Professional Documents
Culture Documents
PIPING PART-1
Amit Vaidya
10th Aug 2021
Overview
Safety
Training Objective
Flow Measurement
Pressure Measurement
Temperature Measurement
5. Drive Slow
ROAD SAFETY TIPS DURING RAINY SEASON
If an Orifice meter is the selected flow element, and Orifice plate sizing dictates a meter run
size less than nominal 2 inch , use an Integral Orifice.
Orifice meter shall be installed in horizontal run. Vertical orifice run shall be used only with
Owner approval.
Minimum “A” (Upstream) dimension shall be 20 pipe dia. And minimum “B” (Downstream)
dimension shall be 5 pipe dia. For Conditioning orifice plate upstream/ downstream should
be 2-2.
Flange Thickness shall be in accordance with ANSI B16.36 minimum of ANSI 300# or heavier
as required with raised face.
Piping isolation valve from taps should be used in accordance with Piping
Specification. End connection of instrument tubing is threaded end.
Extended Nuts and bolts should be used in accordance with Piping Specification.
Straight run requirement of Orifice, Venturi
Conditioning Orifice Plate
Integral Orifice Plate
Orifice assembly Modelling -Points to Look at
The isometric BOM will show two orifice flanges. Orifice flanges are ordered in a set (of
two).
One flange needs the Reporting Requirement set to “Not to be reported” at the part level.
For consistency, make the downstream orifice flange the one that is set to “Not to be
reported.”
Port settings for Port 1 and Port 2. Note that the Pressure Rating may already be set
correctly
Orifice assembly - Isometric
Orifice assembly - Isometric
Restriction Orifice plate(RO)
Restriction orifice plates do not normally require straight lengths in upstream and
downstream piping.
Extended Nuts and bolts should be used in accordance with Piping Specification.
Variable Area meter(Rotameter)
Rotameter must be always mounted vertically, with the outlet connection at the top
and the inlet connection at the bottom. (flow direction is from bottom to top).
It should be installed at a location free from vibration and have sufficient clearance for
occasional float removal for servicing and inspection.
Minimum straight run requirement shall be accordance with ANSI/API (ISO 5167-3) table 3.
Unless otherwise required by service application and piping specification, flow nozzle
shall be designed to bolt between flanges.
In High pressure (1000 psig or higher) application, flow nozzle shall be welded directly
into pipe.
Tap connection shall be installed 1 inside pipe diameter upstream and ½ inside pipe
diameter downstream in accordance with ASME-MFC-3M.
Unless they are bi-directional, averaging Pitot tube elements shall be parentally marked to
indicate proper installation position and flow direction.
Minimum straight run requirement shall be accordance with Pitot element manufacturer’s
recommended length.
Extra heavy flow element and/or double ended support shall be used in large dia. Pipes or
duct or if high flow velocity can cause the element to deflect or vibrate. Manufacturing
installation should be followed.
Averaging Pitot element are subject to plugging and shall be limited to clean process service.
Turbine Meters
Turbine Meter shall be installed so that meters are always In single phase flow and Liquid
full in liquid applications.
A strainer shall be installed upstream of Turbine meter system. Strainer shall be installed
far enough upstream to prevent distortion of flow profile at Turbine meter.
For gas measurements in horizontal lines, the meter should preferably not be located at
the lowest point in order to avoid condensate impacting on the measuring element. For
vortex meters in a vertical line, the flow shall be upwards.
For liquid services, the horizontal or vertical flow line must remain full under all operating
conditions.
Vortex flowmeter size is always downscaled by vendor to achieve full flow, final straight
length requirement should meet vendors recommendation to achieve the required
accuracy.
STRAIGHT RUN REQUIREMENTS OF VORTEX FLOW METERS
Magnetic Flow Meters
As a thumb rule, Minimum upstream & downstream straight run required are 5D & 2D
respectively, however same shall be confirmed with manufacturer.
Correct measuring is possible only if the pipe is full. Avoid the following locations:
Highest point of a pipeline. Risk of air accumulation.
Directly upstream of a free pipe outlet in a vertical pipe.
Ultrasonic Flow Meters
Ultrasonic flow meters can be installed at any point in the pipe run. In horizontal lines,
nozzles shall be in the horizontal plane to avoid the collection of debris.
As a thumb rule, Minimum upstream & downstream straight run required are 10D & 5D,
respectively.
Coriolis Flow Meters (Mass Flow meter)
Coriolis mass flow meters can be mounted in any position, although sometimes it may be
preferred to install the meter tube as self-draining.
Mass flow meter shall be installed so that meter is always liquid full in liquid application.
Mass flow meter shall be installed so that meter is self draining in gas application.
If the sensor is installed in vertical pipeline, liquid should flow upward through sensor and
Gases should be downward.
There are no straight length requirements for Coriolis mass flow meters.
Pressure Measurement
A line class root (isolation) valve shall be provided at each process connection for Pressure
instrument. This valve shall be specified and provided by Piping.
Pressure Gauge Instrument shall be readable from grade, platform or permanent ladder.
There is no specific requirement for PT having its actual instrument either on grade or
Instrument room.
For Tower piping Pressure nozzle connection should always be in Vapor space.
In Differential Pressure connection, keep one instrument should always be non reportable
on isometric.
Temperature Measurement
Temperature Instruments-Points to Look at
Temperature sensors shall be placed in flowing stream, not in segment fluid.
For Tower piping Temperature nozzle connection should always be in liquid space.
Minimum 4” size pipe required and 3” size Elbow required for locate Thermowell.
Instrument Accessibility Level
In general, Four accessibility levels are defined as follows:
Permanent accessibility:
Limited accessibility:
A device has a limited accessibility if it is located not more than 3 ft (1.0 m)
horizontally away from and at a height between 5 ft 6 in ~ 13 ft (1.7 m and 4.0 m)
above grade, platform or walkway, if no obstructions are in place and if such
locations can be safely reached during plant operation by means of a mobile
platform or ladder.
Poor accessibility:
A device has a poor accessibility if it is located more than 13 ft (4.0 m) above grade,
platform or walkway or at any other location that can only be safely reached during
plant operation by installing temporary facilities such as scaffolding or cranes.
Inaccessible: