Professional Documents
Culture Documents
Project Management - Chapter 6
Project Management - Chapter 6
Bharti Consulting
Project Schedule Management
by
Sunil Agrawala,PMP
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Some Philosophies
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
1
Innovation Throughout
Purpose of Session
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
•The key activities that happens as part of Project Time Management are:
•Identifying the list of project activities
•Estimating the time required to complete each of the identified activities
•Sequencing the activities to occur one after the other in a logical manner.
•Developing and finalizing the schedule
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
2
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
• Trends:
Iterative scheduling with a back log: Performs work incrementally when priorities
tend to change frequently. Work is documented in user stories and
prioritized/reprioritized as appropriate.
On-demand scheduling: Work is pulled from a backlog when resources become
available. Is a pull form of planning that works well in balancing work demand
against available resources.
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
3
Innovation Throughout
• The use of agile methods is growing but many PMs still have little or no
personal experience
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
6.2 6.3
Define Sequence
Activities Activities 6.5 6.6
Develop Control
6.4 Schedule Schedule
Estimate
Activity
Duration
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
4
Innovation Throughout
EEF Meetings
OPA
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Define Activities
•Define Activities is the process of identifying the specific actions to be
performed to produce the project deliverables (Work Packages).
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
5
Innovation Throughout
•Expert judgment
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Sequence Activities
•Sequence Activities is the process of identifying and documenting
relationship among the project activities.
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
6
Innovation Throughout
Coding Unit
Module-1 Test-1
Coding Unit
Module-3 Test-3
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
7
Innovation Throughout
Innovation Throughout
8
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
9
Innovation Throughout
Estimation Techniques
One time Estimate: When estimating using a one time estimate, one estimate per activity is
received. For example, the person doing the estimate says that the activity would take 2 weeks.
In real life, people make their best guess and just double the estimate to take care of any
uncertainties. Adding this extra is also called “Padding”
This techniques should be used to only get the high level estimate.
Parametric Estimating: This uses a mathematical model to calculate projected times for an
activity based on historical records from previous projects and other information.
Heuristics: A heuristic means rule of thumb. An example of heuristic is the 80/20 rule that in
quality suggests that 80 percent of quality problems are caused by 20 percent of potential sources
of problem.
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
10
Innovation Throughout
Bottom-up estimating
Meetings
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Develop Schedule
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
11
Innovation Throughout
Develop Schedule
Inputs Tools Outputs
Project management plan Schedule network analysis Schedule baseline
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
12
Innovation Throughout
PERT Example
Activity O M P Expected Standard Activity Range of
or PERT Deviation Variance the
Duration Estimate
A 16 26 48 28 5.5 30.25 28,+/-5.5
B 40 59 88 60.6 8 64 60.6,+/-8
C 40 45 49 44.83 1.5 2.25 44.83,+/-
1.5
D 30 38 42 37.33 2 4 37.33,+/-2
Project 170.76 10 100.5
If A, B, C, D are the only activities in the Project, what's the Project Duration?
The Answer is 170.76 with a standard deviation of 10, so the minimum project duration
is 160.76 and maximum duration is 180.76
The Project standard deviation is calculated by adding all activity variances and taking
the square root of project variance
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
PERT Example
Activity O M P Expected Standard Activity Range of
or PERT Deviation Variance the
Duration Estimate
A 16 26 48 28 5.5 30.25 28,+/-5.5
B 40 59 88 60.6 8 64 60.6,+/-8
C 40 45 49 44.83 1.5 2.25 44.83,+/-
1.5
D 30 38 42 37.33 2 4 37.33,+/-2
Project 170.76 10 100.5
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
13
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
14
Innovation Throughout
Innovation Throughout
Float (Slack):
15
Innovation Throughout
Float
Backward LS LF
Pass
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
16
Innovation Throughout
Critical Path
ES EF
LS LF LS LF LS LF
Duration 2
Start Finish
Task H
ES EF ES EF ES EF
LS LF
LS LF LS LF LS LF
ES EF
Duration 2
Task F
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Forward Pass – Early Start, Early Finish
ES EF ES EF ES EF
0 7 7 13 13 16
Duration 7 Duration 6 Duration 3
Task A Task C Task G
ES EF
LS LF LS LF LS LF
16 18
Duration 2
Start Finish
Task H
ES EF ES EF ES EF LS LF
0 3 3 6 6 9
Duration 3 Duration 3 Duration 3
Task B Task D Task E
LS LF LS LF LS LF
ES EF
3 5
Duration 2
Task F
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
17
Innovation Throughout
Backward Pass – Late Start, Late Finish
ES EF ES EF ES EF
0 7 7 13 13 16
Duration 7 Duration 6 Duration 3
Task A Task C Task G
0 7 7 13 13 16
LS LF LS LF LS LF
ES 0 EF
16 18
Duration 2
Start Finish
Task H
16 18
ES 7 EF ES 7 EF ES 7 EF LS LF
0 3 3 6 6 9
Duration 3 Duration 3 Duration 3
Task B Task D Task E
7 10 10 13 13 16
LS LF LS LF LS LF
ES 8 EF
3 5
Duration 2
Task F
11 13
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Critical Path – Longest Path, Zero Float
ES
0 EF
0 ES
0 EF
ES EF
0 7 7 13 13 16
Duration 7 Duration 6 Duration 3
Task A Task C Task G
0 7 7 13 13 16
LS LF LS LF LS LF
ES 0 EF
16 18
Duration 2
Start Finish
Task H
16 18
ES 7 EF ES 7 EF ES 7 EF LS LF
0 3 3 6 6 9
Duration 3 Duration 3 Duration 3
Task B Task D Task E
7 10 10 13 13 16
LS LF LS LF LS LF
ES 8 EF
3 5
Duration 2
Task F
11 13
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
18
Innovation Throughout
Network Exercise
ES EF ES EF ES EF
LS LF LS LF LS LF
ES EF
ES EF
Duration 10
Start Duration 7 Finish
Task G
Task D
LS LF
ES EF LS LF ES EF
Duration 5 Duration 5
Task E Task F
LS LF LS
LS LF
LF
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Network Exercise - solution
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
19
Innovation Throughout
Schedule Compression
Schedule Compression: Schedule compression is done during project planning to see if the desired
completion date can be met and what will have to change to meet that date.
Two techniques:
Fast Tracking
Crashing
• Crashing:
• Fast tracking:
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Crashing - Example
Activity Original Crash Time Original Crash Extra Crash
Duration Duration Savings Cost in Cost Cost Cost Per
(in (in Dollars Month
Months) Months)
A 14 12 2 12,000 14,000 2,000 1,000
B 10 8 2 16,000 26,000 10,000 5,000
C 3 2 1 15,000 17,000 2,000 2,000
D 7 5 2 12,000 18,000 6,000 3,000
Assuming the Project has a float of -1 month. Which activity would you crash?
The answer is Activity A, as it has the minimum crash cost.
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
20
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Resource Leveling
C, 5
1 4
(4)
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
21
Innovation Throughout
Resource Leveling
a 8
a
6
Workers
Activity
b
4 c c
c
2 c
b b
0
1 2 3 4 5 1 2 3 4 5
Days Days
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
Resource Leveling
8
a
6
a b
Workers
Activity
b 4
c 2 c
0
2 3 4 5 1 2 3 4 5
1
Days Days
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
22
Innovation Throughout
Control Schedule
•Part of Monitoring and Controlling Process Group
•Control Schedule is the process of monitoring the status of the Project
to update project progress and managing changes to the schedule
baseline.
Innovation Throughout
Control Schedule
Inputs Tools Outputs
Schedule compression
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
23
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
Innovation Throughout
13-Feb-11 sunil@bharticonsulting.com
Bharti Consulting
24