Professional Documents
Culture Documents
2007-Wilson-Seismic Vulnerability and Mitigation During Construction
2007-Wilson-Seismic Vulnerability and Mitigation During Construction
of Cable-Stayed Bridges
John C. Wilson1 and Keith Holmes2
Abstract: The implications of earthquake loading during balanced cantilever construction of a cable-stayed bridge are examined.
Finite-element models of a cable-stayed bridge were developed and multiple ground motion time history records were used to study the
Downloaded from ascelibrary.org by New York University on 05/14/15. Copyright ASCE. For personal use only; all rights reserved.
seismic response at the base of the towers for six stages of balanced cantilever construction. Probabilistic seismic hazard relationships
were used to relate ground motions to bridge responses. The results show that there can be a high probability of having seismic responses
共forces/moments兲 in a partially completed bridge that exceed, often by a substantial margin, the 10% /50-year design level 共0.21% per
annum兲 for the full bridge. The maximum probability of exceedance per annum was found to be 20%. This occurs because during
balanced-cantilever construction the structure is in a particularly precarious and vulnerable state. The efficacy of a seismic mitigation
strategy based on the use of tie-down cables intended for aerodynamic stability during construction was investigated. This strategy was
successful in reducing some of the seismic vulnerabilities so that probabilities of exceedance during construction dropped to below 1% per
annum. Although applied to only one cable-stayed bridge, the same approach can be used for construction-stage vulnerability analysis of
other long-span bridges.
DOI: 10.1061/共ASCE兲1084-0702共2007兲12:3共364兲
CE Database subject headings: Bridges, cable-stayed; Seismic effects; Bridges, cantilever; Aerodynamics; Cables; Bridge
construction.
height兲, each with four legs, 192 cables in a fan arrangement, and
two independent continuous superstructures with composite decks
共an east and a west deck兲 with a main span of 381 m and side
spans of 147 m. The two 23.5-m-wide decks are connected to
each tower and to the anchor piers so as to transmit both longi-
tudinal and transverse shear loads into these supports. The bridge
was erected using the balanced cantilever method. Deck extension Fig. 2. Modeling of six stages of balanced cantilever construction
progressed incrementally using preassembled sections, the length
of which equaled the distance between cables 共14.6 m for the side
spans, 15.8 m for the main span兲. Temporary tie-down cables rotation of the superstructure about the global transverse y-axis of
were used to avoid potential aerodynamic instabilities during con- the connection but were fixed for motions in all other degrees of
struction; details about these cables appear later. freedom.
Note that the term “balanced cantilever construction” refers
here to the notion that, during construction, the deck is progres-
Construction Stages
sively extended in an approximately weight-balanced manner on
Six three-dimensional 共3D兲 finite-element models, shown in Fig. both sides of the towers. At a particular stage of construction, due
2, were developed to represent the following stages of construc-
tion: 共1兲 a single bare tower; 共2兲 three stages of balanced-
cantilever extension of the superstructure from a single tower
representing approximately one-eighth, one-fourth, and three-
eighths completion; 共3兲 the half bridge just prior to closure where
the midspan is free and the side span is connected to the approach
pier; and 共4兲 the full completed bridge including both towers.
These six stages were named tower, 10-15, 6-19, 4-21, half, and
full, where the numbers refer to cable locations at the ends of the
cantilevered sections shown in Fig. 3共a兲. A 3D view of the full
model is shown in Fig. 3共b兲, including the global coordinate axes
to which references will be made throughout this paper.
The concrete deck was modeled using shell elements, while
the steel girders, floor beams, and concrete towers were modeled
using 3D beam elements and the cables modeled using uniaxial
tension elements. Rigid offset links were used at the cable-girder,
cable-tower, and girder-deck connections for accurate modeling
of the geometry. To simplify the analysis, and because complete
details on the foundations were not available to the writers, the
tower bases were taken to be fixed in all degrees of freedom.
Even though cable-stayed bridges often have deep foundations,
the use of a fixed base is suitable for this study because the
analysis makes relative comparisons between responses at various
stages of construction 共all stages having a fixed base兲 and does
not evaluate the response in an absolute sense. Connections of the Fig. 3. 共a兲 Cable numbering system for cantilever construction
superstructure to the anchor piers and towers allowed for free models; 共b兲 global coordinate system for bridge
Probabilistic Assessment
Seismic Mitigation
2A and TIE 2B configurations, where the first set of prestress less than the full bridge design criterion of 0.21% per annum
values was based on the minimum prestress necessary to prevent 共hence these values are not shown in Table 8兲. So for this re-
loss of tension in the cables, while the second set was selected to sponse quantity, all of the tie-down configurations are very effec-
minimize the unbalanced dead-load moments. For moments about tive at reducing the seismic vulnerability. For transverse moments
the transverse axis, this refinement in prestress values from TIE under combined loading, the probability of exceedance of the full
2A to TIE 2B resulted in a 15% reduction in ⌿D+E. More system- bridge design level was 1% per annum or less for all configura-
atic optimization of the configuration and prestressing of the tie- tions except TIE 1B. The lowest value, 0.41% per annum, while
down cables could be done, but this was beyond the scope of this still twice the target design value for the full bridge, is still a vast
study. improvement over the 20% per annum for the original 4-21 stage
with no tie-downs. TIE 1B provided effectively no reduction from
Probabilistic Assessment the 20% value for moments from the original configuration.
The probabilistic approach used to assess the tie-down structures
was identical to that described previously. A summary of prob-
abilities associated with the mitigation strategy is presented in Conclusions
Table 8. The probability of exceedance per annum of the full
bridge design-level moments for the critical 4-21 construction The seismic response of a cable-stayed bridge during various
stage was as high as 4.2% for TIE 1 and 2.6% for TIE 2. The stages of balanced cantilever construction has been examined.
reduction in probability of exceedance per annum for both longi- The approach is also applicable to other cable-stayed and long-
tudinal force 共from 3.5 to 1.4%兲 and transverse moment 共from 5.9 span bridges. The results presented here challenge a common mis-
to 2.6%兲 for TIE 2 reflects the substantial impact of this tie-down conception that seismic loading during construction need not be
configuration in reducing the seismic response. considered because of the relatively short duration of construc-
All tie-down configurations reduced the probability of exceed- tion. The analysis presented here shows that the seismic vulner-
ance of dead plus seismic forces in the longitudinal direction to ability during construction may be substantially greater than when