4000 psi 3/4 28 days ORD COST PER CU.M.

DESIGNATION UNIT COST UNIT QUANTITY TOTAL COST


S1 1400 cu.m 0.708 991.2
G 3/4 1500 cu.m 0.56 840
Cement 240 bag 8 1920
Admix 34 lit 3.2 108.8
Water 1 lit 153.9 153.9
Sub total 4013.9

5000 psi 3/4 28 days ORD COST PER CU.M.


DESIGNATION UNIT COST UNIT QUANTITY TOTAL COST
S1 1400 cu.m 0.66 924
G 3/4 1500 cu.m 0.56 840
Cement 240 bag 9 2160
Admix 34 lit 3.6 122.4
Water 1 lit 153.9 153.9
Sub total 4200.3

3000 psi 3/4 28 days ORD COST PER CU.M.


DESIGNATION UNIT COST UNIT QUANTITY TOTAL COST
S1 1400 cu.m 0.7 980
G 3/4 1500 cu.m 0.56 840
Cement 240 bag 7 1680
Admix 34 lit 2.8 95.2
Water 1 lit 153.9 153.9
Sub total 3749.1

1500 psi 3/4 28 days ORD COST PER CU.M.


DESIGNATION UNIT COST UNIT QUANTITY TOTAL COST
S1 1400 cu.m 0.74 1036
G 3/4 1500 cu.m 0.56 840
Cement 240 bag 5 1200
Admix 34 lit 2 68
Water 1 lit 153.9 153.9
Sub total 3297.9

DUNGON BRIDGE - CONCRETE COST ESTIMATE


DESIGNATION DESIGN MIX UNIT COST per cu.m. VOLUME (cu.m.) TOTAL COST
Bored Pile 4000 psi 3/4 28 days 4013.9 70 280,973.00
Girder 5000 psi 3/4 28 days 3749.1 48 179,956.80
Railings 3000 psi 3/4 28 days 4200.3 8 33,602.40
Item 405 4000 psi 3/4 28 days 4013.9 120 481,668.00
Lean Concrete 1500 psi 3/4 28 days 3297.9 12 39,574.80
Sub total 1,015,775.00

MAYUWI BRIDGE - CONCRETE COST ESTIMATE


DESIGNATION DESIGN MIX UNIT PRICE per cu.m. VOLUME (cu.m.) TOTAL PRICE
Bored Pile 4000 psi 3/4 28 days 4013.9 70 280,973.00
Girder 5000 psi 3/4 28 days 3749.1 32 119,971.20
Railings 3000 psi 3/4 28 days 4200.3 8 33,602.40
Item 405 4000 psi 3/4 28 days 4013.9 147 590,043.30
Lean Concrete 1500 psi 3/4 28 days 3297.9 12 39,574.80
Sub total 1,064,164.70