Professional Documents
Culture Documents
Paradip LSTK
Paradip LSTK
NEWSLETTER
VOL . 1, AUG’19
Welcome to the first edition of our e-Newsletter, curated specifically to keep our various
stakeholders updated about Projects involving LSTK-1 Package for “Ethylene Recovery and
Ethylene Glycol” and LSTK-2 Package for Offsite and Utilities at IOCL Paradip Refinery,
Odisha. We will endeavor to keep all of you apprised of the latest developments,
execution milestones, events, and insights concerning the two projects.
Indian Oil Corporation Limited (IOCL) is India's flagship Maharatna national oil company
with business interests straddling the entire hydrocarbon value chain - from refining,
pipeline transportation & marketing, to exploration & production of crude oil & gas,
petrochemicals, gas marketing, alternative energy sources and globalisation of
downstream operations.
Indian Oil Corporation Limited (IOCL) awarded the responsibility of setting up Mono-
Ethylene Glycol (MEG) Plant and building Intermediate and Product Storage, Dispatch
facilities & Utility facilities at IOCL Paradip Refinery, to LTHE.
The project has its own challenges in terms of complex interfaces and tough timelines. The
1
contractual Mechanical Completion is 30 months for LSTK-1 and 24 months for LSTK-2 from
the date of LOI issuance i.e. January 30, 2019.
The LSTK1 Package comprises design, engineering, procurement, supply, fabrication, construction,
inspection, testing, pre‐commissioning, start‐up, commissioning and performance guarantee run test
of the ERU, EG units along with substation and satellite rack room. The new Petrochemical Complex at
Paradip Refinery will produce 357 KTA of Glycols (including MEG ‐ 332 KTA, DEG ‐ 24 KTA, TEG ‐1 KTA).
The LSTK2 Package comprises design, engineering, procurement, supply, fabrication, construction,
inspection, testing, pre‐commissioning, commissioning and performance guarantee run test of the
four Ethylene Storage Spheres & BOG (Boil Off Gas) Package, Product Transfer Pumps, Storage Tanks,
Tanker Loading Gantry, Offsite Pipe Rack, ETP & Flare modification, Brownfield Pipe Rack modification
and Creek Bridge, TEG Barrelling Facility, Cooling Tower for EG & ER Unit, Fire Water Booster Pump
House for EG & ER Unit, Chemical House and Buildings.
While the owner has chosen M/s Toyo Engineering India Pvt Ltd., Mumbai as the Project Management
Consultant (PMC), it has signed up M/s McDermott International Inc. and M/s Scientific Design as
Licensors for Ethylene Recovery Unit (ERU) and Ethylene Glycol Unit (EG) respectively.
The refinery site is located approximately 7 km South West of Paradip Port on the North bank of the
River Kansarbatia and straddling the River Santra approximately 2 km from the shore line. The project
site is located close to the coast line. The shore runs in the northeast – southwest direction parallel to
the prevalent sea current.
The Detailed engineering for LSTK‐1 & 2 is being carried out by L&T‐Chiyoda (LTC), a joint venture
company of L&T, which has proven to be an extremely effective enterprise in our journey of
engineering excellence. LTC is working in close collaboration with the LTHE Project Management team
to deliver key deliverables in a timely manner which in turn help us achieve project completion within
the scheduled time period.
0
100000
200000
300000
400000
500000
600000
15-Jun-19 Upto Mar'19
0.00
22-Jun-19
Jun-19
29-Jun-19
06-Jul-19 Apr'19
0.00
13-Jul-19
Jul-19
20-Jul-19
27-Jul-19
Achieved
May'19
0.00
03-Aug-19 # Tool Box Talks
10-Aug-19
17-Aug-19
Aug-19
Jun'19
0.00
24-Aug-19
31-Aug-19
07-Sep-19
# Personnel HSE Inducted
14-Sep-19 Jul''19
0.00
21-Sep-19
# Safe MHrs (Till 30-Jun-19)
Sep-19
28-Sep-19
05-Oct-19
Aug'19
0.00
# Sr. Management walkthrough
12-Oct-19
19-Oct-19
Oct-19
26-Oct-19
Sept'19
0.00
02-Nov-19
09-Nov-19
Nov-19
23-Nov-19 Oct'19
0.00
30-Nov-19
HSE Performance Indicators
07-Dec-19
14-Dec-19 Nov'19
0.00
21-Dec-19
Dec-19
28-Dec-19
04-Jan-20
Dec'19
0.00
LEADING INDICATORS
11-Jan-20
4
321
2,97,940
1,002
369
18-Jan-20
Jan-20
25-Jan-20
01-Feb-20
08-Feb-20 0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
15-Feb-20
Feb-20
22-Feb-20
Upto Mar'19
0.00
29-Feb-20
07-Mar-20
14-Mar-20
Near Miss
21-Mar-20
Unsafe Acts &
Conditions
Apr'19
0.00
Mar-20
Case
28-Mar-20
First Aid Case
04-Apr-20
11-Apr-20
May'19
0.00
18-Apr-20
Apr-20
Medical Treatment
25-Apr-20
02-May-20
Jun'19
0.00
09-May-20
16-May-20
Lost Time Injury
May-20
23-May-20
30-May-20 Jul''19
0.00
Fatality
06-Jun-20
13-Jun-20
INJURY RATES (TRIR & LTIFR)
20-Jun-20
Jun-20
Aug'19
0.00
27-Jun-20
04-Jul-20
0
0
0
0
0
11-Jul-20
135
Sept'19
0.00
18-Jul-20
Jul-20
25-Jul-20
01-Aug-20
LTIFR (Lost Time Injury Frequency Rate)
Oct'19
0.00
08-Aug-20
15-Aug-20
Aug-20
22-Aug-20
29-Aug-20 Nov'19
0.00
SAFETY PYRAMID
05-Sep-20
Planned
12-Sep-20
19-Sep-20
Sep-20
Dec'19
0.00
26-Sep-20
HSE HIGHLIGHTS
Cold Box
3D – MODEL (EGU)
Substation (SS315N) Satellite Rack Room
(SRR822)
Main Pipe
Rack
Waste Heat
Boiler Area
INSIDE VIEW
CONSTRUCTION HIGHLIGHTS
SPOOL FABRICATION SHOP
Uniqueness
Adequacy check, revamping and enhancement of existing facility like ETP, Creek Bridge,
Flare & Brownfield Pipe rack.
Liquefaction potential prone site due to which a unique foundation concept combining
stone column & piling has been adopted.
LSTK Package – 2 for Offsite & Utilities Project
Paradip Refinery, Odisha
LEADING INDICATORS SAFETY PYRAMID
Fatality 0
# Safe MHrs (Till 30-Jun-19) 2,04,089
Lost Time Injury 0
# Tool Box Talks 544
Medical Treatment 0
# Personnel HSE Inducted 726 Case
First Aid Case 0
# HSE Training Hours 938
Near Miss 1
# Sr. Management walkthrough 9
HSE Performance Indicators Unsafe Acts & 180
Conditions
Upto Mar'19
Jun'19
Jul''19
Sept'19
Dec'19
May'19
Aug'19
Oct'19
Apr'19
Nov'19
Jun'19
Jul''19
Upto Mar'19
Sept'19
Oct'19
May'19
Aug'19
Dec'19
Apr'19
Nov'19
TRIR (Total Recordable Injury Rate) LTIFR (Lost Time Injury Frequency Rate)
Planned
700000
600000
500000
400000
300000
200000
100000
Achieved
0
20-Jul-19
21-Mar-20
29-Jun-19
06-Jul-19
13-Jul-19
27-Jul-19
05-Oct-19
12-Oct-19
19-Oct-19
26-Oct-19
04-Jul-20
11-Jul-20
18-Jul-20
25-Jul-20
07-Sep-19
14-Sep-19
21-Sep-19
28-Sep-19
04-Jan-20
11-Jan-20
18-Jan-20
25-Jan-20
07-Mar-20
14-Mar-20
28-Mar-20
05-Sep-20
12-Sep-20
19-Sep-20
26-Sep-20
15-Jun-19
22-Jun-19
01-Feb-20
08-Feb-20
15-Feb-20
22-Feb-20
29-Feb-20
11-Apr-20
06-Jun-20
13-Jun-20
20-Jun-20
27-Jun-20
07-Dec-19
14-Dec-19
21-Dec-19
28-Dec-19
04-Apr-20
18-Apr-20
25-Apr-20
02-May-20
09-May-20
16-May-20
23-May-20
30-May-20
03-Aug-19
10-Aug-19
17-Aug-19
24-Aug-19
31-Aug-19
01-Aug-20
08-Aug-20
15-Aug-20
22-Aug-20
29-Aug-20
02-Nov-19
09-Nov-19
16-Nov-19
23-Nov-19
30-Nov-19
Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20
Tool Box Talks
SPHERE AREA
ENGINEERING HIGHLIGHTS
EG STORAGE AREA
TEG BARRELING
AREA
EG GANTRY AREA
ENGINEERING HIGHLIGHTS
HAZID STUDY
PROCUREMENT HIGHLIGHTS
PIM AT VENDOR WORKS
PETALS MANUFACTURING
PROCUREMENT HIGHLIGHTS
MANUFACTURING- PIPES & FLANGES
31
SITE PHOTOGRAPHS
UG PIPE FABRICATION ACTIVITY
32
SITE PHOTOGRAPHS
STRUCTURAL MATERIAL RECEIVED SITE
33
SITE PHOTOGRAPHS
FENCING WORK IN PROGRESS
34
SITE PHOTOGRAPHS
TESTING PILE CHIPPING WORK IN PROGRESS – SPHERE AREA
35
SITE PHOTOGRAPHS
REBAR CAGE FABRICATION WORK IN PROGRESS
36
SITE PHOTOGRAPHS
TEST STONE COLUMN WORK – IOTL AREA
37
THANK YOU