Professional Documents
Culture Documents
Structures
journal homepage: www.elsevier.com/locate/structures
A R T I C LE I N FO A B S T R A C T
Keywords: The Botan Bridge, built in Siirt Pervari district, was planned to be the country’s longest free cantilever bridge
Bridge before it collapsed. Free cantilevering is a method of construction where a structure is built outward from a fixed
Construction point to form a cantilever structure, without temporary support, using staged cast-in-situ construction. The
Free cantilever method bridge was designed to connect the Southeastern Anatolia to Eastern Anatolia. It has two piers 105.88 m high
Collapse
and the complete length of the deck is 450 m. Prior to the construction of the bridge, a computer model was
Botan
generated, however there was deviation from the model during the construction without updating the model to
reflect the changes. On December 18, 2018, the bridge collapsed during construction without any casualty
recorded. Furthermore, it also suffered a partial collapse when the mid-span on the Beğendik side fell into the
river. The P1 pier was damaged because the parts falling to P1 were hit. Consequently, It was decided that it had
to be demolished and rebuilt. This article investigates the actual cause of the collapse with recommendations for
future projects.
1. Introduction [15].
Botan Bridge is being constructed with free cantilever technology
The main causes of bridge failures were classified as deficiencies in between Beğendik and Pervari (Siirt) town (Km 1 + 420 and Km
design, specification, construction, maintenance, use of poor materials 1 + 900). Bridge construction started in 2013 and was scheduled to end
and insufficient consideration of external events [1–3]. Failure is gen- in May 2020, but its failure delayed the end time of the bridge. The
erally considered to be performance non-compliance with standards purpose of constructing a bridge at the selected location is to reduce the
[4], some structures collapsed during the construction phase while travel distance between the provinces of the region. The old stone Botan
others failed during their service life [5], which had harmful effects on Bridge has supported transportation until now. The Pervari Dam, built
the social community and the environment [6]. Bridge failures are one 5 km above Pervari district, in the region was constructed for hydro-
of the most serious infrastructure issues of today [7], typically causing electric power generation and flood protection. The old stone Botan
significant economic damage and casualties. This has drawn significant bridge will submerge when the reservoir is full. The new Botan bridge
attention from designers, engineers, researchers and policy makers [8]. structure built with the free cantilever technology method consists of
The practice of engineering must gain as much information as possible segments produced as individual parts. The segments are converted into
from those failures [9]. moulds that are fixed to a traveler with a special structure of moving
A popular technique for building concrete bridges is the free can- steel. The form traveler's ideal layout and weight is crucial for the
tilever technique [10–13]. This method is mainly used for wide spans in structure's design and financial benefit. But, the Botan Bridge collapsed
places where stationary support cannot be used. Free cantilever con- while under construction in the valley of Botan. The failure began in the
struction is a technique of progressively building a cantilever in sections mid-span on the Beğendik side near the P1 pier. The mid-span on the
and stitching it to pre-stressed sections [14]. This method has been used Beğendik side collapsed, and a portion of the bridge fell into the Botan
for many bridges all over the globe. The world five longest span free River.
cantilever concrete bridges are Stolmasundet Bro-Norway (span 301 m, This article investigates the collapse of the Botan Bridge during
1998), Raftsundet, Lofoten-Norway (span 298 m, 1998), Sandsfjord construction with emphasis on the cause of collapse in bridge con-
Bridge-Norway (span 290 m, 2014), Humen, Pearl River-China (span struction. In addition, the analysis of this construction methodology for
270 m, 1997), Varrod bro, Kristiansand-Norway (span 260 m, 1993) a particular project – Botan Bridge case study in Turkey - provides
https://doi.org/10.1016/j.istruc.2020.03.017
Received 1 August 2019; Received in revised form 11 March 2020; Accepted 11 March 2020
2352-0124/ © 2020 Institution of Structural Engineers. Published by Elsevier Ltd. All rights reserved.
M. Ozcelik and O. Tutus Structures 25 (2020) 268–273
Table 1
Material properties for Botan Bridge (Siirt –Turkey) [16].
Materials Elasticity modulus (N/m2) Poisson’s ratio Mass per unit volume (kg/m3) Concrete class
269
M. Ozcelik and O. Tutus Structures 25 (2020) 268–273
Fig. 4. Formwork and steel fixing work at the P1 foundation Beğendik site (a), Pervari site (b).
Fig. 5. The foundation of the P1 on Beğendik side (a), P2 on Pervari side (b).
the design height of the bridge are adapted or compensated for being
The Botan Bridge collapsed while under construction in the valley of
very near in the free cantilever construction. The bridge's design ele-
Botan. The construction of the bridge, which started in 2013, was to be
vation is the final grade plus the camber needed. Figs. 4–6 indicate the
completed in 2018. Construction began from both main piers and
270
M. Ozcelik and O. Tutus Structures 25 (2020) 268–273
Fig. 8. Botan Bridge after collapse, on December 18, 2017 (a, b).
Fig. 9. Condition of box girder top slab on Beğendik side after collapse (a, b).
271
M. Ozcelik and O. Tutus Structures 25 (2020) 268–273
construction phase. However, changes in the site during the construc- 6. Conclusions
tion phase were not transferred to the model and the results were not
updated to reflect the current situation. That is, it took the typical op- Free cantilever bridge construction method is a common method in
erating cycle five days with 12-hour shifts and alternating travelers in places where the ground is not suitable for scaffolding due to water or
two forms with the building crew. The 5-day cycle time may be reduced deep valley crossings such as sea and river. Free cantilevering is a
with concrete admixtures to increase the early strength gain of concrete building technique where, using staged cast-in-situ construction, a
and by the application of partial post-tensioning. But, the form traveler structure is constructed outward from a set point to form a cantilever
was reduced to three days of the working cycle. In this case, the com- structure without temporary assistance. The form traveler's ideal layout
puter model should be created. Changes to the site must be transferred and weight is essential to the structure's design and financial advantage.
to the model and the results need to be updated to reflect the current The typical sequence of operations is summarized as: first, traveler is set
situation. However, the changes were not transferred to the computer up and adapted, and aligned type of deck is obtained after reinforce-
model. The main reason for the failure was the form traveler installa- ment and tendon ducts are placed on the stage. Concreting is accom-
tion and working cycle. The following findings were inevitable as the plished and then pre-stressing tendons are inserted into the section. The
forces became too big. The concrete was not hardened during this time form traveller will be removed in due course. To begin a new cycle, the
and the concrete was broken when the molds were removed. The form traveler is shifted to the next place. Each segment's building
structure was very much affected by the shear forces. Comparing this process is repeated until the bridge is finished. Accordingly, the con-
bridge with others in the past that had no true issues like this one, it was struction stages of the free cantilever bridge should be predicted and
discovered that forces in this bridge that were almost negligible in those computer model should be established. Where necessary, the changes in
of big width-to-span length ratio became dominant forces. The inter- the field should be transferred to the model and the results should be
action of flexural time and shear force in the steel frames with haunch updated to reflect the current situation. However, the casting curve
or intermediate beam length and excentric braced frames with inter- must be considered and controlled with care. Achieving the necessary
mediate connection length is a significant problem of structural analysis strength of the concrete depends on many different variables. This
and design [27]. Failure started in the mid-span near Begendik near P1 period is determined by ambient temperature, concrete form, weight,
pier. The plate on the P1 side may be pinched or crushed with high construction method and concrete temperature. This time period was
compression. In this case, the compression originally carried by the top determined as a duration period of 5-day in the experiments. The 5-day
plate concrete was transferred to the upper part of the web and in the cycle time may be reduced with concrete admixtures to increase the
longitudinal direction caused the webs to bend or crush. It led the de- early strength gain of concrete and by the application of partial post-
cline of the internet plates to move two components of the webs against tensioning. However, the working cycle of the form traveler was re-
each other. As a consequence, the pre-tensioning force has been re- duced to 3-day and its installation was accelerated. The segment under
leased in all longitudinal inner and external tendons at the site. This construction collapsed since the casting control was not carried out. The
eliminated shear on the base plate and improved shear force. The shear fragments from the segment damaged P1. The contractor decided to
force had to be performed by the bottom plate after the web failed. destroy P1 and the rebuilding of P1 began, and concluded that the re-
Therefore, the lower plate failed under shear explaining vertical dis- sults obtained at the planning stage would certainly be applied during
placement. The beam was supported with only the bottom plate. It is the construction phase, contributing to bridging security and the
thus converted into a condition that is simply supported by a very little economy. Botan bridge, which was built with the free cantilever
bending moment from a monolithic connection. The Begendik canti- method in Turkey has the longest span.
lever’s other end is supported by a monolithic mid-span connection.
Thus, the Begendik cantilever simply became a supported beam. Most Declaration of Competing Interest
of the weight on the P1 side was shifted to the Pervari cantilever
through the monolithic linkage in the mid-span. As a result, double The authors declare that they have no known competing financial
drilling in the beam on both sides of the scaffold caused planes of interests or personal relationships that could have appeared to influ-
cutting failure. Stress patterns altered in the Begendik cantilever after ence the work reported in this paper.
becoming a straightforward beam. The reduced plate stresses were now
under tension instead of the compression initially intended. The foun- Acknowledgments
dation plate and the reduced portion of the net broke this stress. When
it dropped into the water, the reduced plate further harmed. When the The authors wish to express their deep gratitude to the AGM and
middle opening on the Begendik side fell into the water, Pervari can- BURAKCAN Engineering Construction and site engineers for their as-
tilever pulled with it. There was no additional damage to the pilot sistance in collecting the necessary information. The authors wish to
cantilever. Parts of the segment damaged P1 and decided to break down thank the editor and anonymous reviewers for their very helpful com-
constructor P1 (Fig. 11). General views are given on the reconstruction ments and suggestions which allowed improving significantly the
of the Botan Bridge in March 2020 (Fig. 12 a-b). manuscript.
272
M. Ozcelik and O. Tutus Structures 25 (2020) 268–273
References [13] Feng C, Ju S, Huang H. Using a simple soil spring model and support vector machine
to determine bridge scour depth and bridge safety. 04015088-1 J Perf Const
Facilities 2016;30(4). https://doi.org/10.1061/(ASCE)CF.1943-5509.0000837.
[1] Choudhury JR, Hasnat A. Bridge collapses around the world: Causes and mechan- [14] Vokunnaya SS, Ravindranatha T, Thite T. Construction stage analysis of segmental
isms. IABSE-JSCE Joint Conference on Advances in Bridge Engineering-III, August cantilever bridge. Int J Civil Eng Tech 2017;8(2):373–82.
21-22 2015, Dhaka, Bangladesh. Amin, Okui, Bhuiyan, Ueda (eds.) ISBN: 978-984- [15] https://www.nrsas.com/ Bridge Construction Equipment. Accessed 15 January
33-9313-5. 2019.
[2] Cook W. Bridge failure rates, consequences, and predictive trends. PhD dissertation, [16] AGM Construction and Ltd. Botan Bridge project report. Ankara. 2014. (in Turkish,
Utah State University Logan, Utah. USA. 2014. unpublished).
[3] Tan J-S, Elbaz K, Wang Z-F, Shen J.S, Chen J. Lessons Learnt from Bridge Collapse: [17] Shamass R, Cashell KA. Behaviour of composite beams made using high strength
A View of Sustainable Management. Sustainability. 2020;12(1205) doi: 10.3390/ steel. Struct 2017;12:88–101.
su12031205. [18] Kirkland B, Kim P, Uy B, Vasdravellis G. Moment–shear–axial force interaction in
[4] Feld J, Carper K. Construction failure. New York: John Wiley & Sons; 1997. composite beams. J Const Steel Res 2015;114:66–76.
[5] Lyu HM, Shen SL, Zhou AN, Yang J. Risk assessment of mega-city infrastructures [19] AASHTO. LRFD Bridge Design Specifications, American Association of State
related to land subsidence using improved trapezoidal FAHP. Sci Total Environ Highway and Transportation Officials, Washington, DC. 2012.
2019:135310. [20] KGM (Turkish Republic, General Directorate of Highways). Technical Specification
[6] Elbaz K, Shen SL, Arulrajah A, Horpibulsuk S. Geohazards induced by anthropic for Road Bridges. https://www.tamyol.com.tr/UserFiles/Content/KGM_Teknik_
activities of geoconstruction: a review of recent failure cases. Arab J Geosci Sartnamesi_2013.pdf. 2013. Accessed 15 January 2019.
2016;9(708). https://doi.org/10.1007/s12517-016-2740-z. [21] LARSA “Section Composer Manual”, A manual for LARSA 4D Finite Element
[7] Lyu HM, Wang GF, Cheng WC, Shen SL. Tornado hazards on June 23rd in Jiangsu Analysis and Design Software Last Revised October 2016, pp. 49.
Province, China: Preliminary investigation and analysis. Nat Hazards [22] SAP2000. Integrated finite element analysis and design of structures basic analysis
2017;85:597–604. reference manual. Computers and Structures Inc. Berkeley, CA, USA. 1998.
[8] Hersi MI. Analysis of bridge failures in the United States (2000-2008). Master’s [23] Momenzadeh SB, Kazemi MT, Hoseinzadeh M. Seismic performance of reduced web
Thesis, Ohio State University, Columbus, OH, USA. 2009. section moment connections. Int J Steel Struc 2017;17:1–13.
[9] Hai DT, Yamada H, Katsuchi H. Present condition of highway bridges in Vietnam: an [24] Montuori R, Muscati R. Smart and simple design of seismic resistant reinforced
analysis of current failure modes and their main causes. Struc Infrastruc Eng concrete frame. Compos Part B: Eng 2017;115:360–8.
2007;3(1):61–73. [25] Dell'Aglio G, Montuori R, Nastri E, Piluso V. A critical review of plastic design
[10] George CL, Satish BM, Chao H, Bastam NF. A study of U.S. Bridge failures, Technical approaches for failure mode control of steel moment resisting frames. Ing Sismica
Report, U.S. Department of Transportation Federal Highway Administration, 2017;34:82–102. ISSN: 0393–1420.
MCEER-13-0008, June 15 2003, 148 pp. ISSN 1520-295X. [26] Ulusay R, Kumsar H, Konagai K, Aydan O. The characteristics of geotechnical da-
[11] Flint MM, Fringer O, Billington SL, Freyberg D, Diffenbaugh NS. Historical analysis mage by the 2011 Van-Ercis¸ earthquake. In: Proceedings of the international
of hydraulic bridge collapses in the Continental United States. J Infrastruct Syst symposium on engineering lessons learned from the 2011 great east Japan earth-
2017;23(3):04017005. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000354. quake, March 1-4, 2012, Tokyo, Japan.
[12] Raphael W, Zgheib E, Chateauneuf A. Experimental investigations and sensitivity [27] Kazemi MT, Sharifi M, Yang J. Mechanism analysis of steel frames considering
analysis to explain the large creep of concrete deformations in the bridge of moment-shear interaction. Adv Struct Eng 2019;22(1):254–67.
Chevire. Case Stud Const Mat 2018;9:00176.
273