51 +PLG-QAB-XDB +LVD-PFX3 G M05/4D

ABB s.r.o.
308
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
- +LVD-PFX1 -FCM4.1 2 M05/2F

TERMINAL UT 4 3044102
309

BK BK

+LVD-PFV1 8 M05/6F
310

BK

Customer
9 -XDI2 +PLG-QAB-XDB 8 P01/7D
321

BK BK

28 +LCB-BGC2 -KFA11 33 P01/7D


322

BK BK

Customer project number


Customer document number
18 +PLG-QAB-XDB P01/7E
323

BK
4

34 -KFA11 +LCB-BGC2 29 P01/7E


324

BK BK

-KFA11 23 P02/3D
325

BK

14 -XDI2 +LCB-BGC2 24 P02/4D


326

BK BK

13 -XDI2 -KFA11 24 P02/3E


327

BK BK

+LCB-BGC2 25 P02/4E
328

BK
5

16 -XDI2 -KFA13 14 P02/5D


329

BK BK

6 +LVR-XDH1 -KFA13 11 P02/5E


330

BK BK

A1 -KFA10 -XDI2 17 P02/6E

Project name
331

BK BK

Page description
6

Alternator G4
TERMINALS =A06+LV-XDX
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X13
A06
8289/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8290/1748

PAGE
A A

M01/7A

M01/7A
S01/3D

S02/3D

S04/3D
X01/3A

X01/4A
S05/8C
DEVICE
PIN

17

50

40
7

1
DESIGNATION

+PLG-QAB-XDB

+PLG-QAB-XDB
DEVICE

B B

+LVR-WE2
-XDA

-XDA

-XDV

-XDV
POTENTIAL/
COLOR

GNYE

GNYE

GNYE

GNYE

GNYE

GNYE

C GNYE C
1 2 3 4 5 6 11 12
TERMINALS
+LV-XE

D D
POTENTIAL/
COLOR
DESIGNATION
DEVICE

E E
DEVICE
PIN

TOTAL TERMINALS COUNT: 8 PCS


TERMINAL TYPE: TERMINAL USLKG 5 0441504
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LV-XE X14 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LVR-XDE1
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
11
40 +ES-QCE1-BGE2 BK
+LV-XDC 401 +LVX02/2C
BK

HAVELKA Libor
Remark
12
41 +ES-QCE1-BGE2 BK
+LV-XDC 402 +LVX02/2D
BK

13
42 +ES-QCE1-BGE2 BK
+LV-XDC 403 +LVX02/3C
BK

Released by
BRAUN Jiri
14
43 +ES-QCE1-BGE2 +LV-XDC 404 +LVX02/3D
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
15
44 +ES-QCE1-BGE2 BK
+LV-XDC 405 +LVX02/4C
BK

16
45 +ES-QCE1-BGE2 +LV-XDC 406 +LVX02/4D

Date
BK BK

22 PCS
17
46 +ES-QCE1-BGE2 BK
+LV-XDX 302 +LVM05/2B
BK

Project number

Document number
18
47 +ES-QCE1-BGE2 BK
+LVD-PFX1 G +LVM05/2C
BK
19
48 +ES-QCE1-BGE2 +LV-XDC 354 +LVQ01/3C

ABB s.r.o.
BK BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812213
20

49 +ES-QCE1-BGE2 BK
+LV-XDC 353 +LVQ01/3D
BK

TERMINAL UTTB 2,5 3044636


21

20 +ES-QCE1-BGE3 BK
+LV-XDC 407 +LVX02/5C
BK

Customer
22

21 +ES-QCE1-BGE3 BK
+LV-XDC 408 +LVX02/5D
BK
23

22 +ES-QCE1-BGE3 BK
+LV-XDC 409 +LVX02/6C
BK

Customer project number


Customer document number
24

23 +ES-QCE1-BGE3 BK
+LV-XDC 410 +LVX02/6D
BK
4

25

24 +ES-QCE1-BGE3 BK
+LV-XDC 411 +LVX02/7C
BK
26

25 +ES-QCE1-BGE3 BK
+LV-XDC 412 +LVX02/7D
BK
27

26 +ES-QCE1-BGE3 BK
+LV-XDX 301 +LVM05/2B
BK
28

27 +ES-QCE1-BGE3 BK
+LVD-PFX1 R +LVM05/2C
BK
29

28 +ES-QCE1-BGE3 BK
+LV-XDC 352 +LVQ01/1C
BK
5

30

29 +ES-QCE1-BGE3 BK
+LV-XDC 351 +LVQ01/1D
BK
31

G +ES-QCE1-RLE3 BK
+LV-XDX 221 +LVM03/7E
BK
32

H +ES-QCE1-RLE3 +LV-XDX 234 +LVM03/7E

Project name
BK BK

Page description
6

Alternator G4
MAN PHNOM PENH 5304532

TERMINALS =A06+LVR-XDE1
7

DCC &
Installation =

Place of installation +

Page
LV

X15
A06
8291/1748

Pages
39
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8292/1748

PAGE

+LVG02/2D

+LVG02/3D

+LVG02/3D

+LVG02/3D
A A

DEVICE
PIN

2
DESIGNATION
DEVICE

B B
+LCT-EA1

+LCT-EA1
POTENTIAL/
COLOR

BK

BK

C C
1 2 11 12
+LVR-XDH
TERMINALS

D D
POTENTIAL/

BK

LB
COLOR

+LV-FCM5.1

+LV-FCM5.1
DESIGNATION
DEVICE

E E
DEVICE

4N
PIN

TOTAL TERMINALS COUNT: 4 PCS


TERMINAL TYPE: TERMINAL UTTB 2,5 3044636
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LVR-XDH X16 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8293/1748

PAGE

+LVM04/7C

+LVM04/7C

+LVM04/7C

+LVM04/7C
+LVM04/7B

+LVM04/7B

+LVP02/5D

+LVP02/5E

+LVP02/4E
A A

DEVICE
PIN

BN

BN

BN

GY

GY

GY
BK

BK

BK
DESIGNATION
DEVICE

B B
+CAB-BGA3

+CAB-BGA3

+CAB-BGA3
+CB-BGA1

+CB-BGA1

+CB-BGA1
+BB-BGA2

+BB-BGA2

+BB-BGA2
POTENTIAL/
COLOR

BN_ITH

BN_ITH

BN_ITH

GY_ITH

GY_ITH

GY_ITH
ITH_10

ITH_11
BK_ITH

BK_ITH

BK_ITH
ITH_1

ITH_2

ITH_3

ITH_5

ITH_6

ITH_7

ITH_9

C C
1 2 3 4 5 6 7 8 9
+LVR-XDH1
TERMINALS

D D
POTENTIAL/

BK

BK

BK

BK
COLOR

+LV-XDX

+LV-XDI2

+LV-KFA13

+LV-XDX
DESIGNATION
DEVICE

E E
DEVICE

210

16

A1

330
PIN

TOTAL TERMINALS COUNT: 9 PCS


TERMINAL TYPE: TERMINAL UT 4-MT 3046139
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
TERMINALS =A06+LVR-XDH1 X17 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8294/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-FCM2.1 MCB S202-C2 ABB CONTROL CIRCUIT 2CDS252001R0024 =A02G01/2C
Protection devices - Circuit breaker - Miniature breakers
-FCM2.1 AUXILIARY CONTACT S2C-H11L ABB CONTROL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/2C
-FCM3.1 MCB S202-K1 ABB SPRING CHARGER CIRCUIT 2CDS252001R0217 Protection devices - Circuit breaker - Miniature breakers =A02G01/4C
-FCM3.1 AUXILIARY CONTACT S2C-H11L ABB SPRING CHARGER CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/4C
-FCM3.1 MCB S202-K3 ABB 2CDS252001R0317 =K000+PLDV01/10617
Protection devices - Circuit breaker - Miniature breakers
-FCM4.1 MCB S202-C1 ABB SIGNAL CIRCUIT 2CDS252001R0014 Protection devices - Circuit breaker - Miniature breakers =A02G01/6C
-FCM4.1 AUXILIARY CONTACT S2C-H11L ABB SIGNAL CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G01/6C
-FCM5.1 MCB S201-C2 NA ABB LIGHTING CIRCUIT 2CDS251103R0024 Protection devices - Circuit breaker - Miniature breakers =A02G02/2C
B -FCM5.1 AUXILIARY CONTACT S2C-H11L ABB LIGHTING CIRCUIT 2CDS200936R0001 Protection devices - General - Accessories =A02G02/2C B
-FCM11.1 MCB S203-Z1 ABB =A02S05/3B;=K000+PLDV01/23217;=K000+PLDV01/26317;=K000+PLDV01/29417;=K000+PLDV01/32517;=K000+PLDV01/35617;=K000+PLDV0
VT - Y WINDING 2CDS253001R0218 Protection devices - Circuit breaker - Miniature breakers
-FCM11.1 AUXILIARY CONTACT S2C-H11L ABB =A02S05/3B;=K000+PLDV01/23317;=K000+PLDV01/26417;=K000+PLDV01/29517;=K000+PLDV01/32617;=K000+PLDV01/35717;=K000+PLDV0
VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories
-FCM12.1 MCB S203-Z2 ABB VT - Y WINDING 2CDS253001R0278 Protection devices - Circuit breaker - Miniature breakers =A02S05/2B
-FCM12.1 AUXILIARY CONTACT S2C-H11L ABB VT - Y WINDING 2CDS200936R0001 Protection devices - General - Accessories =A02S05/2B
-FCM14.1 MCB S201-Z4 ABB VT - OPEN DELTA 2CDS251001R0338 Protection devices - Circuit breaker - Miniature breakers =A02S05/7C
-FCM14.1 AUXILIARY CONTACT S2C-H11L ABB VT - OPEN DELTA 2CDS200936R0001 Protection devices - General - Accessories =A02S05/7C
-KFA2 RELAY CR-U110DC3L ABB PANEL A03 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/4D
-KFA2 HOLDER CR-UH ABB PANEL A03 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/4D
C C
-KFA2 SUPPRESSOR DIODE CR-U 21 ABB PANEL A03 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA2 SOCKET CR-U3S ABB PANEL A03 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/4D
-KFA3 RELAY CR-U110DC3L ABB PANEL A04 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/5D
-KFA3 HOLDER CR-UH ABB PANEL A04 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SUPPRESSOR DIODE CR-U 21 ABB PANEL A04 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA3 SOCKET CR-U3S ABB PANEL A04 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/5D
-KFA4 RELAY CR-U110DC3L ABB PANEL A05 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/6D
-KFA4 HOLDER CR-UH ABB PANEL A05 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/6D
D -KFA4 SUPPRESSOR DIODE CR-U 21 ABB PANEL A05 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/6D D
-KFA4 SOCKET CR-U3S ABB PANEL A05 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/6D
-KFA5 RELAY CR-U110DC3L ABB PANEL A06 OFF 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P01/7D
-KFA5 HOLDER CR-UH ABB PANEL A06 OFF 1SVR405669R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SUPPRESSOR DIODE CR-U 21 ABB PANEL A06 OFF 1SVR405661R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA5 SOCKET CR-U3S ABB PANEL A06 OFF 1SVR405660R0000 Relays, contactors - General - Accessories =A02P01/7D
-KFA9 AUXILIARY RELAY KC6-40E 110-125VDC ABB BB ES OPEN GJH1213001R0404 Relays, contactors - General - Aux. relays =A02P02/2E
-KFA9 SUPPRESSOR DIODE RD-RD7/250 ABB BB ES OPEN GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02P02/2E
-KFA10 RELAY CR-U110DC3L ABB ITH LIMITER TRIP 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02P02/6E
E E
-KFA10 HOLDER CR-UH ABB ITH LIMITER TRIP 1SVR405669R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER TRIP 1SVR405661R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA10 SOCKET CR-U3S ABB ITH LIMITER TRIP 1SVR405660R0000 Relays, contactors - General - Accessories =A02P02/6E
-KFA11 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN TEST POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA11 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN TEST POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA12 AUXILIARY RELAY KC6-40E 110-125VDC ABB CB IN SERVICE POSITION GJH1213001R0404 Relays, contactors - General - Aux. relays =A02M04/6E
-KFA12 SUPPRESSOR DIODE RD-RD7/250 ABB CB IN SERVICE POSITION GHV2501910R0001 Relays, contactors - Contactors - Accessories =A02M04/6E
-KFA13 RELAY CR-U110DC3L ABB ITH LIMITER IN CAB./CB COMP. 1SVR405622R8100 Relays, contactors - General - Aux. relays =A02M04/7E
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
PART LIST X18 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8295/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-KFA13 HOLDER CR-UH ABB ITH LIMITER IN CAB./CB COMP. 1SVR405669R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SUPPRESSOR DIODE CR-U 21 ABB ITH LIMITER IN CAB./CB COMP. 1SVR405661R0000 Relays, contactors - General - Accessories =A02M04/7E
-KFA13 SOCKET CR-U3S ABB ITH LIMITER IN CAB./CB COMP. 1SVR405660R0000 Relays, contactors - General - Accessories =A02M04/7E
-PFV1 INDICATOR CPI PLUS/R 3-52kV NVI/PSI KUVAG VOLTAGE INDICATOR 1000331300 Signal devices - Signal device, acoustic - Voltage =A02S02/5E
indicators
-PFX1 POSITION INDICATOR SUS-01-TT R5/G4 ELECO E/S OPEN / CLOSED 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/2D
indicators
-PFX2 POSITION INDICATOR SUS-01-TT-Q R5/G4 ELECO CB OPEN / CLOSED 1000061151 Signal devices - Signal device, acoustic - Position =A02M05/3D
indicators
B B
-PFX3 POSITION INDICATOR SUS-01-TT R5/G4 ELECO CB IN TEST / SERVICE 1000061152 Signal devices - Signal device, acoustic - Position =A02M05/4D
indicators
-PGA1 AMMETER FB96-1 1000/1A METRA L1 E6911085180 Measuring instruments, test devices - General - =A02S02/5B
Ammeters
-PGA2 AMMETER FB96-1 1000/1A METRA L2 E6911085180 Measuring instruments, test devices - General - =A02S02/5C
Ammeters
-PGA3 AMMETER FB96-1 1000/1A METRA L3 E6911085180 Measuring instruments, test devices - General - =A02S02/5D
Ammeters
-PGA.1 SCALE FB96-1 1000/1A METRA 1000353264 Measuring instruments, test devices - General - =A02S02/6D
C Accessories C
-PGV1 VOLTMETER FB96-1 15000/110V METRA VOLTMETER E6912085623 Measuring instruments, test devices - General - =A02S05/5E
Voltmeters
-RAD1 BOX GH DK6 6 ANSCHL WEIDMUELLER DIODES 1VL7621116R0101 General - Undefined =A02M03/6E
-RAD1 DIODE BY2000 2000V 3A DIOTEC DIODES 1000344927 Semiconductors - General - Diodes =A02M03/6E
-RAR1 MODULE TCS-01 ABB TCS MODUL 1000073007 Resistors - Undefined =A02M04/5D
-SFC1 CONTACT BLOCK MCBH-10 ABB CB CLOSE 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 TEXT CAP "I" GREEN ABB CB CLOSE 1SFA616906R9002 Sensor, switch, and pushbutton - General - Accessories =A02M03/2D
-SFC1 PUSHBUTTON MP1-11C ABB CB CLOSE 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2D
D Pushbuttons D
-SFO1 CONTACT BLOCK MCBH-20 ABB CB OPEN 1SFA611605R1102 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 TEXT CAPS KTC4-9004 ABB CB OPEN 1SFA616904R9004 Sensor, switch, and pushbutton - General - Accessories =A02M04/3B
-SFO1 PUSHBUTTON MP1-11C ABB CB OPEN 1SFA611100R1108 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M04/3B
Pushbuttons
-SFS1 SWITCH T0-3-8222/E EATON LOCAL - REMOTE SWITCH E6901018148 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M03/2B
Selectors switches
-SFT1 CONTACT BLOCK MCBH-10 ABB LAMP TEST 1SFA611605R1101 Sensor, switch, and pushbutton - General - Accessories =A02M05/8D
-SFT1 PUSHBUTTON MP1-10B ABB LAMP TEST 1SFA611100R1006 Sensor, switch, and pushbutton - Switch / pushbutton - =A02M05/8D
E Pushbuttons E
-SFV1 SWITCH T0-2-8004/E EATON VOLTMETER SELECTOR SWITCH 1000041977 Sensor, switch, and pushbutton - Switch / pushbutton - =A02S05/4C
Voltage switches
-XDA.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDA.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
-XDA.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDA.1 BRIDGE EB 4-8 0202142 PHOENIX 1000277010 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 COVER D-URTK 0310020 PHOENIX E6345611702 Terminals - Cover - Covers =A02X01/7D
-XDV.1 BARRIER ATS-RTK 0310224 PHOENIX E6345611703 Terminals - Partition - Partitions =A02X01/7D
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812209
1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
PART LIST X19 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8296/1748

PART LIST
DEVICE TAG MATERIAL DESCRIPTION MANUFACTURER TEXT ABB ORDER NR. MATERIAL CLASSIFICATION POSITION
A A
-XDV.1 BRIDGE EB 2-8 0202154 PHOENIX E6345711772 Terminals - Cross-connector - Cross-connectors =A02X01/7D
-XDV.1 BRIDGE EB 3-8 0202141 PHOENIX 1000049259 Terminals - Cross-connector - Cross-connectors =A02X01/7D

B B

C C

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A06
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812213 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Alternator G4 DCC & Page Pages
ABB s.r.o.
PART LIST X20 39
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8297/1748

A A

B B

-QAB1
VD4G-50/25 p210
17.5 kV
M 2000 A
50 kA

-BCT1,-BCT2,-BCT3
TPU 54.43
P1 150/1/1 A at 40 °C
-PFV1
Core 2: 5P20, 10 VA
C CPI PLUS/R C
Core 1: 0.2Fs5, 10 VA
VALID FOR PANELS:
3 P2
POS. DESIGN. NAME
7 00BBB02GS103 Station Transformer 2

D D

-FA11,
-FA21,
-FA31 -QCE1
MWD 16 ST-UG

-BCN1
E RKU 2918 E
Under cubicle (accessory)
60/1 A; 1FS10, 1,25VA
inner diameter d=180mm

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
SINGLE LINE SCHEME &EFA A01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8298/1748

SHEET INDEX
A PAGE PAGE NAME REVISION A
=A07+LV/A01 SINGLE LINE SCHEME AM
=A07+LV/A02 SHEET INDEX AM
=A07+LV/G01 DC SUPPLY CIRCUITS DC 110 V AM
=A07+LV/G02 AC SUPPLY CIRCUITS AM
=A07+LV/M01 VD4 INTERNAL WIRING AM
=A07+LV/M02 EARTHING SWITCH AM
=A07+LV/M03 CONTROL CIRCUITS AM
B =A07+LV/M04 TRIPPING CIRCUITS AM B
=A07+LV/M05 SIGNAL CIRCUITS AM
=A07+LV/P01 XDI2 SIGNALS AM
=A07+LV/P02 XDI2 SIGNALS AM
=A07+LV/Q01 MAN CONTROL SYSTEM AM
=A07+LV/Q02 MAN CONTROL SYSTEM AM
=A07+LV/S01 CURRENT TRANSFORMER CORE 2 AM
=A07+LV/S02 CURRENT TRANSFORMER CORE 1 AM
C =A07+LV/S03 GFCT AM C
=A07+LV/S05 VOLTAGE METERING AM
=A07+LV/V01 PANEL LAYOUT AM
=A07+LV/W01 LV COMP. DOOR LAYOUT AM
=A07+LV/X01 SPARE TERMINALS AM
=A07+LV/X02 ES SPARE CONTACTS AM
=A07+LV/X03 CB SPARE CONTACTS AM
=A07+LV/X04 MCB SPARE CONTACTS AM
D =A07+LV/X05 TERMINALS =A07+LV-XDA AM D
=A07+LV/X06 TERMINALS =A07+LV-XDC AM
=A07+LV/X07 TERMINALS =A07+LV-XDC AM
=A07+LV/X08 TERMINALS =A07+LV-XDC AM
=A07+LV/X09 TERMINALS =A07+LV-XDI1 AM
=A07+LV/X10 TERMINALS =A07+LV-XDI2 AM
=A07+LV/X11 TERMINALS =A07+LV-XDV AM
=A07+LV/X12 TERMINALS =A07+LV-XDX AM
E =A07+LV/X13 TERMINALS =A07+LV-XDX AM E
=A07+LV/X14 TERMINALS =A07+LV-XE AM
=A07+LV/X15 TERMINALS =A07+LVR-XDE1 AM
=A07+LV/X16 TERMINALS =A07+LVR-XDH AM
=A07+LV/X17 TERMINALS =A07+LVR-XDH1 AM
=A07+LV/X18 PART LIST AM
=A07+LV/X19 PART LIST AM

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
SHEET INDEX A02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8299/1748

SPRING
=A08
CONTROL CHARGER
CIRCUIT CIRCUIT SIGNAL CIRCUIT
-XDI1 1

A A
-XDI1 2

-XDI1 3

-XDI1 4

-XDI1 5

-XDI1 6

B B

-XDI1 1 2 3 4 5 6

C 3 1 13 21 3 1 13 21 3 1 13 21 C
-FCM2.1 -FCM3.1 -FCM4.1
S202-C2 4 2 14 22 S202-K1 4 2 14 22 S202-C1 4 2 14 22
Q01/4C

X04/1C

X04/4D

X04/1C

X04/4C

X04/2C
M01/1B
D +PLG -XDB 25
D
-QAB
-BGS1

-MAS

M
CON+ SIG+
M03/1A M05/1A
CON- -XDB 35 SIG-
M03/1F M01/1D M05/1F
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
DC SUPPLY CIRCUITS DC 110 V &EFS G01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8300/1748

=A08
LIGHTING
CIRCUIT SPARE
-XDI1 7

A A
-XDI1 8

-XDI1 9

-XDI1 10

B B

-XDI1 7 8 9 10

C 1 3N 13 21 C
-FCM5.1
S201-C2 NA 2 4N 14 22
X04/4C

X04/2C

D D
+LVR-XDH 1 11 2 12

CAUTION: WIRES OF
1
LIGHTING AND HEATING
CANNOT BE CHANGED. THEY
ARE PART OF THE DEVICE
+LCT-EA1 AND CANNOT BE
RS-ABB-255/150 DISMANTLED.
2
E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
AC SUPPLY CIRCUITS &EFS G02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8301/1748

CB OPEN, TRUCK IN SERVICE POSITION, SPRING NOT CHARGED


VD4G-50
DOC. NO: 1VCD400155

A A
-XE 11 12

1011

1012
M04/1D

M04/3D

M04/3D

M04/4D

M05/3B

M04/6B
G01/4D

M03/5E

M03/2E

M03/5E

M03/4E
Q02/4C

Q02/2C
X03/6C

X03/6C

X03/3C

X03/2C

X03/5C

X03/3C

X03/8C

X03/4C

X03/5C

X03/4C

X03/7C

X03/7C
+PLG
-QAB
-XDB 24 26 25 CB DISCHARGED
45 4 5 28 7 3 43 31 41 23 8 6 29 11 9 27 32 47 1 40 52 49 10 57 55

CB CHARGED

CB CLOSED
CB OPEN
B B
-BGS2

-BGS1

4 2

-BGT2
0 I
3 1 13 23 33 43 53

-BGB1
-MAS
19 9 11 7 3 5 1 15 13 21 27 23 25 31 14 24 34 44 54
M P

-BGT1
20 10 12 8 4 6 2 16 14 22 28 24 26 32

POSITION
SERVICE
13 23 33 43 53

14 24 34 44 54
C E C

POSITION
-RLE2 A -RLE1 -MBC -MBU -MBO1

TEST
34 36 35 46 20 14 15 38 17 13 2 44 30 33 18 39 22 21 19 37 42 48 50 51 53 54 16 58 56
X03/6D

X03/6D

G01/4E

M03/5E

M03/4E

M03/2E

X03/3D

Q02/4D

Q02/2D

X03/2D

M04/1E

M04/3E

M04/4E

X03/5D

X03/8D

M05/3C

M05/3C

X03/4D

X03/5D

X03/4D

M05/4C

M05/4C

M04/6C

M04/6C

X03/3D

X03/7D

X03/7D
D D

DESIGNAT. FIGURE DESCRIPTION DESIGNAT. FIGURE DESCRIPTION


-MAS FIG.1 MOTOR FOR SPRING CHARGING -BGS2 FIG.26 SIGNALLING - SPRING CHAR./DISCHAR.
-BGS1 FIG.1 CONTACT FOR CHARGER MECHANISM
-MBC FIG.2 CLOSING RELEASE
-RLE1 FIG.3 ELECTROMECHANICAL LOCK CB CLOSING
-MBU FIG.5 UNDERVOLTAGE RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
E -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT E
-MBO1 FIG.7 FIRST OPENING RELEASE -BGB1 FIG.32 AUXILIARY SWITCH CB SHAFT
-RLE2 FIG.8 ELECTROMECHANICAL LOCK CB TRUCK -BGT1 FIG.51 CB TRUCK IN SERVICE (CONNECTED) POSITION
-BGT2 FIG.51 CB TRUCK IN TEST (ISOLATED) POSITION

-XE GROUND TERMINALS -XDB 58-POLE PLUG FOR AUXILIARY CIRCUITS


END SWITCH - PLUG NOT INSERTED

+LCB 20 22 24 26 28
M03/7D

X03/1C

X03/1C

X03/2C
P02/4E

-BGC2
21 23 25 27 29

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
VD4 INTERNAL WIRING &EFS M01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8302/1748

+ES
-QCE1
L1 L2 L3 ST-UG

A A

B B

-XE 1

M05/2B

Q01/3C
X02/2D

X02/3D

X02/4D
40 42 44 46 48
-BGE2
41 43 45 47 49

M03/7E
G
-RLE3
C H C

M05/2B

Q01/1C
X02/5D

X02/6D

X02/7D
+CAB
20 22 24 26 28
-BGE3
-FA11 -FA21 -FA31
SURGE ARRESTER SURGE ARRESTER SURGE ARRESTER 21 23 25 27 29
MWD 16 MWD 16 MWD 16

D D

E E
EARTHING SWITCH OPEN AND
CRANK NOT INSERTED
DESIGNATION DESCRIPTION

-BGE2 EARTHING SWITCH CLOSED

-BGE3 EARTHING SWITCH OPEN AND CRANK NOT INSERTED

-RLE3 EARTHING SWITCH BLOCKING COIL

-FA1,2,3 SURGE ARRESTER


F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
EARTHING SWITCH &EFS M02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8303/1748

CB CLOSING CB CB ES BLOCKING
RELEASE ELECTROMECH. ELECTROMECH. COIL
LOCK CLOSING LOCK TRUCK

LOCAL REMOTE
A A

CON+ CON+
G01/2E -XDX 201 202 203 204 205 M04/1A

SFS1 1
4 3 M03/3B
4 3 1
LOCAL REMOTE +LVD 5 6 M04/3B
+LVD-PFV1
-SFS1 7 8 M04/4B
S02/5E 2
2 9 10 3
T0-3-8222/E
FS943 11 12 Q02/7C
CONTACTS LOC. REM.
B 1-2 -XDC 1 -XDC 3 -XDC 5 -XDC 9 B
3-4
5-6 -XDX 211 212

00BHT01GS103-YB01

00BHT01GS108-YB15
7-8

INTERLOCKING

INTERLOCKING
FOR EXTERNAL

FOR EXTERNAL
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
9 - 10
11 - 12

-XDC 2 -XDC 4 -XDC 6 -XDC 10


C C

13
-KFA9
P02/2E 14 -XDX 219 220

-XDX 213 214


D 20 43 D
+LCB
13 -KFA11
+LVD -BGC2 M04/6E
21 44
-SFC1 M01/1F
14
MP1-11C

M01/8B M01/8B
-XDX 215 216
+PLG -XDB 10 49 -XDX 217 218 221 222

-QAB
43 43
M01/3B M01/2B +LVR
+PLG -XDB -BGT1 -BGT2 +PLG -XDB 31
4 45 -XDE1
-QAB 44 44 -QAB 1 5
-RAD1 -RAD1
M03/8E +ES M03/6E
E -MBC -RLE1 -RLE2 G E

-RLE3
-QCE1
M02/5C
H

-XDB 20 2 6
-XDB 14 M01/2D -XDB 46 +LVR
32
M01/3D M01/2D -XDE1

-XDX 230 231 232 233 234


CON- CON-
G01/3E M04/1F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
CONTROL CIRCUITS &EFS M03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8304/1748

CB CB FIRST CB OPEN ITH LIMITER TRIP CB IN TEST CB IN SERVICE ITH LIMITER IN


UNDERVOLTAGE OPENING POSITION POSITION CAB/CB COMP
RELEASE RELEASE

A A

CON+
M03/8A -XDX 206 207 208 209 210

7
+LVD-SFS1
M03/2B 8
+LVR +LVR
2 1
-XDH1 -XDH1
-XDC 11 -XDC 13 M01/7B
5
+PLG -XDB

ITH_2

ITH_1
52
B +LVD-SFS1 -QAB B
00BHT01GS103-YB32

00BHT01GS103-YB02
M03/2B 6
MAN CONTROL

MAN CONTROL
SYSTEM (CCP)

SYSTEM (CCP)
-BGT2 23 -BGT1 23

-BGA1

-BGA3
12 14 BK BK

+CAB
+CB
-KFA10 XDI2:16
13 P02/6E 11 24 24 GY BN GY BN
+LVD P02/5C
-SFO1

ITH_10
14

ITH_6

ITH_9

ITH_5
MCBH-20 -XDB 53 54
M01/7D M01/7D
+LVR +LVR
8 5 7 4
-XDC 12 -XDC 14 -XDH1 -XDH1

C C
-XDX 223 224 225 226 227

-XDX 228 229

M01/5B M01/5B M01/5B


+PLG -XDB 31 41 +PLG -XDB 23 -RAR1 D C B A
D -QAB -QAB D
3
M01/4B
-BGB1 5

1K2
4K7
22K
5K6
+PLG -XDB 43
-QAB 4 -BGB1
6
-MBU -MBO1
E F G H
-XDB 33 P02/7D
M01/5D XDI2:18
-XDB 30 14
-KFA13 11
-XDB 44 M01/5D
A1 A1 A1 12
CR-U110DC3L
M01/4D -KFA11 -KFA12 24
KC6-40E KC6-40E 21
E 110-125VDC A2 110-125VDC A2 A2 22 E
34
31
32
13 14 Q02/5C 13 14 Q02/6C
14
23 24 P02/3E 23 24 11 P02/5E
33 34 33 34 12
43 44 M03/8D 43 44 24
21 X01/1C
22

-XDX 235 236 237 238


CON-
M03/8F

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
TRIPPING CIRCUITS &EFS M04 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8305/1748

ES OPEN AND ES CLOSED CB OPEN CB CLOSED CB IN TEST CB IN SERVICE LAMP TEST


CRANK NOT POSITION POSITION
INSERTED

A A

SIG+
G01/6E -XDX 301 302 303 304

+LVR +LVR
27 17
-XDE1 -XDE1
M01/6B
+PLG -XDB 11
-QAB
B B
+ES 26 +ES 46 21 27 13 13
-BGE3

-BGE2
-QCE1 -QCE1 -BGB1 -BGT2 -BGT1
M02/7D M02/7C
27 47 22 28 14 14 KUVAG+
S02/6F
-XDB 22 21 50 51
M01/6D M01/6D M01/7D M01/7D
+LVR +LVR
28 18
-XDE1 -XDE1

C C

+LVD 13
-SFT1
MCBH-10
-XDX 305 306 307 308
LAMP TEST 14

D +LVD +LVD +LVD D


-PFX1 -PFX2 -PFX3
SUS-01-TT R5/G4 SUS-01-TT-Q R5/G4 SUS-01-TT R5/G4
DC110V P30 R G DC110V P30 R G DC110V P30 R G

T T T T T T

S02/6F
- - - - - - KUVAG-

E E

-XDX 309 310


SIG-
G01/6E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
SIGNAL CIRCUITS &EFS M05 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8306/1748

ALTERNATOR G5 ALTERNATOR G6 STEP-UP ALTERNATOR G7 SPARE =A08


OFF OFF TRANSFORMER 2 OFF
OFF
-XDI2 1

A A
-XDI2 2

-XDI2 3

-XDI2 4

-XDI2 5

-XDI2 6

-XDI2 7

B B
-XDI2 8

-XDI2 9

-XDI2 10

C C

-XDI2 1 2 3 4 5 6 7 8 9 10

D D

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8307/1748

CB TRUCK INTERLOCKING EARTHING TRUCK INTERLOCKING ITH LIMITER SPARE =A08


TRIPPING

-XDI2 11

A A
-XDI2 12

-XDI2 13

-XDI2 14

-XDI2 15

-XDI2 16

-XDI2 17

B B
-XDI2 18

-XDI2 19

-XDI2 20

XDI2:16
M04/8B
C C

-XDI2 11 12 13 14 15 16 17 18 19 20

XDI2:18
M04/8E

+LVR
D -XDX 325 326
-XDH1
3 -XDX 329 D

ITH_3
14
-KFA10 11
24 12

-BGA2
23 BK 12 14 CR-U110DC3L A2
+LCB

+BB
24
A1 -KFA11 -KFA13 21
-KFA9 M04/6E -BGC2 M04/7E
24 25 GY BN 11 A1 22
KC6-40E M01/1F 34
A2
110-125VDC 31
ITH_11

ITH_7
32
14
11 M04/5B
+LVR 12
E 13 14 M03/5D
-XDX 327 328 9 6 -XDX 330 331 E
23 24 -XDH1
33 34
43 44

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
XDI2 SIGNALS &ELU P02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8308/1748

ES OPEN AND ES CLOSED CONTROL VOLTAGE OPEN DELTA


CRANK NOT 00BHT01GS108-XB01 VOLTAGE MEASURING VOLTAGE
INSERTED MCB OFF MCB OFF MCB OFF
A 00BHT01GS108-XB02 00BHT01GW101-XM84 00BBB01CE011-XM85 00BBB01CE011D-XM85 A

B B

+LVR +LVR
29 19
C -XDE1 -XDE1 C

+ES 28 +ES 48 13 13 13
-BGE3

-BGE2

-QCE1 -QCE1 -FCM2.1 -FCM12.1 -FCM14.1


M02/7D M02/7C G01/2C S05/2B S05/7C
29 49 14 14 14

+LVR +LVR
30 20
D -XDE1 -XDE1 D

-XDC 351 352 353 354 355 356 357 358 359 360

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8309/1748

CB CLOSED CB OPEN CB IN TEST CB IN SERVICE STATION


00BHT01GS103-XB01 00BHT01GS103-XB02 POSITION POSITION TRANSFORMER CB
00BHT01GS103-XB41 00BHT01GS103-XB40 REMOTE
A COMMAND MODE A
00BHT01GS103-XB43

B B

M01/3B M01/3B
C +PLG -XDB 7 +PLG -XDB 28 C
-QAB -QAB
11 9
-BGB1 -BGB1 13 13 11

12 10 -KFA11 -KFA12 +LVD-SFS1


M04/6E 14 M04/6E 14 M03/2B 12

-XDB 17 -XDB 38
M01/3D M01/3D

D D

-XDC 371 372 373 374 375 376 377 378 379

=
E + E

MAN
CONTROL
SYSTEM
(CCP)

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
MAN CONTROL SYSTEM &EFS Q02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8310/1748

L1 L2 L3
A = A
+ PROTECTION CT
00BHT01CE001A/B/C
1 -XDA 17
+CT -XE
P1 P1 P1

DO NOT REMOVE THESE JUMPERS


UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED
-XDA 11

2S1
B TPU 54.43 -BCT1 B
150/1A 2S2
Core 2: 5P20, 10VA
-XDA 12

-XDA 13

2S1
-BCT2
C 2S2 C
-XDA 14
MAN
CONTROL
SYSTEM
(CCP)
-XDA 15

2S1
-BCT3
2S2
D D
-XDA 16

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 2 &EFS S01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8311/1748

L1 L2 L3
A = A
+ CURRENT MEASURING
00BHT01CE003A/B/C
2 -XDA 7
+CT -XE DO NOT REMOVE THESE JUMPERS
UNTIL EXTERNAL DEVICES IN MAN CONTROL SYSTEM ARE SECURELY CONNECTED

+LVD
-PGA1
-XDA 1 17 18 -XDA 18
A
1S1 FB96-1
B TPU 53.43 -BCT1 150/1A B
150/1A 1S2 0-150/300A
Core 1: 0.5Fs5, 10VA RED LINE AT 121 A
-XDA 2 -XDA 19

+LVD
-PGA2
-XDA 3 17 18 -XDA 20
A
1S1 FB96-1
-BCT2 150/1A
C TPU 53.43 1S2 0-150/300A C
-XDA 4
RED LINE AT 121 A
-XDA 21
MAN
CONTROL
+LVD
SYSTEM
-PGA3 (CCP)
-XDA 5 17 18 -XDA 22
A
1S1 FB96-1
-BCT3 150/1A
TPU 53.43 1S2 0-150/300A
RED LINE AT 121 A
D D
-XDA 6 -XDA 23

-BAD1
Ck
-BAD2
Ck
21
-BAD3 +LVD
Ck
-WE

E E
+LVD GND L3 GND L2 GND L1 GND
1
-PFV1 2 M03/7B
CPI PLUS/R 3-52kV NVI/PSI 3
Uaux.
24-230V AC/DC 4
L1 L2 L3 N 5
P2 P2 P2 6
7 8

KUVAG+ KUVAG-
M05/8B M05/8E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
CURRENT TRANSFORMER CORE 1 &EFS S02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8312/1748

A = A
+ GROUND FAULT
CURRENT
00BHT01CE021

L1 L2 L3

B B
+CAB

C C
MAN
CONTROL
SYSTEM
(CCP)

P1 S1
+ACS
D -BCN1 P2 S2 D
RKU 2918
Under cubicle (accessory)
60/1 A
1FS10, 1,25VA, VA

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
GFCT &EFS S03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8313/1748

=A10 =A10

A A

=A10S07/2D =L1-A10
=A10S07/3D =L2-A10 =A10S07/5E =dn-A10
=A10S07/3E =L3-A10 =A10S07/5D =da-A10

-XDV 1 2 3

-XDV 41

B B
+TOP-RAA1
1 3 5 13 21 1 3 5 13 21 1 2
-FCM12.1 -FCM11.1 TR318 27R/J
S203-Z2 14 22 S203-Z1 14 22 500W L=2.5m
2 4 6 2 4 6
VT - Y WINDING VT - Y WINDING
Q01/6C

X04/3C

X04/5C

X04/3C
1 13 21
-FCM14.1
S201-Z4 2 14 22
VT - OPEN DELTA

Q01/7C

X04/4C
=A10

=A10S07/3E
C C
=N-A10 -XDV 42 43 48 49 50
-XE 5
+LVD-SFV1
-XDV 51 52 53 54 L1 L3 L2 T0-2-8004/E

SFS 7
OPEN DELTA
MEASURING MV
0 1 3 5
L1 - L2 PANEL
2 4 6 00BB101CE011D
8
L2 - L3
MAN CONTROL SYSTEM
L3 - L1 (CCP)
D FS1410760 D
VOLTAGE
MEASURING MV CONTACTS 0 L1 - L2 L2 - L3 L3 - L1
PANEL 1-2
00BBB01CE011A/B/C 3-4
5-6
MAN CONTROL SYSTEM 7-8
(CCP)
+LVD-PGV1
17 18
V
E FB96-1 E
15000/110V
0-20kV
RED LINE AT 15 kV

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
VOLTAGE METERING &EFS S05 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8314/1748

=A01+LV =A01
+LCT
DEVICE TAG TEXT DT TYPE QTY
A -FCM2.1 CONTROL CIRCUIT -XDA TERMINAL URTK/S 0311087 20 A
-XDC TERMINAL UT 4 3044102 91
-EA1 -FCM3.1 SPRING CHARGER CIRCUIT
-XDI1 TERMINAL UT 4-QUATTRO 3044571 10
-FCM4.1 SIGNAL CIRCUIT
-XDI2 TERMINAL UT 4-QUATTRO 3044571 20
-RAR1 TCS MODUL -XDV TERMINAL URTK/S 0311087 13
-KFA9 BB ES OPEN -XDX TERMINAL UT 4 3044102 55
+LV +LVR -XE TERMINAL USLKG 5 0441504 7
-KFA11 CB IN TEST POSITION
-XDE1 TERMINAL UTTB 2,5 3044636 22

-RAR1
B -KFA12 CB IN SERVICE POSITION B
-XDH TERMINAL UTTB 2,5 3044636 4
-RAD1
-FCM11.1 VT - Y WINDING -XDH1 TERMINAL UT 4-MT 3046139 9
-KFA10
-KFA13

11

12
9
FA

FA

FA
-FCM12.1 VT - Y WINDING

-K

-K

-K
-XDH
-FCM14.1 VT - OPEN DELTA
-FCM2.1
-FCM3.1
-FCM4.1
-FCM5.1

1
1.1

2.1

-FCM14.1

DE
-XE

-X
1

1
-FCM

-FCM
-FCM5.1 LIGHTING CIRCUIT

1
DH
-X
-KFA10 ITH LIMITER TRIP

-KFA13 ITH LIMITER IN CAB./CB COMP.


C C
-RAD1 DIODES
=A02+LCT
DEVICE TAG TEXT
-XDI1 -XDI2 -XDV
-EA1 LV LIGHTING

-XDX -XDA

-XDC
D D

E E

+LVR-XDE1, -XDH
11,12,13...

21,22,23...

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
PANEL LAYOUT &ELU V01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8315/1748

=A01+LVD
A A
DEVICE TAG TEXT
-PGA1 L1

-PGA2 L2

-PGA3 L3

-PFV1 VOLTAGE INDICATOR

-PFX1 E/S OPEN / CLOSED

B -PFX2 B

A07 Station -PFX3


Transformer 2
-SFS1 LOCAL - REMOTE SWITCH

-SFT1 LAMP TEST

705 mm
-PGA1 -PGA2 -PGA3

-SFO1 CB OPEN

-SFC1 CB CLOSE

-PGV1
-SFV1 VOLTMETER SELECTOR SWITCH
C -PFX3
C
-PFV1
-PGV1 VOLTMETER
-SFO1 -PFX2 -SFC1

-SFV1 -SFS1 -SFT1 -PFX1

D D

800 mm

E E

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
LV COMP. DOOR LAYOUT &ELU W01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8316/1748

ITH LIMITER FLAP IN CAB./CB. COMP.


- TRIP TO LV SWITCHGEAR SPARE WIRES INSIDE LV COMPARTMENT

A +LVD A
-X _

+LVR -WE
=EXT 1 S02/6E PE1 PE2 PE3 PE4 PE5
-XE 3 -XE 6 -WE2 GND

-XE 1 -XE 2 -XE 3 -XE 4 -XE 5 -XE 6 -XE 11 -XE 12


-XDC 509

5
B B

-XDC 7 8 391 392 393 394 395 396


+LVR
201 202 203 204 205
-WE1
GND

C C
22 24
-KFA13
M04/7E 21

D D

-XDC 510

E E

-X _

=EXT

NOTE: ALL UNUSED WIRES AND NOT CONNECTED


WIRES FROM SPARE CONTACTS OF ALL DEVICES ARE
RECOMMENDED TO BE EARTHED AFTER SWITCHGEAR
IS INSTALLED ON SITE.
F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
SPARE TERMINALS &EFS X01 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8317/1748

ES CLOSED ES CLOSED ES CLOSED ES OPEN AND ES OPEN AND ES OPEN AND


CRANK NOT CRANK NOT CRANK NOT
INSERTED INSERTED INSERTED

A A

-XDC 401 403 405 407 409 411

B B

C C
+LVR +LVR +LVR +LVR +LVR +LVR
11 13 15 21 23 25
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

+ES 40 +ES 42 +ES 44 +ES 20 +ES 22 +ES 24


-BGE2

-BGE2

-BGE2

-BGE3

-BGE3

-BGE3
-QCE1 -QCE1 -QCE1 -QCE1 -QCE1 -QCE1
M02/7C M02/7C M02/7C M02/7D M02/7D M02/7D
41 43 45 21 23 25

D D
+LVR +LVR +LVR +LVR +LVR +LVR
12 14 16 22 24 26
-XDE1 -XDE1 -XDE1 -XDE1 -XDE1 -XDE1

E E

-XDC 402 404 406 408 410 412

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
ES SPARE CONTACTS &EFS X02 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8318/1748

PLUG OUT PLUG OUT CB CLOSED CB CLOSED CB CLOSED AND CB CLOSED CB CLOSED CB OPEN CB OPEN CB SPRING CB SPRING CB IN TEST CB IN SERVICE CB OPEN OR IN
IN SERVICE CHARGED DISCHARGED POSITION POSITION TEST POSITION
POSITION

A A

-XDC 421 423 425 427 429 431 433 435 437 439 441 443 445 447 449

B B

C M01/3B M01/3B M01/5B M01/6B M01/6B M01/5B M01/6B M01/1B M01/1B M01/8B M01/8B M01/5B
C
+PLG -XDB 3+PLG -XDB 5 +PLG -XDB 6 +PLG -XDB 9 +PLG -XDB 32 +PLG -XDB 8 +PLG -XDB 27 +PLG -XDB +PLG
24 -XDB 26 +PLG -XDB 57 +PLG -XDB 55 +PLG -XDB 29
-QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB -QAB
15
22 26 28 7 19 -BGB1 23 31 1 25 4 2 53 53 13 33
+LCB +LCB +LCB
-BGB1 -BGB1 16 -BGB1 -BGB1 -BGB1 -BGB1 -BGS2 -BGS2 -BGT2 -BGT1 -BGB1 -BGT2
-BGC2 -BGC2 -BGC2 33
23 27 29 8 20 24 32 2 26 3 1 54 54 14 34
M01/1F M01/2F M01/2F
-BGT1
34
-XDB 13 -XDB 15 -XDB 19 -XDB 42 -XDB 18 -XDB 37 -XDB 34 -XDB 36 -XDB 58 -XDB 56 -XDB 39
M01/3D M01/3D -XDB 16 M01/6D M01/6D M01/5D M01/6D M01/1D M01/1D M01/8D M01/8D M01/5D
M01/8D

D D

E E

-XDC 422 424 426 428 430 432 434 436 438 440 442 444 446 448 450

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
CB SPARE CONTACTS &EFS X03 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved. 1 2 3 4 5 6 7 8319/1748

SUPPLY MCB's MEASURING CONTROL MEASURING


GROUP FAULT MCB's VOLTAGE VOLTAGE
GROUP FAULT MCB OFF MCB OFF

A A

-XDC 501 503 505 507

B B

13

C -FCM5.1 C
G02/2C 14

13
21 21 21 21 21 21 21 13
-FCM4.1
-FCM2.1 -FCM3.1 -FCM4.1 -FCM5.1 -FCM11.1 -FCM12.1 -FCM14.1 G01/6C
-FCM11.1
14
G01/2C 22 G01/4C 22 G01/6C 22 G02/2C 22 S05/3B 22 S05/2B 22 S05/7C 22 S05/3B 14

13
-FCM3.1
G01/4C 14

D D

E E

-XDC 502 504 506 508

F F
Drawn by Checked by Released by Project number 1000047172 Customer project number Project name Installation =
BERCES Erik HAVELKA Libor BRAUN Jiri MAN PHNOM PENH 5304532 A07
245687993 Customer document number
Revision Date Name Remark Document number 1VL3812208
1VL3812214 Customer Place of installation +
AM 17.12.2019 TURKOVIC Date 09.08.2019 Page description LV
Station Transformer 2 DCC & Page Pages
ABB s.r.o.
MCB SPARE CONTACTS &EFS X04 38
EPDS Brno
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDA
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
17 +LVD-PGA1 BK
+CT-BCT1 1S1 S02/4B
BK

HAVELKA Libor
2

Remark
19 -XDA BK
+CT-BCT1 1S2 S02/4B
BK

3
17 +LVD-PGA2 BK
+CT-BCT2 1S1 S02/4C
BK

Released by
4

BRAUN Jiri
21 -XDA +CT-BCT2 1S2 S02/4C
2

BK BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
17 +LVD-PGA3 BK
+CT-BCT3 1S1 S02/4D
BK

6
23 -XDA +CT-BCT3 1S2 S02/4D

Date
BK BK

20 PCS
7
-XE 2:1 S02/4A
GNYE

Project number

Document number
11
+CT-BCT1 2S1 S01/4B
BK
12
+CT-BCT1 2S2 S01/4B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812214
13

+CT-BCT2 2S1 S01/4C


BK

TERMINAL URTK/S 0311087


14

+CT-BCT2 2S2 S01/4C


BK

Customer
15

+CT-BCT3 2S1 S01/4D


BK
16

+CT-BCT3 2S2 S01/4D


BK

Customer project number


Customer document number
17

-XE 1:1 S01/4A


GNYE
4

18

+LVD-PGA1 18 S02/5B
BK
19

-XDA 2 S02/5B
BK
20

+LVD-PGA2 18 S02/5C
BK
21

-XDA 4 S02/5C
BK
22

+LVD-PGA3 18 S02/5D
BK
5

23

-XDA 6 S02/5D
BK

Project name

Page description
6

Station Transformer 2
TERMINALS =A07+LV-XDA
MAN PHNOM PENH 5304532
7

DCC &
Installation =

Place of installation +

Page
LV

X05
A07
8320/1748

Pages
38
F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by
1

TURKOVIC
+LVD-SFS1 3 M03/3B
BK

HAVELKA Libor
2

Remark
-XDX 216 M03/3C
BK

3
-XDX 202 M03/4B
BK

Released by
4

BRAUN Jiri
+PLG-QAB-XDB 10 M03/4C
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
5
-XDX 203 M03/5B
BK

6
-KFA9 13 M03/5C

Date
BK

91 PCS
7
X01/3B

Project number

Document number
8
X01/3B
9
+LVD-PFV1 2 M03/7B

ABB s.r.o.
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812214
10

-XDX 219 M03/7C

TERMINAL UT 4 3044102
BK
11

-XDX 206 M04/1B


BK

Customer
12

-XDX 223 M04/1C


BK
13

+LVD-SFS1 8 M04/4B
BK

Customer project number


Customer document number
14

-XDX 226 M04/4C


BK
4

+LVR-XDE1 30 Q01/1D
351

BK

+LVR-XDE1 29 Q01/2D
352

BK

+LVR-XDE1 20 Q01/3D
353

BK

+LVR-XDE1 19 Q01/4D
354

BK

-FCM2.1 14 Q01/4D
355

BK
5

-FCM2.1 13 Q01/5D
356

BK

-FCM12.1 14 Q01/6D
357

BK

-FCM12.1 13 Q01/6D

Project name
358

BK

Page description
-FCM14.1 14 Q01/7D
359

BK

-FCM14.1 13 Q01/8D
360

BK
6

+PLG-QAB-XDB 17 Q02/2D
371

BK

+PLG-QAB-XDB 7 Q02/3D
372

BK
Station Transformer 2
TERMINALS =A07+LV-XDC

+PLG-QAB-XDB 38 Q02/4D
MAN PHNOM PENH 5304532
373

BK

+PLG-QAB-XDB 28 Q02/4D
374

BK

-KFA11 14 Q02/5D
375

BK
7

-KFA12 14 Q02/6D
376

BK
DCC &

-KFA11 13 Q02/6D
377

BK
Installation =

+LVD-SFS1 12 Q02/7D
378

BK
Place of installation +

+LVD-SFS1 11 Q02/7D
379

BK
Page

X01/3B
391

LV

X06
A07

X01/3B
392

X01/4B
8321/1748

393

Pages
38

X01/4B
394

F
E
B
A

D
© Copyright 2019 ABB. All rights reserved.

F
E
B

C
A

AM
Drawn by
TERMINALS

Revision Date
BERCES Erik
+LV-XDC
1

17.12.2019
DEVICE DEVICE POTENTIAL/ POTENTIAL/ DEVICE DEVICE
PIN COLOR COLOR PIN PAGE

Name
DESIGNATION DESIGNATION

Checked by

TURKOVIC
X01/4B

395

HAVELKA Libor
Remark
X01/4B

396
+LVR-XDE1 11 X02/2B

401
BK

Released by
BRAUN Jiri
+LVR-XDE1 12 X02/2E

402
2

BK

TERMINAL TYPE:
TOTAL TERMINALS COUNT:
+LVR-XDE1 13 X02/3B

403
BK

+LVR-XDE1 14 X02/3E

Date
404
BK

91 PCS
+LVR-XDE1 15 X02/4B

405
BK

Project number

Document number
+LVR-XDE1 16 X02/4E
406
BK

+LVR-XDE1 21 X02/5B

ABB s.r.o.
407
BK

EPDS Brno
3

245687993

09.08.2019
1000047172

1VL3812214
+LVR-XDE1 22 X02/5E

TERMINAL UT 4 3044102
408

BK

+LVR-XDE1 23 X02/6B
409

BK

Customer
+LVR-XDE1 24 X02/6E
410

BK

+LVR-XDE1 25 X02/7B
411

BK

Customer project number


Customer document number
+LVR-XDE1 26 X02/7E
412

BK
4

+LCB-BGC2 22 X03/1B
421

BK

+LCB-BGC2 23 X03/1E
422

BK

+LCB-BGC2 26 X03/1B
423

BK

+LCB-BGC2 27 X03/1E
424

BK

+LCB-BGC2 28 X03/2B
425

BK
5

+LCB-BGC2 29 X03/2E
426

BK

+PLG-QAB-XDB 3 X03/2B
427

BK

+PLG-QAB-XDB 13 X03/2E

Project name