Kindly relocate the

ladder as per
orientation of
Manhole M1.

M/s HUTINI is requested to submit the revised erection drawing of


DM water storage tank incorporating our comments since erection is under
progress.
Structural drawing and piping GA drawing along with BOQ may please be
submitted in line with
This manhole has
erection drawing.
been constructed at
GA Drawings of CO2 absorber is not yet submitted kindly submit the same.
angle 0 degree as
per site condition.

Kindly relocate the


ladder as per
orientation of
Manhole M1.
This manhole has
been constructed at
angle 180 degree as
per site condition.