Prepared by 01-01-2022 Page 1

Purcahse Order Ref No : 1154 DT 03.11.2021 SPOC : MMEPL : Mr.Vijay Kumar SPOC : PPL : Mr
Pulse Pharma Work Schedule
Activity Week-1 Week - 2 Week - 3 Week - 4 Week-5 Week-6 W-7 to W-11

POS Task Description Owner Task duration Remarks

10-Feb

11-Feb

12-Feb

13-Feb
10-Jan

11-Jan

12-Jan

13-Jan

14-Jan

15-Jan

16-Jan

17-Jan

18-Jan

19-Jan

20-Jan

21-Jan

22-Jan

23-Jan

24-Jan

25-Jan

26-Jan

27-Jan

28-Jan

29-Jan

30-Jan

31-Jan

1-Feb

2-Feb

3-Feb

4-Feb

5-Feb

6-Feb

7-Feb

8-Feb

9-Feb
5-Jan

6-Jan

7-Jan

8-Jan

9-Jan
Start date End date Feb14th to March 14th

A Basic Activities
1 PO Release 03.11.2021
1 Release of Advance 05.01.2022 Expected /Assumed

B Engineering 06-01-2022 11-01-2022


Designing of HVAC and Clean Room as per site
1 condition 07-01-2022
2 Design Submital date for approval 09-01-2022

Design Submital date for approval considering inputs


3 11-01-2022
C Customer Related Activities
1 Ducting layout 11-01-2022
2 Wall Panel & Ceiling Panel 11-01-2022
3 RCP 11-01-2022
4 Ahu GA drawing 11-01-2022
5 Ahu & condensing unit location layout 11-01-2022
Target Date for Approval
6 Clean Room Equipments (Pass Boxes) 11-01-2022
C-a RAL Colours for Approval
1 Clean Room Doors 11-01-2022
2 Clean Room Panels 11-01-2022
3 AHU RAL Colours for Panels 11-01-2022
4 Epoxy Flooring 11-01-2022
2 Procurement 25 12-01-2022 06-02-2022
a HVAC 15 12-01-2022 27-01-2022
1 Ahu 15 12-01-2022 27-01-2022
2 Ducting, Insulation and Accessories 5 12-01-2022 17-01-2022
3 HEPA Modules 10 12-01-2022 22-01-2022
4 HEPA Filters and Grills 10 12-01-2022 22-01-2022
5 Condensing units 10 12-01-2022 22-01-2022
6 Control panel 10 12-01-2022 22-01-2022
7 Maghnalic Gauges 10 12-01-2022 22-01-2022
b Cleanroom 21 12-01-2022 02-02-2022
1 80 mm Wallpanels 12 12-01-2022 24-01-2022
2 50 mm Wallpanels 13 12-01-2022 25-01-2022
3 50 mm Ceiling panels 15 12-01-2022 27-01-2022
4 Covings 14 12-01-2022 26-01-2022
5 Double glazed view glass 16 12-01-2022 28-01-2022
6 Clean Room doors 19 12-01-2022 31-01-2022
7 Cleanroom Lights 21 12-01-2022 02-02-2022
C Clean Room Equipments 10 25-01-2022 04-02-2022
1 Pass Boxes 10 25-01-2022 04-02-2022
3 Construction 23 05-02-2022 28-02-2022
A HVAC 20 05-02-2022 25-02-2022
1 Ducting & Insulation 20 05-02-2022 25-02-2022
2 Ahu 12 05-02-2022 17-02-2022
3 Vcd,grills,diffusers 14 05-02-2022 19-02-2022
4 Condensing unit installation 10 05-02-2022 15-02-2022
5 Control panel 10 08-02-2022 18-02-2022
B Cleanroom 23 05-02-2022 28-02-2022
1 Wall panel installation 20 05-02-2022 25-02-2022
2 Ceiling panel installation 20 08-02-2022 28-02-2022
3 Doors & view glass 5 13-02-2022 18-02-2022
4 Commissioning 7 25-02-2022 04-03-2022
a Precommissioning 3 25-02-2022 28-02-2022
b Validation 6 01-03-2022 07-03-2022
c Documentation & handover 6 08-03-2022 14-03-2022