Project Proposal for

Switch Café Al-fresco


Dining Area

14-Oct-2022
Project Overview

Project Name Switch Café Al-fresco Dining Area


Project Description: Roofing Extension
Project Area ????
Project Cost P82.2k
Insert the Revised Design Perspective
Project Duration 11 days

2
Over-all Project Plan
Overview Detailed Activities:
EBS Engineering and Surveying Consultancy EBS Engineering and Surveying Consultancy
Project Timeline
Project Timeline
Project Name: B1 Switch Café Al-fresco Dining Area
Project Name: B1 Switch Café Al-fresco Dining Area Description: Extension Roofing for Switch Café
Description: Extension Roofing for Switch Café
No. of

11-Oct
12-Oct
13-Oct
14-Oct
15-Oct
16-Oct
17-Oct
18-Oct
19-Oct
20-Oct
21-Oct
22-Oct
23-Oct
24-Oct
25-Oct
26-Oct
27-Oct
28-Oct
29-Oct
30-Oct
31-Oct
Item Activity Owner Remarks
Days

11-Oct
12-Oct
13-Oct
14-Oct
15-Oct
16-Oct
17-Oct
18-Oct
19-Oct
20-Oct
21-Oct
22-Oct
23-Oct
24-Oct
25-Oct
26-Oct
27-Oct
28-Oct
29-Oct
30-Oct
31-Oct
No. of
Item Activity Owner 1 Design Planning 1 EBS, Client
Days Flooring - Bricks; Posts - 2 Front
1 Design Planning 1 EBS, Client Discussion of clients requirements 0.3 EBS, Client (bigger in size); 3 Back; Roofing -
Clear Polycarbonate; steel trusses
2 Project Costing 6 EBS Presentation of Initial Design 0.3 EBS, Client
3 FINAL Project Design, Plan and Cost Approval 1 EBS, Client Proposed Design: 7 pillars; brick
4 Contract Planning 2 EBS, Client Approval of Design 0.3 EBS, Client flooring; steel trusses; with side
cover
5 Intial Down payment for Material Cost 1 Client
2 Project Costing 6 EBS
6 Purchase of Materials 1 EBS Material Costing 3 EBS
7 Delivery of Materials 1 EBS Supplier Bidding 2 EBS Eduardson, Jon Lucas
Actual MC is 20% higher than MC
8 Start of Construction Activity 11 EBS Computation of Material Cost 0.5 EBS
estimate using 2018 pricelist
9 Completion and acceptance of Project 0.5 EBS, Client
Supplier Selection 0.5 EBS Bricks - Camiling; Others - Eduardson
10 Full Payment of Project Cost 0.5 Client
Manpower and Construction Costing 1 EBS
Breakdown of Work and Timeline 0.3 EBS 11 Manpower, 7 days construction
Legend: Computation of Manpower Cost 0.3 EBS
Plan Manpower Selection 0.3 EBS 1 skilled; 3 laborers
Done Intial Project Cost Cost is out of
Review of Project Plan and Costing 1 EBS Budget (P87K, excluding other fees);
Delayed
MC = P73.5K; LC = 13.5K
Revised Design; Revised Materials;
Revision of Design, Project Plan and Costing 1 EBS Revised Project Cost within budget
(P82.2K); MC = P50K; LC = P18.5K
3 FINAL Project Design, Plan and Cost Approval 1 EBS, Client
4 Contract Planning 2 EBS, Client
Preparation of Contract 1 EBS
Review and Approval of Contract 1 EBS, Client
5 Intial Down payment for Material Cost 1 Client
6 Purchase of Materials 1 EBS
7 Delivery of Materials 1 EBS
8 Start of Construction Activity 11 EBS
Excavation Works 1
Rebar Works 1
Concreting Works 1
Steel Works 5
Roofing Works 1
CHB/Brick Works 2
9 Completion and acceptance of Project 0.5 EBS, Client
10 Full Payment of Project Cost 0.5 Client

Legend:
Plan
Done
Delayed

3
Project Design and Plan Details
Construction Plan – Manpower, Timeline, Project Cost, Materials

Insert the Revised Design Perspective